HomeMy WebLinkAbout05. Page(s) Advising Contractor of Legal Requirements to Pay Prevailing WageBID FORMS
BID FORMS
8
LIST OF SUBCONTRACTORS
Pursuant to Section 4100 of the Public Contracts Code and section 2-1.33C of the
standard specifications, the Bidder is required to furnish the following information for each
Subcontractor performing more than 1/2 percent (0.5%) of the total base bid. Do not list
alternative subcontractors for the same work. Subcontracting must not total more than
fifty percent (50%) of the submitted bid except as allowed in section 5-1.13 of the standard
specifications.
For Streets & Highways projects, subcontractors performing less than ten thousand dollars
($10,000) worth of work need not be mentioned. Subcontractors required to pay
prevailing wage, must be registered with the Department of Industrial Relations
pursuant to Labor Code section 1725.5 to be listed.
NOTE: If there are no subcontractors, write “NONE” and submit with bid.
Name Under Which
Subcontractor is Licensed License Number
DIR Public
Works
Registration
Number
Address and Phone
Number of Office, Mill or
Shop
Specific
Description of
Subcontract
% of
Total
Base
Bid
Attach additional sheets as needed.
NOTICE TO BIDDERS
NOTICE TO BIDDERS
3
adjustment of existing utility covers, upgrading of select utility frames and covers, striping
and markings, traffic control, and ADA ramp improvements.
The project estimated construction cost is $2,300,000
Contract time is established as 60 working days.
The fixed liquidated damages amount is established at $1,000 per day for failure to
complete the work within the contract time.
In compliance with section 1773 of the Labor Code, the State of California Department of
Industrial Relations has established prevailing hourly wage rates for each type of
workman. Current wage rates may be obtained from the Division of Labor at:
https://www.dir.ca.gov/oprl/DPreWageDetermination.htm
This project is subject to compliance monitoring and enforcement by the Department of
Industrial Relations.
Qualifications
You must possess a valid Class A or C12 Contractor's License at the time of the bid
opening.
You and any subcontractors required to pay prevailing wage must be registered
with the Department of Industrial Relations pursuant to Section 1725.5 of the Labor
Code.
You must have experience constructing projects similar to the work specified for this
project. Provide three similar reference projects completed as either the prime or
subcontractor. All referenced projects must have been completed within the last five years
from this project’s bid opening date.
One of the three referenced projects must have been completed under contract
with a city, county, state or federal government agency as the prime contractor.
All of the referenced projects must be for roadway paving.
Failure to provide reference projects as specified in this section and as required on the
qualification form is cause to reject a bid as being non-responsive.
The City reserves the right to reject any bid based on non-responsiveness if a bidder fails
to provide a bid that complies with all bidding instructions.
The City reserves the right to reject a responsive bid based on the non-responsibility of
the bidder if the Director of Public Works or Designee finds, after providing notice and a
hearing to the bidder, that the bidder lacks the
PRE-CONSTRUCTION MEETING CHECKLIST
PROJECT: SOUTH BROAD STREET IMPORVEMENTS
MEETING DATE: 7-10-19
MEETING TIME: 9:00 AM
MEETING PLACE: 919 Palm – Conference Room 1
1. GENERAL
INTRODUCTIONS AND SIGN IN SHEET
START DATE: JUNE 15,2019
CONTRACT TIME: 60 WORKING DAYS
END DATE: OCTOBER 8,2019
LIQUIDATED DAMAGES: $1,000.00 PER DAY
WORK HOURS: M – F; 7:00 AM TO 4:00 PM WITH NO LANE REDUCTION
9:00 AM TO 4:00 PM WITH LANE REDUCTION
MILLING & PAVING 7:00 PM TO 5:00 AM
2. ADDENDUMS
ADDENDUM NO: 1
3. INSPECTION
REPRESENTATIVES ON SITE:
PRIME CONTRACTOR: PAPICH CONSTRUCTION CO.
CITY INSPECTOR: MARK WILLIAMS
CONSTRUCTION MANAGER/ INSPECTOR: MARK WILLIAMS , HAI NGUYEN
ON SITE FOREMAN:
COMMUNICATION BETWEEN PARTIES – ALL COMMUNICATION ROUTED FROM PRIME CONTRACTOR
THROUGH CITY INSPECTOR
PRIME CONTRACTOR TO SCHEDULE INSPECTIONS AS NEEDED
INTERMITTENT/PERIODIC INSPECTIONS BY CITY REPRESENTATIVE
4. SUBMITTALS
CONTRACTOR SUPPLIED ALL SUBMITTALS PER NOTICE TO PROCEED & PRIOR TO STARTING
WORK?
1. EMERGENCY CONTACT LIST
2. REPRESENTATIVE AT THE SITE OF WORK AUTHORIZED TO SIGN EXTRA WORK TICKETS
3. REPRESENTATIVE AUTHORIZED TO SIGN CHANGE ORDERS
4. CALTRANS EQUIPMENT RENTAL RATES FOR EQUIPMENT USED TO COMPLETE WORK
5. WORK SCHEDULE
6. TRAFFIC CONTROL APPLICATION
7. TRAFFIC CONTROL PLANS
8. WATER POLLUTION CONTROL PLAN
9. LOCATION OF CONSTRUCTION YARD
10. LOCATION OF DISPOSAL SITE
11. EVIDENCE CONSTRUCTION YARD IS CORRECTLY PERMITTED IF CONSTRUCTION YARD IS NOT
YOUR BUSINESS ADDRESS
12. EVIDENCE DISPOSAL YARD IS CORRECTLY PERMITTED.
13. DOOR HANGER FOR NOTIFICATION OF ADJACENT PROPERTIES
MATERIALS
□ ARE MATERIALS READILY AVAILABLE?
□ DELIVERY & STORAGE
OTHER REQUIRED SUBMITTALS
□ SUBMITTAL SCHEDULE
□ TRAFFIC CONTROL PLAN
- (5) DAY REVIEW TIME
- IF VIOLATED, WORK STOPS UNTIL CORRECTED/ (SEE SPECIAL PROVISIONS FOR
LDS)
□ WATER POLLUTION CONTROL PLAN (CITY AND/OR CAL TRANS FORM)
- NEED GRAVEL BAGS & SPILL KIT ON SITE AT ALL TIMES FOR SPILL CONTAINMENT
5. EXTRA WORK
NEW AND UNFORESEEN WORK DETERMINED BY ENGINEER NOT COVERED BY BID ITEMS OR
COMBINATION OF THOSE ITEMS.
PROCEDURE PER STANDARD SPECIFICATIONS SECTION 4-1.05
CITY MUST BE NOTIFIED PRIOR TO ANY EXTRA WORK BEING PERFORMED
6. PERMIT REQUIREMENTS
CITY ENCROACHMENT PERMIT (NO FEE) – CONTRACTOR NEEDS TO SIGN
TRENCHING OVER 5’ REQUIRES ANNUAL CAL OSHA EXCAVATION PERMIT
EVIDENCE THAT CONSTRUCTION YARD / DISPOSAL SITE ARE CORRECTLY PERMITTED
CAL TRANS DOUBLE PERMIT
7. NOTICE TO PUBLIC
DOOR HANGER TO ADJACENT PROPERTIES
- 48 HOURS’ NOTICE REQUIRED WITHIN 100 FT. OF WORK AREAS
- SUBMIT FOR APPROVAL
TRANSIT (BUSES)
- 72 HOURS IN ADVANCE OF WORK REQUIRING TRANSIT LINE REROUTE
- POST ANY TRANSIT STOP AFFECTED 48 HOURS IN ADVANCE
NOTICE TO POLICE & FIRE
NO PARKING PROCEDURES (30 HOUR POSTING PER STANDARD SPECIFICATION 12-3.01)
o CONTACT POLICE DISPATCH AT 805-781-7312
8. SCOPE OF WORK
PLANS AND SPECIFICATIONS
PLAN OF EXECUTION / METHODS PROPOSED BY CONTRACTOR
CITY DETAILS AND REQUIREMENTS / EXPECTATIONS
PRESERVATION OF PROPERTY
PUBLIC SAFETY, HOUSE KEEPING, TRENCH MAINTENANCE (IF VIOLATED, WORK STOPS)
PUBLIC ACCESS TO PROPERTY AND BUSINESSES
POLLUTION CONTROL FOR CREEKS AND DRAIN INLETS (IF VIOLATED, WORK WILL STOP)
SAW CUTTING REQUIRES A VACUUM (IF VIOLATED, WORK WILL STOP)
CONSTRUCTION SURVEY / PRESERVATION OF MONUMENTS AND BENCH MARKS
- LICENSED LAND SURVEYOR TIE OUT ALL MONUMENTS & BENCHMARKS WITH IN 24” OF
WORK AREA (STANDARD SPECIFICATION 5-1.07)
- TIE OUT ALL UTILITY COVERS AND STRIPING
9. SPECIAL REQUIREMENTS OR RESTRICTIONS
COORDINATE UTILITY SHUT OFFS
CITY WILL TURN ALL MAIN LINE VALVES
CONSTRUCTION WATER AT CITY CORPORATION YARD NO LONGER AVAILABLE TO CONTRACTORS
RE-CLAIMED WATER AVAILABLE ANNUAL PERMIT
o CONTACT UTILITY DEPT. AT 805-781-7215
10. PAY ESTIMATES AND CERTIFIED PAYROLL REQUIREMENTS
SUBMIT CERTIFIED PAYROLL FOR PRIME AND ALL SUB-CONTRACTORS WEEKLY
- $1,000 - $10,000 RETENTION FOR UNSATISFACTORY PAYROLL SUBMITTAL
PAY ESTIMATE CUT OFF DATE END OF EACH MONTH
USE OF LISTED SUB-CONTRACTORS ON SITE (0.5% OR $10,000.00) – SEE STANDARD
SPECIFICATIONS SECTION 5
11. PROJECT CLOSEOUT REQUIREMENTS
FINAL PROCEDURE – ALL PROJECTS
- WORK COMPLETED
- NOTICE OF COMPLETION FILED WITH COUNTY (WITHIN 5 DAYS ACCEPTANCE BY PUBLIC
WORKS DIRECTOR)
- CONFIRMATION OF DEPARTMENT OF INDUSTRIAL RELATIONS (DIR) REGISTRATION FOR
PRIME AND SUB CONTRACTORS THROUGH COURSE OF PROJECT
- CITY MANAGER/COUNCIL ACCEPTS PROJECT
- FINAL PAY/RETENTION PAYMENT RELEASED (40 DAYS AFTER NOTICE OF COMPLETION FILED
WITH COUNTY)
WARRANTIES:
- GENERAL – ONE YEAR
RESTORATION OF PRIVATE PROPERTY
MAINTENANCE AGREEMENTS (AND PAYMENT IF APPLICABLE)
AS-BUILT DRAWINGS
ALL PUNCH LIST ITEMS, WARRANTIES, O&M MANUALS, AS-BUILTS SHALL BE COMPLETED/
SUBMITTED WITHIN CONTRACT PERIOD OR LIQUIDATED DAMAGES WILL APPLY
12. CLAIMS
PROCEDURE PER STATE STANDARD SPECIFICATIONS SECTION 9-1.17
- INITIAL NOTICE OF POTENTIAL CLAIM – W ITHIN (5) DAYS DISPUTE FIRST AROSE
- SUPPLEMENTAL NOTICE OF POTENTIAL CLAIM –W ITHIN (15) DAYS OF SUBMITTING INITIAL
NOTICE OF POTENTIAL CLAIM
- FULL AND FINAL DOCUMENTATION OF POTENTIAL CLAIM –W ITHIN (30) DAYS OF
COMPLETION OF WORK RELATED TO POTENTIAL CLAIM
CERTIFIED WITH REFERENCE TO CALIFORNIA FALSE CLAIMS ACT
ALL FORMS ARE AVAILABLE IN THE CITY WEBSITE
13. OTHERS
SITE SAFETY / FIRST AID
RESTROOMS ON SITE – CONTRACTOR TO PROVIDE
ADDITIONAL PLANS AND SPECS NEEDED?
OUTREACH TO RESIDENTS AND BUSINESSES IF NEED TO RESTRICT ACCESS