HomeMy WebLinkAboutItem 08 - Orcutt & Tank Farm Roundabout Design Budget Amendment Request Department Name: Public Works Cost Center: 5010 For Agenda of: June 2, 2020 Placement: Consent Estimated Time: N/A FROM: Matt Horn, Acting Public Works Director Prepared By: Jennifer Rice, Transportation Planner/Engineer SUBJECT: ORCUTT/TANK FARM ROUNDABOUT DESIGN BUDGET AMENDMENT REQUEST (SPEC. #91611) RECOMMENDATION 1. Adopt a draft Resolution approving an amendment to the Orcutt Tank Farm Roundabout Design and Related Budgetary Appropriations (Attachment A); and 2. Appropriate from the Citywide Transportation Impact Fee Fund balance $100,435 to support the Orcutt/Tank Farm Roundabout (Spec. #91611) design phase (Attachment B); and 3. Authorize the Finance Director to increase the Purchase Order to GHD for design services in the amount of $100,435. DISCUSSION Background The Orcutt Area Specific Plan (OASP) and Environmental Impact Report (EIR), adopted in 2010, identified various transportation infrastructure upgrades that would be necessary to support development of the OASP area, including significant impr ovements to the intersection of Tank Farm Road and Orcutt Road. The OASP initially recommended geometric modifications and installation of a traffic signal at Orcutt/Tank Farm to improve traffic safety and operations. With adoption of the General Plan Land Use and Circulation Elements (LUCE) in 2014, the City officially adopted a “roundabout first” policy, prioritizing roundabouts as the preferred design solution where intersection control upgrades are proposed. Subsequently, as part of the entitlement process for the Righetti Ranch development project, the City determined that the Tank Farm/Orcutt intersection should be reconstructed as a roundabout in lieu of a traffic signal as previously proposed. The final conditions of approval for the Righetti Ranch development dictate that the City would take the lead on developing designs for the roundabout and the project would be constructed either by the developer (if construction documents complete by November 2018) or as a City Capital Improvement Plan project prior to issuance of occupancy permits for Righetti Ranch Phase 2 or issuance of building permits for Phase 3 of the development. In Spring of 2018, GHD was awarded the design contract for the roundabout and has since been working closely with the City and Righetti Ranch development team to prepare plans, specifications and estimates for the project. At this point, 90% level construction documents have been completed; however, GHD has expended their current budget due the need for additional design coordination and utility conflict investigation beyond the levels assumed in their original scope of work. Item 8 Packet Page 63 The remaining tasks needed for GHD to complete a construction-ready bid package include (a) response to City comments on 90% design package, (b) preparation of the 100% plans and specifications, and (c) completion of a value engineering and construction phasing analysis, which includes development of innovative construction staging and traffic detour strategies to reduce total construction costs and duration. The purpose of this Council Agenda Report is to request approval to appropriate an additional $100,435 to the project to complete the design work (Attachment C). The Tank Farm/Orcutt Roundabout project supports the Housing and Sustainable Transportation Major City Goals by providing infrastructure needed to support safe and efficient mobility for all users with the planned and pending development of the Orcutt Area. This project also improves pedestrian and bicycle connectivity between the new Orcutt Area neighborhoods and Islay Park. Previous Council or Advisory Body Action On May 19, 2015 the City Council adopted the Mitigated Negative Declaration and approved the Vesting Tentative Map #3063 for the Righetti Ranch development. The original conditions of approval required the development to construct geometric improvements at the Tank Farm/Orcutt intersection and pay a fair share of costs towards future signalization. On January 10, 2018 the Planning Commission proposed recommendations to be forwarded to the City Council regarding amendments to the conditions of approval for Righetti Ranch, including the requirement for construction of a roundabout at the Tank Farm/Orcutt intersection in lieu of a signalized intersection. On February 6, 2018 the City Council approved amendments to the conditions of approvals for the Righetti Ranch development (Tract 3063), including requiring construction of the roundabout prior to issuance of occupancy permits for Phase 2 or building permits for Phase 3 of the development. In July 2018, the Council adopted the FY2017-19 Financial Plan Supplement, allocating $100,000 to start preliminary design work for the roundabout project. Three additional project budget amendments (Attachment D) have subsequently been approved to date to continue incremental design progress (see Fiscal Impact discussion below). Policy Context Per the City’s Purchasing Policy, this request for appropriation of $100,435 Citywide Traffic Impact Fee Funds requires City Council approval. Consistency with COVID-19 Orders and Current Fiscal Contingency Plan. The need for this additional design work was established prior to the COVID-19 orders and the current fiscal contingency Plan. Additionally, the activity of design services is not prohibited under the State and Local emergency orders associated with COVID-19. Finally, completing this effort will result in a shovel-ready project that is anticipated to compete well for future infrastructure stimulus funds and once constructed will provide an economic benefit to the community. Item 8 Packet Page 64 ENVIRONMENTAL REVIEW The California Environmental Quality Act does not apply to the recommended action in this report, because the action does not constitute a “Project” under CEQA Guidelines Sec. 15378, however the following environmental review has been completed relative to the establishment of this project. The Orcutt Area Specific Plan and its Final EIR were approved and certified in March 2010. The Land Use and Circulation Element Final EIR was approved September 2014 includes policy 7.02 stating that where feasible, roundabouts shall be the City’s preferred intersection control alternative due to the vehicle speed reduction, safety and operational benefits of a roundabout. Finally, the Righetti Vesting Tentative Tract Map (VTTM) #3603 (Attachment E) was analyzed in a project-specific Initial Study/Mitigated Negative Declaration and was adopted on May 19, 2015. On February 6, 2018 the City council considered and approved amendments to specified mitigation measures and conditions of approval, which included, but was not limited to, a requirement for the design and construction of the Orcutt/Tank Farm roundabout (MOD-1220- 2017). The Council made a finding that the proposed mitigation measure amendments are consistent with the requirements of the Orcutt Area Specific Plan Final Environmental Impact Report (FEIR) certified and adopted by the City Council on March 2, 2010, and the Initial Study/Mitigated Negative Declaration adopted by the City Council on May 19, 2015 for the VTTM #3063. FISCAL IMPACT Budgeted: No Budget Year: 2017-18 Funding Identified: Yes Fiscal Analysis: Funding Sources Current FY Cost Annualized On-going Cost Total Project Cost General Fund State Federal Fees (Citywide TIF) Previous Allocation $277,490 $277,490 Current Request $100,435 $100,435 Other: Total $377,925 $377,925 GHD is currently one of the City’s consultants on the Traffic Engineering On-Call list that was developed using a competitive Request for Qualifications (RFQ) process. To perform this roundabout design, GHD submitted a proposal for design work for $213,050. The 2017-19 Financial Plan Supplement allocated only $100,000 for Fiscal Year 2017-18 for the study and design of a roundabout at Tank Farm and Orcutt. In order to move forward on the project, GHD was authorized to begin work not to exceed $100,000. In July 2018, the City Council approved additional funding of $113,050 to continue design. Item 8 Packet Page 65 Subsequently, two budget increases were approved in the amounts of $20,645 and $43,795 for additional design updates needed to address utility conflicts and ensure design consistency with adjacent frontage improvements to be constructed by the Righetti Ranch developer. These increases brought the contract amount to a total of $277,490. With this additional request, the total design costs will reach $377,925. As all design work to date was funded through Citywide Transportation Impact Fees (TIF), the TIF Fund is recommended to fund this request of $100,435. The balance of the TIF Fund was approximately $7.4 million as of January 2020. $7.2 million of that balance has been obligated for remaining Capital Improvement Plan Projects and Development Agreement Reimbursements through the 2019-21 Financial Plan. This leaves a balance of approximately $200,000, which is sufficient to support this request of $100,435. Based on current engineer’s estimates, the anticipated construction cost for the roundabout, including contingency, materials testing, and construction management support, is approximately $3.7 million. The total design costs represent approximately 10% of the estimated project construction cost—a ratio consistent with most infrastructure projects of this type. Staff is not requesting authorization to fund construction of this project at this time, but requesting funding to continue progress towards a “shovel-ready” project that could be well-situated for potential Federal or State infrastructure stimulus funding opportunities that may arise in response to t he ongoing COVID-19 emergency. Preparation of the FY 2020-21 Budget Supplement is currently underway and will include recommended adjustments to the FY 2020-21 Capital Improvement Plan program based on anticipated revenue shortfalls due to the COVID-19 pandemic. Funding strategies for construction of the Tank Farm/Orcutt Roundabout project will be assessed as part of this effort. ALTERNATIVES The City Council could choose not to approve the budget amendment request . Staff does not recommend this option as it could result in more costly changes to the design during construction and potential for a delay during construction. Attachments: a - Draft Resolution b - Budget Amendment Request c - Additional Scope of Work No. 3 d - COUNCIL READING FILE - Council Agenda Report dated July 17, 2018 e - Project Map Item 8 Packet Page 66 R ______ RESOLUTION NO. _____ (2020 SERIES) A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF SAN LUIS OBISPO, CALIFORNIA, APPROVING AN AMENDMENT TO THE ORCUTT TANK FARM ROUNDABOUT DESIGN AND RELATED BUDGETARY APPROPRIATIONS WHEREAS, the City of San Luis Obispo’s (City) 2017‐19 Financial Plan Supplement allocated $100,000 for FY 17‐18 for the study and design of a roundabout at the intersection of Orcutt and Tank Farm Roads; and WHEREAS, on October 26, 2017 GHD submit a proposal under their current on-call agreement for transportation services for $213,048.80 and was subsequently awarded the work with authorization not to exceed $100,000; and WHEREAS, additional budget was subsequently authorized up to $277,490 funded from the Transportation Impact Fee Fund; and WHEREAS, City staff has requested the additional budget allocation of $100,435 from the Transportation Impact Fee fund balance; and WHEREAS, the project is a high priority project as it supports the Housing and Sustainable Transportation Major City Goals by providing infrastructure needed to support safe and efficient mobility for all users with the planned and pending development of the Orcutt Area. NOW, THEREFORE, BE IT RESOLVED by the Council of the City of San Luis Obispo as follows: Item 8 Packet Page 67 Resolution No. _____ (2020 Series) Page 2 R ______ SECTION 1. The City Council authorizes staff to transfer $100,435 from the Transportation Impact Fund to the design phase of this project. Upon motion of _______________________, seconded by _______________________, and on the following roll call vote: AYES: NOES: ABSENT: The foregoing resolution was adopted this _____ day of _____________________ 2020. ____________________________________ Mayor Heidi Harmon ATTEST: ____________________________________ Teresa Purrington City Clerk APPROVED AS TO FORM: _____________________________________ J. Christine Dietrick City Attorney IN WITNESS WHEREOF, I have hereunto set my hand and affixed the official seal of the City of San Luis Obispo, California, on ______________________. ____________________________________ Teresa Purrington City Clerk Item 8 Packet Page 68 Department Public Works Fiscal Officer Date Cori Ryan 4/23/2020 Department Head Date Matt Horn 4/23/2020 Cost Center and Account Title Fund Cost Center Account Am ount - Cost Center and Account Title Fund Cost Center Account Am ount Transportation Plan/Engineering - Contract Services 507 5010 71006 100,435.00 100,435.00 Project Title Aw ard Project Task Am ount Orcutt Tank Farm Roundabout Design 91611 91611 2 100,435.00 100,435.00 Account Title Fund Cost Center Account Am ount Transportation Impact Fees 507 0000 (100,435.00) (100,435.00) Accounting Date Budget Manager or Finance Director Date Posted By Date Period BUDGET AMENDMENT REQUEST CHANGE TO FUND BALANCE, WORKING CAPITAL OR DESIGNATION PROJECTS AND AWARDS EXPENDITURES AND TRANSFERS OUT REVENUES AND TRANSFERS IN PURPOSE Per May 2020 CAR, appropriate $100,435 from TIF fund to Orcutt/Tank Farm Roundabout Design project (91611) account Item 8 Packet Page 69 GHD Project No. 11151202 Date 02/26/2020 1 M2460AA007 / 11151202 AMENDMENT TO AGREEMENT BETWEEN CONSULTANT AND CLIENT Amendment No. 3 to Agreement dated 01/29/2018 between GHD Inc. (Consultant) and City of San Luis Obispo (Client). Project Number / Name: 11151202/Purchase Order #24218 – Provide Professional Consultant for Design of the Orcutt & Tank Farm Roundabout per City Specification #91611. Client hereby requests and authorizes Consultant to perform additional and/or revised services as set forth in this Amendment. Scope of work and terms of compensation as set forth below. Additional Scope of Work 0601: Tank Farm Road Culvert Modification Evaluation & Preliminary Design At the request of the City, GHD proceeded with evaluating piping directly from the basin into the culvert on Tank Farm Road. Base on this direction, GHD has prepared a basis of design and calculations, and have developed the preliminary Tank Farm Road culvert modification design. 0602: 90% Plans, Specifications and Estimates (PS&E) At the request of the City, GHD proceeded with updating theTank Farm Road/Orcutt Road Roundabout P&E to reflect additional comments provided by the City on the previous design; evaluate and revise the plans (as needed) to reflect utility pothole information and any identified conflicts; complete and incorporate the Tank Farm culvert modification plans into the 90% P&E; and expand the project design both north on Orcutt Road and west on Tank Farm Road to match to conform limits with Cannon’s improvements. The project drainage study was also re-evaluated and updated to address additional project drainage resulting from expanding the project limits to match the conform limits with Cannon’s improvements. Finally, the City has determined that they will be responsible for construction and that specifications will need to be prepared. Ninety-percent (90%) P&E and updated drainage report will be submitted to the City for review. 0603: 100% Final PS&E Upon receiving 90% comments from the City, GHD shall update 90% PS&E to 100% Final PS&E and resubmit to the City for final review. GHD will also update and submit a final drainage report. The City’s 90% comments will be summarize, responses provided and the comments/responses submitted to the City concurrent with the 100% submittal. 0604: Orcutt Road Shoofly Feasibility Study This phase is to evaluate the feasibility of constructing a shoofly on the northeast corner of the Orcutt Road/Tank Farm intersection. From the concept drawing and description provided by the City, the purpose of the shoofly is to provide a temporary two-way by-pass route for Orcutt Road (both north and south legs) while closing the west leg of Tank Farm Road assumed from Wavertree Street east through the project intersection. The intent is to allow most of the roundabout construction to occur at the same time to accelerate the construction schedule. Item 8 Packet Page 70 GHD Project No. 11151202 Date 02/26/2020 2 M2460AA007 / 11151202 Within this phase, GHD will evaluate the feasibility of constructing the shoofly. This evaluation will include identifying in plan view the preliminary construction limits of the shoofly and potential physical limitations including the existing Orcutt Road culvert and right of way encroachments primarily limited to temporary construction easements (TCE’s). The preliminary design will also accommodate a “California Legal 65-ft” design vehicle. GHD will also develop preliminary stage construction exhibits with initial construction working days estimates for each construction stage. The preliminary construction stages and working days estimates will be compared to the current stage construction plans and working days estimate and a conclusion will be provided as to whether construction would be accelerated with shoofly option. GHD will also prepare a traffic analysis that evaluates and compares current traffic operations and safety conditions to conditions projected to result with construction of the shoofly and closure of Tank Farm Road between Wavertree Street and the Orcutt Road intersection to through traffic. It is assumed that this study will focus on weekday AM and PM hour conditions at the following intersections: 1. Orcutt Rd/Spanish Oaks Dr (GHD to obtain new intersection counts) 2. Orcutt Rd/Tank Farm Rd (available City intersection data) 3.Orcutt Rd/Johnson Ave (available City intersection data) 4.Orcutt Rd/Laurel Ln (available City intersection data) 5.Orcutt Rd/Broad St (available City intersection data) 6.Broad St/Industrial Wy (available City intersection data) 7.Broad St/Tank Farm Rd (available City intersection data) 8.Tank Farm Rd/Brookpine Dr (available City intersection data) 9.Tank Farm Rd/Wavertree St (GHD to obtain new intersection counts) The results, conclusions and recommendations developed both from the preliminary shoofly engineering evaluations and traffic analysis will be summarized in an Orcutt Road Shoofly Feasibility Study that will be submitted to the City for review and comment. 0605: Optional Orcutt Road Temporary Shoofly Design If requested by the City, this phase includes preparing plans, specifications and Engineer’s estimate to construct the temporary Orcutt Road shoofly. At this time the following plans are estimated (14 Sheets): Title Sheet (1) General Notes (1) Typical Cross Sections (1) Demolition Plan (1) Layout (1) Profile (1) Construction Details (1) Grading Plan (1) Utility Plan (1) Temporary Drainage Plan/Details (1) Construction Area Signs (1) Stage Construction (3) GHD will prepare 90% PS&E to be submitted to the City for review. Upon receiving 90% comments from the City, GHD shall update 90% PS&E to 100% Final PS&E and resubmit to the City for final review. The City’s 90% comments will also be summarize, responses provided and the comments/responses submitted to the City concurrent with the 100% submittal. 0606: Optional Miscellaneous Coordination This task includes additional services that can be provided by GHD that is not included in Phases 0601 Item 8 Packet Page 71 GHD Project No. 11151202 Date 02/26/2020 3 M2460AA007 / 11151202 through 0605. These services include, but not limited to, assisting the City in coordinating with Cannon and minor design revisions and miscellaneous items not covered within the previous phases. GHD will notify the City and receive authorization to proceed prior to providing additional services within this phase. 0607: Optional Construction Support Services If requested of the City, GHD will provide the following services under this phase as needed: 1. Project Management and Coordination: GHD will be available to respond to the City to resolve issues raised by the City or contractor (through the City) during construction of the project. Also included are the project management duties for the work performed under this construction support services task. 2. Respond to Requests for Information (RFI): GHD will provide support to the City in response to formal requests for information from the contractor (provided through the City) and clarification of questions from the City. For budgeting purposes, GHD’s responses to up to 10 RFI’s are assumed for this task. 3. Review Submittals: GHD will review specific material submittals for specialty items as requested by the City. 4. Project and Field Meetings: GHD’s attendance at project progress meetings and field meetings will be as requested by the City. For budgeting purposes, up to five (5) project progress meetings and/or field meetings are assumed by GHD within this task. 5. Changes and Revisions: Changes and revisions to the project plans may be required due to differing site conditions encountered in the field during construction. GHD will revise the project plans as needed to address the differing conditions or accommodate changes requested by the City or contractor (through the City). For budgeting purposes, GHD’s assumes up to five (5) changes and revisions to the project plans requested by the City and not included under other Construction Support Services tasks. 6. Technical Support of Contract Change Orders: GHD will, if requested, provide advice and technical support for up to five (5) construction contract change orders. GHD shall provide responses to RFI’s and other questions provided by the City within three (3) working days unless notified by GHD that the response(s) will require additional time to prepare. The primary contact for GHD shall be Joe Weiland (805.858.3131, joseph.weiland@ghd.com). The alternative contact shall be Jorge Vanegas-Moran (805.858.3130, jorge.vanegas-moran@ghd.com). Fee Estimate GHD’s estimated fee to complete the services described in the “Additional Scope of Work” under Phases 0601 through 0604 is $64,933.00 as summarized below by phase. Item 8 Packet Page 72 GHD Project No. 11151202 Date 02/26/2020 4 M2460AA007 / 11151202 Phase/Description Phase Fee 0601: Tank Farm Road Culvert Modification Evaluation & Preliminary Design $13,809.00 0602: 90% PS&E $24,259.00 0603: 100% Final PS&E $ 7,145.00 0604: Orcutt Road Shoofly Feasibility Study $19,720.00 Total Estimated Fee: $64,933.00 GHD’s estimated fee to complete the “Optional” services described in the “Additional Scope of Work” under Phases 0605 through 0607 is $74,717.00 as summarized below by phase. Phase/Description Phase Fee 0605: Optional Orcutt Road Temporary Shoofly Design1 $20,502.00 0606: Optional Miscellaneous Coordination1 $15,000.00 0607: Optional Construction Support Services1 $39,215.00 Total Estimated Optional Fee: $74,717.00 1. Use of the “Optional Phase” fee requires prior authorization from the City of San Luis Obispo Terms and conditions All terms and provisions specified in the original Agreement dated 01/29/2018 are in effect. No other agreements, guarantees, or warranties are in effect. Please contact me if there are any questions regarding this requested amendment. Sincerely, GHD Inc. Joseph W. Weiland, PE Senior Manager Item 8 Packet Page 73 Orcutt Tank Farm Roundabout Project Location Map Item 8 Packet Page 74