HomeMy WebLinkAbout2020-06-17Filippin Engineering
354-D S. Fairview Ave.
Goleta, California 93117
P: (805) 845-4602
Project: 194501 - SLO Marsh Street Bridge
Replacement
919 Palm St.
San Luis Obispo, California 93401
P: 8057817200
Daily Log Inspection: Wednesday 6/17/2020
NOTES LOG
No.Comments
1 Souza on site prepping for verification pile locations. In doing so Souza was digging down at abutment 1 near the sewer
siphon area to establish another well point. In doing so the ground water flowing through the excavation became turbid and
didn't settle out in the baker tank before discharge. Thus leading to a failing test which in turned shut down the discharge into
the creek.
Souza was working on getting a second baker tank onsite as well as having a water truck come and take a few loads out of the
baker tank.
2 Condon Johnson's drill rig didn't show up as scheduled it was 2 hours late thus CJ could not start driling thier first plum
verification pile.
Steve Douzer saw cutting was onsite to cut the retaining wall along the SE corner were the new retaining wall ties into.
3 Condon Johnson recieved a delievery of the galvanized bar for the micro pile. Jerry M. (FE) spoke with Jose T. (Condon
Johnson) about CJ sending over the COC's for all material onsite.
4 Conclusion with Padre and Souza on the failed test for de watering is that well holes need to be established and then allowed
to settle and second baker tank needs to be added to hell the filtration process to achieve de watering approval.
5 Kritz Trucking on site to haul of structure ex material
6 Condon Johnson was not aware of the submittal response to 19.2 that was sent to Souza on Thursday 6/11
MANPOWER LOG 14 Workers | 112.0 Man Hours
No.Contact/
Company
Notes: Workers # Hours Man Hours Location
1 Souza Garrett Vanfleet- Carpenter Foreman
BI 22/37
1 8.0 8.0
2 Souza Clay Souza-Operator
BI 22/37
1 8.0 8.0
3 Souza Steve Hellberg-Carpenter
BI 22/37
1 8.0 8.0
4 Souza Dana Missamore-Laborer
Flagging/22/37
1 8.0 8.0
5 Souza Mike Kenutje-Carpenter Apprentice
BI 22/37
1 8.0 8.0
6 Souza Shane Heilman-Laborer
BI 22/37
1 8.0 8.0
Filippin Engineering Page 1 of 8 Printed on 7/17/2020 at 12:03 PM PDT
MANPOWER LOG 14 Workers | 112.0 Man Hours
No.Contact/
Company
Notes: Workers # Hours Man Hours Location
7 Condon Johnson Jose Toual-Operator Foreman
BI 37
1 8.0 8.0
8 Condon Johnson Eric Sampson-Mechanic
BI37
1 8.0 8.0
9 Condon Johnson Francisco Toro-Laborer
BI 37
1 8.0 8.0
10 Condon Johnson Juan Dones-Operator
BI 37
1 8.0 8.0
11 Condon Johnson Gene Breshears-Operator
BI 37
1 8.0 8.0
12 Condon Johnson Chris Cleary-Laborer
BI 37
1 8.0 8.0
13 Dozier Concrete
Cutting
Steve Dozier-Owner
BI 47
1 8.0 8.0
14 D. Cry Inc.Tom Adams-Operator
BI 22
1 8.0 8.0
14 112.0
EQUIPMENT LOG
No.Equipment Name Cost Code Hrs Operating Hrs Idle Inspected?Inspection Time Location
1 2500 Gmc Crew cab No 01:15 PM
Notes:Souza
2 Cat 336 excavator No 01:15 PM
Notes:Souza
3 Cat 349 excavator No 01:15 PM
Notes:D.Crye
4 F250 crew truck No 01:15 PM
Notes:Condon Johnson
5 Gout Mixing/pump station No 01:15 PM
Notes:Condon Johnson
6 F450 Super Duty No 01:15 PM
Notes:Souza
7 Doosan P185 Air
Compressor
No 01:15 PM
Notes:Souza
Filippin Engineering Page 2 of 8 Printed on 7/17/2020 at 12:03 PM PDT
EQUIPMENT LOG
No.Equipment Name Cost Code Hrs Operating Hrs Idle Inspected?Inspection Time Location
8 F550 crew truck No 01:15 PM
Notes:Doizer saw cutting
9 F550 Utility Truck No 01:25 PM
Notes:Condon Johnson
10 Cat 308 Mini Excavator No 01:25 PM
Notes:Condon Johnson
11 Sullair 1150xh
aircompressor
No 01:25 PM
Notes:Condon Johnson
12 United rentals big generator No 01:25 PM
Notes:Condon Johnson
13 Ecco 512-36 JCB forklift No 01:25 PM
Notes:Condon Johnson
14 Skid Steer with Bucket No 01:25 PM
Notes:Souza
OBSERVED WEATHER CONDITIONS
Weather Delay Sky Temp Average Precipitation Wind Ground/Sea Calamity
No
WEATHER REPORT
Temperature Precipitation Since Humidity Windspeed
Low High Avg Midnight 2 Days Ago 3 Days Ago Low Avg High Dew Avg Max Gust
53°F 77°F 64°F 0.00 in.0.01 in.0.01 in.36%56%83%47°F 5.3 mph 8 mph 15 mph
DAILY SNAPSHOT
06:00 AM 09:00 AM 12:00 PM 03:00 PM 06:00 PM 09:00 PM
clear-day
53°F
clear-day
67°F
clear-day
77°F
clear-day
76°F
clear-day
72°F
clear-night
63°F
Filippin Engineering Page 3 of 8 Printed on 7/17/2020 at 12:03 PM PDT
PHOTOS
5263BC05-5628-4702-A8C6-CC9D0F42A886.jpeg
603A282E-DE28-4054-82B0-972B8C860080.jpeg
34E6DDCA-317C-42CC-BE09-08635EDFD99F.jpeg
037765A1-35F8-47D2-A0E1-8941BCEC63EA.jpeg
1F9A9AC5-CAEB-4826-9077-32A03D814147.jpeg
73270E48-54C5-4AB9-9F31-8F0B0D95DF8A.jpeg
28D8F815-AA82-4C41-9F23-6E65DCAD198E.jpeg
8931257C-4060-44A2-B519-8A195D98782C.jpeg
Filippin Engineering Page 4 of 8 Printed on 7/17/2020 at 12:03 PM PDT
DBDAA8EF-2DA7-4743-9D19-26794F27FBDA.jpeg
3A46E3B8-0B5D-4527-B5BC-F3574E9E7158.jpeg
66B4BF19-1ACA-48FB-9132-B616190B1376.jpeg
156D1563-D555-496C-867E-34DB6AFA6C85.jpeg
768C8BB7-1A44-4592-9B66-2CE3C8A5A3C5.jpeg
15261AD8-8082-472E-BBEE-7AAA84C07E34.jpeg
DE23C240-808F-4261-AA38-5C8259141EA5.jpeg
8256CE3B-C2CE-4C74-82FA-7B582D816EF4.jpeg
Filippin Engineering Page 5 of 8 Printed on 7/17/2020 at 12:03 PM PDT
2ECA56DA-7FBB-4546-8C17-F66264D38141.jpeg
F2BC6EA3-0311-487C-A154-CCC65FBCCA45.jpeg
D58054C9-EC7B-483B-B053-4BFD748C1575.jpeg
958D8D79-92CB-40BF-99A4-E6EE120518B0.jpeg
9D41B67F-3FE8-4D25-956F-4DC93DE5A221.jpeg
5611A38E-B012-4E03-9A18-370258CF47A5.jpeg
F10A355B-E3F6-4D73-ADED-A6704B1F4989.jpeg
6A63CC8E-A2BF-405D-8071-FA63D53998A7.jpeg
Filippin Engineering Page 6 of 8 Printed on 7/17/2020 at 12:03 PM PDT
6CB7E402-4EBD-4611-92BB-614FB7C0985D.jpeg
B2508082-3451-40BB-AE1E-AE0F739A42C1.jpeg
8B540F8A-3FD1-40C0-A842-53CD4FF89D98.jpeg
29BB6387-A50A-4FDC-8B9B-B7AD1A1A5D78.jpeg
FADEF546-0E80-4086-A0CD-09581CEAA9D0.jpeg
F97CAF21-629A-4A05-B6B6-AA9A513BF04D.jpeg
77353D4D-227F-4BA4-98E8-40F8536CC7FF.jpeg
164CF507-B3C5-4692-A9F1-2D6FD6FC31A2.jpeg
Filippin Engineering Page 7 of 8 Printed on 7/17/2020 at 12:03 PM PDT
2576CF3B-C665-45F7-B026-88946A521E0B.jpeg 6BA933E1-EF23-4EA5-A88D-214DC3E3BE7F.jpeg
By Date Copies To
Filippin Engineering Page 8 of 8 Printed on 7/17/2020 at 12:03 PM PDT
Jerry Missamore 6/17/2020