HomeMy WebLinkAbout2020-06-30Filippin Engineering 354-D S. Fairview Ave. Goleta, California 93117 P: (805) 845-4602 Project: 194501 - SLO Marsh Street Bridge Replacement  919 Palm St. San Luis Obispo, California 93401 P: 8057817200 Daily Log Inspection: Tuesday 6/30/2020      NOTES LOG   No.Comments   1 Souza on site at 7 AM continue on structure excavation for the footings. Spoke with Garrett V. (Souza Foreman) he informed me that the schedule was to keep excavating for the next couple of days and be ready for CJ. CJ is not suppose to begin the production pile until Monday July 6 as of right now.   2 2 kritz end dumps running to haul off material to Prado Rd. dump site. D. Crye Long reach and also Souza 336 excavator loading trucks   3 Spoke with Kenny W. (Padre) about Souza adding some filter fabric and dirt along the North side of the diversion so that Souza could extend their access ramp into Abutment 1 side. Kenny (Padre) Cleared area to continue work.   4 Garrett V. (Souza) informed me at 9:30 AM there was some concrete from an old fallen down wall, that is in the way of digging for abutment 2 footing that was going to be hauled off at force account. Concrete was pulled out a couple days ago and the first time this was brought to the attention of FE about being force account work.   5 Meet with Will S. (Souza) and went over monthly quantities for pay estimate for June at 2 PM.  6 Schedule for the rest of the week is to continue to finish up structure ex and install crane mats for CJ to be able to access footing. Also layout SW corner to figure out how far into the footing to the north the shoring was set to brace the exsiting WW at the Davita property.      MANPOWER LOG 5 Workers  |   40.0 Man Hours  No.Contact/ Company Notes: Workers # Hours Man Hours Location   1 Souza Garrett Vanfleet-Carpenter Foreman BI 22   1 8.0 8.0       2 Souza Clay Souza-Operator BI 22   1 8.0 8.0       3 Souza Mylan Elder-Carpenter BI 22   1 8.0 8.0       4 Souza Dana Missamore-Laborer BI 22 Flagging   1 8.0 8.0       5 D. Cry Inc.Thomas Switzer-Operatore BI 22   1 8.0 8.0          5  40.0      Filippin Engineering Page 1 of 4 Printed on 7/17/2020 at 12:16 PM PDT      EQUIPMENT LOG No.Equipment Name Cost Code Hrs Operating Hrs Idle Inspected?Inspection Time Location   1 2500 Gmc Crew cab 8.0 No   01:15 PM    Notes:Souza  2 Cat 336 excavator 8.0 No   01:15 PM    Notes:Souza  3 Cat 336 excavator 8.0 No   01:15 PM    Notes:D.Crye  4 F450 Super Duty 8.0 No   01:15 PM    Notes:Souza  5 Doosan P185 Air Compressor 8.0 No   01:15 PM    Notes:Souza  6 Skid Steer with Bucket 8.0 No   01:25 PM    Notes:Souza    OBSERVED WEATHER CONDITIONS Weather Delay Sky Temp Average Precipitation Wind Ground/Sea Calamity   No        WEATHER REPORT Temperature Precipitation Since Humidity Windspeed Low High Avg Midnight 2 Days Ago 3 Days Ago Low Avg High Dew Avg Max Gust 54°F 76°F 64°F 0.00 in.0.01 in.0.03 in.48%69%93%53°F 5.0 mph 9 mph 14 mph   DAILY SNAPSHOT 06:00 AM 09:00 AM 12:00 PM 03:00 PM 06:00 PM 09:00 PM clear-day   55°F clear-day   65°F clear-day   75°F clear-day   75°F clear-day   73°F clear-night   61°F     Filippin Engineering Page 2 of 4 Printed on 7/17/2020 at 12:16 PM PDT    PHOTOS FBCE900A-8AF2-4991-AA79-303D83DA0659.jpeg  32B33C59-573C-4055-A6BC-F75D5F382DDD.jpeg  D19D38F8-3CAC-4346-B4DE-59C075D4080B.jpeg  C5D01B44-2AC9-4569-B6EF-8ACCD43AA5B1.jpeg  10DEB063-02E5-49E0-BFB4-A7D93951FBFA.jpeg  2F0C67C0-D6F5-46DA-B226-218DE7EE45F5.jpeg  3127D296-361C-497E-A43A-87EB157640BE.jpeg  71529440-C4D2-4F79-A2BA-DEFF46A3E010.jpeg    Filippin Engineering Page 3 of 4 Printed on 7/17/2020 at 12:16 PM PDT    1AE047D8-465A-4948-883E-B99601BEBA30.jpeg  9617C453-F29E-4DDB-B610-A214A0029D1A.jpeg  2C25E58E-5270-4B62-B81C-953C5663F23A.jpeg  F5D5B872-6688-46C0-A0B9-FDB4BB5F8329.jpeg  877A8543-0A4C-4458-A704-FBCF89814445.jpeg      By  Date  Copies To     Filippin Engineering Page 4 of 4 Printed on 7/17/2020 at 12:16 PM PDT        Jerry Missamore 6/30/2020