Daily Log Inspection: Tuesday 6/30/2020
NOTES LOG
No.Comments
1 Souza on site at 7 AM continue on structure excavation for the footings. Spoke with Garrett V. (Souza Foreman) he informed
me that the schedule was to keep excavating for the next couple of days and be ready for CJ. CJ is not suppose to begin the
production pile until Monday July 6 as of right now.
2 2 kritz end dumps running to haul off material to Prado Rd. dump site. D. Crye Long reach and also Souza 336 excavator
loading trucks
3 Spoke with Kenny W. (Padre) about Souza adding some filter fabric and dirt along the North side of the diversion so that
Souza could extend their access ramp into Abutment 1 side. Kenny (Padre) Cleared area to continue work.
4 Garrett V. (Souza) informed me at 9:30 AM there was some concrete from an old fallen down wall, that is in the way of digging
for abutment 2 footing that was going to be hauled off at force account. Concrete was pulled out a couple days ago and the
first time this was brought to the attention of FE about being force account work.
5 Meet with Will S. (Souza) and went over monthly quantities for pay estimate for June at 2 PM.
6 Schedule for the rest of the week is to continue to finish up structure ex and install crane mats for CJ to be able to access
footing. Also layout SW corner to figure out how far into the footing to the north the shoring was set to brace the exsiting WW
at the Davita property.
MANPOWER LOG 5 Workers | 40.0 Man Hours
No.Contact/
Company
Notes: Workers # Hours Man Hours Location
1 Souza Garrett Vanfleet-Carpenter Foreman
BI 22
1 8.0 8.0
2 Souza Clay Souza-Operator
BI 22
1 8.0 8.0
3 Souza Mylan Elder-Carpenter
BI 22
1 8.0 8.0
4 Souza Dana Missamore-Laborer
BI 22
Flagging
1 8.0 8.0
5 D. Cry Inc.Thomas Switzer-Operatore
BI 22
1 8.0 8.0
5 40.0
Filippin Engineering Page 1 of 4 Printed on 7/17/2020 at 12:16 PM PDT
EQUIPMENT LOG
No.Equipment Name Cost Code Hrs Operating Hrs Idle Inspected?Inspection Time Location
1 2500 Gmc Crew cab 8.0 No 01:15 PM
Notes:Souza
2 Cat 336 excavator 8.0 No 01:15 PM
Notes:Souza
3 Cat 336 excavator 8.0 No 01:15 PM
Notes:D.Crye
4 F450 Super Duty 8.0 No 01:15 PM
Notes:Souza
5 Doosan P185 Air
Compressor
8.0 No 01:15 PM
Notes:Souza
6 Skid Steer with Bucket 8.0 No 01:25 PM
Notes:Souza
OBSERVED WEATHER CONDITIONS
Weather Delay Sky Temp Average Precipitation Wind Ground/Sea Calamity
No
WEATHER REPORT
Temperature Precipitation Since Humidity Windspeed
Low High Avg Midnight 2 Days Ago 3 Days Ago Low Avg High Dew Avg Max Gust
54°F 76°F 64°F 0.00 in.0.01 in.0.03 in.48%69%93%53°F 5.0 mph 9 mph 14 mph
DAILY SNAPSHOT
06:00 AM 09:00 AM 12:00 PM 03:00 PM 06:00 PM 09:00 PM
clear-day
55°F
clear-day
65°F
clear-day
75°F
clear-day
75°F
clear-day
73°F
clear-night
61°F
Filippin Engineering Page 2 of 4 Printed on 7/17/2020 at 12:16 PM PDT
PHOTOS
FBCE900A-8AF2-4991-AA79-303D83DA0659.jpeg
32B33C59-573C-4055-A6BC-F75D5F382DDD.jpeg
D19D38F8-3CAC-4346-B4DE-59C075D4080B.jpeg
C5D01B44-2AC9-4569-B6EF-8ACCD43AA5B1.jpeg
10DEB063-02E5-49E0-BFB4-A7D93951FBFA.jpeg
2F0C67C0-D6F5-46DA-B226-218DE7EE45F5.jpeg
3127D296-361C-497E-A43A-87EB157640BE.jpeg
71529440-C4D2-4F79-A2BA-DEFF46A3E010.jpeg
Filippin Engineering Page 3 of 4 Printed on 7/17/2020 at 12:16 PM PDT
1AE047D8-465A-4948-883E-B99601BEBA30.jpeg
9617C453-F29E-4DDB-B610-A214A0029D1A.jpeg
2C25E58E-5270-4B62-B81C-953C5663F23A.jpeg
F5D5B872-6688-46C0-A0B9-FDB4BB5F8329.jpeg
877A8543-0A4C-4458-A704-FBCF89814445.jpeg
By Date Copies To
Filippin Engineering Page 4 of 4 Printed on 7/17/2020 at 12:16 PM PDT
Jerry Missamore 6/30/2020