HomeMy WebLinkAbout2020-07-06Filippin Engineering
354-D S. Fairview Ave.
Goleta, California 93117
P: (805) 845-4602
Project: 194501 - SLO Marsh Street Bridge
Replacement
919 Palm St.
San Luis Obispo, California 93401
P: 8057817200
Daily Log Inspection: Monday 7/6/2020
NOTES LOG
No.Comments
1 Souza and Condon Johnson on site at 7 AM. Souza laid out pile in abutment 2 footing. CJ doing 3 test holes to verify depth of
bedrock.
Jerry M. (FE) had conversation with Stewart S. (Souza) Jose Toual(CJ) about how the time was going to be quantified for the
extra 2.5' of drilling. Intial indication from CJ was that it would be 1 HR approx. for the day if CJ can get 8 a day.
Padre was on site to preform the environmental training for the new CJ crew members on site today.
2 Padre had Souza skimm the top of the baker tank off and remove all of what look to be plastic shavings from HDPE pipe that
was cut. Souza also changed the filters in the added filter out of the banker tank.
3 CJ drill rig broke down in the creek area. CJ working on getting rig up and running.
4 CJ got drill rig up and running at 10:30 AM drilled two test holes 3.18' feet to the west of pile 53 & 36. Pile 53 location bedrock
at 191.83 Pile 36 bedrock at 190.00'
Drilled hole between pile 51 & 52 hit bedrock at 184.72 . Between piles 70 & 74 drilled down 43.24' elevation 156.45' and was
unclear if bedrock was hit or if it was crumbly bed rock.
5 Souza had another failing test for truebudity. RFI was sent in to modify the dewatering system to allow Souza to discharge the
clear well points directly into a filter bag at the outlet of the diversion. Alyssa (Padre) spoke with waterboard and they were on
board with this ammendement to allow Souza to do this so the baker tanks get longer to settle out during the turbid times of
work.
MANPOWER LOG 12 Workers | 96.0 Man Hours
No.Contact/
Company
Notes: Workers # Hours Man Hours Location
1 Souza Garrett Vanfleet- Carpenter Foreman
BI 22/37
1 8.0 8.0
2 Souza Clay Souza-Operator
BI 22/37
1 8.0 8.0
3 Souza Dana Missamore-Laborer
BI 38/39
1 8.0 8.0
4 Souza Mike Kenutje-Carpenter Apprentice
BI 38/39
1 8.0 8.0
5 Condon Johnson Jose Toual-Operator Foreman
BI 37
1 8.0 8.0
6 Condon Johnson Francisco Toro-Laborer
BI 37
1 8.0 8.0
Filippin Engineering Page 1 of 3 Printed on 7/17/2020 at 12:20 PM PDT
MANPOWER LOG 12 Workers | 96.0 Man Hours
No.Contact/
Company
Notes: Workers # Hours Man Hours Location
7 Condon Johnson Juan Dones-Operator
BI 37
1 8.0 8.0
8 Condon Johnson Chris Cleary-Laborer
BI 37
1 8.0 8.0
9 Condon Johnson Charles Lee-Project Engineer
BI 37
1 8.0 8.0
10 Condon Johnson Eric Oliveros-Laborer
BI 37
1 8.0 8.0
11 Condon Johnson Jose Vasquez-Laborer
BI 37
1 8.0 8.0
12 Souza Mylan Elder-Laborer
BI 37
1 8.0 8.0
12 96.0
EQUIPMENT LOG
No.Equipment Name Cost Code Hrs Operating Hrs Idle Inspected?Inspection Time Location
1 2500 Gmc Crew cab No 01:15 PM
Notes:Souza
2 Cat 336 excavator No 01:15 PM
Notes:Souza
3 Cat 349 excavator No 01:15 PM
Notes:D.Crye
4 F250 crew truck No 01:15 PM
Notes:Condon Johnson
5 Gout Mixing/pump station No 01:15 PM
Notes:Condon Johnson
6 F450 Super Duty No 01:15 PM
Notes:Souza
7 Doosan P185 Air
Compressor
No 01:15 PM
Notes:Souza
8 F550 crew truck No 01:15 PM
Notes:Doizer saw cutting
9 F550 Utility Truck No 01:25 PM
Notes:Condon Johnson
10 Cat 308 Mini Excavator No 01:25 PM
Notes:Condon Johnson
Filippin Engineering Page 2 of 3 Printed on 7/17/2020 at 12:20 PM PDT
EQUIPMENT LOG
No.Equipment Name Cost Code Hrs Operating Hrs Idle Inspected?Inspection Time Location
11 Sullair 1150xh
aircompressor
No 01:25 PM
Notes:Condon Johnson
12 United rentals big generator No 01:25 PM
Notes:Condon Johnson
13 Ecco 512-36 JCB forklift No 01:25 PM
Notes:Condon Johnson
14 Skid Steer with Bucket No 01:25 PM
Notes:Souza
OBSERVED WEATHER CONDITIONS
Weather Delay Sky Temp Average Precipitation Wind Ground/Sea Calamity
No
WEATHER REPORT
Temperature Precipitation Since Humidity Windspeed
Low High Avg Midnight 2 Days Ago 3 Days Ago Low Avg High Dew Avg Max Gust
56°F 78°F 67°F 0.01 in.0.01 in.0.01 in.38%54%75%50°F 7.7 mph 12 mph 17 mph
DAILY SNAPSHOT
06:00 AM 09:00 AM 12:00 PM 03:00 PM 06:00 PM 09:00 PM
clear-day
58°F
clear-day
68°F
clear-day
75°F
clear-day
75°F
clear-day
78°F
clear-night
69°F
By Date Copies To
Filippin Engineering Page 3 of 3 Printed on 7/17/2020 at 12:20 PM PDT
Jerry Missamore 7/6/2020