HomeMy WebLinkAbout2020-07-07Filippin Engineering
354-D S. Fairview Ave.
Goleta, California 93117
P: (805) 845-4602
Project: 194501 - SLO Marsh Street Bridge
Replacement
919 Palm St.
San Luis Obispo, California 93401
P: 8057817200
Daily Log Inspection: Tuesday 7/7/2020
NOTES LOG
No.Comments
1 Souza and Condon Johnson on site at 7 AM. Souza was adjusting dewatering lines and cleaning out bottom of abutment 2
footing. Condon Johnson was prepping to start drilling pile at abutment 1 Pile #3
2 As drill rig was walking down to abutment 1 it shut down and was down for 2 hours before it was back up and running. Began
to dig for Pile #3 at 10:00 AM. Were drilled out to bond length elevation 164.90 by 10:30. Reason for starting at Pile #3 was
due to shoring for existing wing wall in the way.
3 Meet with Alyssa B. & Kenny W. (Padre) , Freddy (City of SLO) Jerry M. (FE) to discuss the new dewatering system and also
any other concerns the enviromentalist had. Adding more gravel bags to the upstream coffer dam was discussed as well as
the potential for the bank to fail new Abutment 2 RW when the footing and RSP is dug into place. Also disscused was needing
to add a shade cloth to the banker tanks so that the water in the tanks would bot exceed the 5 degree variance for the creek.
All concerns were talked about with Garrett V. (Souza Foreman)
4 Spoke to Lyle N. (City of SLo) about the pending RFI for the micropile positions near the sewer siphon as well and the #2 pile
that is being requested to become veritcal.
5 Condon Johnson started grouting at 3:30PM and finished up at 4:30. Ended up getting Pile # 3,5,7, & 11.
Total Depth of Pile #3 was 31.5'. Pile # 5 was 31.42'. Pile #7 was 32'. Pile #11 was 31.4'
6 Earthsystems was onsite for QC on Souza's side of work. Spoke with Garrett V. (Souza Foreman) about the rest of the
schedule for the week for QA and QC schedule.
7 Meet with Gino F. (FE) and went over site specific details about micro pile. Also other site specific details to get Gino filled in.
8 Total time tracked by Jerry M. (FE) for extra depth of 2' at 3 piles and 2.5' at one pile was 20 minuets over all. Extra work ticket
from CJ to follow
MANPOWER LOG 11 Workers | 88.0 Man Hours
No.Contact/
Company
Notes: Workers # Hours Man Hours Location
1 Souza Garrett Vanfleet- Carpenter Foreman
BI 22/37
1 8.0 8.0
2 Souza Clay Souza-Operator
BI 22/37
1 8.0 8.0
3 Souza Mike Kenutje-Carpenter Apprentice
BI 38/39
1 8.0 8.0
4 Condon Johnson Jose Toual-Operator Foreman
BI 37
1 8.0 8.0
5 Condon Johnson Francisco Toro-Laborer
BI 37
1 8.0 8.0
Filippin Engineering Page 1 of 11 Printed on 7/17/2020 at 12:20 PM PDT
MANPOWER LOG 11 Workers | 88.0 Man Hours
No.Contact/
Company
Notes: Workers # Hours Man Hours Location
6 Condon Johnson Juan Dones-Operator
BI 37
1 8.0 8.0
7 Condon Johnson Chris Cleary-Laborer
BI 37
1 8.0 8.0
8 Condon Johnson Charles Lee-Project Engineer
BI 37
1 8.0 8.0
9 Condon Johnson Eric Oliveros-Laborer
BI 37
1 8.0 8.0
10 Condon Johnson Jose Vasquez-Laborer
BI 37
1 8.0 8.0
11 Souza Mylan Elder-Laborer
BI 37
1 8.0 8.0
11 88.0
EQUIPMENT LOG
No.Equipment Name Cost Code Hrs Operating Hrs Idle Inspected?Inspection Time Location
1 2500 Gmc Crew cab No 01:15 PM
Notes:Souza
2 Cat 336 excavator No 01:15 PM
Notes:Souza
3 Cat 349 excavator No 01:15 PM
Notes:D.Crye
4 F250 crew truck No 01:15 PM
Notes:Condon Johnson
5 Gout Mixing/pump station No 01:15 PM
Notes:Condon Johnson
6 F450 Super Duty No 01:15 PM
Notes:Souza
7 Doosan P185 Air
Compressor
No 01:15 PM
Notes:Souza
8 F550 crew truck No 01:15 PM
Notes:Doizer saw cutting
9 F550 Utility Truck No 01:25 PM
Notes:Condon Johnson
10 Cat 308 Mini Excavator No 01:25 PM
Notes:Condon Johnson
Filippin Engineering Page 2 of 11 Printed on 7/17/2020 at 12:20 PM PDT
EQUIPMENT LOG
No.Equipment Name Cost Code Hrs Operating Hrs Idle Inspected?Inspection Time Location
11 Sullair 1150xh
aircompressor
No 01:25 PM
Notes:Condon Johnson
12 United rentals big generator No 01:25 PM
Notes:Condon Johnson
13 Ecco 512-36 JCB forklift No 01:25 PM
Notes:Condon Johnson
14 Skid Steer with Bucket No 01:25 PM
Notes:Souza
OBSERVED WEATHER CONDITIONS
Weather Delay Sky Temp Average Precipitation Wind Ground/Sea Calamity
No
WEATHER REPORT
Temperature Precipitation Since Humidity Windspeed
Low High Avg Midnight 2 Days Ago 3 Days Ago Low Avg High Dew Avg Max Gust
51°F 75°F 63°F 0.01 in.0.01 in.0.01 in.42%61%87%49°F 6.3 mph 12 mph 15 mph
DAILY SNAPSHOT
06:00 AM 09:00 AM 12:00 PM 03:00 PM 06:00 PM 09:00 PM
clear-day
51°F
clear-day
66°F
clear-day
75°F
clear-day
75°F
clear-day
69°F
clear-night
61°F
PHOTOS
0A1B545B-B5C6-405D-A812-72CBDB85CA5D.jpeg FDC24646-223D-4E0C-A1FD-FD22971AA386.jpeg
Filippin Engineering Page 3 of 11 Printed on 7/17/2020 at 12:20 PM PDT
6BE64986-9B04-4336-9EE3-8D1D6B1218CA.jpeg
194C4B93-E11D-47BC-BF30-12A0E88401AC.jpeg
26BA5C51-5F91-4A59-BF36-1076E7017E69.jpeg
042DAD87-D751-428F-AFE1-4CF3D64FC0FE.jpeg
262AF019-78E5-430D-A75E-FCC0580F43C6.jpeg
382AD79D-DE8D-4D36-9F29-691D23712EDB.jpeg
65D185B6-DCCF-4AAF-A79E-5931D93C7D01.jpeg
149A21F7-0D58-426E-B009-BAAF570AEBE3.jpeg
Filippin Engineering Page 4 of 11 Printed on 7/17/2020 at 12:20 PM PDT
13F4C0ED-AD69-4B67-BB47-ACAE81E8073F.jpeg
D7DA9562-33F3-411B-8F21-D540B709E87C.jpeg
6351D6F4-2AB7-4CE6-9BA1-14B57B3E4C36.jpeg
6F8B8869-532B-47C0-A303-90A7A92E82D0.jpeg
2F357206-118D-48CC-887E-3EF00527D581.jpeg
F9242B0E-127D-4BA1-AFB2-EC0456B08F26.jpeg
AD8BDD92-58CA-48F1-B425-C19EF5D5ED0F.jpeg
AA0B16D0-4FB7-424F-B966-DB0C87DE485A.jpeg
Filippin Engineering Page 5 of 11 Printed on 7/17/2020 at 12:20 PM PDT
64BB5EB0-0EF4-4D71-A265-1BA37D974723.jpeg
6B97806E-EBAF-4D75-B21B-C9FF3B3C598D.jpeg
C1DD5345-A1FB-4419-9F89-1E7D02E483C7.jpeg
526B9369-4AB8-48E1-A586-AC8C5F11302E.jpeg
2D06EFD6-687C-4AEB-B1EE-7402906DD5B4.jpeg
BEAC0BAC-9230-4207-A295-AD9EB1E71CA2.jpeg
5C55AD66-AEA3-4215-9541-AD4E9268917E.jpeg
F88CDF4B-A56A-4C09-BC8F-D186659D6823.jpeg
Filippin Engineering Page 6 of 11 Printed on 7/17/2020 at 12:20 PM PDT
6F5A6791-2513-4985-A85A-FC522B6295BF.jpeg
E22F4872-AF32-4C22-8230-699E3870C4C3.jpeg
2DD91916-7DCD-4656-B94D-06B3EEACE5A8.jpeg
30EBA229-1A95-424F-BEEA-88085DAFC207.jpeg
5B9D67EF-30E9-453D-85A9-AB5DABFD7F37.jpeg
1FA8BC12-BE60-42B9-92D7-8A5B1E8C454C.jpeg
A949B072-89FF-4063-A29D-E4F0D8533C9E.jpeg
3239CF22-A4B0-4B6D-ADBE-2D2812880C86.jpeg
Filippin Engineering Page 7 of 11 Printed on 7/17/2020 at 12:20 PM PDT
E1961438-2395-425B-AB21-8354E9BAC142.jpeg
B057EE91-C9BA-4763-BB07-7D77304984C6.jpeg
5128596F-FBD2-41EA-9819-C2859FA2B9E4.jpeg
6576E82C-1A7A-411E-85EC-1DCC95CD5D8D.jpeg
3FCDB3F7-4683-422A-B9FD-FD7BB7ABA827.jpeg
A4519173-8F04-4B98-A881-1638321E38DD.jpeg
4C11844C-33C1-4270-8766-5FF1135AAE85.jpeg
A5706D02-B5BB-48E6-93BA-A550CB183EFF.jpeg
Filippin Engineering Page 8 of 11 Printed on 7/17/2020 at 12:20 PM PDT
540FB02B-21F6-4382-81FF-3E8FC1EE437F.jpeg
B75B4D91-6141-4819-A118-0D68EBECF3B7.jpeg
558032EA-3226-4F82-905B-0C716977D833.jpeg
41906DBD-E323-4EF3-8932-46FC7B418144.jpeg
43E27CE7-A7E0-4323-83CF-38BC759AFC0C.jpeg
507C2303-2B39-4FC4-981E-2F004E26E054.jpeg
00C83234-04BA-4F63-A735-8F6D64D06798.jpeg
86F6D1E1-9181-48A9-9404-80F114E6EBBF.jpeg
Filippin Engineering Page 9 of 11 Printed on 7/17/2020 at 12:20 PM PDT
5338F9A3-9068-4D12-9C56-A157CAABCE83.jpeg
A895735F-AF88-4C66-8BA6-D7E17F6867DC.jpeg
8E005DBA-18C4-4A4A-8557-766842AA03A5.jpeg
D81826AE-B55F-4BDF-9CC9-000D9C68CE5A.jpeg
06E76AE8-99D6-4B90-BCCB-F9637C6D8D55.jpeg
97B050A4-B720-4DD1-A617-505240820F53.jpeg
BC9239C8-8383-48B6-B91B-93FCBFCCB291.jpeg
1D53E30E-38A4-4BFE-9126-1D092B34DB9C.jpeg
Filippin Engineering Page 10 of 11 Printed on 7/17/2020 at 12:20 PM PDT
BE42FC51-BD84-43D3-8CC0-AD07C4808998.jpeg
ED856C67-8681-4A32-90EC-30592601BB9D.jpeg
68099474-F261-4BE8-B896-1E51CED995D6.jpeg
By Date Copies To
Filippin Engineering Page 11 of 11 Printed on 7/17/2020 at 12:20 PM PDT
Jerry Missamore 7/7/2020