Daily Log Inspection: Thursday 7/9/2020
NOTES LOG
No.Comments
1 Souza and Condon Johnson onsite at 7 AM. Condon Johnson continued on abutment 1 piles. Drilled and grouted piles
10,13,20,22,24,24,31. Condon Johnson came up with two extra work tickets dated 7/7 and 7/8. For the added lengths of micro
pile in abutment 1. Total added length to date is 19.33'.
2 Weekly meeting was held to discuss look ahead schedule, enviro issues and public coordination.
Souza indicated that approx. 2 weeks footing for abutment 1 would be poured.
3 Spoke with Garrett V. (Souza) and Jose T. (CJ) about testing schedule for next week and reminded Souza that testing had to
be done.
MANPOWER LOG 11 Workers | 88.0 Man Hours
No.Contact/
Company
Notes: Workers # Hours Man Hours Location
1 Souza Garrett Vanfleet- Carpenter Foreman
BI 22/37
1 8.0 8.0
2 Souza Clay Souza-Operator
BI 22/37
1 8.0 8.0
3 Souza Mike Kenutje-Carpenter Apprentice
BI 38/39
1 8.0 8.0
4 Condon Johnson Jose Toual-Operator Foreman
BI 37
1 8.0 8.0
5 Condon Johnson Francisco Toro-Laborer
BI 37
1 8.0 8.0
6 Condon Johnson Juan Dones-Operator
BI 37
1 8.0 8.0
7 Condon Johnson Chris Cleary-Laborer
BI 37
1 8.0 8.0
8 Condon Johnson Charles Lee-Project Engineer
BI 37
1 8.0 8.0
9 Condon Johnson Eric Oliveros-Laborer
BI 37
1 8.0 8.0
Filippin Engineering Page 1 of 3 Printed on 7/17/2020 at 12:20 PM PDT
MANPOWER LOG 11 Workers | 88.0 Man Hours
No.Contact/
Company
Notes: Workers # Hours Man Hours Location
10 Condon Johnson Jose Vasquez-Laborer
BI 37
1 8.0 8.0
11 Souza Mylan Elder-Laborer
BI 37
1 8.0 8.0
11 88.0
EQUIPMENT LOG
No.Equipment Name Cost Code Hrs Operating Hrs Idle Inspected?Inspection Time Location
1 2500 Gmc Crew cab No 01:15 PM
Notes:Souza
2 Cat 336 excavator No 01:15 PM
Notes:Souza
3 Cat 349 excavator No 01:15 PM
Notes:D.Crye
4 F250 crew truck No 01:15 PM
Notes:Condon Johnson
5 Gout Mixing/pump station No 01:15 PM
Notes:Condon Johnson
6 F450 Super Duty No 01:15 PM
Notes:Souza
7 Doosan P185 Air
Compressor
No 01:15 PM
Notes:Souza
8 F550 crew truck No 01:15 PM
Notes:Doizer saw cutting
9 F550 Utility Truck No 01:25 PM
Notes:Condon Johnson
10 Cat 308 Mini Excavator No 01:25 PM
Notes:Condon Johnson
11 Sullair 1150xh
aircompressor
No 01:25 PM
Notes:Condon Johnson
12 United rentals big generator No 01:25 PM
Notes:Condon Johnson
13 Ecco 512-36 JCB forklift No 01:25 PM
Notes:Condon Johnson
14 Skid Steer with Bucket No 01:25 PM
Notes:Souza
Filippin Engineering Page 2 of 3 Printed on 7/17/2020 at 12:20 PM PDT
OBSERVED WEATHER CONDITIONS
Weather Delay Sky Temp Average Precipitation Wind Ground/Sea Calamity
No
WEATHER REPORT
Temperature Precipitation Since Humidity Windspeed
Low High Avg Midnight 2 Days Ago 3 Days Ago Low Avg High Dew Avg Max Gust
52°F 74°F 62°F 0.01 in.0.01 in.0.02 in.47%68%91%51°F 3.9 mph 7 mph 11 mph
DAILY SNAPSHOT
06:00 AM 09:00 AM 12:00 PM 03:00 PM 06:00 PM 09:00 PM
partly-cloudy-night
54°F
partly-cloudy-day
59°F
clear-day
72°F
clear-day
74°F
clear-day
70°F
clear-night
62°F
By Date Copies To
Filippin Engineering Page 3 of 3 Printed on 7/17/2020 at 12:20 PM PDT
Jerry Missamore 7/9/2020