Loading...
HomeMy WebLinkAbout2020-07-10Filippin Engineering 354-D S. Fairview Ave. Goleta, California 93117 P: (805) 845-4602 Project: 194501 - SLO Marsh Street Bridge Replacement  919 Palm St. San Luis Obispo, California 93401 P: 8057817200 Daily Log Inspection: Friday 7/10/2020      NOTES LOG   No.Comments   1 Souza and Condon Johnson on site at 7 AM. CJ continue on Abutment 1 micro pile. CJ turned the drill around this morning to get the north side of abutment 1.   2 Souza added gravel bags to the upstream coffer dam and also got abutment 2 ready for CJ to walk on the pads for micro pile to jump every other pile.   3 Kenny W. was onsite to observe the placement of the gravel bags at the upstream coffer dam.  4 Meet with Steve. S. (Souza) onsite and went over pile 1 location and shoring that was in place for the bracing of the existing wing wall. Discussed different options if indeed Pile #1 had to be installed. Discussed how the wall could be braced and maybe pull the first pile closet to the existing wall if need be. Possibly moving pile #1 and leaving the shoring in place and re configuring the footing along with new wing wall.   5 As of 11:30 piles # 34,32,30,28 had been drilled to 20' embedment length. Elevation running about 188.00 to 189.25 in depth. Still lower than the boring log of 190.00. Not the assumed 2.5' by CJ in the beginning of the process after the verification piles.   6 Bedrock depths at pile are as follows Pile # 34-189.90, Pile #30-189.1, Pile # 28-188.00, Pile #25-189.40, Pile #17-188.73, Pile #15-188, Pile #9-187.65 These elevations are based on FE measurements in the field.   7 Post grout on the following piles: 13, 14, 29, 31.     MANPOWER LOG 11 Workers  |   88.0 Man Hours  No.Contact/ Company Notes: Workers # Hours Man Hours Location   1 Souza Garrett Vanfleet- Carpenter Foreman BI 22/37   1 8.0 8.0       2 Souza Clay Souza-Operator BI 22/37   1 8.0 8.0       3 Souza Mike Kenutje-Carpenter Apprentice BI 38/39   1 8.0 8.0       4 Condon Johnson Jose Toual-Operator Foreman BI 37   1 8.0 8.0       5 Condon Johnson Francisco Toro-Laborer BI 37   1 8.0 8.0       6 Condon Johnson Juan Dones-Operator BI 37   1 8.0 8.0       7 Condon Johnson Chris Cleary-Laborer BI 37   1 8.0 8.0         Filippin Engineering Page 1 of 3 Printed on 7/17/2020 at 12:20 PM PDT       MANPOWER LOG 11 Workers  |   88.0 Man Hours  No.Contact/ Company Notes: Workers # Hours Man Hours Location   8 Condon Johnson Charles Lee-Project Engineer BI 37   1 8.0 8.0       9 Condon Johnson Eric Oliveros-Laborer BI 37   1 8.0 8.0       10 Condon Johnson Jose Vasquez-Laborer BI 37   1 8.0 8.0       11 Souza Mylan Elder-Laborer BI 37   1 8.0 8.0          11  88.0      EQUIPMENT LOG No.Equipment Name Cost Code Hrs Operating Hrs Idle Inspected?Inspection Time Location   1 2500 Gmc Crew cab No   01:15 PM    Notes:Souza  2 Cat 336 excavator No   01:15 PM    Notes:Souza  3 Cat 349 excavator No   01:15 PM    Notes:D.Crye  4 F250 crew truck No   01:15 PM    Notes:Condon Johnson  5 Gout Mixing/pump station No   01:15 PM    Notes:Condon Johnson  6 F450 Super Duty No   01:15 PM    Notes:Souza  7 Doosan P185 Air Compressor No   01:15 PM    Notes:Souza  8 F550 crew truck No   01:15 PM    Notes:Doizer saw cutting  9 F550 Utility Truck No   01:25 PM    Notes:Condon Johnson  10 Cat 308 Mini Excavator No   01:25 PM    Notes:Condon Johnson  11 Sullair 1150xh aircompressor No   01:25 PM    Notes:Condon Johnson  12 United rentals big generator No   01:25 PM    Notes:Condon Johnson    Filippin Engineering Page 2 of 3 Printed on 7/17/2020 at 12:20 PM PDT      EQUIPMENT LOG No.Equipment Name Cost Code Hrs Operating Hrs Idle Inspected?Inspection Time Location   13 Ecco 512-36 JCB forklift No   01:25 PM    Notes:Condon Johnson  14 Skid Steer with Bucket No   01:25 PM    Notes:Souza    OBSERVED WEATHER CONDITIONS Weather Delay Sky Temp Average Precipitation Wind Ground/Sea Calamity   No        WEATHER REPORT Temperature Precipitation Since Humidity Windspeed Low High Avg Midnight 2 Days Ago 3 Days Ago Low Avg High Dew Avg Max Gust 55°F 79°F 67°F 0.00 in.0.01 in.0.02 in.42%66%91%54°F 4.0 mph 6 mph 10 mph   DAILY SNAPSHOT 06:00 AM 09:00 AM 12:00 PM 03:00 PM 06:00 PM 09:00 PM partly-cloudy-night   57°F clear-day   68°F clear-day   79°F clear-day   79°F clear-day   76°F clear-night   65°F     By  Date  Copies To     Filippin Engineering Page 3 of 3 Printed on 7/17/2020 at 12:20 PM PDT        Jerry Missamore 7/10/2020