Project: 194501 - SLO Marsh Street Bridge
Replacement
919 Palm St.
San Luis Obispo, California 93401
P: 8057817200
Daily Log Inspection: Friday 7/17/2020
NOTES LOG
No.Comments
1 Souza and Condon Johnson onsite at 7 AM to preform proof test on production pile #8. Souza prepping abutment 2 side for
Condon Johnson to begin drilling.
2 Condon Johnson preformed test on Pile #8 at 9 AM. Test was completed by 9:30 and passed the acceptable load test. The
fluctuation between kips was less than the specs called out for 1-2 difference.
3 Went over extra work tickets with Lyle N. (CIty of Slo) also got them organized.
4 Condon Johnson done testing Pile #28 at 11 AM. CJ was moving testing material to pile #34 in preparing for test on Monday
7/20. All work is contract work as testing is a required step in the micro pile installation.
5 Sewer Siphon on the on abutment 2 side appears to be in the footing for approx. 1' for 3'2'' from back edge of footing.
6 15.5’ of ESA fence installed.
7 Went over water stop areas in the plans with Ethan S. (Souza) over the phone and led him to the Caltrans Standard plans for
details.
8 Condon Johnson has couplers and material onsite to start at abutment 2 micro pile. Questioned was posed to Will S. (Souza)
about getting started with material onsite and no answer was given back.
MANPOWER LOG 10 Workers | 80.0 Man Hours
No.Contact/
Company
Notes: Workers # Hours Man Hours Location
1 Souza Garrett Vanfleet- Carpenter Foreman
BI 22/37
1 8.0 8.0
2 Souza Mike Kenutje-Carpenter Apprentice
BI 38/39
1 8.0 8.0
3 Condon Johnson Jose Toual-Operator Foreman
BI 37
1 8.0 8.0
4 Condon Johnson Francisco Toro-Laborer
BI 37
1 8.0 8.0
5 Condon Johnson Juan Dones-Operator
BI 37
1 8.0 8.0
6 Condon Johnson Chris Cleary-Laborer
BI 37
1 8.0 8.0
7 Condon Johnson Charles Lee-Project Engineer
BI 37
1 8.0 8.0
Filippin Engineering Page 1 of 3 Printed on 7/23/2020 at 12:46 PM PDT
MANPOWER LOG 10 Workers | 80.0 Man Hours
No.Contact/
Company
Notes: Workers # Hours Man Hours Location
8 Condon Johnson Eric Oliveros-Laborer
BI 37
1 8.0 8.0
9 Condon Johnson Jose Vasquez-Laborer
BI 37
1 8.0 8.0
10 Souza Mylan Elder-Laborer
BI 37
1 8.0 8.0
10 80.0
EQUIPMENT LOG
No.Equipment Name Cost Code Hrs Operating Hrs Idle Inspected?Inspection Time Location
1 2500 Gmc Crew cab No 01:15 PM
Notes:Souza
2 Cat 336 excavator No 01:15 PM
Notes:Souza
3 Cat 349 excavator No 01:15 PM
Notes:D.Crye
4 F250 crew truck No 01:15 PM
Notes:Condon Johnson
5 Gout Mixing/pump station No 01:15 PM
Notes:Condon Johnson
6 F450 Super Duty No 01:15 PM
Notes:Souza
7 Doosan P185 Air
Compressor
No 01:15 PM
Notes:Souza
8 F550 crew truck No 01:15 PM
Notes:Doizer saw cutting
9 F550 Utility Truck No 01:25 PM
Notes:Condon Johnson
10 Cat 308 Mini Excavator No 01:25 PM
Notes:Condon Johnson
11 Sullair 1150xh
aircompressor
No 01:25 PM
Notes:Condon Johnson
12 United rentals big generator No 01:25 PM
Notes:Condon Johnson
13 Ecco 512-36 JCB forklift No 01:25 PM
Notes:Condon Johnson
Filippin Engineering Page 2 of 3 Printed on 7/23/2020 at 12:46 PM PDT
EQUIPMENT LOG
No.Equipment Name Cost Code Hrs Operating Hrs Idle Inspected?Inspection Time Location
14 Skid Steer with Bucket No 01:25 PM
Notes:Souza
OBSERVED WEATHER CONDITIONS
Weather Delay Sky Temp Average Precipitation Wind Ground/Sea Calamity
No
WEATHER REPORT
Temperature Precipitation Since Humidity Windspeed
Low High Avg Midnight 2 Days Ago 3 Days Ago Low Avg High Dew Avg Max Gust
55°F 69°F 61°F 0.00 in.0.00 in.0.01 in.67%80%93%55°F 4.3 mph 7 mph 12 mph
DAILY SNAPSHOT
06:00 AM 09:00 AM 12:00 PM 03:00 PM 06:00 PM 09:00 PM
partly-cloudy-night
58°F
partly-cloudy-day
60°F
clear-day
69°F
clear-day
70°F
clear-day
66°F
partly-cloudy-night
60°F
By Date Copies To
Filippin Engineering Page 3 of 3 Printed on 7/23/2020 at 12:46 PM PDT
Jerry Missamore 7/17/2020