HomeMy WebLinkAbout2020-07-24Filippin Engineering
354-D S. Fairview Ave.
Goleta, California 93117
P: (805) 845-4602
Project: 194501 - SLO Marsh Street Bridge
Replacement
919 Palm St.
San Luis Obispo, California 93401
P: 8057817200
Daily Log Inspection: Friday 7/24/2020
NOTES LOG
No.Comments
1 Souza and Condon Johnson onsite at 7AM. Condon Johnson continued on abutment #2 micro pile.
Souza cleaning up around abutment 1 footing and tiding up site.
Jerry M.(FE) spoke with Steve S. (Souza) about the added steel in the SW corner that needs to be added with moving of the
micro pile the existing wing wall batter and the shoring layout that is in the corner. Steve said no additional costs from Souza if
Souza was paid in full for the concrete in that footing. Steve was also indicated that he was only going to pass through sub
related extra costs that were presented to Souza. Jerry M. (FE) relayed all information to Gino F. (FE).
2 CJ only had six couplers to start the day, so Earthsystems was bumped up to 12:30 PM for the start of grouting.
Delivery of couplers to finish out abutment 2 was scheduled for 1 PM today but CJ was uncertain if the couplers would arrive
on time.
3 Souza brought back up generator to site to help run pumps. The original turned off on its own at lunch time and caused site to
fill with water.
Appears CJ will be grouting abutment 1 pile on Monday and Iron workers on Tuesday as of now. No response from
Earthsystems or Dokken.
4 Earthsystems onsite at 12:30 PM to preform QA on grouting of the micro pile for FE
5 Six piles installed today with 6.5' over all delta for added length through the six piles.
6 Shade cloth was added to outer most baker tank to help with temp of the water.
MANPOWER LOG 10 Workers | 72.0 Man Hours
No.Contact/
Company
Notes: Workers # Hours Man Hours Location
1 Souza Garrett Vanfleet- Carpenter Foreman
BI 37
1 8.0 8.0
2 Souza Clay Souza-Operator
BI 37
1 4.0 4.0
3 Condon Johnson Jose Toual-Operator Foreman
BI 37
1 8.0 8.0
4 Condon Johnson Francisco Toro-Laborer
BI 37
1 8.0 8.0
5 Condon Johnson Juan Dones-Operator
BI 37
1 8.0 8.0
Filippin Engineering Page 1 of 3 Printed on 10/16/2020 at 12:07 PM PDT
MANPOWER LOG 10 Workers | 72.0 Man Hours
No.Contact/
Company
Notes: Workers # Hours Man Hours Location
6 Condon Johnson Chris Cleary-Laborer
BI 37
1 8.0 8.0
7 Condon Johnson Charles Lee-Project Engineer
BI 37
1 8.0 8.0
8 Condon Johnson Eric Oliveros-Laborer
BI 37
1 8.0 8.0
9 Condon Johnson Jose Vasquez-Laborer
BI 37
1 8.0 8.0
10 Souza Mylan Elder- Apprentice Carpenter
BI 37/38
1 4.0 4.0
10 72.0
EQUIPMENT LOG
No.Equipment Name Cost Code Hrs Operating Hrs Idle Inspected?Inspection Time Location
1 2500 Gmc Crew cab No 01:15 PM
Notes:Souza
2 Cat 336 excavator No 01:15 PM
Notes:Souza
3 Cat 349 excavator No 01:15 PM
Notes:D.Crye
4 F250 crew truck No 01:15 PM
Notes:Condon Johnson
5 Gout Mixing/pump station No 01:15 PM
Notes:Condon Johnson
6 F450 Super Duty No 01:15 PM
Notes:Souza
7 Doosan P185 Air
Compressor
No 01:15 PM
Notes:Souza
8 F550 Utility Truck No 01:25 PM
Notes:Condon Johnson
9 Cat 308 Mini Excavator No 01:25 PM
Notes:Condon Johnson
10 Sullair 1150xh
aircompressor
No 01:25 PM
Notes:Condon Johnson
Filippin Engineering Page 2 of 3 Printed on 10/16/2020 at 12:07 PM PDT
EQUIPMENT LOG
No.Equipment Name Cost Code Hrs Operating Hrs Idle Inspected?Inspection Time Location
11 United rentals big generator No 01:25 PM
Notes:Condon Johnson
12 Ecco 512-36 JCB forklift No 01:25 PM
Notes:Condon Johnson
13 Skid Steer with Bucket No 01:25 PM
Notes:Souza
14 Caterpillar Reachlift No 01:45 AM
Notes:Souza
OBSERVED WEATHER CONDITIONS
Weather Delay Sky Temp Average Precipitation Wind Ground/Sea Calamity
No
WEATHER REPORT
Temperature Precipitation Since Humidity Windspeed
Low High Avg Midnight 2 Days Ago 3 Days Ago Low Avg High Dew Avg Max Gust
53°F 71°F 62°F 0.01 in.0.02 in.0.02 in.63%82%100%56°F 4.8 mph 8 mph 13 mph
DAILY SNAPSHOT
06:00 AM 09:00 AM 12:00 PM 03:00 PM 06:00 PM 09:00 PM
partly-cloudy-night
54°F
partly-cloudy-day
60°F
clear-day
70°F
clear-day
71°F
clear-day
70°F
clear-night
61°F
By Date Copies To
Filippin Engineering Page 3 of 3 Printed on 10/16/2020 at 12:07 PM PDT
Jerry Missamore 7/24/2020