354-D S. Fairview Ave.
Goleta, California 93117
P: (805) 845-4602
Project: 194501 - SLO Marsh Street Bridge
Replacement
919 Palm St.
San Luis Obispo, California 93401
P: 8057817200
Daily Log Inspection: Friday 8/21/2020
NOTES LOG
No.Comments
1 Souza 7-man crew worked on AB1 placing whalers and double-2"x4" horizontal support for south form spaced approximately
12" spacing. Top support follows cross slope of road; spacing about 4'. Also observed 26 EA struts holding AB1 at about 11'
above footing and just below top support. Laborer cleaning up tie wire at footing interface. 3 EA weepholes placed along AB1
at 51", 64", 56"(east-west). Rebar not complete near east side where diagonal bars. Reminded Garrett to install 3" weephole at
15' centers along top of footing per Std. Spec. 51-1.03E(7) for hydrostatic pressure relief. Crews trying to figure falsework
anchors--plans just received. Souza may core after PCC pour?? Observed LBR changing filter bag on downstream dewater
discharge pipe. Indicated sample tested by biologist and required changing--occurs approximately weekly. Weephole rebar not
complete at this time. Observed 12 EA struts supporting AB2 wall toward channel. Observed 12 EA supports(2-2"x8") holding
AB1 rebar legs spaced approximately 8' apart.
2 PSG 4-man crew working on AB2 rebar. Placed 61 EA #9 vertical bars at 6" spacing in 30' section with 17 EA #5 horizontal
bars at 12" spacing. Two chair spacer rows holding 24" apart, placed at 4' from top and 11' from top. Not complete rebar tie.
3 On-site meeting with SoCal Gas at 9am to coordinate sleeve installation and schedule work by utility company. Attendees
include: Claudia Turner, David Cox, Gino Filippin, Jeff Payne, Will Stoudenmire, Garrett VanFleet, Stuart Souza, Lyle Nemeth.
SoCal Gas will have Souza install sleeve and arrange payment between 2 parties. The City agrees to use 10" diameter sleeve;
SDR-35 or PVC Schedule 40 acceptable. SoCal Gas requested 1-2 week notice prior to performing work. Souza indicated
sleeve should be on-site by 9/16/20. Lyle, City of SLO, indicated the other utilities will be responsible for sleeve and Souza will
provide pricing. All parties agreed to have Souza take lead on installation of sleeve for schedule purposes.
MANPOWER LOG 14 Workers | 112.0 Man Hours
No.Contact/
Company
Notes: Workers # Hours Man Hours Location
1 Souza Garrett Vanfleet- Carpenter Foreman
BI 39
1 8.0 8.0
2 Souza Clay Souza-Operator
BI 39
1 8.0 8.0
3 Souza Mylan Elder- Apprentice Carpenter
BI 39
1 8.0 8.0
4 Souza Steve Helenberg-Carpenter
BI 39
1 8.0 8.0
5 Souza Mark Missamore-Carpenter Foreman
BI 39
1 8.0 8.0
6 Pacific Steel Group Tyler Hintz- Ironworker
BI43
1 8.0 8.0
7 Pacific Steel Group John Hamilton-Foreman ironworker
BI 43
1 8.0 8.0
Filippin Engineering Page 1 of 4 Printed on 10/22/2020 at 08:38 AM PDT
MANPOWER LOG 14 Workers | 112.0 Man Hours
No.Contact/
Company
Notes: Workers # Hours Man Hours Location
8 Pacific Steel Group James Hintz- Iron Worker
BI 43
1 8.0 8.0
9 Pacific Steel Group Kyle Macintosh- Iron worker
BI 43
1 8.0 8.0
10 Pacific Steel Group Kieth Matthews- iron worker Foreman
BI 43
1 8.0 8.0
11 Souza Dana Missamore-LBR
BI 39
1 8.0 8.0
12 Souza Mike Kountche-CARP Apprentice
BI 39
1 8.0 8.0
13 Pacific Steel Group Jesus Garcia-Iron Worker
BI 43
1 8.0 8.0
14 Pacific Steel Group Prospero Salvedra-Iron Worker
BI 43
1 8.0 8.0
14 112.0
EQUIPMENT LOG
No.Equipment Name Cost Code Hrs Operating Hrs Idle Inspected?Inspection Time Location
1 2500 Gmc Crew cab No 08:00 AM
Notes:Souza
2 Cat 336 excavator No 08:00 AM
Notes:Souza
3 F450 Super Duty No 08:00 AM
Notes:Souza
4 Caterpillar Reachlift No 08:00 AM
Notes:Souza
5 3500 GMC crew truck No 08:00 AM
Notes:Souza
6 Cat 336 Long Reach
Excavator
No 08:00 AM
Notes:D. Crye
7 Cat 308 Mini Excavator No 08:00 AM
Notes:Souza
8 2500 Gmc Crew cab No 08:00 AM
Notes:Souza
Filippin Engineering Page 2 of 4 Printed on 10/22/2020 at 08:38 AM PDT
EQUIPMENT LOG
No.Equipment Name Cost Code Hrs Operating Hrs Idle Inspected?Inspection Time Location
9 305 Cat Mini Excavator No 08:00 AM
Notes:Souza
10 Doosan P185 Air
Compressor
No 08:00 AM
Notes:Souza
11 2500 GMC flatbed No 08:00 AM
Notes:PSG
12 Big Tex trailer No 08:00 AM
Notes:Souza
13 Rental Man Lift United
Rentals
No 08:00 AM
Notes:Souza
14 Sciiscor lift United Rentals No 08:00 AM
Notes:Souza
VISITOR LOG
No.Visitor Start Time End Time Details
1 Makayla Hoffman(Padre)07:00 AM 07:30 AM Performed water quality inspection. Conducted
environmental training for new PSG employees.
2 Dominque(Souza)07:00 AM 07:05 AM Provided as-built drawing information for sanitary sewer
system recently installed.
3 Claudia Turner-SoCal Gas 09:00 AM 09:45 AM Coordination meeting with SoCal Gas and Souza for sleeve
installation and schedule work.
4 David Cox-ARB 09:00 AM 09:45 AM SoCal Gas representative for coordination meeting with
Souza.
OBSERVED WEATHER CONDITIONS
Weather Delay Sky Temp Average Precipitation Wind Ground/Sea Calamity
No Smoke Hot 84 None Light Wind
WEATHER REPORT
Temperature Precipitation Since Humidity Windspeed
Low High Avg Midnight 2 Days Ago 3 Days Ago Low Avg High Dew Avg Max Gust
59°F 85°F 71°F 0.01 in.0.02 in.0.02 in.35%56%78%54°F 4.9 mph 7 mph 12 mph
DAILY SNAPSHOT
06:00 AM 09:00 AM 12:00 PM 03:00 PM 06:00 PM 09:00 PM
clear-night
59°F
clear-day
67°F
clear-day
82°F
partly-cloudy-day
85°F
partly-cloudy-day
81°F
partly-cloudy-night
74°F
Filippin Engineering Page 3 of 4 Printed on 10/22/2020 at 08:38 AM PDT
By Date Copies To
Filippin Engineering Page 4 of 4 Printed on 10/22/2020 at 08:38 AM PDT
Jeff Payne 8/21/2020