HomeMy WebLinkAbout2020-08-25Filippin Engineering
354-D S. Fairview Ave.
Goleta, California 93117
P: (805) 845-4602
Project: 194501 - SLO Marsh Street Bridge
Replacement
919 Palm St.
San Luis Obispo, California 93401
P: 8057817200
Daily Log Inspection: Tuesday 8/25/2020
NOTES LOG
No.Comments
1 Souza on site at 7 AM gearing up to set front panels at abutment #1. Souza installed the 3'' weep holes at the bottom of the
abutment 1 before the front panels where placed.
2 PSG on site installed wing wall rebar at both left and right WW at abutment #1. Continued erecting abutment 2 steel.
3 Preformed Daily visual inspection of dewatering and creek area.
Spoke with Rosa and Lyle and about the edge of deck line up at the Davitia connection and what the options were. Lyle, Rosa,
and myself agreed that keeping the bridge deck independent of the overhang was the right thing to due incase of down the
road repairs needed to either structure. Pulling a straight line or steeping in at that location was good with Rosa.
4 Looked at submitted bracing plan from Souza. At first glance seemed ok but was going to dig into further after a field review
with the plans.
5 Rescheduled Earthsystems for Friday @ 10:30 per Garrett V. (Souza).
6 Measured up concrete quanitity for abutment 1. came up with 14.7 loads of concrete. 140+/- CY
MANPOWER LOG 11 Workers | 88.0 Man Hours
No.Contact/
Company
Notes: Workers # Hours Man Hours Location
1 Souza Garrett Vanfleet- Carpenter Foreman
BI 39
1 8.0 8.0
2 Souza Mylan Elder- Apprentice Carpenter
BI 39
1 8.0 8.0
3 Souza Steve Helenberg-Carpenter
BI 39
1 8.0 8.0
4 Souza Mark Missamore-Carpenter Foreman
BI 39
1 8.0 8.0
5 Pacific Steel Group Tyler Hintz- Ironworker
BI43
1 8.0 8.0
6 Pacific Steel Group John Hamilton-Foreman ironworker
BI 43
1 8.0 8.0
7 Pacific Steel Group James Hintz- Iron Worker
BI 43
1 8.0 8.0
8 Souza Dana Missamore-LBR
BI 39
1 8.0 8.0
Filippin Engineering Page 1 of 3 Printed on 10/16/2020 at 12:15 PM PDT
MANPOWER LOG 11 Workers | 88.0 Man Hours
No.Contact/
Company
Notes: Workers # Hours Man Hours Location
9 Souza Mike Kountche-CARP Apprentice
BI 39
1 8.0 8.0
10 Souza Clay Souza-Operator
BI 39
1 8.0 8.0
11 Souza Raymond Garcia-Carpenter Apprentice
BI 39
1 8.0 8.0
11 88.0
EQUIPMENT LOG
No.Equipment Name Cost Code Hrs Operating Hrs Idle Inspected?Inspection Time Location
1 2500 Gmc Crew cab No 08:00 AM
Notes:Souza
2 Cat 336 excavator No 08:00 AM
Notes:Souza
3 F450 Super Duty No 08:00 AM
Notes:Souza
4 Caterpillar Reachlift No 08:00 AM
Notes:Souza
5 3500 GMC crew truck No 08:00 AM
Notes:Souza
6 Cat 336 Long Reach
Excavator
No 08:00 AM
Notes:D. Crye
7 Cat 308 Mini Excavator No 08:00 AM
Notes:Souza
8 2500 Gmc Crew cab No 08:00 AM
Notes:Souza
9 305 Cat Mini Excavator No 08:00 AM
Notes:Souza
10 Doosan P185 Air
Compressor
No 08:00 AM
Notes:Souza
11 2500 GMC flatbed No 08:00 AM
Notes:PSG
12 Big Tex trailer No 08:00 AM
Notes:Souza
13 Rental Man Lift United
Rentals
No 08:00 AM
Notes:Souza
Filippin Engineering Page 2 of 3 Printed on 10/16/2020 at 12:15 PM PDT
EQUIPMENT LOG
No.Equipment Name Cost Code Hrs Operating Hrs Idle Inspected?Inspection Time Location
14 Sciiscor lift United Rentals No 08:00 AM
Notes:Souza
OBSERVED WEATHER CONDITIONS
Weather Delay Sky Temp Average Precipitation Wind Ground/Sea Calamity
No
WEATHER REPORT
Temperature Precipitation Since Humidity Windspeed
Low High Avg Midnight 2 Days Ago 3 Days Ago Low Avg High Dew Avg Max Gust
61°F 76°F 66°F 0.01 in.0.01 in.0.02 in.65%83%97%61°F 5.0 mph 9 mph 14 mph
DAILY SNAPSHOT
06:00 AM 09:00 AM 12:00 PM 03:00 PM 06:00 PM 09:00 PM
partly-cloudy-night
62°F
partly-cloudy-day
66°F
clear-day
74°F
clear-day
76°F
clear-day
69°F
partly-cloudy-night
63°F
By Date Copies To
Filippin Engineering Page 3 of 3 Printed on 10/16/2020 at 12:15 PM PDT
Jerry Missamore 8/25/2020