HomeMy WebLinkAbout2020-08-28Filippin Engineering
354-D S. Fairview Ave.
Goleta, California 93117
P: (805) 845-4602
Project: 194501 - SLO Marsh Street Bridge
Replacement
919 Palm St.
San Luis Obispo, California 93401
P: 8057817200
Daily Log Inspection: Friday 8/28/2020
NOTES LOG
No.Comments
1 Souza on site at 7 AM getting abutment 1 ready for concrete pour.
PSG on site erection steel at abutment 2 and abutment 2 retaining wall.
2 Souza began concrete pour at approx. 10:45 AM. Garrett indicated that there will be 6 to 7 trucks running on the pour. Myers
Drilling had their concrete pump onsite to install the concrete into the abutment. Pour rate is approx 4' an hour.
3 Spoke with Steve S. (Souza) about the SW corner shoring and Steve implied that Souza was going to leave the first beam in
place closet to the exsiting WW. Steve implied it was cheaper to abanden then to mess with.
4 Souza finished pour with a total of 15 loads. 142.50 CY into abutment #1.
5 It was agreed to in the field that 2 finishers for 1 hour of OT would be extra for finishing up under the rebar due to the contour
grade sheet change.
6 RFI 45 for differing site condition was sent back to Souza as well as the official stance from the City on the Water Sampling.
7 Went over RSP limits with Jeff P. at abutment 1 left side.
MANPOWER LOG 11 Workers | 88.0 Man Hours
No.Contact/
Company
Notes: Workers # Hours Man Hours Location
1 Souza Garrett Vanfleet- Carpenter Foreman
BI 39
1 8.0 8.0
2 Souza Mylan Elder- Apprentice Carpenter
BI 39
1 8.0 8.0
3 Pacific Steel Group Tyler Hintz- Ironworker
BI43
1 8.0 8.0
4 Pacific Steel Group John Hamilton-Foreman ironworker
BI 43
1 8.0 8.0
5 Pacific Steel Group James Hintz- Iron Worker
BI 43
1 8.0 8.0
6 Souza Dana Missamore-LBR
BI 39
1 8.0 8.0
7 Souza Mike Kountche-CARP Apprentice
BI 39
1 8.0 8.0
8 Souza Clay Souza-Operator
BI 39
1 8.0 8.0
Filippin Engineering Page 1 of 3 Printed on 10/16/2020 at 12:15 PM PDT
MANPOWER LOG 11 Workers | 88.0 Man Hours
No.Contact/
Company
Notes: Workers # Hours Man Hours Location
9 Souza Raymond Garcia-Carpenter Apprentice
BI 39
1 8.0 8.0
10 Souza Christian Valincia- Cement Mason
BI 39
1 8.0 8.0
11 Souza Luis Lemous-Ceballos-Cement Mason
BI 39
1 8.0 8.0
11 88.0
EQUIPMENT LOG
No.Equipment Name Cost Code Hrs Operating Hrs Idle Inspected?Inspection Time Location
1 2500 Gmc Crew cab No 08:00 AM
Notes:Souza
2 Cat 336 excavator No 08:00 AM
Notes:Souza
3 F450 Super Duty No 08:00 AM
Notes:Souza
4 Caterpillar Reachlift No 08:00 AM
Notes:Souza
5 3500 GMC crew truck No 08:00 AM
Notes:Souza
6 Cat 336 Long Reach
Excavator
No 08:00 AM
Notes:D. Crye
7 Cat 308 Mini Excavator No 08:00 AM
Notes:Souza
8 2500 Gmc Crew cab No 08:00 AM
Notes:Souza
9 305 Cat Mini Excavator No 08:00 AM
Notes:Souza
10 Doosan P185 Air
Compressor
No 08:00 AM
Notes:Souza
11 2500 GMC flatbed No 08:00 AM
Notes:PSG
12 Big Tex trailer No 08:00 AM
Notes:Souza
13 Rental Man Lift United
Rentals
No 08:00 AM
Notes:Souza
Filippin Engineering Page 2 of 3 Printed on 10/16/2020 at 12:15 PM PDT
EQUIPMENT LOG
No.Equipment Name Cost Code Hrs Operating Hrs Idle Inspected?Inspection Time Location
14 Sciiscor lift United Rentals No 08:00 AM
Notes:Souza
15 40 Ton Crane No 08:50 AM
Notes:Bragg Crane
OBSERVED WEATHER CONDITIONS
Weather Delay Sky Temp Average Precipitation Wind Ground/Sea Calamity
No
WEATHER REPORT
Temperature Precipitation Since Humidity Windspeed
Low High Avg Midnight 2 Days Ago 3 Days Ago Low Avg High Dew Avg Max Gust
53°F 73°F 62°F 0.00 in.0.01 in.0.02 in.53%73%87%53°F 4.4 mph 8 mph 11 mph
DAILY SNAPSHOT
06:00 AM 09:00 AM 12:00 PM 03:00 PM 06:00 PM 09:00 PM
partly-cloudy-night
54°F
partly-cloudy-day
58°F
clear-day
71°F
clear-day
72°F
clear-day
67°F
clear-night
61°F
By Date Copies To
Filippin Engineering Page 3 of 3 Printed on 10/16/2020 at 12:15 PM PDT
Jerry Missamore 8/28/2020