Daily Log Inspection: Tuesday 9/8/2020
NOTES LOG
No.Comments
1 Souza on site at 7 AM prepping to set back panels at abutment 2. The water cure burleen will be removed at abutment 1 as
well.
Garrett V. (Souza) indicated that possible RFI will be forthcomming to eliminate the batter in the retaining wall and just pour it
20'' thick all the way up.
2 Spoke with Garrett V. (Souza) and told him the silt fence at the outlet of the TCDS needs some attention to get stood back up.
Appears the road is sliding into the area of the fence.
3 Meet with Lyle N. (City of SLO) and went over abutment 2 right side retaining wall area where the chain link fence comes off
and reconnects to the existing fence. 2 options exist to either add the 9'' curb all the way to the bridge or backfill and leave dirt
down 1-2'' and leave it alone. Souza already has to repair the part of the park that has been torn out by the excavation.
4 Started list for pay quantities for the Month of September
5 Steve S. (Souza) had conversation about the RSP and Contour grading in front of the soldier pile wall. FE indicated that it
appears to work out that elevation 213 would cover the 2' minimum necessary to bury the wall and then work backwards down
the slope to achieve proper 1.5:1 on slope for RSP. The bottom would need to be keyed in at 5' min by 2.5' wide.
MANPOWER LOG 7 Workers | 56.0 Man Hours
No.Contact/
Company
Notes: Workers # Hours Man Hours Location
1 Souza Garrett Vanfleet- Carpenter Foreman
BI 39
1 8.0 8.0
2 Souza Mylan Elder- Apprentice Carpenter
BI 39
1 8.0 8.0
3 Souza Dana Missamore-LBR
BI 39
1 8.0 8.0
4 Souza Mike Kountche-CARP Apprentice
BI 39
1 8.0 8.0
5 Souza Clay Souza-Operator
BI 55/56
1 8.0 8.0
6 Souza Edgar Lopez-Cement Mason
BI 39,56
1 8.0 8.0
7 Souza Tommy Russo-Laborer
BI 39
1 8.0 8.0
7 56.0
Filippin Engineering Page 1 of 2 Printed on 10/16/2020 at 12:17 PM PDT
EQUIPMENT LOG
No.Equipment Name Cost Code Hrs Operating Hrs Idle Inspected?Inspection Time Location
1 2500 Gmc Crew cab No 08:00 AM
Notes:Souza
2 F450 Super Duty No 08:00 AM
Notes:Souza
3 Caterpillar Reachlift No 08:00 AM
Notes:Souza
4 3500 GMC crew truck No 08:00 AM
Notes:Souza
5 Cat 336 Long Reach
Excavator
No 08:00 AM
Notes:D. Crye
6 2500 Gmc Crew cab No 08:00 AM
Notes:Souza
7 Rental Man Lift United
Rentals
No 08:00 AM
Notes:Souza
8 Cat 308 Mini Excavator No 08:00 AM
Notes:Souza
OBSERVED WEATHER CONDITIONS
Weather Delay Sky Temp Average Precipitation Wind Ground/Sea Calamity
No
WEATHER REPORT
Temperature Precipitation Since Humidity Windspeed
Low High Avg Midnight 2 Days Ago 3 Days Ago Low Avg High Dew Avg Max Gust
59°F 75°F 67°F 0.00 in.0.01 in.0.01 in.56%68%94%56°F 4.0 mph 5 mph 9 mph
DAILY SNAPSHOT
06:00 AM 09:00 AM 12:00 PM 03:00 PM 06:00 PM 09:00 PM
clear-night
63°F
clear-day
68°F
clear-day
72°F
clear-day
76°F
clear-day
68°F
clear-night
61°F
By Date Copies To