Project: 194501 - SLO Marsh Street Bridge
Replacement
919 Palm St.
San Luis Obispo, California 93401
P: 8057817200
Daily Log Inspection: Wednesday 10/28/2020
NOTES LOG
No.Comments
1 Souza on site at 7 AM and moved 336 excavator to abutment 1 side of the project to begin structure backfill.
At 7 AM the vibration monitoring systems was re installed on both sides of the bridge so that Souza could continue structure
backfill on the Davita side of the project.
2 Spoke with Souza about mainting effeciant traffic control as the trucks pulled in and out on the Osos side of the project as not
to back up Osos.
Spoke with Claudia at Davita about the upcomming events and loosing access on Marsh side of the project due to the work
needing to be done.
3 Anit Graffitti was sprayed on the soldier pile wall CIP and beams on the creek side of the wall.
4 Went over DEWR with Will S. (Souza) in the office at Marsh St. STill have 10 DEWR that at not aggreeable too.
5 Set up Earthsystems for tomorrow at 10 and 2:30 for abutment 1 compaction testing.
6 Kritz trucking hauled in DG from Hanson Margarita for structure backfill material. 4 End dumps.
7 Earthsystems on site at 2:30PM for compaction test on the fist 2' of abutment 1 side. Indications are the material passed but
Jose (Earthsystems) took another sample because of the fluctuation in moister content. There is sample that matches the
density report but passing tests and mositures not being consitient. Mostiure says optimum at 11.5% but at the same time at
9% material was appeared to be pumping and wet.
8 United rentals was onsite and picked up the baker tank that was used for dewatering.
9 Installed 2 'of 1.5'' rock starting at elevation 204' +/- to get above the water table and then installed Hanson DG at elevation
206 +/- to elevation 209+/- before testing.
MANPOWER LOG 9 Workers | 67.0 Man Hours
No.Contact/
Company
Notes: Workers # Hours Man Hours Location
1 Souza Garrett Vanfleet- Carpenter Foreman
BI24
General site clean up
1 9.0 9.0
2 Souza Dana Missamore-LBR
BI24
Traffic control
1 8.0 8.0
3 Souza Clay Souza-Operator
BI 24-8hrs
1 8.0 8.0
4 Souza Mylan Elder-Apprentice Carpenter
General site clean up
1 9.0 9.0
Filippin Engineering Page 1 of 3 Printed on 11/3/2020 at 01:43 PM PST
MANPOWER LOG 9 Workers | 67.0 Man Hours
No.Contact/
Company
Notes: Workers # Hours Man Hours Location
5 Souza Mike Keuntje - Carpenter
BI24
Clean up site
1 8.0 8.0
6 Souza Larry Wompler-Operator
BI 24
1 8.0 8.0
7 Souza Guy Branch-Teamster
BI 24
1 8.0 8.0
8 Souza Carlos Pina- Cement Mason
BI 24
1 8.0 8.0
9 Souza Roman Reyes-Cement Mason
BI 24
1 1.0 1.0
9 67.0
EQUIPMENT LOG
No.Equipment Name Cost Code Hrs Operating Hrs Idle Inspected?Inspection Time Location
1 2500 Gmc Crew cab No 08:00 AM
Notes:Souza
2 F450 Super Duty No 08:00 AM
Notes:Souza
3 Cat 336 excavator No 08:20 AM
Notes:Souza
4 CAT Telescope Fork Lift No 08:35 AM
Notes:Souza
5 Kenworth H2O truck No 08:45 PM
Notes:Souza
6 C34 cat compactor 6.0 2.0 No 08:23 PM
Notes:Souza
7 Cat 305 Mini Excavator No 08:00 AM
Notes:Souza
OBSERVED WEATHER CONDITIONS
Weather Delay Sky Temp Average Precipitation Wind Ground/Sea Calamity
No
Filippin Engineering Page 2 of 3 Printed on 11/3/2020 at 01:43 PM PST
WEATHER REPORT
Temperature Precipitation Since Humidity Windspeed
Low High Avg Midnight 2 Days Ago 3 Days Ago Low Avg High Dew Avg Max Gust
49°F 78°F 61°F 0.00 in.0.00 in.0.00 in.13%37%50%33°F 3.7 mph 7 mph 10 mph
DAILY SNAPSHOT
06:00 AM 09:00 AM 12:00 PM 03:00 PM 06:00 PM 09:00 PM
clear-night
50°F
clear-day
58°F
clear-day
76°F
clear-day
78°F
clear-day
68°F
clear-night
59°F
By Date Copies To
Filippin Engineering Page 3 of 3 Printed on 11/3/2020 at 01:43 PM PST
Jerry Missamore 10/28/2020