Loading...
HomeMy WebLinkAbout2020-10-28Filippin Engineering 354-D S. Fairview Ave. Goleta, California 93117 P: (805) 845-4602 Project: 194501 - SLO Marsh Street Bridge Replacement  919 Palm St. San Luis Obispo, California 93401 P: 8057817200 Daily Log Inspection: Wednesday 10/28/2020      NOTES LOG   No.Comments   1 Souza on site at 7 AM and moved 336 excavator to abutment 1 side of the project to begin structure backfill. At 7 AM the vibration monitoring systems was re installed on both sides of the bridge so that Souza could continue structure backfill on the Davita side of the project.   2 Spoke with Souza about mainting effeciant traffic control as the trucks pulled in and out on the Osos side of the project as not to back up Osos. Spoke with Claudia at Davita about the upcomming events and loosing access on Marsh side of the project due to the work needing to be done.   3 Anit Graffitti was sprayed on the soldier pile wall CIP and beams on the creek side of the wall.  4 Went over DEWR with Will S. (Souza) in the office at Marsh St. STill have 10 DEWR that at not aggreeable too.  5 Set up Earthsystems for tomorrow at 10 and 2:30 for abutment 1 compaction testing.  6 Kritz trucking hauled in DG from Hanson Margarita for structure backfill material. 4 End dumps.  7 Earthsystems on site at 2:30PM for compaction test on the fist 2' of abutment 1 side. Indications are the material passed but Jose (Earthsystems) took another sample because of the fluctuation in moister content. There is sample that matches the density report but passing tests and mositures not being consitient. Mostiure says optimum at 11.5% but at the same time at 9% material was appeared to be pumping and wet.   8 United rentals was onsite and picked up the baker tank that was used for dewatering.  9 Installed 2 'of 1.5'' rock starting at elevation 204' +/- to get above the water table and then installed Hanson DG at elevation 206 +/- to elevation 209+/- before testing.      MANPOWER LOG 9 Workers  |   67.0 Man Hours  No.Contact/ Company Notes: Workers # Hours Man Hours Location   1 Souza Garrett Vanfleet- Carpenter Foreman BI24 General site clean up   1 9.0 9.0       2 Souza Dana Missamore-LBR BI24 Traffic control   1 8.0 8.0       3 Souza Clay Souza-Operator BI 24-8hrs   1 8.0 8.0       4 Souza Mylan Elder-Apprentice Carpenter General site clean up   1 9.0 9.0         Filippin Engineering Page 1 of 3 Printed on 11/3/2020 at 01:43 PM PST       MANPOWER LOG 9 Workers  |   67.0 Man Hours  No.Contact/ Company Notes: Workers # Hours Man Hours Location   5 Souza Mike Keuntje - Carpenter BI24 Clean up site   1 8.0 8.0       6 Souza Larry Wompler-Operator BI 24   1 8.0 8.0       7 Souza Guy Branch-Teamster BI 24   1 8.0 8.0       8 Souza Carlos Pina- Cement Mason BI 24   1 8.0 8.0       9 Souza Roman Reyes-Cement Mason BI 24   1 1.0 1.0          9  67.0      EQUIPMENT LOG No.Equipment Name Cost Code Hrs Operating Hrs Idle Inspected?Inspection Time Location   1 2500 Gmc Crew cab No   08:00 AM    Notes:Souza  2 F450 Super Duty No   08:00 AM    Notes:Souza  3 Cat 336 excavator No   08:20 AM    Notes:Souza   4 CAT Telescope Fork Lift No   08:35 AM    Notes:Souza  5 Kenworth H2O truck No   08:45 PM    Notes:Souza  6 C34 cat compactor 6.0 2.0 No   08:23 PM    Notes:Souza  7 Cat 305 Mini Excavator No   08:00 AM    Notes:Souza    OBSERVED WEATHER CONDITIONS Weather Delay Sky Temp Average Precipitation Wind Ground/Sea Calamity   No        Filippin Engineering Page 2 of 3 Printed on 11/3/2020 at 01:43 PM PST      WEATHER REPORT Temperature Precipitation Since Humidity Windspeed Low High Avg Midnight 2 Days Ago 3 Days Ago Low Avg High Dew Avg Max Gust 49°F 78°F 61°F 0.00 in.0.00 in.0.00 in.13%37%50%33°F 3.7 mph 7 mph 10 mph   DAILY SNAPSHOT 06:00 AM 09:00 AM 12:00 PM 03:00 PM 06:00 PM 09:00 PM clear-night   50°F clear-day   58°F clear-day   76°F clear-day   78°F clear-day   68°F clear-night   59°F     By  Date  Copies To     Filippin Engineering Page 3 of 3 Printed on 11/3/2020 at 01:43 PM PST        Jerry Missamore 10/28/2020