HomeMy WebLinkAboutItem 08 - COUNCIL READING FILE_h_CIP Status Report 2021-23 ATTACHMENT X STATUS OF CURRENT CIP PROJECTS As of December 2020 STATUS OF 2019-21 CAPITAL IMPROVEMENT PROJECTS Purpose The purpose of this report is to provide the Council with a concise summary of the status of the City’s Capital Improvement Plan (CIP) projects. Of the 110 projects that have been financially active during the 2019-21 Financial Plan period: 1. 29 are complete, 2. 13 will be complete within 6 months, 3. 32 will be complete within 12 months, 4. 36 will be complete in more than 12 months. Within the last 24 months the following projects have been completed: 1. Stafford/Kentucky Sewer Line Replacement Project (December 2019). The Stafford/Kentucky Sewer Line Replacement Project (Project) rehabilitated 1,785 feet of sewer main. The Project includes installation of 100 lineal feet of sewer line by “jack and bore” construction, 295 lineal feet of sewer line by open trenching, 341 lineal feet of sewer line by pipe bursting, and 1,049 feet of cure-in-place pipe (CIPP) polyester lining. This project furthers the ongoing program to maintain aging and deteriorating infrastructure, thus reducing the need for preventative maintenance and emergency repairs, ensuring uninterrupted wastewater flow, and minimizing the potential for related health hazards to the public. The total construction cost was $1.1 Million. Complete, 29 Complete in 6 months, 13 Complete in 12 months, 32 Complete in more than 12 months, 36 0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100% 2. Sewer Lining 2016 (October 2019). This project rehabilitated 2,848 feet of existing sewer pipe on Broad, Mission and in an easement area adjacent to Chorro Street and Benton Way. Cured in place pipe (CIPP), a trenchless rehabilitation method was utilized to rehabilitate the sewer main. This project furthers the ongoing program to maintain aging and deteriorating infrastructure, thus reducing the need for preventative maintenance and emergency repairs, ensuring uninterrupted wastewater flow, and minimizing the potential for related health hazards to the public. The total construction cost was $480,500. 3. Waterline Replacement 2016 (June 2019). This project replaced approximately 5,300 lineal feet of waterline on Pacific, Boysen, Chorro and Sierra streets. The waterlines replaced with this project are substandard and deteriorated. Their replacement eliminated capacity limitations and improved water flow for fire protection as well as resulted in lower costs to the City and reduced customer impacts associated with emergency repairs. The project also replaced 284 lineal feet of CMP and upgrade four catch basins to the current City-standard. This work was necessary to facilitate the stability and safety of trenching for the waterline replacements. The total construction cost was $1.88 Million. 4. Osos/Leff/Santa Barbara Sewerline Project (January 2020). The Osos/Leff/Santa Barbara Sewerline Project (Project) rehabilitated 2,364 feet of sewer main. The project replaced 698 feet of sewer main by open trenching on Santa Barbara and Osos. The project also included installation of 1,666 feet of sewer main by pipe bursting on Leff, Church and Osos Streets. This project furthers the ongoing program to maintain aging and deteriorating infrastructure, thus reducing the need for preventative maintenance and emergency repairs, ensuring uninterrupted wastewater flow, and minimizing the potential for related health hazards to the public. The total construction cost was $920,000. 5. Sewer Lining 2019 (September 2019). This project rehabilitated 1,320 feet of existing vitrified clay sewer pipe installed in the mid to late 1950s in an easement area adjacent to Albert Drive. Cured in place pipe (CIPP), a trenchless rehabilitation method was utilized to rehabilitate the sewer main. This project furthers the ongoing program to maintain aging and deteriorating infrastructure, thus reducing the need for preventative maintenance and emergency repairs, ensuring uninterrupted wastewater flow, and minimizing the potential for related health hazards to the public. The Total Construction cost was $198,000 6. 54 Highland Drive (May 2019). On September 28, 2018, a fire hydrant failed, saturating the ground at 54 Highland Drive and causing a slope failure. The project restored the failed slope and replaced 42 lineal feet of failing storm drain corrugated metal pipes (CMP) covered in soil due to the slope failure. Total cost of construction was $178,000. 7. South Broad Street Improvements (September 2019). This project rehabilitated South Broad Street between Tank Farm Road and the City Limit, just north of Farmhouse Lane. Rehabilitation required removal of the old deteriorated and failing asphalt and replacement with a new asphalt section structurally sufficient for the traffic loading conditions. This method of reconstruction was determined to be the most cost effective, with an expected service life of 15- 20 years. Total cost of construction was $1.84 Million 8. El Capitan Bridge Replacement (December 2019). El Capitan Bridge connects pedestrian pathways from El Capitan Way to Poinsettia Drive near French Park. The original wooden bridge was constructed in conjunction with the adjacent housing development in the late 90’s and was to be owned and maintained by adjacent property owners. In January 2015, the wooden bridge was destroyed when a large eucalyptus tree fell onto it. Subsequently, the City took ownership of this important bridge connection and funded design and construction of it its replacement. The new pedestrian bridge– which is 33-feet long–is made of steel with wood decking and entered service in December 2019. Total replacement cost was $96,000. 9. Mission Plaza Railing Upgrade (February 2020). This project replaced approximately 39’ lineal feet of existing railing in Mission Plaza along San Luis Obispo Creek behind the amphitheater. The existing railing had openings greater than the current ADA standards for safety. This project is part of an ongoing program to replace railing within the Mission Plaza that does not meet ADA standards and Building Codes as well as ensures safety for the community. Total replacement cost was $20,000. 10. Foothill Pipe Burst Project. This project consisted of pipe bursting an existing 6” clay pipe sewer main and replace with 8” HDPE pipe from Foothill to Rougeot Place. Three sewer laterals were reconnected to the main and 26 Chorro property’s sewer lateral was relocated to the sewer main off Chorro Street. A 6” VCP sewer pipe was abandoned at Foothill. The total project construction cost was $252,000. 11. Fire Station 3 Painting (September 2019). This project consisted of the ten-year maintenance painting of the Fire Station 3 exterior walls. All exterior surfaces were thoroughly cleaned and prepped for new paint in their original colors, including the flagpole. All facades, windows and other appurtenances around the Fire Station were cleaned as well. Total painting cost was $9,300. 12. City Hall Painting (September 2019). This project consisted of the ten-year maintenance painting of the City Hall exterior walls, and the sealing of the masonry components of the exterior walls and walkways. All exterior surfaces were thoroughly cleaned and prepped for new paint in their original colors, including the first-floor window wells. The masonry panels and stairway features were cleaned and sealed with a clear water-resistant coating. All tile facades, windows and other appurtenances around City Hall were cleaned as well. The total painting cost was $39,000. 13. Higuera Sidewalk Repair (May 2020). A deteriorated section of sidewalk with basement space below that was starting to fail was replaced with new Mission-Style sidewalk along with a structural steel beam and pan decking reinforcement system to support the sidewalk above. Total Project cost was $268,000. 14. City Facilities HVAC Project (November 2020) Existing HVAC units and equipment were replaced with new energy-efficient equipment at the Parks & Recreation Administration Building, the Utilities Administration Building and the City/County Library. This project replaced mostly roof-mounted HVAC units for the Utilities Building and Library and attic and ground units for Parks & Recreation. Total construction cost was $149,000. 15. City Hall Charging Station (July 2020). A solar-powered portable charging station for electric vehicles was installed in the City Hall parking lot. This source of free energy can accommodate the charging of two City Fleet electric vehicles, has battery capacity for nighttime and inclement weather situations, and the charging is distributed by ChargePoint. The total cost was $81,000 16. Fire Station 4 Emergency Backup Generator Project (September 2019). This project consisted of replacing the existing emergency back-up generator with a new 50-kilowatt natural gas generator on a concrete pad away from the building and sleeping quarters. The new generator will provide reliable emergency back-up electrical power for all electrical circuits at Fire Station 4. This is a critical facility requiring a high degree of reliability during an outage or major emergency. The total construction cost was $76,000. 17. Pickleball Courts Project (September 2019). This project consists of constructing three dedicated pickleball courts on the former basketball court and filling in the sand volleyball court to create a new basketball area at French Park. Additionally, the project regraded the curb ramp to make it compliant with ADA standards. The total project construction expenditure was $146,000. Before Construction After Construction 18. South Hills Radio Site Upgrades (October 2020). The City’s primary radio site is located in a City leased space at the top of South Hills. This site was constructed in the 1980’s, has served the City well over the past 30 plus years, but is now failing. This equipment provides day to day public safety radio communications. The South Hills site as well as the additional radio sites at Fire Stations 2 and 3, and the 919 Palm Parking Structure make up the City’s communication network. This project consisted of the removal and replacement of the existing radio shelter, generator, and antenna poles. The project included a new prefabricated structure to enclose and protect the existing radio and network equipment. A new generator was installed to power the facility in case of an emergency or loss of power. Lastly, a new 100’ radio tower was built to boost signal reception and transmission at the site. The total construction cost was $870,000. 19. Islay Hill Park Playground Equipment Replacement (October 2020). This project consisted of replacing the existing playground equipment at Islay Hill Park Playground with new equipment within the existing footprint. Additionally, the project completed some pathway improvements from the bathrooms to the playground. The project also regraded the ADA parking spaces and replaced the curb ramp from the parking lot to the bathrooms. The total cost of the project was $563,000. 20. Swim Center Bath House Roof Repair (September 2020). This project consists of some spot repair work and a new fluid applied roofing system to repair the S.L.O. Swim Center Bath House roof. The City used Ghemco products for the fluid applied roofing system. The contractor applied additional topcoat to increase the product warranty to twenty years. 21. S.L.O. Swim Center Therapy Pool Replaster (September 2019). This project consisted of the removal and replacement of the existing therapy pool plaster and other minor improvements to provide a pool in compliance with current regulatory requirements. Replastering eliminated the potential for health and safety concerns by rehabilitating the pool’s inner shell. Additional components of the project included new tiling along all steps, new depth markers, replacement of damaged waterline tile, new stainless steel grabrail steps, new underwater lights, and a new ADA compliant lift. The total project construction cost was $116,000. 22. Meadow Park Pedestrian Bridges Replacement (April 2020). This project consisted of replacing two existing wooden bridges with new prefabricated steel truss bridges with concrete decks. Additionally, the project completed some pathway improvements beyond the approach to the King Street Bridge. The total construction cost was $234,000. Installation of King Street Bridge Post Construction 23. Wash Water Tank No. 2 Rehabilitation (December 2019). Water storage is provided in 11 tanks and two reservoirs located throughout the City. The tanks range in size from 40,000 to 7.5 million gallons. Regular maintenance of water storage tanks provides an ongoing benefit to the economy, environment, and public health. The effects of corrosion on steel tanks can lead to structural failure, leaks, and water contamination which can affect the health of its users. Through interior and exterior inspection, the Wash Water Tank No. 2 at the Water Treatment Plant was determined to be a high priority because of coating deficiencies. The project consisted of an interior and exterior rehabilitation to the tank and some added safety features. The total project cost was $159,000. 24. Bridge Deck Sealing 2020 (July 2020). Three bridges in the City were experiencing deterioration in their concrete decks: Nipomo Street at Monterey, South Broad Street at Fuller, and Fuller Street at South Broad. To prevent further water intrusion and prolong the bridge deck life, the City applied a Methacrylate sealant to each bridge deck. The total project cost was $75,000. 25. City Hall Fire Line Replacement (October 2020). City Hall lacked a double check water valve for use during fire water flows. This project removed the existing fire department connection and pressure indicator valve and then replaced it with a double check water valve. The total construction cost was $60,000. Pre-Construction Post-Construction 26. Parking Structure LED Retrofit, 842 Palm and 919 Palm (September and November 2020). The Parking Structures at 842 and 919 Palm Street utilized traditional high-pressure sodium (HPS) lighting throughout the structures since the original construction of both parking structures. To implement the Climate Action Major City Goal and achieve cost savings as outlined in the City’s Fiscal Health Response Plan, the City retrofitted the existing lighting fixtures with energy efficient LED lighting, saving the City approximately $30,000 in lighting costs per year. Pre-Construction Post-Construction 27. Mission Plaza Cameras 2019 (February 2020). The Mission Plaza is a popular attraction for both tourists and residents. The Police Department requested the that two security cameras be installed in the plaza to aid in monitoring areas prone to unlawful activity. The locations proposed in the project were determined in order to help eliminate “blind spots” that had previously exist on the plaza. The project consisted of the installation of two 20’ poles for the security cameras to be mounted on along with the electrical conduit required to power the cameras. The total project costs were $37,000. 28. Silt Removal 2020 (September 2020). Silt carried by storm water settles at points in the creek where storm water flow velocity decreases. This reduction in velocity allows solids suspended in the water to settle out. As these deposits build up, the capacity of the creek decreases and risk of flooding of the surrounding areas increases. The regular removal of built up silt increases channel capacity and removes the conditions conductive for blocking flow. The 2020 silt removal project included two sites: the Prefumo Creek at LOVR and the Prefumo Creek approximately 700 ft downstream from the Laguna Lake outfall at Madonna Rd. In total approximately 1510 cubic yards of silt were removed. The total project cost was $69,000. Pre-Construction Post-Construction 29. Bullock Lane CMP Replacement (November 2020). A tributary to Acacia Creek passes underneath Bullock Lane via a culvert which coveys flow underneath the road. The original culvert was constructed of corrugated metal pipe (CMP), and although no record drawings of the culvert were found in City files, it is estimated to be at least 50 years old. The city became aware that the CMP and supporting headwalls were beginning to fail approximately ten years ago and in 2012 public works began investigating potential replacement options. During the 2018-19 and 2019-20 rain season the deterioration of the culvert and headwalls was found to be accelerating suggesting failure was imminent. In response Public Works prioritized the work to be completed prior to the start of the 2020 rainy season. The total construction cost was $318,000. Pre-Construction Post-Construction Capital Improvement Projects that are ongoing in the construction phase: 1. Marsh Street Bridge Replacement: The Marsh Street Bridge, located near the intersection of Marsh and Santa Rosa Streets, was approved by the City Council in January 2013 for removal and replacement. This followed a determination by the California Department of Transportation (Caltrans) that the existing bridge, built in 1909, is structurally deficient. An assessment concluded that a complete replacement of the existing bridge was the most prudent and cost-effective alternative given the age of the structure. The total construction budget is $4.8 million with completion expected January 2021. 2. Roadway Sealing: This project follows the City Pavement Maintenance Program, which calls for the re- surfacing and re-striping of local streets located in Pavement Areas 4 and 5. Concurrent with this effort, staff also incorporated Complete Street Elements into streets undergoing rehabilitation, including the creation of Neighborhood Greenways and community approved Neighborhood Traffic Management activities. This project is expected to be completed in December 2020 with a budget of $1.8 million. 3. Swim Center Shower Repair: The existing water mixing valve in the Sinsheimer pool shower system is aging and cannot properly regulate the outgoing water temperature. In order to ensure delivery of water within the proper temperature range, the boiler temperature has been reduced, resulting in accelerated wear and tear on the system. The existing water mixing valve will be replaced with an electronic water control station that allows the boilers and shower system to operate within the preferred temperature range. This system should also deliver hot water to the shower users without the burst of cold water the current system occasionally provides. The construction budget is $30,000 and the work is expected to be completed in December 2020. 4. Railroad Safety Trail Taft to Pepper: The Railroad Safety Trail (RRST) has long been one of the highest-priority multimodal transportation projects in the City of San Luis Obispo (City)—a crosstown, dedicated facility for pedestrians and bicyclists connecting the southern City limits north to California Polytechnic State University (Cal Poly). Over the past two decades, approximately 40 percent of the total four-mile trail has been completed and existing portions of the trail are enjoyed by over 1,000 pedestrians and cyclists per day. This project includes construction of the next segment of the RRST from Taft Street to Pepper Street. It segment was included in the 2013 Bicycle Transportation Plan (Attachment A) and supports the current Major City Goal to improve Sustainable Transportation in the City. The project is expected to be completed Spring 2021 with a budget of $6 million. 5. Fire Station 1 HVAC: Fire Station 1, constructed in 1996, is the main campus for the Fire Department’s four stations in the City. The main building houses the Fire Department Administrative personnel and the shift firefighters, and the indoor space temperature is conditioned by seven HVAC units. The seven HVAC units are the original mechanical units since the fire station was built and now are approximately 24 years old. The units are starting to show their age as in recent years there have been equipment breakdowns. This project will replace those units. The construction budget for this project is $140,000 and the work is expected to be completed in January 2021. 6. Wastewater Facility Upgrade: SLO Water Plus improves the WRRF’s ability to recover resources traditionally classified as waste. The upgrade will improve the plant’s efficiency while helping reduce our dependency on reservoir and groundwater supplies long into the future. It will deliver significant long-term benefits to water quality, the environment, resilience and community education. The project is expected to be completed in Spring 2023 with a budget of $120 million. 7. Downtown Parklets: The COVID-19 pandemic has created a national, state, and local public health emergency and unprecedented and pervasive economic impacts posing risk to the wellbeing of the community. This is clearly evident in the City of San Luis Obispo, as local businesses have been devastated economically by this event, especially restaurants, hotels and retail establishments within the City’s Downtown Core - the economic and cultural hub of the City. In support of local businesses, Council authorized the City Manager to implement the Open SLO program. At peak parklet implementation, 40 temporary parklets were installed of which 30 semi-permanent parklets have replaced the temporary installations. Staff are currently working to upgrade 7 temporary parklets and install parklets for businesses still on the waiting list. To date, $300,000 has been budgeted for Open SLO parklets implementation. Overall Status of the City’s Current CIP Projects This report summarizes the status of all 81 CIP projects with financial activity during the 2019-21 Financial Plan period presented under Major City Goal, Other Important Objective and Regular priorities. No. Project Total Project Budget (Approximate) Current Completed Percentage Major City Goal: Multimodal Transportation 1 Meadow Park Pathway Maintenance $120,000.00 80 2 2021 Downtown Pavement Improvements Project $2,895,000.00 50 3 Prado Road Bridge Widening 2018 $11,075,000.00 20 4 Bob Jones Trail Prefumo Creek Connection to Oceanaire $216,000.00 5 5 Railroad Safety Trail Taft to Pepper - 2018 $4,653,700.00 70 6 Bob Jones Trail Octagon Barn Connection $206,000.00 100 7 Higuera Street Widening: Fontana to Chumash $365,500.00 50 8 Orcutt Tank Farm Roundabout Design $213,050.00 90 9 Railroad Safety Trail Pepper to Train Station $30,000.00 15 10 California Taft Roundabout $1,260,000.00 25 11 Broad Street Corridor PHB $270,000.00 40 12 Santa Fe at Tank Farm 2018 $45,000.00 5 13 Higuera at 50 Higuera Widening $947,500.00 5 14 Prado Road Interchange $57,000,000.00 25 15 Marsh Street Bridge Replacement Project $8,342,900.00 75 Other Important Objective 2017/19 Downtown Vitality 16 Mission Plaza Restroom - 2019 $105,000.00 85 No. Project Total Project Budget (Approximate) Current Completed Percentage 17 Mid-Higuera Bypass $9,000,000.00 50 Other Important Objective 2015/17 Neighborhood Wellness 18 Buchon and Santa Rosa Storm Drainage Improvements Project $250,000.00 50 Other Important Objective 2015/17 Laguna Lake Restoration 19 Laguna Lake Dredging and Sediment Management Project Implementation $650,000.00 50 Other Important Objective 2013/15 Infrastructure Maintenance 20 Facility Upgrade 2017 $140,209,000.00 50 Other Important Objective 2011/13 Infrastructure Maintenance 21 Calle Joaquin Siphon and Lift Station Replacement $3,300,397.22 60 Regular Priority 22 Fire Station 2 Tower $200,000.00 20 23 Sinsheimer Irrigation & Drainage $600,000.00 60 24 Sinsheimer Court Entrance Hardscape $60,000.00 70 25 MFR: Swim Center Co-generation Plant $85,000.00 25 26 Corporation Yard Tenant Improvement Design $50,000.00 100 27 Corp Yard Fuel Island Siding Design $14,750.00 100 28 Fire Station #1 HVAC $21,800.00 95 29 City Hall Landing Repair $25,000.00 50 30 Broad and Leff Culvert Repair Design $10,000.00 95 No. Project Total Project Budget (Approximate) Current Completed Percentage 31 Railroad Crossing Upgrade - California & Foothill $740,000.00 10 32 Woodbridge Drainage $210,000.00 5 33 Reservoir No. 2 Replacement 2017 $5,750,000.00 30 34 Bee Bee, Cuesta, Loomis Waterline Replacement $1,750,000.00 50 35 Craig, Christina, Jaycee Waterline Replacement $2,160,000.00 50 36 Terrace Hill PRV $607,892.00 90 37 Verde Luneta Ramona Sewer Replacement Project $1,392,000.00 50 38 Tassajara, Cerro Romauldo, Jeffrey, Westmont Sewer $1,320,000.00 50 39 Chorro/Murray Sewer Replacement $444,000.00 60 40 Parks and Recreation Interior Office Rehabilitation $455,000.00 50 41 North Broad Street Neighborhood Park $740,000.00 50 42 Police Station Replacement Conceptual Design $80,000.00 40 43 KVEC Tower $250,000.00 5 44 Fire Radio Receive Site at Fire Station #4 $106,875.00 5 45 Cheng Park Revitalization $50,000.00 15 46 Swim Center Therapy Pool Boiler $15,000.00 20 47 Council Hearing Room TI $60,000.00 50 48 Fire Station #1 Administration/Fleet Maintenance Roofs $101,500.00 25 49 Fire Station 3 Roof Replacement $50,000.00 25 50 Swim Center Shower Repair $71,000.00 85 No. Project Total Project Budget (Approximate) Current Completed Percentage 51 Downtown Renewal Broad Street West Side Higuera to Marsh $850,000.00 25 52 Fire Station 1 - Solar Installation $0.00 5 53 Swim Center - Solar Installation $0.00 5 54 Neighborhood Greenway Sign Project $30,000.00 80 55 Silt Removal 2021 $60,000.00 5 56 South Street Landscape $100,000.00 5 57 Pismo/Johnson/SL Creek Bank Stabilization $20,000.00 5 58 Park Major Maintenance 2021 - Railroad Bike Path Fencing $150,000.00 5 59 Nipomo Street Reconstruction $400,000.00 33 60 Roadway Sealing 2020 $1,500,000.00 90 61 Buchon Street Traffic Calming $143,200.00 50 62 Higuera Street Paving $220,000.00 60 63 Anholm Neighborhood Greenway Phase 2 $1,100,000.00 20 64 Pedestrian Crossing Improvements $40,000.00 20 65 Bus Yard Parking Lot Maintenance (Grant Funds through Transit) $500,000.00 0 66 Fire Station 2 Parking Lot Maintenance $45,000.00 0 67 French Park Parking Lot Maintenance $80,000.00 0 68 Palm Nipomo Garage $1,581,989.15 35 69 Parking Structure Maintenance (All Structures) $1,800,000.00 20 No. Project Total Project Budget (Approximate) Current Completed Percentage 70 Energy Efficient Lighting Retrofits $0.00 80 71 Parking Structure Elevator Repair $77,500.00 85 72 Storm Drain System - Trash Capture Devices $25,000.00 5 73 WTP Backup Generator $2,200,000.00 10 74 WTP Energy Efficiency Project $14,750,000.00 40 75 Reservoir 1 Cover Replacement $780,000.00 60 76 Highland Waterline Replacement $600,000.00 20 77 Sewer Lift Station Replacement - Foothill $1,890,000.00 20 78 Sewer Lift Station Replacement - Airport $2,130,000.00 20 79 Sewer Lift Station - New Buckley Station $1,780,000.00 50 80 Poinsettia Creek Walk - Park Maintenance $200,000.00 20 81 Air Compressor Replacement - Fire Station 1 $80,000.00 65