HomeMy WebLinkAboutItem 10 - Authorization to advertise Meadow Park Pathways Maintenance Project
Department Name: Public Works
Cost Center: 5002
For Agenda of: May 18, 2021
Placement: Consent
Estimated Time: N/A
FROM: Matt Horn, Public Works Director
Prepared By: Hai Nguyen, Engineer III
SUBJECT: AUTHORIZATION TO ADVERTISE MEADOW PARK PATHWAYS
MAINTENANCE, SPECIFICATION NO. 1000021
RECOMMENDATION
1. Authorize staff to advertise for bids and approve the project plans (Attachment A) and
special provisions (Attachment B) for Meadow Park Pathways Maintenance, Specification
Number 1000021; and
2. Authorize the City Manager to award the construction contract for the bid total if the lowest
responsible bid is within the Engineer’s Estimate of $360,000 and the funding amount is
consistent with the adopted 2021-23 budget appropriation for this project.
DISCUSSION
Background
Bicycle and pedestrian pathways in City parks and facilities require ongoing maintenance to
provide users a safe and quality experience. The asphalt pathways at Meadow Park are failing
with severe cracking, rutting, and potholes. Trees that are adjacent to the pathway, or more
specifically tree roots, are causing the damage. More than 50% of the pathways within Meadow
Park are in poor condition and must be repaired.
This project was originally bid in December 2018 and a contract for construction was awarded.
Due to constructability challenges created by the variable condition of the existing pathway
condition, tree root conflicts, and utility conflicts the contract was terminated at no cost to the
City (Attachment C). This project has now been redesigned to address the previous
constructability issues. This project is being proposed for bidding now, prior to final CIP Budget
Adoption to secure contracts and begin and complete construction during the summer which is
the ideal time for paving.
Project Scope
This project will repair approximately 4,300 linear feet of pathways (Attachment D) and replace
one removable bollard. The pathway repair consists of milling off and replacing 4 inches of hot
mix asphalt. Pavement areas damaged by tree roots will be reconstructed. Some existing tree
roots may need to be cut, but all work adjacent to trees will be at the direction of the City
Arborist.
Item 10
Packet Page 29
Previous Council or Advisory Body Action
This project was originally identified in the 2017-19 Financial Plan that was approved by
Council. This project was then deferred with the FY 20-21 Budget Supplement.
Policy Context
Per the October 2018 Purchasing Policy Update to the July 2015 Financial Management Manual,
Council approval is required for Public Projects that cost over $175,000.
Public Engagement
Public engagement was done during the initial identification of this project to be included in the
2017-19 Financial Plan.
CONCURRENCE
There is concurrence from Parks and Recreation and Public Works departments with the
proposed recommendations outlined in this document.
ENVIRONMENTAL REVIEW
This project is exempt from environmental review under Section 15301 Class 1 (existing
facilities) of the California Environmental Quality Act (CEQA) Guidelines because the project
proposes to maintain existing pathways. The project is consistent with the applicable general
plan policies as well as with applicable City Regulations.
FISCAL IMPACT
Budgeted: Yes Budget Year: 2021-22
Funding Identified: Yes
Fiscal Analysis:
Staff is recommending this project be approved for advertising in advance of the Budget
Adoption for 2021-22 to allow for project implementation during the summer which is the ideal
time for paving. If the budget is approved as proposed, the funding will be made available July 1,
2021 to complete this project. If a lower funding level is approved by Council in the 2021-23
Financial Plan, staff may need to adjust the project scope to the approved budget, which will
delay the project.
Funding Sources FY Cost
Annualized
On-going Cost
Total Project
Cost
General Fund $345,900 $345,900
State
Federal
Fees
Sewer Fund $73,600 $73,600
Total $419,500 $419,500
Item 10
Packet Page 30
General Fund Sewer Fund
Construction Estimate $296,000 $64,000 $360,000
Contingencies (15%)$44,400 $9,600 $54,000
Total for Construction $340,400 $73,600 $414,000
Materials Testing $5,000 $0 $5,000
Printing $500 $0 $500
Total Project Cost $345,900 $73,600 $419,500
Current Project Balance:$650 $41,550
Additional Funding FY21-23 $350,000 $85,000
Downtown Paving 2021 $0 (39,675)
Remaining Balance:$4,750 $13,275
Meadow Park Pathways Maitenance, Specification No. 1000021
Meadow Park Pathways
Maintenance (1000021)
Sewer Manhole Cover
Adjustments (1000084)Project Total
Costs
There is a balance of $650 in the project account (1000021). Additional funding of $250,000
from the Local Revenue Measure Fund and $100,000 from Capital Outlay Fund is proposed in
the 2021-2023 Financial Plan Capital Improvement Plan and 2021-22 budget to provide adequate
funding for this project.
Another source of funding includes the Sewer Manhole Cover Adjustments Account (1000084)
to support adjustment of sewer facilities to new pavement elevation. There is currently a balance
of $41,550 in the account. Additional funding of $85,000 is proposed in the 2021-2023 Financial
Plan Capital Improvement Plan to provide adequate funding for this project and the 2021
Downtown Pavement Improvements Project.
ALTERNATIVES
Deny Authorization to advertise. The City Council may choose not to authorize project
advertisement prior to consideration of the 2021-23 budget review and approval. Staff does not
recommend this option, as the pathways are in need of repairs. Staff has recommended this
unique timing to try and get the project completed over the summer which is the ideal time for
paving.
Attachments:
a - COUNCIL READING FILE - 1000021 Plans
b - COUNCIL READING FILE - 1000021 Specifications
c - City Manager Report to Terminate Project
d - Project Vicinity Map
Item 10
Packet Page 31
City of San Luis Obispo, City Manager Report
`
Final City Manager Approval Approver Name Date Approved
ACM Community Services Shelly 7/29/18
Reviewer Routing List Reviewer Name Date Reviewed
City Engineer MH 7/18/19
City Attorney CB 7/24/19
Finance BE 7/24/19
July 16, 2019
FROM: Daryl Grigsby, Director of Public Works MH for
DG 7/18/19
PREPARED BY: Hai Nguyen, Engineer III
SUBJECT: Meadow Park Pathways Maintenance, Specifications No. 1000021 –
Contract Termination
RECOMMENDATION
Terminate contract with Souza Engineering Contracting in the amount of $118,090 for Meadow
Park Pathways Maintenance Project.
DISCUSSION
Background
On December 10, 2018 the City Manager authorized inviting bids for the Meadow Pathways
Maintenance Project, Specification Number 1000021. Bids were opened on January 10, 2019 and
Souza Engineering Contracting, Inc. (Souza) was the lowest responsible bidder with a proposal of
$118,090 for the total project. The project was approved for award on February 4, 2019 (Attachment
1).
The project preconstruction meeting was held on February 28, 2019. During the meeting, Souza’s
project manager asserted that existing site conditions posed constructability challenges and that design
changes should be implemented by Contract Change Order. Staff investigated and determined that
changes proposed by Souza, if implemented, would have resulted in undue risk to the City due to a
change in character of the contract work for which the resulting cost was unpredictable, but likely to
exceed the approved project budget. Souza’s proposal would also have impacted the drainage
characteristics of the pathway which would negatively affect pathway longevity.
Despite the above findings, Staff’s investigation revealed that the existing conditions would require a
more robust pavement section to ensure cohesiveness of the pavement structure and support of the
heavy construction equipment completing the milling and paving operations. Staff prepared a Cost
Request to Souza with these contract modifications. Souza returned a proposal that would have
approximately doubled the total project costs.
Item 10
Packet Page 32
Meadow Park Pathways Maintenance (1000021) – Contract Termination Page 2
As a result of the potential cost overruns, Staff have agreed with Souza to terminate the project at zero
cost to the City.
Project Development
Staff will complete further investigation of project conditions to determine the most appropriate
changes to the current design, which may include additional pavement areas allowing for better
turning movements for maintenance vehicles and a thicker pavement section to further extend the
life of the pathways.
FISCAL IMPACT
The project will be re-designed for construction within the available account balance of $137,090,
with work to take place in Summer 2020. It should be noted that high demand for contract labor
has recently resulted in substantial increases in project costs. In the event costs exceed the available
budget, Staff will seek additional funding sources to complete the work.
ALTERNATIVES
Deny termination of the contract. City Manager may choose not to terminate the contract. This
alternative is not recommended because existing funds are not sufficient to support construction
costs.
ATTACHMENTS
1. 1000021 CMR Award Report
https://slocitycloud.sharepoint.com/sites/SLOHub/Administration/citymanagersreports/Shared Documents/Public Works/2019/CIP
Engineering/1000021 Meadow Park Pathways - Contract Termination/1000021 CMR Termination.docx
Item 10
Packet Page 33
PROJECT LOCATION
MEADOW PARK PATHWAYS
MAINTENANCE
1 OF 1
Item 10
Packet Page 34