Daily Log Inspection: Monday 1/4/2021
NOTES LOG
No.Comments
1 Observatoin By Jerry Missamore:
Souza crew on site at 7 AM to wrk on extra work in the Maino Parking lot installing a 6'' curb along the west bank from the type
742 barrier rail to the north along the redwood tree to allow water to drain on to the dirt area of the parking lot at the far north
end.
Souza crews also working on re installing the curb at the Davita Hollister Property.
Lee Wilson on site to finsih splicing wires together for the lighting system.
Spoke with Lyle N. (City Of SLO) about the banner arms needed to be installed on the lights and he was going to bring out Lee
Wilson unsure if they were going to install today.
2 Souza crews were only able to demo the parking lot driveway area at the Davita Hollister property today.
Went over December pay estimate with Steve S. (Souza) and Jeff P. (FE).
3 Spoke with Garrett V. (Souza) about expansion joints in the curb and also deep joints at the Maino Property
4
5 Review of the Type C411 rail today and there appeard to be a white efflulence that came out the rail and discolored the rail.
Spoke with Garrett V. and Steve S. (Souza) about the discoloration and and Steve indicated Souza should get of Calportland
and let them come look at the concrete and see if it is a reaction with every the anti graffitti.
MANPOWER LOG 8 Workers | 64.0 Man Hours
No.Contact/
Company
Notes: Workers # Hours Man Hours Location
1 Souza Garrett Vanfleet- Carpenter Foreman
extra work 8 hours
BI 57 2 hours
1 8.0 8.0
2 Souza Dana Missamore-Laborer
BI 57
extra work 2 hrs
1 8.0 8.0
3 Souza Mylan Elder-Carpenter Apprentice
extra work
BI 57
1 8.0 8.0
4 Souza Raymond Garcia-Carpenter Apprentice
extra work 8hrs
1 8.0 8.0
5 Souza Carlos Pina-Cement Mason
extra work 10 hrs
Bi 57
1 8.0 8.0
Filippin Engineering Page 1 of 2 Printed on 1/14/2021 at 03:00 PM PST
MANPOWER LOG 8 Workers | 64.0 Man Hours
No.Contact/
Company
Notes: Workers # Hours Man Hours Location
6 Souza Jorge Garcia-Cement Mason
extra work 10 hrs
BI 57
1 8.0 8.0
7 Lee Wilson Electric Jason Haynes-Apprentice electrician
BI 116 5 hrs
1 8.0 8.0
8 Lee Wilson Electric Jason Heller- Electrician Foreman
BI 116 5 hrs
1 8.0 8.0
8 64.0
EQUIPMENT LOG
No.Equipment Name Cost Code Hrs Operating Hrs Idle Inspected?Inspection Time Location
1 2500 GMC utility Truck No 09:20 AM
Notes:Lee Wilson
2 F450 Super Duty No 09:20 AM
Notes:Souza
3 Dump Trailer No 09:20 AM
Notes:Souza
OBSERVED WEATHER CONDITIONS
Weather Delay Sky Temp Average Precipitation Wind Ground/Sea Calamity
No
WEATHER REPORT
Temperature Precipitation Since Humidity Windspeed
Low High Avg Midnight 2 Days Ago 3 Days Ago Low Avg High Dew Avg Max Gust
46°F 58°F 52°F 0.01 in.0.02 in.0.03 in.76%86%97%48°F 3.4 mph 8 mph 12 mph
DAILY SNAPSHOT
06:00 AM 09:00 AM 12:00 PM 03:00 PM 06:00 PM 09:00 PM
partly-cloudy-night
47°F
partly-cloudy-day
52°F
cloudy
57°F
cloudy
59°F
partly-cloudy-night
57°F
partly-cloudy-night
54°F
By Date Copies To
Filippin Engineering Page 2 of 2 Printed on 1/14/2021 at 03:00 PM PST
Jerry Missamore 1/4/2021