HomeMy WebLinkAbout2021-01-13Filippin Engineering
354-D S. Fairview Ave.
Goleta, California 93117
P: (805) 845-4602
Project: 194501 - SLO Marsh Street Bridge
Replacement
919 Palm St.
San Luis Obispo, California 93401
P: 8057817200
Daily Log Inspection: Wednesday 1/13/2021
NOTES LOG
No.Comments
1 Arrived on site at 9:30.
Post were grouted and in place. Top of fence railing was not level because it was following the grade of the retaining wall (7.5"
rise from bridge railing to 4' park fence). Conversation with Lyle (City) and Jeff (FE), it was decided that the top of fence needs
to be level with the bridge railing.
I spoke with Garret (Souza) and explained the situation, he agreed that the fence should be level. It was decided that 2 of the 3
post would come out leaving the post closest to the bridge railing. The fence would be a max of 6' tapering down 7.5" as it gets
to the 4' fence.
Anthony (CCF) left the site at 11:50. Mike (Souza) and Ryan (CCF) started working on removing the 2 posts. Using a
rotohammer and jack, the fence posts were removed. 2nd post was removed at 2:15. Ryan (CCF) and Mike (Souza) left site at
2:30.
Coatings on the new fence structure started to fail (bubbling/peeling). I called Garrett and asked them what the coating
process was- He explained that they HDG the structure then sprayed rustoleum over. I explained that surface prep on HDG is
required so that the coatings would adhere.
Steve (Souza) showed up on site and we had a conversation about the coatings- He agreed that the galvanized surfaces
needed to be prepped prior to topcoating and he will get materials from Sherwin Williams to properly prep and coat the steel.
They plan on stripping spray paint, rolling on primer, and then rolling on finish coat. One of the posts was not removed and will
have to be prepped/coated in the field.
MANPOWER LOG 3 Workers | 19.0 Man Hours
No.Contact/
Company
Notes: Workers # Hours Man Hours Location
1 Souza Mike Keuntje- truck & dump trailer
1 7.0 7.0
2 Souza Central Coast Fence- Ryan Lundeberg-
Foreman-6500 silverado truck 33
1 8.0 8.0
3 Souza Central Coast Fence- Anthony
Leornas/laborer
1 4.0 4.0
3 19.0
OBSERVED WEATHER CONDITIONS
Weather Delay Sky Temp Average Precipitation Wind Ground/Sea Calamity
No
Filippin Engineering Page 1 of 2 Printed on 2/4/2021 at 01:30 PM PST
WEATHER REPORT
Temperature Precipitation Since Humidity Windspeed
Low High Avg Midnight 2 Days Ago 3 Days Ago Low Avg High Dew Avg Max Gust
47°F 73°F 59°F 0.01 in.0.02 in.0.03 in.24%45%74%36°F 8.8 mph 13 mph 26 mph
DAILY SNAPSHOT
06:00 AM 09:00 AM 12:00 PM 03:00 PM 06:00 PM 09:00 PM
clear-night
49°F
partly-cloudy-day
57°F
partly-cloudy-day
69°F
partly-cloudy-day
72°F
partly-cloudy-night
65°F
clear-night
60°F
By Date Copies To
Filippin Engineering Page 2 of 2 Printed on 2/4/2021 at 01:30 PM PST
Austin Della 1/13/2021