Loading...
HomeMy WebLinkAboutItem 6f. Railroad Safety Trail Taft to Pepper Additional Sidewalk and Lighting - Contract Change Orders Item 6f Department: Public Works Cost Center: 5010 For Agenda of: 7/20/2021 Placement: Consent Estimated Time: N/A FROM: Matt Horn, Public Works Director Prepared By: Bryan Wheeler, Transportation Planner / Engineer III SUBJECT: RAILROAD SAFETY TRAIL TAFT TO PEPPER ADDITIONAL SIDEWALK AND LIGHTING – CONTRACT CHANGE ORDERS, SPEC #91375 RECOMMENDATION 1. Authorize the installation of shared-use path lighting per City Engineering Standards along the Railroad Safety Trail (Taft to Pepper) alignment, deviating from Architectural Review Commission Resolution No. ARC-1008-17, Condition 3, which calls for “bollard style lighting”; and 2. Approve a construction contract change order to increase the Railroad Safety Trail (Taft to Pepper) Project construction contract by $40,000 to cover anticipated costs to install additional path safety lighting; and 3. Approve the transfer of $120,000 in funds from the Street Reconstruction and Resurfacing Master Account (Spec. No. 90346) to the Railroad Safety Trail (Taft to Pepper) project account (Spec. No. 91375) to fund additional pavement restoration along Pepper Street, increasing the total Railroad Safety Trail project budget from $6,060,108 to $6,180,108; and 4. Authorize the City Engineer to approve subsequent construction contract change orders up to and in excess of $100,000 if within total available project budget of $6,180,108. DISCUSSION Background In August of 2020, the construction contract for the Railroad Safety Trail (Taft to Pepper) Project, Spec. No. 91375, was awarded to Souza Contraction Inc. in the amount of $3,774,960. The project includes the extension of the Railroad Safety Trail south of Cal Poly from Taft Street to Pepper Street, including a pedestrian/bicycle bridge crossin g over the Union Pacific Railroad (UPRR) tracks between Phillips and Pepper Street. Construction began in October, 2020, and is progressing on schedule, with an anticipated completion date of September of 2021. At this time, staff has identified two modifications to the project designs that would improve the safety and functionality of the final project: 1. Safety Lighting: Installation of additional safety lighting along the trail alignment . Page 869 of 1183 Item 6f 2. Trail Extension: Extension of the southern terminus of the shared -use path from mid-block on Pepper Street approximately 200 feet further south to the intersection of Pepper Street & Mill Street. These two elements were contemplated in the original project designs but were ultimately omitted due to concerns that the total costs would exceed the available project budget, which could have resulted in further project delays and increased risk of forfeiting $3.2 million in Caltrans grant funds. The construction contract award ultimately came in below the initial Engineer’s Estimate and staff anticipates that there are sufficient contingency funds within the project budget to fund these additional design modifications, which are described in further detail below. Additional Safety Lighting As originally designed, the project included lighting only at the end points of the trail and along the portions of the trail alignment on the elevated bridge structure. However, upon further consideration staff recommends additional pathway lighting to maintain a consistent level of illumination throughout the trail and increase the perceived comfort of using the off-street pathway at night. While the City’s Architectural Review Committee (ARC) originally recommended use of short “bollard-style” fixtures for any trail lighting, City staff recommends the installation of City Standard pathway lighting (Attachment A), consistent with the existing lighting installations along other segments of the Railroad Safety Trail south of the Jennifer Street Bridge and within the recently construct ed trail segments in the Orcutt Area. See additional discussion later in this staff report regarding the proposed deviation from the ARC’s original recommendation. The proposed contract change order would include the installation of four (4) additional path lights along the trail segment that shifts away from California Boulevard behind the California Highway Patrol offices. An electrical conduit was already installed along this segment as part of the original project plans to power the lights along the bridge crossing the UPRR tracks; thus, additional hard-wired path lighting can be added without significant modifications to the existing electrical infrastructure. The estimated cost for this additional lighting is $40,000. Extension of Trail Terminus The current plans for the Railroad Safety Trail (Taft to Pepper) project reflect a southern terminus of the path mid-block on Pepper Street, approximately 200 feet north of the Pepper Street/Mill Street intersection. As originally designed, the tr ail terminus would include a ramp for bicycles to exit the trail to a shared travel lane on Pepper Street, while pedestrians would use the ramp to cross to the opposing side of Pepper Street mid-block to access the existing sidewalks on the west side (no sidewalks exist on the east side of Pepper Street). Staff is proposing to modify the project plans to include extension of the trail along the east side of Pepper Street 200 feet south to the Pepper Street/Mill Street intersection. In addition, the Pepper Street/Mill Street intersection would be converted to all-way stop control and hi-visibility crosswalks would be installed. Page 870 of 1183 Item 6f Extending the pathway at this time will provide a superior final project, with a seamless, ADA-compliant route all the way to the intersection of Mill and Pepper Streets without directing pedestrians to cross at an uncontrolled mid-block crossing on Pepper Street. In addition, constructing this extension at this time as part of the larger construction contract may provide cost savings compared to pursuing this modification at a later date as a stand-alone project. Attachment B illustrates the proposed path extension. Staff is currently working with the construction contractor to obtain a cost estimate to add this work as a contract change order. To avoid any unnecessary delays with continuing construction of the project, staff is requesting that Council authorize the City Engineer to approve subsequent contract change orders for this project if the related costs are within the total approved project budget and there are sufficient remaining contingency funds to complete construction. Pepper Street Reconstruction and Paving With the proposed construction change order to extend the Railroad Safety Trail project south to Mill Street, as discussed above, additional pavement repairs will be required along Pepper Street. This section of Pepper Street is proposed to be reconstructed later this fall as part of the 2021 Downtown Pavement Improvements Project and was included in the 2021 paving project bid package as an Additive Alternative to the base project. At the time this report was authored, the 2021 Downtown Pavement Improvements Project was still out to bid and a construction contract has yet to be awarded. In order to avoid any additional unnecessary construction impacts to the Pepper Street neighborhood following completion of the Railroad Safety Trail project, staff recommends that all of the pavement reconstruction proposed for Pepper Street be completed as part of current Railroad Safety Trail construction activities. In turn, the Pepper Street bid Additive Alternative would not be included in the contract award for the 2021 Downtown Pavement Improvements Project. To facilitate this approach, staff is requesting that Council authorize the transfer of $120,000 in 2021-2022 funds from the Streets Reconstruction and Resurfacing Master Account (Spec. No. 90346) originally intended for the Pepper Street portion of the 2021 paving project to the Railroad Safety Trail (Taft to Pepper) project account (Spec. No. 91375). Effectively, the funds originally planned for the Pepper Street paving as part of the 2021 paving project would instead be used to fund this same work as part of the Railroad Safety Trail project. Previous Council or Advisory Body Action On May 5, 2017, the Architectural Review Committee (ARC) approved the design and environmental study for the Railroad Safety Trail (Taft to Pepper) Project. In the ARC resolution approving the project (Attachment C), the committee included Condition #3, which related to the recommended style of path lighting: Final project design and construction drawings shall show the locations of all exterior lighting, including a graphic representation of the proposed lighting fixtures and cut sheets. The selected fixture(s) shall be shielded to ensure that light is directed downward consistent with the requirements of the City' Page 871 of 1183 Item 6f s Night Sky Preservation standards contained in Chapter 17. 23 of the Zoning Regulations. Lighting shall be low level (less than four feet in height), bollard style, and continuous (outside of street sources of lighting). The City Engineer and maintenance staff have significant concerns regarding potential for vandalism and maintenance requirements for low-height bollard-style lighting fixtures, particularly when located in off-street locations out of eyesight from well-populated public streets/spaces. Further, the City does not currently have a standard bollard-style lighting fixture and does not maintain an inventory of spare equipment to repair these type o f fixtures. For this reason, staff is requesting Council approval to allow for the installation of City Standard path lighting fixtures, which include an overhead light mounted at 16 feet in height, with a fixture design consistent with City Night Sky Preservation standards, and backlight shields that effectively illuminate the path, while minimizing light spillover beyond the footprint of the path itself. These path lights have been installed throughout the City, including along other segments of the Railroad Safety Trail, and have provided effective lighting with infrequent maintenance needs. The City Council approved advertisement of the Railroad Safety Trail (Taft to Pepper) Project on March 17, 2020 (Attachment D), and delegated award authority to the City Manager. The award of the Project was approved by the City Manager on August 21, 2020 (Attachment E). Policy Context The Railroad Safety Trail is identified as a “Tier 1” (highest priority) project in the City’s Active Transportation Plan (ATP) and supports the Major City Goal for Climate Action, Open Space and Sustainable Transportation. The proposed design modification to extend the trail to the Pepper Street/Mill Street intersection is consistent with the project alignment identified in the ATP, and the proposed path lighting installations are consistent with the ATP Design Guidelines, summarized as follows: 8.18 Vandal-resistant lighting shall be provided for all shared-use paths and shall be consistent with City plans, located overhead (including in under crossings), generally not more than 16 feet high, direct light downward, have bulbs well recessed to avoid direct glare, and comply with City regulations and engineering standards. 8.19 Solar path lighting options should be considered for new installations. While the City is investigating a range of solar path lighting products, a City Standard solar path lighting fixture has not yet been selected. While staff plans to incorporate solar path lighting into future projects once a standard product has been confirmed, City Standard hard-wired path lighting is proposed for this particular installation because there is existing electrical conduit available, and this solution is expected to reduce up-front capital costs and result in more certain long-term maintenance obligations. Page 872 of 1183 Item 6f Public Engagement Development of the Railroad Safety Trail (Taft to Pepper) Project included several public engagement opportunities, including outreach activities as part of the City’s previous Bicycle Transportation Plan, recently adopted Active Transportation Plan, and several project-specific public hearings for the City’s Active Transportation Committee, ARC and City Council meetings. This specific agenda item was noticed consistent with the City’s Public Engagement and Noticing (PEN) Manual. CONCURRENCE The Public Works Director, City Engineer, Construction Manager and Community Development Director concur with the recommendations in this staff report. ENVIRONMENTAL REVIEW An Initial Study/Mitigated Negative Declaration (IS/MND) was prepared for this Project, approved by the ARC, and filed to the County of San Luis Obispo on May 1 5, 2017. As mentioned above, the original project proposed low-height lighting only along the bridge structure; however, staff proposes additional safety lighting to improve the perceived safety of the pathway at night. The additional lighting would use a City Standard path lighting fixture, which conforms with the City’s Night Sky Ordinance, and would include backlight shields to minimize light spillover beyond the footprint of the path itself. The Community Development Director has reviewed this proposal and determined that the additional lighting would not create potential significant aesthetic impacts, and the final project design remains in substantial conformance with the original project description and mitigation requirements identified in the approved IS/MND. FISCAL IMPACT Budgeted: Yes Budget Year: 2017-18 Funding Identified: Yes Page 873 of 1183 Item 6f Fiscal Analysis: Funding Sources Total Budget Available Current Funding Request Remaining Balance (uncommitted) Annual Ongoing Cost General Fund $0 $0 $0 Local Revenue Measure $117,108 $0 $0 Local Revenue Measure (transfer from Streets R&R Account) $0 $120,000 $120,000 State $3,494,000 $0 $0 Federal $0 $0 $0 Sewer Fund $50,000 $0 $0 Other: TIF $2,399,000 $0 $416,517 Total $6,060,108 $120,000 $536,517 $ Sewer Fund (602.950 1.71501) Downtwon Paving Improvement Project (90346) 507 Fund 401 Fund 201 Fund 507 Fund 602 101 Fund Bid Total:$163,852 $3,244,000 $117,108 $250,000 $0 $0 $3,774,960 Contingencies $630,000 $0 $0 $0 $0 $0 $630,000 Total for Construction $793,852 $3,244,000 $117,108 $250,000 $0 $0 $4,404,960 Construction Management:$518,934 $518,934 Materials Testing:$96,013 $96,013 Design Support:$129,994 $129,994 UPRR Plancheck $75,000 $75,000 Proejct Sewer Work $50,000 $50,000 ROW Acquisition Costs $368,690 $368,690 Total Project Cost $1,982,483 $3,244,000 $117,108 $250,000 $50,000 $0 $5,643,591 Available Project Balace $416,517 $0 $0 $0 $0 $0 $416,517 Total Project Budget $2,399,000 $3,244,000 $117,108 $250,000 $50,000 $0 $6,060,108 Additional Funding:$0 $0 $0 $0 $120,000 $120,000 New Project Budget $6,180,108 Available Project Balance (after current transfer request) $536,517 Railroad Safety Trail - Taft to Pepper, Specification No. 91375 TIF Account (507.5010. 71006) ATP Grant Account (401.5010.710 06) Local Revenue Account (201.5010. 71006) SHA Grant Account (507.5010. 71006) Project Total Costs Page 874 of 1183 Item 6f The project was approved as part of the 2017-19 Financial Plan. When awarded, the there was a total of $6,010,108 available in the project budget, which was sufficient to fully fund the total costs of construction, contingencies, construction engineering support, construction management support, and materials testing services. An additional $50,000 was allocated to the project from the Sewer Fund (602.9501.71501) for to improve an existing sewer line under a Council-approved change order. Contingencies for the project were set at $630,000, and $213,483 in contingency funding has been expended thus far. Staff is estimating the additional path lighting will cost $40,000. Staff is requesting a transfer of $120,000 from the 2021 Downtown Paving Improvements Project, Spec. 1000167 for this work. This amount is the prorated portion of the project allocated for the street reconstruction on Pepper Street. This portion of Pepper Street will be removed from the 2021 Downtown Paving Improvements Project. With this transfer of funds and after accounting for the $40,000 expenditure for additional path lighting, a total of $496,517 will remain in the project account for the proposed extension of the path south to Mill Street. Staff believes that this funding will be sufficient to fund the path extension to Mill Street and any minor additional costs that may arise through completion of the project. Approval of the staff recommendations presented in this report is requested at this time, as there will not be another opportunity to present these requests for Council approval until August 17th, as there is no Council hearing scheduled for the first week in August. The construction contract is scheduled to be completed by September 10th, and staff and the contractor will need time to process a change order before the end of construction. Delaying until August 17th may not provide enough time to receive the necessary approvals or to complete the work. Remaining unused funds from the project account will be transferred back to the corresponding account balances, depending on fund source, upon completion of construction. ALTERNATIVES 1. City Council could deny the request to utilize City Standard path lighting fixtures, deviating from the ARC’s previous recommendation to use low-height “bollard-style” lighting along the trail. Staff does not recommend this, as bollard -style lighting presents a higher risk of vandalism and increased ongoing maintenance costs. Further, the City does not have an approved standard bollard -style light fixture, thus, City Streetlight Maintenance staff would need to invest additional resources in order to maintain a new product in a state of good repair. 2. City Council could deny the request to authorize the City Engineer to approve additional construction contract change orders and require that staff return to the Council to approve subsequent change orders exceeding $100,000. Staff does not recommend this, as could result in project delays and potential for increased costs to either re-mobilize the current contractor or to implement these changes as future stand-alone capital projects. Page 875 of 1183 Item 6f 3. City Council could deny the request to transfer funds from the Street Reconstruction and Resurfacing Master Account (Spec. No. 90346) to the Railroad Safety Trail (Taft to Pepper) project account (Spec. No. 91375) to fund additional pavement restoration along Pepper S treet. Under this alternative, the Railroad Safety Trail project would restore a portion of the pavement area on Pepper Street, then the remainder of the pavement would be rehabilitated as part of the 2021 Downtown Pavement Improvements Project later this fall. Staff does not recommend this alternative, as this would result in extended construction impacts and inconvenience to the Pepper Street neighborhood. ATTACHMENTS A. City Standard Plan for Path Lighting (Eng. Std. 7905) B. Railroad Safety Trail (Taft to Pepper) – Pathway Extension Plan C. Architecture Review Commission Resolution (ARC-1008-17, May 15, 2017) D. Council Agenda Report – Railroad Safety Trail Authorization to Advertise (March 17, 2020) E. City Manager Report – Railroad Safety Trail Construction Contract Award Page 876 of 1183 MANUFACTURER & MODEL NO: LUMINAIRE: LUMINIS SR135-L1W30r1-R2/APA-PAA518 POLE: LUMINIS PAA518-BKT (Confirm with City the latest luminaire and pole model no. before ordering) COLOR: Jet Black Marine grade powder coat (BKT). INSTALLATION NOTES: (T) HOUSING/SHADE: Cast aluminum housing and shade. Corrosion resistant 356 aluminum alloy with 0.1% CU content. (2) LED: (SR135-L1 W30r1-R2) Light-emitting Diode, 4000K, 34W input watts, minimum 4170 delivered lumens, IES Type II distribution, full cutoff. (3) POWER SUPPLY/DRIVER: (120-277) multi-volt power supply. Verify system voltage before ordering. (4) POLE MOUNT: (APA) 1%" 0 shepherd arm aluminum side pole mount. (5) POLE: (PAA518) Luminis 5" diameter x min .125 wall. 6061-T6 aluminum alloy, 18' height, rated for min. 80 MPH wind load with reinforced cast base plate and cast aluminum base cover. Provide end cap. (¥) ANCHOR BOLTS: Galvanized steel, %" 0 x 30" with 4" leg, (4) total with galvanized nuts and washers (8) total. @ PCC FOUNDATION: Class 3 concrete (S) PULL BOX: See Engineering Standard 7520. (9) CONDUIT: 2" min. @) Install City furnished light number plaque. 4 1X2X3 5 10! 18’ / GENERAL NOTES:16'± A. Verify lighting system voltage before ordering. B. Luminaire and post shall be from same manufacturer. C. Include photo cell on each pole unless controlled by a remote photocell or as noted otherwise on plans. D. Install light/pole per manufacturer's directions and Section 86 of the Standard Specifications. E. Conductors, conduit, ground rod, and circuitry must comply with Engineering Standard 7520. 2' from edge of path Pack grout in gap between base plate and foundation after plumbing the fixture. Allow drainage from inside pole. lMMFG TIFF ® r^ 636" :4 ‘2. ■ 7 b X 97T- IU Lighting Pull Box lid flush with grade for finished surfaces, 1" above grade in other areas, at each post light. See Engineering Standard 7520.Foundation or direct burial 24" 0 REVISIONS BY APP DATE E Design / text SR BL 1-14 PATH LIGHTINGin nFixture Model; Drafting edits JDL MH 5-13 >I . g Drafting edits JDL MH 2-14 7905STANDARD CURRENT AS OF: AUGUST 2020 Page 877 of 1183 Page 878 of 1183 Reference Documents:City Standard Specifications - May 2018 EditionCity Engineering Standards - May 2018 Edition1.IT SHALL BE THE RESPONSIBILITY OF THE CONTRACTOR ORPERMITTEE TO CONTACT "UNDERGROUND SERVICE ALERT OFNORTHERN CALIFORNIA" BY PHONE AT 8-1-1 FORTY-EIGHT (48)HOURS PRIOR TO START OF CONSTRUCTION FOR LOCATION OFPOWER, TELEPHONE, OIL AND NATURAL GAS UNDERGROUNDFACILITIES. CONTRACTOR OR PERMITTEE SHALL ALSOCONTACT THE APPROPRIATE AGENCY FOR THE LOCATION OFCABLE T.V., WATER, SEWER, DRAINAGE OR UNDERGROUNDFACILITIES.2. THE CONTRACTOR SHALL POSSESS A CLASS 'A' LICENSE AT THETIME OF BID OPENING.index to planssheet no.descriptiongeneral notes:San Luis Obispo County, CaliforniaRailroad Safety TrailTaft to PepperProject1234-567APPROVED BYSPECIFICATION NO. DATEofSHEETManuel Guzman, Construction Engineering Manager R.C.E. C78236 Approved Datefor Matthew Horn, City Engineer7June 2021913751FILE NO./LOCATIONTITLE SHEETTYPICAL SECTIONSPLAN AND PROFILECONSTRUCTION DETAILSUTILITY PLANPAVEMENT DELINEATION & SIGN PLANAB - AGGREGATE BASEAC - ASPHALT CONCRETEAP - ANGLE POINTBC - BEGIN HORIZONTAL CURVEBeg - BEGINC&G - CURB AND GUTTERConc - CONCRETEDI - DRAINAGE INLETEC - END HORIZONTAL CURVEElev - ELEVATIONExist - EXISTINGFL - FLOW LINEHMA - HOT MIX ASPHALTL - LENGTHLt - LEFTNo. - NUMBERN.T.S. - NOT TO SCALEO.C. - ON CENTEROG - ORIGINAL GROUNDPCC - PORTLAND CEMENT CONCRETE - POINT OF COMPOUND CURVER - RADIUSRt - RIGHTR/W - RIGHT OF WAYShld - SHOULDERSNS - STREET NAME SIGNSt - STREETSTA - STATIONStd - STANDARDSW - SIDEWALKT - SEMI-TANGENTTC - TOP OF CURBUPRR - UNION PACIFIC RAILROADVar - VARIESabbreviations:END CONSTRUCTIONSTA "PS" 104+97.72BEGIN CONSTRUCTIONSTA "PS" 102+67.80N01600'800'PRELIMINARY, NOTFOR CONSTRUCTIONSUBMITTAL100%sheet indexT-1X-5L-5CD-10 TO CD-11U-5PD-5T-1N:\US\San Luis Obispo\Projects\561\11221358\Digital_Design\ACAD 2018\Civil 3D\11221358T001.dwg 6/14/2021 3:19:30 PMPage 879 of 1183 "PS" LINE91375CITY SPECIFICATION NO.DATE:PROJECT TITLE:SHEET TITLE:ofSHEET NO.7DESIGNED BY:DRAWN BY:CHECKED BY:J. WALTERAPPROVED BY:J. WALTERSCALE:PLAN FILE NO. / LOCATION6/14/21N:\US\San Luis Obispo\Projects\561\11221358\Digital_Design\ACAD 2018\Civil 3D\11221358X001.dwg 6/14/2021 3:23:45 PM2N.T.S.TYPICAL SECTIONSJ. VANEGAS-MORANJ. VANEGAS-MORANX-5PRELIMINARY, NOTFOR CONSTRUCTIONSUBMITTAL100%Page 880 of 1183 91375CITY SPECIFICATION NO.DATE:PROJECT TITLE:SHEET TITLE:ofSHEET NO.7DESIGNED BY:DRAWN BY:CHECKED BY:J. WALTERAPPROVED BY:J. WALTERSCALE:PLAN FILE NO. / LOCATION6/14/21N:\US\San Luis Obispo\Projects\561\11221358\Digital_Design\ACAD 2018\Civil 3D\11221358L001.dwg 6/14/2021 3:59:31 PM3H: 1" = 20' ; V: 1" = 4'PLAN AND PROFILEJ. VANEGAS-MORANJ. VANEGAS-MORANNL-5PRELIMINARY, NOTFOR CONSTRUCTIONSUBMITTAL100%Page 881 of 1183 91375CITY SPECIFICATION NO.DATE:PROJECT TITLE:SHEET TITLE:ofSHEET NO.7DESIGNED BY:DRAWN BY:CHECKED BY:J. WALTERAPPROVED BY:J. WALTERSCALE:PLAN FILE NO. / LOCATION6/14/21N:\US\San Luis Obispo\Projects\561\11221358\Digital_Design\ACAD 2018\Civil 3D\11221358C001.dwg 6/14/2021 3:28:33 PM41" = 20'CONSTRUCTION DETAILS - REMOVAL PLANJ. VANEGAS-MORANK.SANNC-10PRELIMINARY, NOTFOR CONSTRUCTIONSUBMITTAL100%Page 882 of 1183 91375CITY SPECIFICATION NO.DATE:PROJECT TITLE:SHEET TITLE:ofSHEET NO.7DESIGNED BY:DRAWN BY:CHECKED BY:J. WALTERAPPROVED BY:J. WALTERSCALE:PLAN FILE NO. / LOCATION6/14/21N:\US\San Luis Obispo\Projects\561\11221358\Digital_Design\ACAD 2018\Civil 3D\11221358C002.dwg 6/14/2021 3:57:33 PM51" = 5'CONSTRUCTION DETAILS - CURB RAMP DETAILSJ. VANEGAS-MORANK. SANNC-11PRELIMINARY, NOTFOR CONSTRUCTIONSUBMITTAL100%STAMPED CONCRETE DETAILSTAMPED CONCRETE NOTES:Page 883 of 1183 LEGEND:NOTES:91375CITY SPECIFICATION NO.DATE:PROJECT TITLE:SHEET TITLE:ofSHEET NO.7DESIGNED BY:DRAWN BY:CHECKED BY:J. WALTERAPPROVED BY:J. WALTERSCALE:PLAN FILE NO. / LOCATION6/14/21N:\US\San Luis Obispo\Projects\561\11221358\Digital_Design\ACAD 2018\Civil 3D\11221358U001.dwg 6/14/2021 3:46:57 PM61" = 20'UTILITY PLANJ. VANEGAS-MORANJ. VANEGAS-MORANU-5NPRELIMINARY, NOTFOR CONSTRUCTIONSUBMITTAL100%Page 884 of 1183 91375CITY SPECIFICATION NO.DATE:PROJECT TITLE:SHEET TITLE:ofSHEET NO.7DESIGNED BY:DRAWN BY:CHECKED BY:J. WALTERAPPROVED BY:J. WALTERSCALE:PLAN FILE NO. / LOCATION6/14/21N:\US\San Luis Obispo\Projects\561\11221358\Digital_Design\ACAD 2018\Civil 3D\11221358PD001.dwg 6/14/2021 3:48:58 PM71" = 20'PAVEMENT DELINEATION AND SIGN PLANJ. VANEGAS-MORANJ. VANEGAS-MORANNPD-5PRELIMINARY, NOTFOR CONSTRUCTIONSUBMITTAL100%NPage 885 of 1183 Page 886 of 1183 RESOLUTION NO. ARC -1008-17 A RESOLUTION OF THE ARCHITECTURAL REVIEW COMMISSION OF THE CITY OF SAN LUIS OBISPO, CALIFORNIA, APPROVING THE DESIGN OF 1,700 -LINEAR FOOT SECTION OF THE RAILROAD SAFETY TRAIL (TAFT TO PEPPER), INCLUDING A BRIDGE OVER THE UNION PACIFIC RAILROAD TRACKS AND ASSOCIATED TREE REMOVALS, AND ADOPTION OF A MITIGATED NEGATIVE DECLARATION, AS REPRESENTED IN THE STAFF REPORT AND ATTACHMENTS DATED MAY 15, 2017 WEST OF CALIFORNIA BOULEVARD, TAFT TO PEPPER (ARCH -0360-2017) WHEREAS, the Architectural Review Commission of the City of San Luis Obispo conducted a public hearing in the Council Hearing Room of City Hall, 990 Palm Street, San Luis Obispo, California, on May 15, 2017, pursuant to a proceeding instituted under ARCH -0360-2017, City of San Luis Obispo Public Works Department, applicant; and WHEREAS, notices of said public hearing were made at the time and in the manner required by law; and WHEREAS, the Architectural Review Commission of the City of San Luis Obispo has duly considered all evidence, including the testimony of the applicant, interested parties, and evaluation and recommendations by staff, presented at said hearing; and NOW, THEREFORE, BE IT RESOLVED by the Architectural Review Commission of the City of San Luis Obispo as follows: SECTION 1. Findings. The Architectural Review Commission hereby grants approval to application ARCH -0360-2017, based on the following findings: 1, That the project will not be detrimental to the health, safety, and welfare of persons living or working at the site or in the vicinity because the project will be compatible with site constraints and the scale and character of the site and the surrounding neighborhood. 2. The proposed Railroad Safety Trail (Taft to Pepper segment) is consistent with General Plan Circulation Element Policies regarding bicycle transportation by: expanding the bicycle network to encourage bicycle use and making bicycling safe, convenient and enjoyable Policies 4.1.1 Bicycle Use and 4.1.5 Bikeway Design and Maintenance); encouraging the use of bicycles by students and staff traveling to local educational facilities (Policy 4.1.2 Campus and School Site Trips); by identifying and pursuing the acquisition of right-of-ways needed to implement the Railroad Safety Trail as identified in the Bicycle Transportation Plan Policy 4.1.10 Right-of-way Acquisition); and by obtaining railroad right-of-way and easements to establish a separated bike path and pedestrian trail through San Luis Obispo Policy 4.2.5 Railroad Bikeway and Trail). 3. The project implements the Bicycle Transportation Plan (November 2013), which identifies the Railroad Safety Trail as "the top priority project" and calls for safe, reliable, and efficient Page 887 of 1183 Resolution No. ARC -1008-17 ARCH -0360-2017 (Railroad Safety Trail — Taft to Pepper) Page 2 connections to all major destinations throughout the City, for both transportation and recreational purposes. The project furthers implementation of bicycling network objectives identified in the Bicycle Transportation Plan, including Objective 3 (increase bicycle use for transportation to a 20% mode share). SECTION 2. Environmental Review, The Architectural Review Commission hereby adopts the proposed Mitigated Negative Declaration and associated Mitigation and Monitoring Program, finding that it adequately addresses the project's potentially significant impacts on the environment, with the incorporation of the following mitigation measures: Air Ouality Mitigation Measure AO -1: During construction/ground disturbing activities, the applicant shall irrrplement the following particulate (dust) control measures. These measures shall be shown on grading and building plans. In addition, the contractor shall designate a person or persons to monitor the dust control program and to order increased watering, modify practices as necessary, to prevent transport of dust offsite. Their duties shall include holiday and weekend periods when work may not be in progress. The name and telephone number of such persons shall be provided to the Community Development and Public Works Departments prior to commencement of construction. a. Reduce the amount of disturbed area where possible. b. Use water trucks or sprinkler systems in sufficient quantities to prevent airborne dust from leaving the Project site and from exceeding the APCD's limit of 20 percent opacity for no greater than three minutes in any 60 -minute period. Increased watering frequency will be required whenever wind speeds exceed 15 mph and cessation of grading activities during periods of winds over 25 mph. Reclaimed (non -potable) water is to be used in all construction and dust -control work. c. All dirt stock pile areas (if any) shall be sprayed daily and covered with tarps or other dust barriers as needed. d. Permanent dust control measures identified in the approved Project revegetation and landscape plans shall be implemented as soon as possible, following completion of any soil disturbing activities. e. Exposed grounds that are planned to be reworked at dates greater than one month after initial grading shall be sown with a fast germinating, non-invasive, grass seed and watered until vegetation is established. f. All disturbed soil areas not subject to revegetation shall be stabilized using approved chemical soil binders, jute netting, or other methods approved in advance by the APCD. g. All roadways, driveways, sidewalks, etc. to be paved shall be completed as soon as possible. In addition, building pads shall be laid as soon as possible after grading unless seeding or soil binders are used. h. Vehicle speed for all construction vehicles shall not exceed 15 mph on any unpaved surface at the construction site. i. All trucks hauling dirt, sand, soil, or other loose materials, are to be covered or shall maintain at least two feet of freeboard (minimum vertical distance between top of load and top of trailer) in accordance with California Vehicle Code Section 23114. j. Install wheel washers where vehicles enter and exit unpaved roads onto streets, or wash off trucks and equipment leaving the site. Page 888 of 1183 Resolution No. ARC -1008-17 ARCH -0360-2017 (Railroad Safety Trail — Taft to Pepper) Page 3 k. Sweep streets at the end of each day if visible soil material is carried onto adjacent paved roads. Water sweepers shall be used with reclaimed water where feasible. Roads shall be pre -wetted prior to sweeping when feasible. If drought conditions persist at the time of construction, the following alternative methods for dust control are recommended. The contractor or builder shall implement the use of an APCD-approved dust suppressant(s) to reduce the amount of water used for fugitive dust control. For a list of suppressants, see Section 4.3 of the CEQA Air Quality Handbook that can be accessed at the following website: slocleanair.org/business/landuseceqa.php. Monitoring Pro am, AQ -1: These conditions shall be noted on all Project grading and building plans. Public Works Inspectors shall conduct field monitoring. Mitigation Measure A0-2: Prior to any construction activities at the site, the Project proponent shall ensure that all equipment and operations are compliant with California Air Resource Board and APCD permitting requirements, by contacting the APCD Engineering Division at (805) 781- 5912 for specific information regarding permitting requirements. Monitoring Program, AQ -2: These conditions shall be noted on all Project grading and building plans. Public Works Inspectors shall conduct field monitoring. Mideation .Measure AQ 3: To reduce impacts to sensitive receptors as a result of emissions from diesel vehicles and equipment used to construct the Project and export soil from the Project site, the applicant shall implement the following idling control techniques: 1. California Diesel Idling Regulations a. On -road diesel vehicles shall comply with Section 2485 of Title 13 of the California Code of regulations. This regulation limits idling from diesel -fueled commercial motor vehicles with gross vehicular weight ratings of more than 10,000 pounds and licensed for operation on highways. It applies to California and non -California based vehicles. In general, the regulation specifies that drivers of said vehicles: 1. Shall not idle the vehicle's primary diesel engine for greater than 5 minutes at any location, except as noted in Subsection (d) of the regulation; and, 2. Shall not operate a diesel -fueled auxiliary power system (APS) to power a heater, air conditioner, or any ancillary equipment on that vehicle during sleeping or resting in a sleeper berth for greater than five minutes at any location when within 1,000 feet of restricted area, except as noted in Subsection (d) of the regulation. b. Off-road diesel equipment shall comply with the five-minute idling restriction identified in Section 2449(d)(2) of the California Air Resources Board's In -Use Off -Road Diesel regulation. c. Signs must be posted in the designated queuing areas and job sites to remind drivers and operators of the state's 5 -minute idling limit. 2. Diesel Idling Restrictions Near Sensitive Receptors (residential homes). In addition to the State required diesel idling requirements, the Project applicant shall comply with these more restrictive requirements to minimize impacts to nearby sensitive receptors: Page 889 of 1183 Resolution No. ARC -1008-17 ARCH -0360-2017 (Railroad Safety Trail — Taft to Pepper) Page 4 a. Staging and queuing areas shall not be located within 1,000 feet of sensitive receptors. b. Diesel idling within 1,000 feet of sensitive receptors shall not be permitted. c. Use of alternative fueled equipment is recommended. d. Signs that specify the no idling areas must be posed and enforced at the site. 3. Soil Transport. The final volume of soil that will be hauled off-site, together with the fleet mix, hauling route, and number of trips per day will need to be identified for the APCD. Specific standards and conditions will apply. Monitoring Program, AQ -3: These conditions shall be noted on all Project grading and building plans. Public Works Inspectors shall conduct field monitoring. Mitigation Measure AQ -4: Prior to construction, a geological evaluation shall be conducted to determine the presence of NOA. If NOA is not present, an exemption request must be filed with the APCD. If NOA is found, the City must comply with all requirements outlined in the Asbestos Air Toxics Control Measure (ATOM), which may include development of an Asbestos Dust Mitigation Plan and an Asbestos Health and Safety Program for approval by the APCD. Monitoring Proff, n, AQ -4: These conditions shall be noted on all Project grading and building plans. Public Works Inspectors shall conduct field monitoring. If required, the Asbestos Dust Mitigation Plan and Asbestos Health and Safety Program shall be submitted to APCD prior to grading and construction. A copy of the Asbestos Dust Mitigation Plan and Asbestos Health and Safety Program shall be available onsite during grading and construction, and shall be implemented as necessary. Mitigation Measure AQ -5: If asbestos containing materials are encountered during construction activities, the Project may be subject to various regulatory jurisdictions, including the requirements stipulated in the National Emission Standard for Hazardous Air Pollutants (40 CFR 61, Subpart M asbestos NESHAP). Monitoring Pro am, AQ -5: These conditions shall be noted on all Project grading and building plans. Public Works Inspectors shall conduct field monitoring. Mitigation Measure AQ -6: Should hydrocarbon contaminated soil be encountered during construction activities, the APCD must be notified as soon as possible and no later than 48 hours after affected material is discovered to determine if an APCD Permit will be required. In addition, the following measures shall be implemented immediately after contaminated soil is discovered: 1. Covers on storage piles shall be maintained in place at all times in areas not actively involved in soil addition or removal; 2. Contaminated soil shall be covered with at least six inches of packed uncontaminated soil or other TPH-non-permeable barrier such as plastic tarp. No headspace shall be allowed where vapors could accumulate; Covered piles shall be designated in such a way to eliminate erosion due to wind or water. No openings in the covers are permitted; Page 890 of 1183 Resolution No. ARC -1008-17 ARCH -0360-2017 (Railroad Safety Trail — Taft to Pepper) Page 5 4. The air quality impacts from the excavation and haul trips associated with removing the contaminated soil must be evaluated and mitigated if total emissions exceed the APCD's construction phase thresholds; 5. During soil excavation, odors shall not be evident to such a degree as to cause a public nuisance; and, 6. Clean soil must be segregated from contaminated soil. The notification and permitting determination requirements shall be directed to the APCD Engineering & Compliance Division at (805) 781-5912. Monitoring Program, AQ -6. These conditions shall be noted on all Project grading and building plans. Public Works Inspectors shall conduct field monitoring. Biological Resources Mitigation Measure BI0-1: In the event that special -status plant species are observed within the Project site, all individuals will be flagged by a qualified biologist prior to construction activities, so that they may be avoided. If special -status plants cannot be avoided by Project activities, the appropriate permits will be obtained prior to the start of construction activities. A restoration plan will be prepared for the Project (BIO -2), and will be implemented as necessary. Monitoring Program, B10-1: This condition shall be noted on all Project grading and building plans. City staff will periodically inspect the site regarding continued compliance with the above mitigation measure. Mitigation Measure BI0-2: Prior to construction, the City will prepare a restoration plan that provides for a 1:1 restoration ratio for temporary and permanent impacts, unless otherwise directed by regulatory agencies. Any revegetation will be conducted using only native plant species, and will be conducted outside of the UPRR right-of-way. The restoration plan will include specifications for invasive species abatement and monitoring. Monitoring Program, BIO -2: This condition shall be noted on all Project grading and building plans. The restoration plan shall be reviewed by the City's Natural Resources Manager. City staff will periodically inspect the site for implementation of the restoration plan and continued compliance with the above mitigation measure. Mitigation Measure „B10-3: Prior to construction, a Storm Water Pollution Prevention Plan or Water Pollution Control Plan for the Project will be prepared. Provisions of this plan shall be implemented during and after construction as necessary to avoid and minimize erosion and storm water pollution in and near the work area. Monitoring Proaram, BIO -3: This condition shall be noted on all Project grading and building plans. The Storm Water Pollution Prevention Plan or Water Pollution Control Plan shall be reviewed by the RWQCB and City's Natural Resources Manager. City staff will periodically inspect the site for implementation of the Storm Water Pollution Prevention Plan or Water Pollution Control Plan and continued compliance with the above mitigation measure. Page 891 of 1183 Resolution No. ARC -1008-17 ARCH -0360-2017 (Railroad Safety Trail — Taft to Pepper) Page 6 Mitigation Measure Bio -4: Prior to construction, all personnel will participate in an environmental awareness training program conducted by a qualified biologist. Monitorimr, Program, BIO -4: The contractor shall provide City staff proof of compliance regarding implementation of the environmental awareness training program. Mitivation Measure B10-5: During construction, the cleaning and refueling of equipment and vehicles will occur only within a designated staging area and at least 100 ft from wetlands or culverts that outflow to wetlands. At a minimum, equipment and vehicles will be checked and maintained on a daily basis to ensure proper operation and avoid potential leaks or spills. Monitorin.g Pro am BIO -5: This condition shall be noted on all Project grading and building plans. City staff will periodically inspect the site regarding continued compliance with the above mitigation measure. N itiaation Measure BIO 6: Prior to removal of Eucalyptus tree or other large trees, a qualified biologist will survey the trees to determine presence of roosting monarch butterflies. If roosting is identified (e.g., a visible "clump" over a period of time), tree removal will be scheduled outside of the roosting period (generally November to March). Monitoring Pro am BIO -6: This condition shall be noted on all Project grading and building plans. City staff will periodically inspect the site regarding continued compliance with the above mitigation measure. Mitigation Measure BI0-7: If construction activities are proposed during the typical nesting season (February 15 to September 1), a nesting bird survey will be conducted by a qualified biologist no more than two weeks prior to the start of construction to determine presence/absence of nesting birds within the Biological Study Area and immediate vicinity. Caltrans will be notified if nesting birds are observed during the surveys and will facilitate coordination with the USFWS if necessary to determine an appropriate avoidance strategy. Likewise, coordination with CDFW will be facilitated by the City if necessary to devise a suitable avoidance plan. If raptor nests are observed within the Project site during the pre -construction nesting bird surveys, the nest(s) shall be designated an Environmental Sensitive Area and protected by a minimum 500 -foot avoidance buffer until the breeding season ends or until a qualified biologist determines that all young have fledged and are no longer reliant upon the nest or parental care for survival. Similarly, if active passerine nests are observed within the Project Site during the pre -construction nesting bird surveys, the nest(s) shall be designated an Environmentally Sensitive Area and protected by a minimum 250 -foot avoidance buffer until the breeding season ends or until a qualified biologist determines that all young have fledged and are no longer reliant upon the nest or parental care for survival. Resource agencies may consider proposed variances from these buffers if there is a compelling biological or ecological reason to do so, such as protection of a nest via concealment due to site topography. Moriitoring Pro , ain BIO -7: This condition shall be noted on all Project grading and building plans. City staff will periodically inspect the site regarding continued compliance with the above mitigation measure. Page 892 of 1183 Resolution No. ARC -1008-17 ARCH -0360-2017 (Railroad Safety Trail — Taft to Pepper) Page 7 Mitigation Measure BI0-8 Prior to construction, the City will prepare a Tree Protection and Restoration Plan to be reviewed and approved by the City Arborist and City Natural Resources Manager. Requirements shall include but not be limited to: the protection of trees with construction setbacks from trees; construction fencing around trees; grading limits around the base of trees as required; and a replacement plan for trees removed including replacement at a minimum 1:1 ratio. Removal of native trees shall require a minimum 4:1 replacement ratio. The Tree Protection and Restoration Plan shall include, but not be limited to, the following information: a. Specific areas proposed for revegetation and their size. b. Implementation plan (rationale for expecting implementation success, responsible parties, schedule, site preparation, and planting plan); c. Specific habitat management and protection concepts to be used to ensure long-term maintenance and protection of the trees (i.e.: quarterly and annual surveys to be conducted for a minimum of five years; protection fencing and signage where necessary; and weed abatement); d. Contingency measures in the event a planted tree does not survive, including replacement of the tree to ensure no net loss of trees in the long-term; e. Reporting requirements to ensure consistent data collection and reporting methods used by monitoring personnel; f. Funding mechanism. Monitoring Program, BIO -8: The Tree Protection and Restoration Plan shall be approved by the City Arborist and Natural Resources Manager prior to construction. Compliance with the Plan and submittal of required Monitoring Reports will be verified by the City Arborist and Natural Resources Manager. Cultural Resources 1'Iiti ,atioij Measure CR -1: If, during the course of constructing and implementing the proposed Project, archaeological, paleontological, or cultural resources (i.e., prehistoric sites, historic sites, or isolated artifacts and features) are discovered, the contractor shall halt all ground disturbing activities immediately within 50 feet of the discovery, the City shall be notified, and a professional archaeologist, architectural historian, or paleontologist (depending on the nature of the finding) shall be retained to determine the significance of the discovery. The City shall consider mitigation recommendations presented by the professional, and the City shall consult and agree upon implementation of a measure(s) that they deem feasible and appropriate. Such measures may include avoidance, preservation in place, excavation, documentation, curation, data recovery, or other appropriate measures. The City shall be required to implement any mitigation necessary for the protection of archaeological, paleontological, and cultural resources. Monitoring Program, CR -1: All mitigation measures shall be noted on Project grading and building plans, and be clearly visible to contractor and City inspectors. City staff will periodically inspect the site for continued compliance with the above mitigation measure. Mideat on_Measure CR -2: In the event of human burial discovery, no further disturbance shall occur within 100 feet of the finding until the County of San Luis Obispo (County) Coroner has made a determination of origin and disposition pursuant to PRC Section 5097.98. The County Coroner must be notified of the find immediately. If the human remains are determined to be Page 893 of 1183 Resolution No. ARC -1008-17 ARCH -0360-2017 (Railroad Safety Trail — Taft to Pepper) Page 8 Native American, the County Coroner will notify the Native American Heritage Commission within 24 hours, which will determine and notify a Most Likely Descendant (MLD). The City shall allow the MLD to complete an inspection of the site (typically within 48 hours of notification) and shall comply with MLD recommendations, which may include scientific removal and nondestructive analysis of human remains and items associated with Native American burials. Monitoring* Program„ CR -2: All mitigation measures shall be noted on Project grading and building plans, and be clearly visible to contractor and City inspectors. City staff will periodically inspect the site for continued compliance with the above mitigation measure. Miti ation Measure CR -3: Additional archaeological surveys will be conducted in association with subsequent environmental review pursuant to the California Environmental Quality Act if Project limits are extended beyond the present survey limits. Monitoring; Program, CR -3: If Project conditions change, additional cultural surveys and reporting will be conducted. Mifi,4ation Measure CR -4: During removal of vegetation within any areas previously determined to be inaccessible due to vegetation, including an approximately 100 -foot segment behind the California Highway Patrol facility, a qualified archaeologist shall monitor vegetation removal and conduct a surface survey to confirm the presence or absence of archaeological resources. In the event of resource discovery during the survey, and at any time during construction, the resource shall be evaluated pursuant to mitigation measure CR -1 and the City of San Luis Obispo Archaeological Resource Preservation Program Guidelines (October 2009). Prior to redirecting or resuming construction, a Cultural Resources Monitoring Plan, prepared by a qualified archaeologist, shall be prepared and implemented in the event of resource discovery. The Monitoring Plan shall include at a minimum: a. List of personnel involved in the monitoring activities; b. Inclusion of involvement of the Native American community, as appropriate; c. Description of how the monitoring shall occur; d. Description of frequency of monitoring (e.g., full-time, part time, spot checking); e. Description of what resources are expected to be encountered; f. Description of circumstances that would result in the halting of work at the project site e.g., What is considered "significant" archaeological resources?); g. Description of procedures for halting work on the site and notification procedures; and h. Description of monitoring reporting procedures. Monitoring Program, CR -4: All mitigation measures shall be noted on Project grading and building plans, and be clearly visible to contractor and City inspectors. The City shall oversee survey efforts, and shall review and approve the Monitoring Plan, as required. Hazards and Hazardous Materials lid ration Measure HAZ-1: Prior to construction, as recommended in the Initial Site Assessment Padre, April 2016), the City shall complete a Preliminary Site Investigation Report including, but not limited to, testing and analysis of soils to be disturbed as a result of grading and construction activities. The Report shall include, but not be limited to: sampling and analysis methodology, Page 894 of 1183 Resolution No. ARC -1008-17 ARCH -0360-2017 (Railroad Safety Trail — Taft to Pepper) Page 9 including the advancement of shallow drill holes along the proposed ground disturbance areas, collection of discrete soil samples from shallow soils, and chemical analysis of selected soil samples for presence of total petroleum hydrocarbon constituents, lead, arsenic, and chlorinated herbicides; and identification of the concentration of petroleum hydrocarbons and chlorinated herbicides. In the event that elevated concentrations of suspected contaminants are indicated in shallow soils, the City will prepare a Contaminated Materials Management Plan (CMMP) for implementation during the course of the construction activities. The CMMP shall include but not be limited to detailed procedures to properly manage and dispose contaminated soils disturbed during the course of the Project construction activities, in accordance with local, state, and federal regulations. Monitoring Program, HAZ-1: These conditions shall be noted on all Project grading and building plans. Public Works Inspectors shall conduct field monitoring. If required, the CMMP shall be submitted to the City prior to grading and construction. A copy of the CMMP shall be available onsite during grading and construction, and shall be implemented as necessary. Mitigation Measure HAZ-2: TPH-containing soil, lead -contaminated soil, herbicide -containing soil, and lead-based paint containing building materials demolished as part of the Project will be segregated and properly packaged and disposed of at a licensed facility. Monitoring Program, HAZ-2: These conditions shall be noted on all Project grading and building plans. Public Works Inspectors shall conduct field monitoring. Noise Mitigation Measure N-1: All equipment will have sound -control devices that are no less effective than those provided on the original equipment. No equipment will have an unmuffled exhaust. Monitoring Program, N-1: These conditions shall be noted on all Project grading and building plans. Public Works Inspectors shall conduct field monitoring. Mitigation Measure N-2: As directed by Caltrans, the contractor will implement appropriate additional noise mitigation measures, including changing the location of stationary construction equipment, turning off idling equipment, rescheduling construction activity, notifying adjacent residents in advance of construction work, and installing acoustic barriers around stationary construction noise sources. Monitoring, Program, N-2: These conditions shall be noted on all Project grading and building plans. Public Works Inspectors shall conduct field monitoring. Mitigation Measure N-3: At least twenty (20) days prior to commencement of construction, the contractor shall provide written notice to all property owners, businesses, and residents within 300 feet of the trail alignment. The notice shall contain a description of the Project, the construction schedule, including days and hours of construction, the name and phone number of the City's Project environmental coordinator and contractor(s), site rules and conditions of approval pertaining to construction activities. Page 895 of 1183 Resolution No. ARC -1008-17 ARCH -0360-2017 (Railroad Safety Trail — Taft to Pepper) Page 10 Monitoring Program, N-3: These conditions shall be noted on all Project grading and building plans. Mitisation Measure N4: Construction (including preparation for construction work, such as equipment transportation) shall only be permitted Monday through Saturday between the hours of 7:00 a.m. and 7:00 p.m. Construction shall not occur on legal holidays. Monitoring Program, N-4: These conditions shall be noted on all Project grading and building plans. Public Works Inspectors shall conduct field monitoring. Mitiea_tion Measure N -S: All construction equipment, including trucks and stationary equipment, shall be professionally maintained and fitted with standard manufacturers' mufflers, silencing devices and engine covers. Monitoring Program. N-5: These conditions shall be noted on all Project grading and building plans. Public Works Inspectors shall conduct field monitoring. Mitigation Measure N-6: Temporary construction noise barriers (blanket type or non - reflective solid type, minimum 10 feet tall at road grade, rated at STC -25 or better) shall be installed and maintained between pile drilling work areas and affected residences on Pepper Street during bridge construction. Noise levels shall be monitored for compliance. Monitoring Program, N-6: These conditions shall be noted on all Project grading and building plans. Public Works Inspectors shall conduct field monitoring. Transportation/Traffic Mitigation Measure T-1: Prior to construction, a Traffic Management Plan will be prepared for the Project, which will identify measures to follow during lane closure, reconfiguration, and striping on California Boulevard. The Traffic Management Plan shall include, but not be limited to, the following: a. Identified lane closures, including vehicle, bicycle, and pedestrian sidewalk closures or limitations. b. Safety measures including signage, safety cones, and temporary lighting. c. Use of personnel to direct vehicular traffic, bicycle traffic, and pedestrians. MonitorinJg Program, T-1: This condition shall be noted on all Project grading and building plans. Public Works Inspectors shall conduct field monitoring. SECTION 3. Action. The Architectural Review Commission hereby grants approval to application ARCH -0360-2017, with incorporation of the following conditions: Conditions Planning The Architectural Review Commission's approval of this project will expire after three years Page 896 of 1183 Resolution No. ARC -1008-17 ARCH -0360-2017 (Railroad Safety Trail — Taft to Pepper) Page 11 if construction has not started. On request, the Community Development Director may grant a single, one-year extension. 2. Final project design and construction drawings shall be in substantial compliance with the project plans approved by the ARC. A separate, full-size sheet shall be included in working drawings that lists all mitigation measures and conditions of project approval listed as sheet number 2. Reference shall be made in the margin of listed items as to where in plans requirements are addressed. Any change to approved design, colors, materials, or other conditions of approval must be approved by the Community Development Director or Architectural Review Commission, as deemed appropriate. 3. Final project design and construction drawings shall show the locations of all exterior lighting, including a graphic representation of the proposed lighting fixtures and cut -sheets. The selected fixture(s) shall be shielded to ensure that light is directed downward consistent with the requirements of the City's Night Sky Preservation standards contained in Chapter 17.23 of the Zoning Regulations. Lighting shall be low level (less than four feet in height), bollard style, and continuous (outside of street sources of lighting). 4. Construction plans shall demonstrate the use of high quality materials. Guardrails and railings shall meet minimum City and Union Pacific Railroad standards, and shall emulate materials used around and on the Jennifer Street Bridge. The bridge shall provide at least ten feet of vertical space. 5. Construction plans shall include a landscape plan for review and approval by the Community Development Director. The plans shall incorporate graffiti -deterrents on and around proposed abutments and bridge structures. Upon motion of Commissioner Beller, seconded by Commissioner Root, and on the following roll call vote: AYES: Commissioners Nemcik, Rolph, Root, Starzyk, Beller, Vice -Chair Soll, and Chair Wynn NOES: None ABSENT: None The foregoing resolution was adopted this 15th day of May, 2017. in, Doug Davi on, Secretary Architectural Review Commission Page 897 of 1183 Page 898 of 1183 Department Name: Public Works Cost Center: 5010 For Agenda of: March 17, 2020 Placement: Consent Item Estimated Time: N/A FROM: Shelly Stanwyck, Assistant City Manager, Community Services Prepared By: Bryan Wheeler, Transportation Planner-Engineer III SUBJECT: AUTHORIZATION TO ADVERTISE AND AWARD RAILROAD SAFETY TRAIL TAFT TO PEPPER PROJECT, SPECIFICATION NO. 91375 RECOMMENDATION 1. Approve plans and specifications for the Railroad Safety Trail Taft to Pepper Project (Project), Specification No. 91375 and authorize staff to formally advertise for bids; and 2. Authorize the City Manager to award the construction contract if the lowest responsible bid is within the publicly disclosed funding amount of $5,070,600; and 3. Authorize the City Manager to award the construction management contract if the lowest responsible bid is within the publicly disclosed funding amount of $603,750; and 4. Authorize the City Manager to award the railroad services contracts for flagging and permitting, not to exceed the publicly disclosed funding amount of $110,000.    DISCUSSION Background The Railroad Safety Trail (RRST) has long been one of the highest-priority multimodal transportation projects in the City of San Luis Obispo (City)—a crosstown, dedicated facility for pedestrians and bicyclists connecting the southern City limits north to California Polytechnic State University (Cal Poly). Over the past two decades, approximately 40 percent of the total four-mile trail has been completed and existing portions of the trail are enjoyed by over 1,000 pedestrians and cyclists per day. This Project proposal includes construction of the next segment of the RRST from Taft Street to Pepper Street. It segment was included in the 2013 Bicycle Transportation Plan (Attachment A) and supports the current Major City Goal to improve Sustainable Transportation in the City. The RRST extension from Taft Street to Pepper Street will encompass about 0.4 miles from the existing trail alignment on the west side of California Boulevard, near Taft Street, south along the existing bridge crossing over Highway 101, then shifting away from California Boulevard behind the California Highway Patrol (CHP) property to a new bicycle/pedestrian bridge crossing over the Union Pacific Railroad (UPRR) and connecting Phillips Lane to Pepper Street. A Project vicinity map and bridge rendering shown below (Figure 1 & 2). Page 899 of 1183 Figure 1: Study Area Map Figure 2: Rendering of Railroad Safety Trail Bridge over UPRR Tracks between Phillips and Pepper Page 900 of 1183 Caltrans Active Transportation Program Grant In 2015, the City applied for a Caltrans Active Transportation Program (ATP) grant for the Project and was awarded $3.24 million in funding towards Project construction. Over the past five plus years, the Project progressed with planning, design, environmental review, permitting and right-of-way acquisition to the current “shovel-ready” stage. After diligent negotiations with UPRR, the State, and a private property owner, all property acquisition necessary to construct the Project were completed in summer of 2019. At this time, staff has completed the Plans, Specifications and Estimates and the Project is ready to be advertised for construction. Project Scope of Work The construction package attached to this Report includes plans and specifications for construction of the RRST between Taft Street and Pepper Street. The designs include the following elements: a. Taft Street to Highway 101 Overcrossing – Separated Class I bicycle/pedestrian trail along the west side of California Boulevard from Taft Street to the Highway 101 overcrossing. b. Highway 101 Overcrossing – On-street Class IV protected two-way bikeway (“cycle track”) along the existing California Boulevard bridge crossing over Highway 101. A metal railing physically separates cyclists from motor vehicles and the existing sidewalk serves pedestrian travel along the bridge. c. Highway 101 Overcrossing to Phillips Lane – Separated Class I bicycle/pedestrian trail shifts behind the CHP headquarters connecting to the Phillips Lane cul-de-sac. d. Phillips Lane to Pepper Street – A new bicycle/pedestrian bridge connects Phillips Lane on the north side of the UPRR tracks south to Pepper Street. e. Other Elements 1. ADA curb ramps and path-of-travel upgrades at the Highway 101 bridge. 2. Widening of the Highway 101 offramp at California Boulevard to provide additional queue storage (a requirement for Caltrans approval) 3. Resurfacing and re-striping along California Boulevard from Taft Street to the Northbound Hwy 101 On- and Off-ramps. 4. Lighting system for the Class I trail. Construction plans, specifications, and engineer’s estimate are provided as City Council Reading Files as Attachment B thru D. Next Phases of the Railroad Safety Trail Project Upon completion of the Project, several gaps will remain along the RRST, totaling approximately 1.5 miles. With completion of planned and pending development within the Orcutt Area, the segment of the RRST between Tank Farm Road and the Jennifer Street Bridge is anticipated to be fully connected within the next few years. This leaves about a one-mile gap between Pepper Street and the Jennifer Street Bridge to complete the four-mile continuous crosstown route. The preferred alignment and type of facility to complete this final RRST gap will be identified in the City’s Active Transportation Plan, which is currently being drafted, and is scheduled for completion later in 2020. Page 901 of 1183 Public Engagement This Project was vetted by the City’s Bicycle Advisory Committee in 2011 and has continued to be identified as a top project priority each year by the Active Transportation Committee (ATC). The project was included in the 2013 Bicycle Transportation Plan and 2014 General Plan Circulation Element, each of which included several public engagement opportunities. During public outreach activities conducted in fall of 2019 for the upcoming Active Transportation Plan, completion of the RRST was commonly expressed as one of the highest priority projects for community members. Policy Consistency This project is identified in the RRST Plan, adopted in 2002, the General Plan Circulation Element, and the City’s Bicycle Transportation Plan (BTP), adopted in 2013. Construction of this RRST segment furthers the adopted 2019-21 Major City Goal: Multi-Modal Transportation - Prioritize implementation of the Bicycle Master Plan, pedestrian safety, and the Short-Range Transit Plan. CONCURRENCE The Project has been reviewed by the ATC and is a top priority for the committee to achieve the City’s Sustainable Transportation Major City Goal. Updates have been provided to the ATC throughout the project process. The project came before City Council on August 20, 2019 to approve the transfer of funds from the Transportation Impact Fee Program to the project. The RRST project was included in the Citywide Transportation Impact Fee (TIF) program, and staff requested the transfer of $2,894,163 in total from the Citywide TIF account to the RRST project account to fund the property acquisition ($496,000) and construction funding shortfall ($2,398,163). ENVIRONMENTAL REVIEW An initial study of this Project was conducted, and a Mitigated Negative Declaration (MND) was filed to the County of San Luis Obispo on May 19, 2017. All construction plans conform to those mitigations found in the MND. FISCAL IMPACT Budgeted: Yes Budget Year: 2017-18 Funding Identified: Yes Page 902 of 1183 Fiscal Analysis: RRST- Taft to Pepper (91375) Project Costs Construction Costs $4,440,600 Construction Contingencies (15%) $630,000 Total Costs for this Construction Contract $5,070,600 Additional Items Outside Construction Contract (UPRR Items) $110,000 Construction Management & Materials Testing $603,750 Total for Construction $5,784,350 Project Funding State Funds (Caltrans ATP Grant & SHA Funds) $3,494,000 Local Funds (Citywide TIF & Local Revenue Measure) $2,516,108 Total Available Funds $6,010,108 Funding Sources Current FY Cost Annualized On-going Cost Total Project Cost General Fund (LRM) $117,108 State (ATP Grant) $3,244,000 State (SHA) $250,000 Federal $0 Fees $0 Other: Citywide TIF $2,399,000 Total $6,010,108 The total construction cost for this project is estimated at $5,784,350, which includes construction costs and contingencies related to this bid package ($5,070,600), construction management and materials testing ($603,750) and related railroad flagging and permit review costs, ($110,000). Construction Management support for this project will be procured via a Request for Proposals (RFP) process through the City’s existing on-call construction management contracts. To date, $748,717 has been used or encumbered for property acquisition, environmental review and project design. ALTERNATIVES The Council may choose not to authorize advertising for construction at this time. However, this is not recommended because there is adequate funding for the project, the improvements will provide a much-desired expansion of the Railroad Safety Trail to Cal Poly for bicyclists and pedestrians, and this project will set up a critical link for the Railroad Safety Trail to connect with Downtown San Luis Obispo. Further, if a construction contract is not awarded by June 2020, the City would risk forfeiture of the $3.24 million in Caltrans ATP grant funds. Page 903 of 1183 Attachments: a - Project Page from 2013 Bicycle Transportation Plan b - COUNCIL READING FILE - Project Plans c - COUNCIL READING FILE - Special Provisions d - COUNCIL READING FILE - Project Estimate Page 904 of 1183 City of San Luis Obispo, City Manager Report Final City Manager Approval Approver Name Date Approved City Administration Shelly 8/21/2020 Reviewer Routing List Reviewer Name Date Reviewed City Attorney MJ 8/21/20 Finance NH 8/21/20 August 21, 2020 FROM: Luke Schwartz, Transportation Manager (for Matt Horn, Public Works Director) LJS 6/21/2020 PREPARED BY: Bryan Wheeler, Transportation Planner/Engineer III SUBJECT: Railroad Safety Trail Taft to Pepper, Spec 91375 Construction Contract and Materials Testing Award RECOMMENDATION 1. Award a contract to Souza Construction Inc. in the amount of $3,774,960.26 for construction of the “Railroad Safety Trail Project, Specification No. 91375” (Attachment A); and 2. Approve issuance of Purchase Order to Earth Systems in the amount of $96,013 for Materials Testing Services for the “Railroad Safety Trail Project, Specification No. 91375” (Attachment C); and 3. Approve a Purchase Order Amendment for TRC Engineering, increasing their approved budget by $99,814 for construction engineering support for the “Railroad Safety Trail Project, Specification No. 91375” (Attachment D). DISCUSSION Construction Contract On March 17, 2020, the City Council authorized the City Manager to award the construction contract for the upcoming Railroad Safety Trail (“RSST”) Taft to Pepper project if the lowest responsible bid is within the publicly disclosed funding amount of $5,070,600. The Council Agenda Report for this item is provided for reference as Attachment B. The project was advertised for bidding on June 6th, 2020. Bids were received on July 9th, 2020 by the five construction firms listed below: • Souza Construction Inc. • Bough Construction • Granite Construction • R. Burke Construction • Papich Construction Page 905 of 1183 Railroad Safety Trail Taft to Pepper, Spec 91375 Award Page 2 The bids were all determined as responsive after review by staff and the design consultant, TRC Engineering. Table 1 shows the breakdown of bid cost for the project: Table 1: Construction Contract Bids Staff reviewed the bid documents, legal requirements, and Disadvantaged Business Enterprise (DBE) goal documentation, and concluded that the apparent low bidder provided the lowest cost responsive bid. Staff therefore recommends awarding the construction contract to Souza Construction Inc. for the Project. Souza’s bid proposal is provided for reference as Attachment A. Materials Testing On June 4, 2020 a Request for Proposals was solicited to the City’s on-call Materials Testing firms to provide materials testing services in conjunction with construction of the RRST project. Two proposals were received on June 26, 2020 from the following consultants: • Earth Systems • GeoSolutions The proposals were reviewed by two internal CIP Engineering staff as well as the project design consultant. The proposals were ranked based off the firm’s qualifications, experience of staff, project understanding and approach to the work, familiarity with State and Federal Procedures and references. Earth Systems ranked the highest by all three reviewers, primarily for their extensive knowledge and experience on structures and bridges, and the understanding of the test involved for the project. The following table shows the breakdown of reviewers scores: Table 2: Materials Testing Consultant Proposal Score (out of 25 points) Earth Systems 16.75 GeoSolutions 15 Based on the qualifications of Earth Systems, and their high-ranking proposal, staff is recommending awarding the Materials Testing Services to Earth Systems. Their proposal, provided for reference as Attachment C, is $11,197 over the estimated cost for materials testing identified in the March 17, 2020 Council Agenda Report. However, there are sufficient funds remaining in the total approved project budget to cover the additional cost required for materials testing and staff is recommending proceeding with issuance of a purchase order to Earth Systems for these services. It should be noted that the proposals for Construction Management Services and Materials Testing were solicited using the City’s established on-call contracts for these services and are not eligible to be paid with grant funds. There are sufficient local funds allocated to the project to cover these costs. Design Support Additional construction support is required from the project design consultant, TRC Engineering, to cover review of bridge submittals and Requests for Information (RFIs) and to continue coordination with Union Pacific Railroad during construction activities. The design consultant’s proposal for a contract amendment to provide construction support services is included for Engineer's Estimate Souza Brough Granite R. Burke Papich Total Bid amount $4,440,600 $3,774,960.26 $4,155,070.15 $4,845,580.00 $4,914,475.20 $5,566,119.83 Page 906 of 1183 Railroad Safety Trail Taft to Pepper, Spec 91375 Award Page 3 reference as Attachment D. There are sufficient local funds within the total approved project budget to cover these costs. This work would be billed on a time and material basis, with the remaining funds to be allocated back to the corresponding local fund account (Traffic Impact Fee Program) upon completion of construction. FISCAL IMPACT The project was approved as part of the 2017-19 Financial Plan. Currently, there is $6,010,108 available in the project budget, which is sufficient to fully fund the total costs of construction, construction engineering support, construction management support, and materials testing services. The $3,774,960.26 bid cost proposed by Souza Construction, Inc. is within the authorized amount of $5,070,600, is below the engineer’s estimate of $4,440,600, and leaves $780,387 remaining in the project account. Remaining funds from the project account will be transferred back to the Traffic Impact Fee fund account upon completion of construction. Construction Contract:$3,774,960 Construction Contingencies (15%):$630,000 Construction Management:$518,934 UPRR Items Outside Construction Contract $110,000 Materials Testing $96,013 TRC Construction Engineering Support $99,814 Total Estimated Project Cost:$5,229,721 Current Project Budget (State Funds):$3,494,000 Current Project Budget (Local Funds):$2,516,108 Total Budget:$6,010,108 Remaining Funds:$780,387 Railroad Safety Trail Taft to Pepper, Specification No. 91375 ALTERNATIVES Deny awarding the project. The City Manager could choose to not award the contract. Staff does not recommend this alternative. The City would be unable to proceed with the construction phase. This could put the federal funding in jeopardy as the project must be awarded for construction prior to December 31, 2020. ATTACHMENTS A. Souza Construction Inc. Project Bid B. CAR 3/17/2020 Authorizing City Manager to Award C. Earth Systems Proposal D. TRC Proposal https://slocitycloud.sharepoint.com/sites/SLOHub/Administration/citymanagersreports/Shared Documents/Public Works/2020/Transportation/91375 RRST Taft To Pepper Construction Award/91375 Award CMR.docx Page 907 of 1183 Page 908 of 1183