Department: Community Development
Cost Center: 4003
For Agenda of: 8/24/2021
Placement: Consent
Estimated Time: N/A
FROM: Michael Codron, Community Development Director
Prepared By: Dan Van Beveren, Senior Civil Engineer
SUBJECT: PARTIAL ACCEPTANCE OF PUBLIC IMPROVEMENTS FOR TRACT
3096, SAN LUIS RANCH
RECOMMENDATION
Adopt a Resolution entitled, “A Resolution of the City Council of the City of San Luis
Obispo, California, accepting the completed Public Improvements of Tract 3096; certifying
the completed Private Subdivision Improvements of Tract 3096; releasing the Securities
for the completed portions of Tract 3096; and authorizing the Director of Public Works to
accept the remaining improvements and to release the remaining Securities once all the
improvements are deemed complete.”
DISCUSSION
Background
Tract 3096 is a subdivision of a property known as San Luis Ranch. In 2017, a Tentative
Map was submitted to the City, and proposed the creation of 304 lots consisting of:
1. 282 single family residential lots
2.Two multi-family residential lots
3. 14 park lots
4.One open space lot
5.One agricultural land lot
6.Three commercial lots
7.One lot to be used for a required Agricultural Heritage and Learning Center
Construction of the improvements began in 2019 and is still ongoing.
Partial Acceptance of a Portion of Improvements
The improvements within the subdivision will consist of new street construction, three new
roundabouts, medians, curb, gutter, sidewalks, Class 1 multi-use paths, streetlights,
domestic water and recycled water mains, sewer mains, fire hydrants, storm drain
improvements, and landscaping. Thus far, work has been completed for some of the
required public improvements including the domestic and recycled water mains and the
sewer collection system.
Page 185 of 271
Item 5h
The recommended action includes the acceptance of the completed items, reduces the
securities for the work that is completed, and authorizes the Public Works Direct or to
accept the remaining public improvements once they are deemed complete and to
release the remaining securities on behalf of the City Council once the work is completed.
Previous Council Action
The Tentative Map for Tract 3096 was approved by City Council on July 18, 2017 by
Resolution No. 10822 (2017 Series).
A supplemental Final Environmental Impact Report (FEIR) was approved by City Council
on July 17, 2018 by Resolution No. 10927 (2018 Series).
A Development Agreement with the Subdivider was approved by City Council on August
21, 2018 by Ordinance No. 1649 (2018 Series).
The final map for Tract 3096 was approved by City Council on November 27, 2018 by
Resolution No. 10961 (2018 Series).
Policy Context
The City Council accepts public improvements and certifies completion of private
improvements in accordance with the Subdivision Map Act and the City’s Subdivision
Regulations.
Public Engagement
The Public Engagement process was completed with the approval of the Tentative Map.
CONCURRENCE
The Public Works Director and the Utilities Director concur with the recommended action.
ENVIRONMENTAL REVIEW
The San Luis Ranch Specific Plan, General Plan Amendment, Vesting Tentative Tract
Map 3096 and related entitlements and the associated Final Environmental Impact Report
(EIR) and Mitigation, Monitoring, and Reporting Plan were approved and certified on July
18, 2017 (Resolution 10822, 2017 Series). On July 17, 2018, the City Council approved
an amendment to the San Luis Ranch Specific Plan, approved the Development
Agreement to implement the project, and certified the associated Final Supplemental EIR
and modified Mitigation, Monitoring, and Reporting Plan (Resolution 10927, 2018 Series).
Ordinance 1649 (2018 Series) was adopted by the City Council on August 21, 2018
approving the Development Agreement. The necessary findings and environmental
review requirements related to the development of Tract 3096, including associated
improvements, were made with the Specific Plan, Development Agreement, and tentative
map approvals; therefore, no further environmental review is required as part of this
Council action.
Page 186 of 271
Item 5h
FISCAL IMPACT
Budgeted: No Budget Year: N/A
Funding Identified: No
Fiscal Analysis:
Funding
Sources
Total Budget
Available
Current
Funding
Request
Remaining
Balance
Annual
Ongoing
Cost
General Fund N/A
State
Federal
Fees
Other:
Total
Typical maintenance and operation of newly accepted public facilities will be required for
the street and utility improvements. Increasing the maintenance budget for the small,
incremental increase in infrastructure to be maintained does not occur with each
acceptance of public facilities. The maintenance budget for the improvements is
evaluated and adjusted as needed with the City’s adoption of its two -year financial plan,
which will reflect the increased need in maintenance cost.
ALTERNATIVES
Council could reject the staff recommendation delegating the authority to the Public
Works Director to accept the remaining improvements and require that the acceptance
be returned to a future Council meeting for acceptance by the City Council. This
alternative is not recommended because the oversight by the Public Works Director will
ensure that all improvements are completed to City standards prior to the release of
financial guarantees. Ultimately, acceptance of the public improvements is required in
accordance with the Tentative Map approvals, Department of Real Estate process
assumptions, and Homeowners Association CC&R’s.
ATTACHMENTS
A – Draft Resolution to partially accept Public Improvements for Tract 3069
B – Vicinity Map for Tract 3069
C – Site Map for Tract 3069
Page 187 of 271
Page 188 of 271
R ______
RESOLUTION NO. _____ (2021 SERIES)
A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF SAN LUIS
OBISPO, CALIFORNIA, ACCEPTING THE COMPLETED PUBLIC
IMPROVEMENTS OF TRACT 3096; CERTIFYING THE COMPLETED
PRIVATE SUBDIVISION IMPROVEMENTS OF TRACT 3096;
RELEASING THE SECURITIES FOR THE COMPLETED PORTIONS OF
TRACT 3096; AND AUTHORIZING THE DIRECTOR OF PUBLIC WORKS
TO ACCEPT THE REMAINING IMPROVEMENTS AND TO RELEASE
THE REMAINING SECURITIES ONCE ALL THE IMPROVEMENTS ARE
DEEMED COMPLETE
WHEREAS, the City Council approved the Tentative Map for Tract 3096 by
Resolution No. 10822 (2017 Series); and
WHEREAS, the City Council approved a supplemental Final Environmental Impact
Report for Tract 3096 by Resolution No. 10927 (2018 Series); and
WHEREAS, the City Council approved a Development Agreement with the
subdivider by Ordinance No. 1649 (2018 Series); and
WHEREAS, the City Council approved the final map for Tract 3096 per Resolution
No. 10961 (2018 Series); and
WHEREAS, the subdivider has satisfactorily completed a portion of the public
improvements in accordance with City standards, specifications and the approved plans,
and has requested that the City accept these public improvements for maintenance and
operation by the City; and
WHEREAS, the subdivider has satisfactorily completed a portion of the private
improvements in accordance with City standards, specifications and the approved plans,
and has requested that the City certify completion of these private improvements; and
WHEREAS, the subdivider has on file the appropriate securities to guarantee the
completion of the remaining subdivision improvements as shown on the approved plans.
NOW, THEREFORE, BE IT RESOLVED by the Council of the City of San Luis
Obispo as follows:
SECTION 1. The City Council hereby accepts a portion of the public
improvements for Tract 3096, specifically, the water distribution network, the sewer
collection system, and the recycled water distribution system within the Tract boundary.
SECTION 2. The City Council hereby certifies completion of a portion of the
required private subdivision improvements within the Tract 3096 boundary.
Page 189 of 271
Resolution No. _____ (2021 Series) Page 2
R ______
SECTION 3. The Faithful Performance securities guaranteeing completion of the
on-site and off-site improvements may be reduced with the approval of the Director of
Public Works upon submittal of the following items:
1. Progress record drawings for the completed improvements; and
2. Certification by the Engineer of Record for the completion of the public
improvements.
SECTION 4. The corresponding Labor & Materials security may be released after
90 days from the date of acceptance of the improvements in accordance with Section
66499.7(h) of the California Government Code.
SECTION 5. The Director of Public Works is hereby authorized to accept the
remaining improvements and to release the remaining securities on behalf of the City
Council once the work is completed to the City’s satisfaction.
Page 190 of 271
Resolution No. _____ (2021 Series) Page 3
R ______
SECTION 6. The security guaranteeing the workmanship and materials may be
released by the Director of Public Works upon the successful completion of the 12 -month
warranty time period from the date of acceptance of the improvements.
Upon motion of Council Member ___________, seconded by Council Member
___________, and on the following roll call vote:
AYES:
NOES:
ABSENT:
The foregoing resolution was adopted this _____ day of _______________ 20 21.
___________________________
Mayor Heidi Harmon
ATTEST:
______________________
Teresa Purrington
City Clerk
APPROVED AS TO FORM:
______________________
J. Christine Dietrick
City Attorney
IN WITNESS WHEREOF, I have hereunto set my hand and affixed the official seal of the
City of San Luis Obispo, California, on ______________________.
___________________________
Teresa Purrington
City Clerk