HomeMy WebLinkAbout11/2/2021 Item 3a, Horn/Nelson - Staff Agenda CorrespondenceCity of San Luis Obispo, Council Memorandum
City of San Luis Obispo
Council Agenda Correspondence
DATE: November 2, 2021
TO: Mayor and Council
FROM: Matt Horn, Public Works Director
Brian Nelson, Acting City Engineer
VIA: Derek Johnson, City Manager
SUBJECT: ITEM 3a – PUBLIC SAFETY CENTER PROGRAM AND DESIGN UPDATE
Below are a series of Council posed questions and staff responses in preparation to this
evening’s Study Session on the Public Safety Center Program and Design Update. The
purpose of this Study Session is to provide preliminary feedback to staff on the future
programming and design and pathway’s regarding a replacement Public Safety Center.
This evening does not represent final approval of designs, programming , and/or use of
said center. The purpose of tonight is to receive a briefing on the long history of the
project, next steps, and direction from council on program and design concepts.
1) Please provide information on how the estimated 128 parking spaces needed
for the new public safety center was developed. What can we do to
encourage people to NOT drive to work, and therefore require fewer parking
spots onsite?
Parking counts were completed and incorporated in the 2021 Space Needs
Assessment which is included as Attachment D of the report and shown on page
22. Parking space needs are based on the number of current and future staff as
well as all associated department vehicles. As conceptualized, the proposed
parking structure was sized to meet minimum needs and construction of this
project would require implementation of programmatic measures to use alternative
modes of transportation and reduce parking demand for future staffing levels.
Sworn staff City fleet and personal vehicles were prioritized with other non-sworn
staff needs. When operating the facility, priority will be placed on non-single
passenger vehicle parking.
It is important to note, that this site is also proposed to house the City’s Emergency
Operations Center (EOC), Training, Community Room, and additional parking is
required for large event or “surge capacity”. Lastly, the site offers virtually no street
parking and given the nature of operations, especially in emergency operations,
parking must be contained within a secured area.
Item 3.a – PUBLIC SAFETY CENTER PROGRAM AND DESIGN UPDATE Page 2
2) What was considered when deciding to locate the EOC in the Public Safety
Facility? Was this design modeled off other facilities? With the addition of
a Community Room in this building, would that be able to serve as a Family
Assistance Center in an emergency?
The current EOC is within the City, at Fire Station Number 1, a building designed to
withstand most emergency events. The current facility is insufficient in 2021; and is
significantly deficient when full team deployment occurs. The Ludwick Community Center
serves as a back up to Fire Station #1 and as a USO Center from the 1940s is also not
designed for modern EOC use. Staff, in studying City EOCs, has found central location to
City facilities to be the current best practice model for urbanized agencies. Staff has
recommended including a new EOC in the Public Safety Center in order to collocate this
facility and take advantage of construction of the new Public Safety Center.
The new EOC would be designed with public space (for media briefings), operational
space and appropriate break-out rooms for focused response and planning activities, and
would include integrated technical support. Should the Cities EOC be compromised or in
danger, a "back-up" EOC could be set up outside the City and use the County EOC or
other locations in order to fully support City operations.
The City’s EOC as conceptualized is not modeled after any specific jurisdictions’
facility, however this (a Public Safety Facility with an EOC) is a common industry
design for municipalities similar in size. Facilities for Santa Barbara County and
Paso Robles were toured and the consultant team has worked on planning,
designing and building EOC’s. Santa Barbara County’s facility is a stand-alone
facility that is collocated with regional fire facilities. The City of Paso Robles Public
Safety building uses an EOC that is dual designed as an EOC and training room.
The Paso Robles facility is in the downtown corridor and a backup facility is located
near the Airport Terminal.
The Community Room is an important component to the new Public Safety Center
and is intended to be used more regularly and to hold community meetings on
public safety and for a place for families, businesses and others to seek support
during Emergency Operations. In an Emergency, a Family Assistance Center is
could be established at this location or at a, County or Cal Poly facility depending
on the nature and scope of the emergency. The Community Room will allow for
increased City support for cooling and warming operations during inclement
weather. This will also allow for facility staff to support direct service needs for the
Community’s vulnerable populations during those times.
Item 3.a – PUBLIC SAFETY CENTER PROGRAM AND DESIGN UPDATE Page 3
3) Have various community groups (BIPOC, GALA, etc.) been given the
opportunity to weigh in on any of the design elements yet?
As this is the conceptual phase of the project, community groups and public
outreach and input is planned and will occur for the next step in the process. A full
public engagement plan will be developed following direction so that Staff can
convey the scope and program of the project. The project and building is at a early
schematic level of design and the design is expected to be adjusted to meet
community input on design. This Study Session is intended to check in with
Council to obtain early-stage conceptual project input to ensure leadership
supports the current concepts. A few notable elements as currently conceived is
the provision of inclusive and equitable spaces including non-gender based “locker
room”, exercise facilities, and the Community Room.
4) What is the anticipated funding plan including funding sources for this
project?
With the adoption of the 2021-23 Financial Plan, Council allocated the use of
Measure G20 revenues in the amount of $100,000 in Fiscal Year (FY) 2021-22
and $300,000 in FY 2022-23 These funds support public outreach and the project
entitlement process, including environmental review, as well as preliminary
designs. Staff anticipates with the 2023-25 Financial Plan Council’s review of
funding allocations for final design, permitting, and initial construction services.
The current funding plan and model anticipates the construction will be debt
financed. The funding model currently anticipates Measure G -20 funds will be
used to support the annual debt service payments. The debt payments were
integrated into the fiscal analysis of the capital program, retaining a projected $15
million of annual Measure G-20 funding for other capital needs within the
community such as parks amenities, street resurfacing, and downtown
improvements. This funding plan was developed based upon an evaluation by the
City’s Municipal Advisor regarding the long -term funding availability and capital
needs of the community. In anticipation of this funding plan, the City has worked
to retain its AA+ rating with both S&P and Fitch Ratings and maintained a relatively
low debt burden to date.
5) On page 129 that it notes in 2003, we had about 90 FTEs in the
department. But, then, somewhere else it noted that the current department
FTEs are still about 90. We have not grown at all since 2003? What number
of staff is this building being built to accommodate?
The Police Department currently has 90 Full Time Employees (FTE) as noted and
as Community and daily populations have increased, staff has largely not changed
for over 10 years. Staff continually studying appropriate staffing and programming
Item 3.a – PUBLIC SAFETY CENTER PROGRAM AND DESIGN UPDATE Page 4
levels for both sworn and non-sworn employees. Growth in the number of staff is
anticipated in the next 30 years. Before coming to Council with any staffing
changes, the Police Department will be undertaking a long term strategic plan that
incorporates the pillars of 21st Century Policing, federal and state police reports
and explores other models for public safety.
Currently the City is experiencing increasing call volumes for all police services,
and population growth which are traditional indicators that more staff will be
required in the future. As the City continues to examine a diversified response
philosophy, whereby more civilian teams specializing in addressing complex and
interconnected sociological issues are utilized, more space will be required the
collaborative needs of police officers and field personnel. The Facility is currently
designed with approximately 66 workspaces for staff, such as report writing desks,
individual offices and open work stations. This is less than the total FTEs for the
department as traffic and patrol officers share report writing spaces and do not
require a dedicated space.
6) The current design for the men’s restroom and locker room includes
accessible bathroom stalls and showers, but I didn’t see that in the women’s
restroom and locker room. Is this an oversight? Are gender-neutral
facilities included in the building design?
The initial conceptual design started with the traditional separation of men’s and
women’s restroom and locker areas. The plans however are being revised to
reimagine a single, open “locker room” for all genders, that is open to the fitness
area with multiple individual private changing rooms and with single
accommodation restroom facilities in each, with some being ADA compliant. This
design breaks down traditional barriers to inclusivity and provides a positive team
atmosphere for all employees. This will provide equity for all gender identities and
inclusion into locker room and fitness activities interactions, while maintaining a
private space for showering and changing . No longer will employees be required
to utilize gender specific department facilities.
7) What is the construction cost estimate for the new public safety facility?
Based upon the current schematic design level the approximate anticipated costs
are shown below and includes a market escalation for cost increases until the
anticipated construction or the fifth year of the current financial plan. Please note
this estimate is based upon staff’s current understanding of the project. As designs
are developed, stakeholder input is received, and the project works its way through
the entitlement process cost will change. While Council and the community have
the ability to shape and address cost s some cost will be market driven including
contractor and worker availability and supply chain issues.
Item 3.a – PUBLIC SAFETY CENTER PROGRAM AND DESIGN UPDATE Page 5
Cost Breakdown for Schematic Design
Building $27M
Parking Structure $5.6M
On-Site and Off-Site Improvements $3.4M
Permits, Radio and Data Systems, Temp Facilities & Construction
Contingency
$5.2M
Equipment and Furnishings $1.7M
Construction Engineering, Management and Testing $1.4M
Market Escalation (3.5 % per year) $7.7M
Conceptual Project Budget: $52M
8) Please provide photos of the Palo Alto Public Safety Building exterior for
comparison, see below. (8 Stories, 56,000 SQFT, $117M)