October 8, 2020 Sent via email
Brian Starr, SDG Architects
762 Higuera Street, Suite 212
San Luis Obispo, California 93401
Subject: Completeness Review #5: ARCH-0161-2019; USE-0500-2019; VAR-0499-2019 (1911
Johnson). Review of amendment to the Master Plan for the French Hospital Campus
and proposed new patient tower, and parking structure with heli-pad, including a
proposed height variance.
Dear Brian Starr:
Thank you for the September 11, 2020 re-submittal for the proposed Master Plan amendment, new
patient tower, and parking structure and associated use permit and variance applications. We have
reviewed your application and found it to be incomplete. We will be unable to process your
application until additional information and/or revisions have been submitted, to the satisfaction of
the Community Development Director. Preliminary review is necessary to ensure that staff has
adequate information to evaluate your project and identify any conflicts with City standards or
guidelines. The purpose of this letter is to provide you with a list of items that need to be addressed
prior to taking action on your project.
Preliminary review indicates that your application will remain in an incomplete status until the
following information and/or revisions are submitted:
Note: Upon resubmittal please provide a narrative indicating where responses to these items can be
found on plans.
Department comments/completeness items:
Planning Division - Community Development Department
1. Regarding property ownership, the City is requesting an applicant funded agreement regarding
at-risk processing in order to continue processing the requested entitlements while private
negotiations continue. If this is agreeable, we request that Dignity Health’s legal counsel please
contact the City Attorney’s Office for additional information and procedures regarding the
agreement. Please note, a condition of approval will require that Dignity Health provide
documentation of their ownership of the property, or other similar documentation allowing for
their development of the property.
ARCH-0161-2019– Completeness Review #5
October 8, 2020
Page 2
Contact information:
Markie Jorgensen, Assistant City Attorney
City Attorney's Office
990 Palm Street, San Luis Obispo, CA 93401-3249
E mjorgens@slocity.org
T 805.781.7141
2. Comment remains: Pursuant to the City’s Tree Ordinance, and updated procedures for tree
removal requests associated with major development review entitlements, the project will require
review by the Tree Committee. The Committee will provide a recommendation to the Planning
Commission. The following additional information is required:
a. An arborist report that identifies and discusses each tree within the development footprint
(including, but not limited to, structural development, grading, staging areas, ground cover
removal, changes in drainage patterns, and associated off-site improvements) including
those trees proposed for removal and those trees that will remain.
b. A site plan that includes accurate drip line delineation and cross sections of construction
work impacting both trees proposed for removal and trees planned to remain (some of this
information is shown on the revised plan sheets; please provide requested supplemental
information).
If you have any questions on the above planning comments, or any questions regarding this letter,
please contact me at 805-781-7176, or by e-mail at: sscott@slocity.org
The above list includes all of the items initially identified as necessary for us to certify your
application as complete. The City may ask for additional information upon more detailed review of
your project. If you have any questions regarding this letter or the specific items necessary to submit
for a complete application, please contact me at (805) 781-7176.
Sincerely,
Shawna Scott
Senior Planner