Loading...
HomeMy WebLinkAbout10-15-2013 c4 sewer lin replacement FROM: Daryl R. Grigsby, Director of Public Works Prepared By: Matt Horn, Supervising Civil Engineer SUBJECT: SEWERLINE REPLACEMENT, SPECIFICATION NO. 90916C RECOMMENDATION 1. Reject all bids received for the Sewerline Replacement, Specification No. 90916B project. 2. Approve the plans and specifications for the Sewerline Replacement, Specification No. 90916C. 3. Authorize staff to advertise for bids and authorize the City Manager to award the contract if the lowest responsible bid is within the Engineer’s Estimate of $850,000. 4. Approve the transfer of up to $264,600 into the construction phase of the project account at the time of project award from the Sewer Fund Completed Projects Account and the Wastewater Collection Master Account. DISCUSSION Replacement of wastewater collection pipes is part of an ongoing program to replace aging and deteriorating infrastructure. This program has several objectives: 1) Ensure reliable removal of waste; 2) Reduce the need for emergency repairs; 3) Reduce the need for preventive maintenance; and 4) Ensure uninterrupted wastewater flow without health hazard or effluent leakage. This project will accomplish these objectives for part of the City’s wastewater collection system. The scope of this project includes replacing sewerlines in portions of Beach, Islay and Chorro Streets. The existing sewerlines are maintenance intensive and need additional capacity. Portions of the existing sewer system will be increased in size from six and eight inch diameter pipes to eight, ten, and 12 inch diameter pipes increasing the system’s capacity. Maintenance needs will be reduced because of the new and larger sewerlines. In 2011 this project was awarded to a contractor to complete all planned work. A utility conflict in Pismo Street required the cancellation of that contract, completion of portions of the Pismo Street work in coordination with ConocoPhillips, and re-advertisement of the remaining work. On July 2, 2013 Council authorized the re-advertisement of the remaining work. The bids received on July 25, 2013 were in excess of the estimated construction costs of $785,000. Staff recommends rejecting all bids, revising the estimated construction costs and rebidding the project. Bidders identified several manholes that were deeper than typically found requiring larger excavations and additional cost. Experience and Reference Requirements Meeting Date Item Number 10/15/13 C4 - 1 Sewerline Replacement, Specification No. 90916C Page 2 This project will require the contractor to replace these sewerlines using a predominantly trenchless process. The two specified methods of installation are pipe bursting and pipe reaming. Using a trenchless process will allow for a higher quality seamless pipe to be installed at a lower cost due to the lower pipe installation cost as compared to conventional trenching. While the trenchless installation process for sewerline replacement is advantageous in this situation, it requires a contractor with specific experience and expertise to complete this work. A contractor with limited trenchless pipe installation experience could damage the sewer system, cause sewage spills, and increase public inconvenience during the installation process. For these reasons, staff is requesting the contractors to submit references documenting the experience of the firm completing the trenchless installation work. CONCURRENCES The Community Development Department has given this project a categorical exemption from environmental review. FISCAL IMPACT This sewerline replacement project is originally identified in the 2009-11 Financial Plan and carried over to the 2011-13 Financial Plan, Appendix B, on page 3-92, which identifies a $1,300,000 budget estimate for this project. Supplemental funding of up to $264,600 is requested from the Sewer Fund Completed Projects account and the Wastewater Collection Master account, which has an available balance of $200,000 and $570,500 respectively to support this request. Staff recommends transferring funding from these accounts (not to exceed $264,600) to the project account at time of contract award, based on construction bid amounts. ATTACHMENT Vicinity Map Construction (Engineer's Estimate):$850,000 Construction Contingencies:$85,000 Total for Construction:$935,000 Materials Testing:$11,000 Miscellaneous (incl. printing)$500 Total for other costs:$11,500 Total Cost of Project $946,500 Project Account (90916) Available Funding:$682,100 Sewer Fund Completed Projects Account $200,000 Master WWC System Account (90239) Available Funding:$570,500 C4 - 2 Sewerline Replacement, Specification No. 90916C Page 3 AVAILABLE FOR REVIEW IN THE COUNCIL OFFICE Plans and Special Provisions \\chstore4\team\council agenda reports\2013\2013-10-15\sewerline replacement 90916c (grigsby-horn)\90916c car.docx C4 - 3 C4 - 4