HomeMy WebLinkAbout10-15-2013 c6 transfer of additional funding for trench repair
FROM: Daryl R. Grigsby, Director of Public Works
Prepared By: Kyle Rowland, Engineering Inspector
SUBJECT: TRANSFER OF ADDITIONAL FUNDING FOR TRENCH REPAIR-JOB ORDER
CONTRACT 2013, SPECIFICATION NO. 91196
RECOMMENDATION
Appropriate an additional $162,000 from the Water Fund Completed Projects account and Water
Fund Working Capital to the Trench Repair Master account for use on trench repairs.
DISCUSSION
Background
Throughout the course of the year, small street repairs need to be completed following repair of
underground pipelines and on areas of street settlement. When a water or sewer pipe is repaired,
Utility Department staff complete the work on the pipeline and then temporarily patch the roadway.
Engineering Division staff collects the location information after the repair is made and issues a
construction contract to replace the temporary patch with a stronger, permanent asphalt patch. This
is currently performed on an as-needed basis using Trench Repair and Minor Concrete – Job Order
Contract – 2013 (JOC). The current was approved in July of 2013 for a two year period.
The current Utility Trench Repair JOC has been developed to pay the contractor for each square
foot of roadway repaired, regardless of number of pieces of equipment or the number of staff the
contractor plans to use. This methodology is consistent with other types of projects the City
completes and has made it simpler for the contractors to prepare and submit proposals.
Current Status
The current Financial Plan includes $125,000 from the Utility funds to complete the anticipated
amount of trench repair. Recently, however, the backlog of repairs has been growing such that the
$125,000 is inadequate for timely construction of the permanent patch work. Based on the existing
backlog, an estimated additional $162,000 is required to complete those repairs. Public Works and
Utilities staff will be reviewing past and anticipated future work to determine the most appropriate
annual budget for ongoing trench repair in the future. If there is a recommended change this may be
included in upcoming Financial Plans.
Last fiscal year, the City generated 17 Task Orders, totaling $362,000. This has proven to be an
effective and efficient method of completing roadway repairs. Water Distribution accounted for 13 of
the Task Orders, 3 Task Orders were for Street Reconstruction and Resurfacing, and 1 addressed a
Wastewater Collection repair. These Task Orders contained multiple roadway repairs and minor utility
repair work. Trench repair funding comes from three different Master Account sources: Street
Reconstruction and Resurfacing (R&R), Water Distribution Trench Repair and Collection System
Improvement.
Meeting Date
Item Number October 15, 2013
C6 - 1
Transfer of Additional Funding for Trench Repair JOC 91196 Page 2
While City staff is capable of completing trench repairs, the current volume would detract from
their ability to perform the necessary preliminary patching and repair work in advance of Measure
Y-funded microsurfacing on local streets. By operating this JOC project, the maintenance staff
remains focused on delivering Measure Y priority paving work, and the contractor provides rapid
response for utility trench repairs and minor concrete work as needed. Contract preparation costs are
kept to a minimum as well, by using this on-call service concept.
Water Distribution Permanent Trench Repairs
Currently the City has 216 water line repair locations with temporary asphalt concrete patches. In
order to eliminate this backlog and complete permanent repairs to these temporary patches, the
Water Distribution Division is requesting the appropriation of an additional $162,000 to the Water
Distribution Trench Repair Master Account. This will provide additional funding for the completion
of trench repairs.
City staff is actively engaged in improving the timeliness and quality of permanent patch repair on
City streets. One recent enhancement has been the use of Google Earth to locate and bundle the
existing trench work to enable the Contractor to evaluate and streamline repairs. In addition, staff is
continually monitoring and inspecting trench repairs to insure compliance with City Standards.
CONCURRENCES
This project is exempt from environmental review since it is a maintenance and replacement project
and a Notice of Exemption has been filed through the Community Development Department.
The Utilities Department concurs with this transfer of this funding in order to make permanent
repairs to temporary roadway patches.
FISCAL IMPACT
The source of funding for waterline trench repairs is the Trench Repair Master Account and
identified in the 2013-15 Financial Plan, Appendix B, Pages 3-114 through 3-119. Currently, there
is $138,896 available in the Trench Repair Master account. The proposed transfer of additional
funding will come from the Water Fund Completed Projects account ($60,000) and Water Fund
Working Capital ($102,000).
Funding
Available
Funding
Used
Funding
Available
Funding
Used
Funding
Available
Funding
Used
Trench Repair Master 91147 $ 43,800 25,525$ $ 191,775 177,879$ 138,896$ -$
Street Reconstruction and Resurfacing Master 90346 $ 89,483 -$ $ 658,157 165,870$ 1,200,000$ -$
Collection System Improvement Master 90239 $ 370,732 -$ $ 244,560 22,830$ 495,000$ -$
Total $ 504,015 $ 25,525 1,094,492$ 366,579$ 1,833,896$ -$
Account
2011-12 FY 2012-13 FY 2013-14 FYTask Order Funding Sources
C6 - 2
Transfer of Additional Funding for Trench Repair JOC 91196 Page 3
ALTERNATIVES
Deny authorization to transfer. The City Council could choose not to transfer the additional
funding for this project. This is not recommended because the JOC program is a cost-effective way
in which to get necessary maintenance work complete in a short timeframe.
ATTACHMENT
CAR to Advertise Trench Repair & Minor Concrete JOC-2013, Spec. 91196
t:\council agenda reports\2013\2013-10-15\transfer of additional funding for trench repair (grigsby-rowland)\car-transfer of additional funding for trench repair 91196.docx
Fiscal Impact Summary
Account Account Number Current
Proposed
Change
Ending
Balance
Water Fund Working Capital (102,000)$
Water Fund Completed Projects 99899999186,935$ (60,000)$ 126,935$
Trench Repair Master 91147953138,896$ 162,000$ 300,896$
Total -$
C6 - 3
FROM: Daryl R. Grigsby, Director of Public Works
Prepared By: Kyle Rowland, Engineering Inspector
SUBJECT: TRENCH REPAIR AND MINOR CONCRETE, JOB ORDER CONTRACT
– 2013, SPECIFICATION NO. 91196
RECOMMENDATIONS
1. Approve plans and specifications for the Trench Repair and Minor Concrete, Job Order
Contract - 2013, Specification No. 91196.
2. Authorize staff to advertise for bids and authorize the City Manager to award the contract to
the lowest responsible bidder.
DISCUSSION
Background
Throughout the course of the year, small street repairs need to be completed due to repair on
underground pipelines, or street areas that have settled significantly. When a water or sewer pipe
is repaired, Utility Department staff complete the work to the pipeline and then temporarily patch
the roadway. Engineering Division staff collects the location information after the repair is made
and issues a construction contract periodically to replace the temporary patch with a stronger and
more permanent asphalt patch. This is currently performed on an as-needed basis using Utility
Trench Repair–Job Order Contract-2011, entered into in March of 2012 for one year. In order to
streamline this activity and allow these permanent repairs to be completed more rapidly, while
still retaining the benefits of low bids, staff is proposing re-establishing a Job Order Contract
(JOC) for trench repair work for the upcoming year.
JOC is an alternative bidding procedure that was approved by the voters and added to the City’s
Charter on November 5, 2002 (See Attachment 1). Simply put, it is an on-call service contract.
The JOC provisions allow the City to perform maintenance related construction projects for
repair, remodeling or other repetitive work under a unit price contract. The City first
implemented a JOC program shortly after the Charter amendment was approved by the voters.
The Gordian Group was retained to develop the JOC program in which 160,000 pre-priced
construction tasks were developed and the contractors bid a percentage mark-up. The Gordian
Group developed the specifications and a contract was awarded in August 2003. The City used
this contract for about 2 years.
Multiple projects were completed using the JOC and the success of the program evaluated. The
160,000 pre-priced construction tasks covered every imaginable type of work and broke it down
into very small elements, such as traffic control where the City paid per cone costs. This minute
breakdown required staff to spend a great deal of time unraveling a cost proposal to see if it made
5/7/2013
C6 - 4
Trench Repair and Minor Concrete, Job Order Contract - 2013, Specification No. 91196 Page 2
sense for the work proposed to be completed or if there were unnecessary elements in the
proposal. The additional staff time needed for review made controlling City costs more
challenging.
Engineering staff revisited the JOC concept in 2011 and created a contract serving as a “focused
program.” Instead of bidding a JOC program which covers every imaginable type of work and
essentially pays the contractor for each worker and each piece of equipment that is used to
complete the work, staff has developed a program that bids the finished product. The current
Utility Trench Repair JOC has been developed to pay the contractor for each square foot of
roadway repaired, regardless of number of pieces of equipment or the number of staff the
contractor plans to use. This methodology is consistent with other types of projects the City
completes and has made it simpler for the contractors to prepare and submit proposals, and
streamlined delivery of work. Last year, the City generated 14 Task Orders, totaling $345,000
and proving to be an effective approach of handling roadway repairs.
The proposed Trench Repair and Minor Concrete JOC – 2013 is modeled after the successful
Utility Trench Repair JOC, but has been expanded to include other, easily identified work items
and extends the contract time to 24 months. The new contract items are various types of minor
concrete work construction, including sidewalk repairs and ramps. These changes will expedite
delivery of routine, ongoing, small City funded construction projects. While this contract will be
available for City funded work, other Utilities such as the Gas Company, PG&E and Charter
Communications would be required to create their own contract with their own contractor if they
want a similar system for those projects.
How JOC Contracts Work
When Engineering staff is notified of the specific sites needing repair by maintenance staff in
both the Utilities and Public Works departments, and from members of the public, locations are
entered into a GIS database for tracking and documentation. Engineering compiles the work in a
Task Order with a manageable number of locations marked for repair. With this information the
contractor will calculate the cost of the repairs based on the contract prices established through
the JOC contract.
Once staff has verified the contractor’s calculation is correct, a purchase order will be issued for
the work, authorized by the City Engineer for projects of $25,000 or less, and by the City
Manager for all other projects within approved budget. Task Orders in excess of approved budget
will return to Council for approval. This process follows the City Purchasing Policy and the
authorization limits have been set by the Council in Resolution 9444 as part of the JOC program
(See Attachment 2).
Once the work is authorized at the appropriate level and budget transfer completed, a work order
is issued to complete the repair and work can commence. Payment and close out of the individual
task orders will generally follow existing practices, with the exception that a final report is not
completed on individual task orders. The program will be assessed to determine its effectiveness.
If the program works well, other focused JOC projects will be recommended for release to handle
the more routine project work.
C6 - 5
Trench Repair and Minor Concrete, Job Order Contract - 2013, Specification No. 91196 Page 3
Routine repairs can, and sometimes are, completed by staff. This is a very effective approach
when immediate response is needed, or funding is not readily available for contract services. This
delivery method is not routinely used due to the very high volume of repair requests and the need
for street maintenance support work to be completed in advance of microsurfacing projects to
streamline delivery of those projects. By operating this JOC project, the maintenance staff
remains focused on delivering Measure Y priority paving work, while still providing a rapid
response for utility trench repairs and minor concrete work as needed. Contract preparation costs
are kept to a minimum as well, by using this on-call service concept.
CONCURRENCES
This project is exempt from environmental review since it is a maintenance and replacement
project and a Notice of Exemption has been filed through the Community Development
Department.
FISCAL IMPACT
This contract does not obligate any funds for construction. Once the contract has been executed,
staff will begin scoping work and issuing work orders. Funding will be transferred into this
project account from previously approved and funded Capital Improvement Plan projects, not-to-
exceed the funding authorized by Council or authorization limits as approved by Council
Resolution Number 9444 (2003 Series). Transfers of existing appropriations between projects
will be completed in accordance with Council adopted financial policies. The funding sources
for this work include the Street Reconstruction and Resurfacing (R&R) Master Account, Water
Distribution System Improvement – Trench Repair Master Account, Collection System
Improvement Master Account, and the Sidewalk Repair Master Account.
ALTERNATIVE
Deny authorization to advertise. The City Council could choose not to authorize the
advertisement of the project. This is not recommended because the JOC program is a cost-
effective way in which to get necessary maintenance work complete in a short timeframe.
ATTACHMENTS
1. Council Agenda Report, Authorizing JOC
2. Resolution 9444 (2003 Series)
AVAILABLE FOR REVIEW IN THE COUNCIL OFFICE
Trench Repair and Minor Concrete - JOC - 2013 Specifications
T:\Council Agenda Reports\2013\2013-05-07\2013 Trench Repair & Minor Concrete JOC 91196 (Grigsby-Rowland)\91196 CAR Advertise.doc
C6 - 6
Attachment 1
C6 - 7
Attachment 1
C6 - 8
Attachment 1
C6 - 9
Attachment 1
C6 - 10
Attachment 1
C6 - 11
Attachment 1
C6 - 12
Attachment 1
C6 - 13
Attachment 1
C6 - 14
Attachment 2
C6 - 15
Attachment 2
C6 - 16
Attachment 2
C6 - 17
Attachment 2
C6 - 18
Attachment 2
C6 - 19
Page intentionally left
blank.
C6 - 20