HomeMy WebLinkAbout05-20-2014 C8 San Luis RanchCity of San Luis Obispo, Council Agenda Report, Meeting Date, Item Number
FROM: Derek Johnson, Community Development Director
Prepared By: Doug Davidson, Deputy Director, Community Development
SUBJECT: AUTHORIZATION OF CONTRACT FOR CONSULTING SERVICES TO
CONTINUE PROCESSING THE SAN LUIS RANCH PROJECT
RECOMMENDATION
Authorize the Community Development Director to execute a contract with John Rickenbach
Consulting not to exceed $60,750 for Phase Two processing of the San Luis Ranch project.
DISCUSSION
Background
Due to record-high permit activity, the Community Development Department has been using
outside consultant assistance to augment staff resources in order to provide timely response to
the applications. For San Luis Ranch, the Community Development Department solicited
proposals from qualified organizations to provide responsible and comprehensive assistance in
processing all stages of the project. Funding for the plan review is being paid directly by the
applicant rather than using the permit revenue funds allocated to the department during the
review of the mid-year budget.
John F. Rickenbach Consulting submitted a proposal and was selected based on their extensive
local planning experience. The firm’s principal, John Rickenbach, was the project manager of the
first Environmental Impact Report (EIR) when Dalidio Ranch was the Marketplace project, and
he also worked on the City’s General Plan EIR in 1994.
On November 21, 2013, the City Manager entered into a Reimbursement Agreement with the
developer, Coastal Community Builders, Inc. The Reimbursement Agreement sets the
parameters for the developer to reimburse the City for consultant costs associated with managing
the application through the full entitlement process. Shortly thereafter, the City Manager signed
the Consultant Services Contract with John Rickenbach for Phase One (Pre-Application) not to
exceed 24,395 (including the City’s administrative charge). Phase Two is $60,750 which
requires Council authorization since it is over $25,000.
The consultant’s work effort is divided into two phases as follows:
Phase One: Manage pre-application review among internal staff and all work associated
with Planning Commission and City Council Study Sessions to initiate the formal
applications. Phase One of the consultant’s work is complete with the Initiation of the
project applications on April 1, 2014 by the City Council. On April 1, 2014 the Council also
approved the Processing Memorandum of Understanding and authorized the staff to initiate
5/20/14
C8 - 1
San Luis Ranch Consulting Services Page 2
the Development Agreement and issue Requests for Proposals for the Environmental Impact
report.
Phase Two: Manage project’s development review process including all staff meetings, staff
reports, public hearings, planning entitlements with supervision and assistance from a City
project planner and input from other Departments. Phase Two includes processing the
General Plan/Zoning Amendments, Specific Plan, Annexation, Development Agreement,
Development Plan, Tentative Tract Maps, while overseeing the environmental review
process and providing detailed technical, and policy review and analysis of the project
components through the development review process.
Development on the 131.3 acre property would include a mixture of residential and non-
residential uses, although substantial portions of the site would be preserved in agricultural uses
or open space. Under a Specific Plan, up to 500 dwelling units could be built at various densities,
with up to 200,000 square feet of commercial, 150,000 square feet of office, as well as a 200-
room hotel and conference center. The project site is currently outside the City, but within its
Sphere of Influence, and would require annexation.
The project as conceptually proposed is envisioned to implement the draft policies as articulated
in the LUCE update. The following entitlements and reviews would be required to implement
the project:
1. General Plan Amendment/Pre-Zoning (being programmatically evaluated in the LUCE
EIR)
2. Specific Plan
3. Development Agreement
4. Development Plan/Tentative Tract Map(s)
5. Architectural Review
6. Project Level Environmental Review (under the California Environmental Quality Act)
FISCAL IMPACT
The City of San Luis Obispo would pay the consultant for Phase Two work on a time and
materials basis against a maximum, not-to-exceed budget of $60,750, including professional fees
and associated expenses (Attachment 1, Consultant’s Scope of Work and Cost Estimate). The
developer will reimburse the City for all actual costs for the consultant’s services, plus a 30
percent City administration fee. The total reimbursement from the developer to the City is not-to-
exceed $78,975.
ALTERNATIVES
1. The City Council could opt not to authorize additional work from John Rickenbach
Consulting. This is not recommended because it would run counter to the City Council’s
action to Initiate the applications on April 1, 2014. Staff does not have the resources
currently to take over processing of the application.
2. The Council could direct the Community Development Director to renegotiate the contract
with John F. Rickenbach Consulting to expand or reduce the scope of work. This is not
C8 - 2
San Luis Ranch Consulting Services Page 3
recommended because staff and the consultant have reviewed the scope of work/cost
estimates and found it appropriate for the level of work required.
ATTACHMENTS
1. Consultant’s Scope of Work and Cost Estimate
t:\council agenda reports\2014\2014-05-20\SanLuisRanchConsultingServices(johnson-davidson)\report - sanluisranch.docx
C8 - 3
John
F.
Rickenbach
Consulting
San
Luis
Ranch
Contract
Planning
Services
City
of
San
Luis
Obispo
- 1 -
A.
SCOPE
OF
SERVICES
JFR
Consulting
proposes
the
following
work
program,
which
includes
these
conceptual
tasks
in
two
broad
phases
(with
an
optional
third
phase):
Phase
1
–
Pre-‐Application
Review
(Completed
in
April
2014)
• Task
1:
Project
Initiation
• Task
2:
Evaluate
Project
Application
• Task
3:
Set
Public
Hearing
Dates
for
Application
• Task
4:
Prepare
Staff
Report
• Task
5:
Present
Application
at
Study
Sessions
(assume
2)
• Task
6:
Coordinate
with
City
Staff
and
applicant
to
revise
application,
as
needed
• Task
7:
Ongoing
meetings
with
City
staff
and
project
team
as
needed
(assume
3)
Phase
2
–
Development
Review
Process
• Task
1:
Coordination
Meeting
with
City
Staff
• Task
2:
Prepare
Schedule
to
Coordinate
Project
with
LUCE
Update
• Task
3:
Participate
in
Public
Workshops
and
Scoping
Meeting
• Task
4:
Prepare
Initial
Study/CEQA
Determination
• Task
5:
Help
Develop
Possible
Alternative
Project
Concepts
for
Review
• Task
6:
EIR
Consultant
Coordination
Process
(if
EIR
is
needed)
a. Coordinate
with
Responsible
Agencies
to
Develop
EIR
Work
Scope
b. Prepare
EIR
Request
For
Proposals
c. Assist
Staff
in
EIR
Consultant
Selection
d. Review
Administrative
Draft
EIR
e. Coordinate
with
City
Staff
to
Release
Draft
EIR
f. Coordinate
with
Staff
and
CEQA
Consultant
to
respond
to
Public
Input
on
DEIR
g. Review
and
Coordinate
Final
EIR
• Task
7:
Coordinate
Fiscal
Analysis
with
City
Staff
and
Consultant
• Task
8:
Set
Public
Hearing
Dates
• Task
9:
Staff
Report
Preparation
and
Review
• Task
10:
Present
Project
at
Public
Hearings
(assume
2)
• Task
11:
Revise
Findings,
Evidence
and
Project
Conditions
• Task
12:
Coordinate
with
City
staff
and
applicant
to
revise
plan
as
needed
• Task
13:
Ongoing
Meetings
with
City
Staff
and
project
team
(assume
8)
Phase
3
–
LAFCo
Application
and
Coordination
(optional
task)
Each
of
these
tasks
is
described
in
greater
detail
below.
It
should
be
noted
that
the
specific
tasks
and
level
of
effort
associated
with
each
one
may
change
based
on
unforeseen
circumstances,
or
the
City’s
desire
to
reallocate
consulting
resources
to
produce
a
more
transparent
outcome
in
a
more
cost
or
time-‐efficient
manner.
Our
intent
in
writing
this
scope
is
to
be
responsive
to
the
City’s
current
request,
understanding
that
we
will
work
with
the
City
to
refine
the
scope
prior
to
executing
the
contract.
With
that
in
mind,
here
are
the
specific
tasks
associated
with
each
phase:
Attachment 1
C8 - 4
John
F.
Rickenbach
Consulting
San
Luis
Ranch
Contract
Planning
Services
City
of
San
Luis
Obispo
- 2 -
Phase
1
–
Pre-‐Application
Review
(Completed
in
April
2014)
This
phase
of
the
project
includes
the
steps
involved
in
reviewing
the
preliminary
application,
working
with
staff
and
the
applicant
to
revise
the
application
as
needed,
and
ultimately
presenting
it
to
the
Planning
Commission
and
City
Council
for
their
input.
With
their
authorization,
the
project
will
undergo
the
formal
development
review
process,
which
is
covered
in
Phase
2.
Task
1.
Project
Initiation.
John
Rickenbach
will
attend
a
kickoff
meeting
with
City
staff,
the
purpose
of
which
will
be
to
confirm
the
study
objectives,
refine
our
proposed
approach
as
needed,
and
gather
any
key
existing
documentation
related
to
the
project.
Our
basic
goal
in
this
meeting
is
to
determine
how
we
can
best
help
City
staff
in
the
most
efficient
and
effective
way
possible
given
potential
time,
budget
and
staffing
constraints.
We
will
confirm
the
key
products
and
schedule
associated
with
the
effort,
and
establish
communication
protocols
among
City
staff,
the
application
team,
and
the
community
in
general.
The
kickoff
meeting
will
also
provide
an
opportunity
to
strategize
and
discuss
other
long-‐range
issues
such
as
public
workshops,
key
stakeholders,
and
community
outreach
methods.
This
task
also
includes
the
review
of
existing
application
materials,
which
may
necessitate
a
follow-‐up
meeting
or
phone
call
to
refine
the
project
approach
established
at
the
kickoff
meeting.
Deliverables:
Attend
kickoff
meeting;
confirm
study
goals;
receive
and
review
project
application
materials;
refine
our
approach
with
City
staff
as
needed.
Task
2.
Evaluate
Project
Application.
This
step
builds
on
the
initial
review
of
the
project
application
in
Task
1.
The
purpose
of
this
task
is
to
critically
evaluate
the
application
to
determine
whether
or
not
it
is
complete,
and
to
determine
what
additional
materials
would
be
needed
to
ensure
that
the
application
is
complete
in
the
context
of
the
State’s
permit
streamlining
requirements.
This
step
also
entails
a
preliminary
review
of
the
proposed
project
parameters,
sufficient
to
gain
an
understanding
of
the
major
issues
likely
to
be
encountered
in
the
development
review
process,
both
from
a
policy
and
physical
perspective.
This
step
will
include
a
review
of
the
property
history,
its
relationship
to
County
Measure
J,
previous
environmental
documents,
applicable
City
regulations,
and
the
relationship
of
the
property
with
respect
to
the
City’s
ongoing
Land
Use
and
Circulation
Elements
(LUCE)
Update
process,
along
with
recommendations
from
the
LUCE
Task
Force
and
Planning
Commission
related
to
the
property.
With
respect
to
County
Measure
J,
our
review
will
describe
the
measure’s
complex
history,
legal
challenges,
and
applicability
to
the
current
effort.
Measure
J
was
approved
by
a
Countywide
vote
in
2006,
which
allowed
development
under
County
regulations
(not
City
regulations).
A
subsequent
legal
challenge
overturned
the
measure
in
2008,
which
was
subsequently
reversed
on
appeal
in
2009.
Based
on
this
preliminary
review,
it
may
be
useful
to
coordinate
a
site
visit
with
City
staff
to
confirm
or
address
questions
that
may
be
raised
through
this
review.
Ultimately,
we
will
prepare
a
memo
for
the
City’s
project
planner
that
summarizes
our
findings
and
recommendations
regarding
the
preliminary
application
review.
Deliverables:
Review
an
evaluate
existing
application
materials;
determine
the
completeness
of
the
application;
review
application
relative
to
City
regulations
and
previous
Attachment 1
C8 - 5
John
F.
Rickenbach
Consulting
San
Luis
Ranch
Contract
Planning
Services
City
of
San
Luis
Obispo
- 3 -
actions
taken
on
the
site,
including
County
Measure
J.
Prepare
a
memorandum
to
City
staff
that
summarizes
the
key
points
of
the
review.
Task
3.
Set
Public
Hearing
Dates
for
Application.
We
will
work
with
City
staff
to
develop
a
preliminary
schedule
and
establish
public
hearing
dates
before
the
Planning
Commission
and
City
Council
to
review
the
preliminary
application,
consistent
with
timing
requirements
under
the
State
Permit
Streamlining
Act.
This
step
is
necessary
because
the
Planning
Commission
and
City
Council
must
authorize
the
processing
of
a
General
Plan
Amendment,
rezoning,
annexation
and
related
entitlements
to
develop
the
property
in
the
City
before
the
formal
development
review
process
can
begin.
Deliverables:
Set
public
hearing
dates
for
Planning
Commission
and
City
Council
review
of
the
application
to
determine
whether
they
will
authorize
further
processing
of
a
possible
General
Plan
Amendment
and
other
related
entitlements.
Task
4.
Prepare
Staff
Report
with
City
Staff
Review.
Based
on
direction
from
City
staff,
John
Rickenbach
will
prepare
a
staff
report
that
summarizes
the
project’s
history,
current
application,
and
preliminary
review
of
the
application
relative
to
City
regulations
and
other
key
issues,
including
Measure
J.
Crucially,
the
staff
report
will
also
address
the
project’s
status
relative
to
the
current
Airport
Land
Use
Plan
(ALUP)
safety
zones,
and
how
the
proposed
changes
to
the
ALUP
may
impacts
the
proposed
development
concept.
The
staff
report
will
also
address
how
the
timing
of
this
project
relates
to
the
LUCE
update,
and
how
the
two
processes
could
be
coordinated.
The
staff
report
will
include
a
recommendation
relative
to
the
further
processing
of
the
project
through
the
development
review
process.
The
document
will
include
all
attachments
and
exhibits
as
needed,
using
City
templates.
The
City’s
project
planner
will
review
the
draft
staff
report,
which
will
be
revised
before
being
presented
for
distribution.
Deliverables:
Prepare
a
staff
report
evaluating
the
current
application,
making
a
recommendation
regarding
whether
it
should
be
processed
for
further
review.
City
staff
will
review
the
report
before
it
is
finalized.
Task
5.
Present
Application
at
Study
Sessions
to
Authorize
Further
Processing.
John
Rickenbach
would
present
the
application
before
the
Planning
Commission
and
City
Council
for
the
purpose
of
allowing
these
bodies
to
determine
whether
or
not
to
authorize
further
processing
of
the
application.
This
is
necessary
because
the
application
involves
a
General
Plan
Amendment,
would
require
rezoning,
and
would
ultimately
require
annexation
to
the
City.
John
would
prepare
a
PowerPoint
presentation,
coordinated
with
City
staff,
and
present
this
item
before
the
Planning
Commission
and
City
Council.
Deliverables:
Present
the
application
to
the
Planning
Commission
and
City
Council
based
on
a
PowerPoint
presentation.
Task
6.
Coordinate
with
City
Staff
and
Applicant
to
Revise
Application
as
needed.
If
authorized
for
further
processing,
we
will
work
with
City
staff
and
the
applicant
team
to
revise
the
project
application
to
address
public
concerns
and
specific
feedback
from
the
Planning
Commission
and
City
Council.
We
Attachment 1
C8 - 6
John
F.
Rickenbach
Consulting
San
Luis
Ranch
Contract
Planning
Services
City
of
San
Luis
Obispo
- 4 -
will
provide
direction
to
the
applicants,
and
review
their
subsequent
changes
to
the
application
(including
any
substantive
project
changes)
before
continuing
with
further
project
processing.
Deliverables:
Provide
direction
to
project
applicant
to
revise
project
application;
review
the
revised
application
and
coordinate
with
City
staff
as
needed
before
proceeding
with
formal
development
review
process.
Task
7.
Ongoing
Meetings
with
City
Staff.
Through
the
course
of
this
project
phase,
we
expect
to
meet
with
City
staff
on
several
occasions.
Our
scope
of
work
assumes
at
three
(3)
meetings
with
staff
during
the
pre-‐application
phase,
in
addition
to
the
Kickoff
Meeting,
which
is
covered
in
Task
1.
Deliverables:
Meeting
attendance,
follow-‐up
as
needed
Phase
2
–
Development
Review
Process
This
phase
of
the
project
includes
the
steps
involved
in
reviewing
the
processing
the
formal
application,
reviewing
the
proposed
project
in
detail,
guiding
the
application
through
the
California
Environmental
Quality
Act
(CEQA)
process,
and
the
formal
public
review
process
associated
with
both
the
CEQA
review
and
development
review
processes.
This
phase
also
includes
close
coordination
with
staff,
both
in
terms
of
meetings,
as
well
as
the
preparation
of
staff
reports
and
related
presentations
before
the
Planning
Commission
and
City
Council.
Task
1.
Coordination
Meeting
with
City
Staff.
John
Rickenbach
will
attend
a
coordination
meeting
with
City
staff,
the
purpose
of
which
will
be
to
confirm
the
study
objectives
in
the
wake
of
the
City
Council’s
authorization
of
the
project
for
development
review.
We
will
agree
on
the
project
parameters
for
study
as
authorized
by
the
City
Council,
identify
key
issues
raised
during
that
process,
and
confirm
a
rough
outline
of
the
development
review
process,
particularly
in
the
context
of
the
LUCE
Update.
We
will
also
confirm
that
the
applicant
has
submitted
revised
application
materials
that
address
the
issues
raised
during
the
pre-‐application
study
sessions
before
continuing
with
the
development
review
process.
Deliverables:
Attend
coordination
meeting;
confirm
study
goals;
receive
revised
project
application
materials;
refine
our
approach
with
City
staff
as
needed.
Task
2.
Prepare
Schedule
to
Coordinate
with
LUCE
Update.
Based
on
the
input
received
in
Task
1,
we
will
develop
a
project
schedule
that
coordinates
this
effort
in
the
context
of
the
LUCE
Update.
The
schedule
will
show
haw
the
two
processes
dovetail
and
can
be
coordinated,
such
that
the
two
processes
can
remain
consistent
with
one
another.
This
schedule
will
be
reviewed
by
City
staff
before
being
publicly
distributed
via
the
City’s
website.
Deliverables:
Prepare
a
schedule
coordinating
the
proposed
project
with
the
schedule
for
the
LUCE
Update,
to
be
reviewed
by
City
staff
prior
to
public
distribution.
Attachment 1
C8 - 7
John
F.
Rickenbach
Consulting
San
Luis
Ranch
Contract
Planning
Services
City
of
San
Luis
Obispo
- 5 -
Task
3.
Participate
in
Public
Workshops
and
Scoping
Meeting.
John
Rickenbach
will
participate
in
two
public
workshops
coordinated
by
the
City
for
the
purpose
of
soliciting
public
input
on
the
content
of
the
draft
Specific
Plan.
He
will
also
attend
and
participate
in
the
EIR
scoping
meeting
conducted
by
the
City.
Deliverables:
Attend
two
public
workshops
and
one
EIR
scoping
meeting
coordinated
by
the
City.
Task
4.
Prepare
Initial
Study
and
CEQA
Determination.
With
input
from
City
staff,
we
will
prepare
an
Initial
Study
pursuant
to
the
California
Environmental
Quality
Act
(CEQA)
that
provides
a
preliminary
evaluation
of
the
proposed
project’s
potential
environmental
impacts.
The
Initial
Study
will
be
prepared
using
the
City’s
approved
format,
and
address
all
requirements
of
the
CEQA
statute
(Pub.
Res.
Code
Section
21000
et
seq.)
and
the
State
CEQA
Guidelines
(14
California
Code
of
Regulations
[CCR]
15000
et
seq.).
CEQA
requires
that
all
state
and
local
government
agencies
consider
the
environmental
consequences
of
projects
for
which
they
have
discretionary
authority
before
they
approve
or
implement
such
projects.
The
Initial
Study
is
a
public
document
used
by
the
City
to
determine
whether
the
project
may
have
a
significant
effect
on
the
environment.
Based
on
the
Initial
Study,
we
will
work
with
City
staff
to
make
the
determination
of
the
appropriate
CEQA
document
to
prepare.
If
the
City
finds
substantial
evidence
that
any
aspect
of
the
project,
either
alone
or
in
combination
with
other
projects,
may
have
a
significant
effect
on
the
environment,
the
City
is
required
to
prepare
an
Environmental
Impact
Report
(EIR)
to
analyze
the
project.
If
the
lead
agency
finds
no
substantial
evidence
that
the
project
or
any
of
its
aspects
may
cause
a
significant
impact
on
the
environment,
a
Negative
Declaration
may
be
prepared.
If,
over
the
course
of
the
analysis,
the
project
is
found
to
have
a
significant
impact
on
the
environment
that,
with
specific
mitigation
measures,
can
be
reduced
to
a
less
than
significant
level,
a
Mitigated
Negative
Declaration
(MND)
may
be
prepared.
Based
on
the
past
history
of
the
project,
previous
CEQA
documentation,
and
the
level
of
controversy
surrounding
the
project,
it
is
likely
that
an
EIR
will
be
required.
However,
this
will
not
be
known
until
we
have
prepared
the
Initial
Study,
and
determined
the
extent
to
which
the
proposed
project
may
be
self-‐
mitigating;
that
is,
the
extent
to
which
through
project
design,
many
of
the
potential
impacts
have
already
been
addressed,
and
impacts
may
then
be
considered
to
be
less
than
significant.
If
an
early
determination
is
made
to
prepare
an
EIR,
the
Initial
Study
may
be
used
to
identify
which
issues
require
further
study
in
the
EIR,
and
which
can
be
adequately
addressed
through
the
discussion
within
the
checklist.
Although
mitigation
measures
may
be
included
in
an
Initial
Study
that
leads
to
an
EIR,
we
would
recommend
that
all
issues
requiring
mitigation
should
be
evaluated
in
the
EIR.
This
will
help
avoid
confusion
for
the
EIR
consultant,
and
allow
a
comprehensive
“apples-‐to-‐apples”
comparison
of
project
alternatives
studied
in
the
EIR.
For
example,
if
the
Initial
Study
demines
that
a
certain
issue
does
not
require
further
study
in
the
EIR
based
on
mitigation
measures
applied
to
the
project,
it
would
be
difficult
to
provide
a
meaningful
analysis
of
that
issue
relative
to
potential
project
alternatives,
particularly
if
that
alternative
may
result
in
a
greater
impact
relative
to
that
issue.
If
an
EIR
is
required,
then
the
steps
under
Task
5
of
this
scope
of
work
would
apply.
Otherwise,
Task
5
is
not
needed.
The
Initial
Study
will
rely
extensively
on
existing
studies,
the
project
application,
as
well
as
City
regulations
and
templates.
Attachment 1
C8 - 8
John
F.
Rickenbach
Consulting
San
Luis
Ranch
Contract
Planning
Services
City
of
San
Luis
Obispo
- 6 -
Deliverables:
Prepare
a
CEQA
Initial
Study
and
work
with
staff
to
make
an
appropriate
CEQA
determination
regarding
whether
an
EIR
or
a
Mitigated
Negative
Declaration
should
be
prepared.
If
an
EIR
is
determined
to
be
needed,
then
the
steps
under
Task
5
would
apply.
Task
5.
Develop
Possible
Alternative
Project
Concepts.
The
Initial
Study
will
identify
aspects
of
the
proposed
project
that
could
result
in
potentially
significant
impacts.
As
we
put
this
document
together,
we
will
work
with
City
staff
to
develop
potential
project
modifications
that
could
address
one
or
more
of
these
possible
impacts.
Ultimately,
we
will
discuss
these
with
the
applicant
team.
These
concepts
will
either
be
used
to
modify
the
project
itself,
or
form
the
basis
of
potential
project
alternatives
that
could
be
examined
in
an
EIR,
if
the
determination
is
made
that
an
EIR
is
necessary.
We
suggest
that
the
development
of
alternative
project
concepts
be
a
result
of
an
open
dialogue
with
the
applicant
team,
to
ensure
that
such
ideas
can
be
implemented,
and
are
not
just
theoretical.
The
purpose
of
this
exercise
is
to
produce
a
better
project,
and
to
the
extent
possible,
use
the
CEQA
process
to
help
guide
these
potential
changes.
Deliverables:
Work
with
City
staff
and
the
applicant
team
to
develop
project
concepts
that
may
address
one
or
more
of
the
preliminarily
identified
impacts
that
are
discussed
in
the
CEQA
Initial
Study.
Task
6.
EIR
Consultant
Coordination
Process
(if
EIR
is
needed).
This
task
applies
only
if
the
City
makes
the
determination
that
an
EIR
will
be
needed
to
satisfy
CEQA
requirements.
If
this
is
the
case,
we
will
take
the
lead
in
developing
the
steps
needed
to
hire
and
manage
a
third-‐party
consultant
who
will
prepare
an
EIR
for
the
proposed
project.
This
task
involves
the
entire
process
from
working
with
various
responsible
agencies
(including
but
not
limited
to
the
California
Department
of
Fish
and
Wildlife,
Regional
Water
Quality
Control
Board,
Caltrans,
and
SLO
Air
Pollution
Control
District)
to
develop
a
scope
of
work,
drafting
a
Request
For
Proposals
(RFP),
hiring
the
consultant,
and
working
with
the
consultant
as
they
prepare
the
EIR
document.
We
will
work
with
the
City’s
project
planner
on
these
tasks,
and
coordinate
closely
throughout
the
entire
EIR
process.
The
specific
steps
involved
in
this
task
include:
a. Coordinate
with
Responsible
Agencies
to
Develop
EIR
Work
Scope
b. Prepare
EIR
Request
For
Proposals
c. Assist
Staff
in
EIR
Consultant
Selection
d. Review
Administrative
Draft
EIR
e. Coordinate
with
City
Staff
to
Release
Draft
EIR
f. Coordinate
with
Staff
and
CEQA
Consultant
to
respond
to
Public
Input
on
DEIR
g. Review
and
Coordinate
Final
EIR
Deliverables:
Coordinate
with
City
staff
in
the
development
of
an
EIR
work
scope,
preparation
of
an
RFP,
hiring
an
EIR
consultant,
and
managing
that
consultant
throughout
the
process.
The
tasks
also
include
acting
as
the
lead
reviewer
of
the
CEQA
document,
and
coordination
of
that
review
with
other
City
departments
as
well
as
outside
agencies.
Attachment 1
C8 - 9
John
F.
Rickenbach
Consulting
San
Luis
Ranch
Contract
Planning
Services
City
of
San
Luis
Obispo
- 7 -
Task
7.
Coordinate
Fiscal
Analysis
with
City
Staff
and
Consultant.
We
will
oversee
and
coordinate
a
fiscal
impact
report,
which
will
be
prepared
by
a
third
party
consultant.
The
report
will
analyze
the
fiscal
impacts
to
the
City
from
the
proposed
development
project.
We
will
prepare
the
appropriate
findings
to
support
the
study,
and
include
supporting
evidence
in
the
draft
resolution
attached
to
the
staff
report.
Deliverables:
Coordinate
fiscal
study
prepared
by
an
outside
consultant,
and
summarize
findings
in
the
staff
report,
supported
by
clear
evidence.
Task
8.
Set
Public
Hearing
Dates
for
Project
Consideration.
This
step
involves
working
with
City
staff
to
establish
public
hearing
dates
before
the
Planning
Commission
and
City
Council
to
review
the
project
for
possible
approval.
Deliverables:
Set
public
hearing
dates
for
Planning
Commission
and
City
Council
consideration
of
the
project.
Task
9.
Prepare
Staff
Report
with
City
Staff
Review.
Based
on
direction
from
City
staff,
John
Rickenbach
will
prepare
a
staff
report
that
summarizes
the
project
components,
CEQA
review,
public
input
received,
and
potential
project
conditions
of
approval.
The
Staff
Report
will
discuss
the
project
in
the
context
of
the
LUCE
Update,
and
its
consistency
with
other
relevant
policies
and
documents
that
affect
planning
within
the
City,
including
the
ALUP.
The
staff
report
will
include
a
recommendation
relative
to
possible
project
approval.
The
document
will
include
all
attachments
and
exhibits
as
needed,
using
City
templates.
Our
scope
and
cost
estimate
also
includes
the
preparation
of
CEQA
Findings
for
the
project.
If
this
task
is
instead
to
be
handled
by
an
EIR
consultant,
our
cost
would
be
reduced
commensurately.
The
City’s
project
planner
will
review
the
draft
staff
report,
which
will
be
revised
before
being
presented
for
distribution.
Deliverables:
Prepare
a
staff
report
evaluating
the
proposed
project,
with
a
recommendation
regarding
whether
it
should
be
approved.
City
staff
will
review
the
report
before
it
is
finalized.
Task
10.
Present
Project
at
Public
Hearings
(assume
4).
John
Rickenbach
will
present
the
project
before
the
Planning
Commission
and
City
Council
for
their
potential
approval.
John
will
prepare
a
PowerPoint
presentation,
coordinated
with
City
staff,
and
present
this
item
before
the
Planning
Commission
and
City
Council.
Deliverables:
Present
the
project
at
up
to
4
hearings
before
the
Planning
Commission
and
City
Council
based
on
a
PowerPoint
presentation.
Task
11.
Revise
Findings,
Evidence
and
Project
Conditions.
Based
on
input
received
from
the
Planning
Commission
and
City
Council,
we
will
revise
the
project
findings,
evidence
and
conditions
as
needed
to
support
their
direction.
We
will
discuss
and
confirm
these
changes
with
staff
before
creating
a
final
version
of
the
project
findings.
Attachment 1
C8 - 10
John
F.
Rickenbach
Consulting
San
Luis
Ranch
Contract
Planning
Services
City
of
San
Luis
Obispo
- 8 -
Deliverable:
We
will
revise
the
project
findings
and
supporting
evidence
based
on
input
received
from
the
Planning
Commission
and
City
Council
for
City
staff
review,
finalization
and
distribution.
Task
12.
Coordinate
with
City
staff
and
applicant
to
revise
plan
as
needed.
Assuming
the
project
is
approved,
based
on
City
Council
direction,
and
supported
by
the
findings
prepared
in
the
previous
task,
we
will
work
with
City
staff
and
the
project
applicant
to
revise
and
finalize
their
plan
to
be
consistent
with
those
findings
and
project
conditions.
Deliverable:
We
will
work
with
staff
and
the
project
applicant
to
revise
the
revise
the
plan
(if
approved)
to
be
consistent
with
the
City
Council
findings
and
required
project
conditions.
Task
13.
Ongoing
Meetings
with
City
Staff.
Through
the
course
of
this
project
phase,
we
expect
to
meet
with
City
staff
on
several
occasions.
Our
scope
of
work
assumes
at
eight
(8)
meetings
with
staff
during
the
development
review
phase,
in
addition
to
the
Coordination
Meeting,
which
is
covered
in
Task
1.
We
understand
that
this
is
an
estimate,
and
the
number
of
meetings
may
be
higher
or
lower,
depending
on
how
the
process
unfolds.
Deliverables:
Meeting
attendance,
follow-‐up
as
needed
Phase
3
–
LAFCo
Application
and
Coordination
(optional
task)
Although
not
called
for
in
the
City’s
RFP,
as
an
optional
task
we
can
support
City
staff
through
the
annexation
phase
of
the
project,
which
will
be
required
before
the
project
can
be
developed
in
the
City.
This
step
would
include
working
with
Local
Agency
Formation
Commission
(LAFCo)
staff,
putting
together
the
application
for
annexation,
describing
the
project’s
service
needs
relative
to
LAFCo
requirements,
and
evaluating
the
project’s
consistency
with
LAFCo
policies,
including
those
associated
with
the
conversion
of
prime
agricultural
land
and
the
provision
of
water
supply.
We
understand
that
the
ultimate
determination
of
consistency
with
LACFo
policies
must
be
made
by
LAFCo,
but
in
our
experience,
it
is
useful
to
coordinate
closely
with
LAFCo
staff
throughout
the
entire
development
review
process
to
ensure
that
the
project
is
on
the
right
track,
and
that
the
application
process
will
go
in
a
more
timely
fashion.
In
this
way,
if
there
are
issues
to
be
resolved,
then
they
can
be
addressed
early
in
the
process.
At
this
time,
we
are
not
providing
a
cost
estimate
for
these
services,
but
can
do
so
upon
request.
Attachment 1
C8 - 11
John
F.
Rickenbach
Consulting
San
Luis
Ranch
Contract
Planning
Services
City
of
San
Luis
Obispo
- 9 -
B.
PROJECT
TEAM
The
contract
will
be
managed
locally
by
John
F.
Rickenbach
Consulting,
with
John
Rickenbach
as
Project
Manager.
John
will
handle
all
day-‐to-‐day
coordination
with
the
City
and
be
the
primary
contact.
Based
on
experience,
this
type
of
assignment
requires
a
high
level
of
consulting
expertise
and
ability
to
gain
the
trust
of
many
players,
including
City
staff,
project
applicant,
resource
agencies,
advocacy
groups,
and
most
importantly
the
community
at
large.
The
City
will
have
John’s
full
commitment
to
this
assignment,
and
he
will
not
offload
any
project
responsibility
to
junior
staff
or
interns.
As
an
optional
concept
that
the
City
could
also
consider,
it
may
be
useful
to
bring
in
additional
experts
in
engineering
and
biological
resources
to
review
aspects
of
the
proposed
plan
early
on,
if
the
City
does
not
have
staff
or
time
to
fully
address
these
aspects
of
project
review.
They
may
also
be
useful
in
reviewing
the
CEQA
document
prepared
for
the
project.
To
that
end,
we
would
bring
in
Michael
K.
Nunley
&
Associates
(civil
engineering)
and
Kevin
Merk
Associates
(biological
resources
and
regulatory
permitting)
if
desired
by
the
City,
with
whom
John
has
worked
successfully
in
the
past.
John
F.
Rickenbach
Consulting
and
partner
firms
are
all
locally
based
in
San
Luis
Obispo
County,
and
bring
principal-‐level
staff
to
this
assignment.
Key
staff
and
their
roles
are
summarized
below
and
described
in
more
detail
in
the
Qualifications
section
of
this
proposal.
Resumes
for
the
key
staff
are
included
in
the
Appendix.
John
Rickenbach,
AICP,
will
serve
as
Principal
in
Charge
and
Project
Manager
for
this
assignment.
In
this
role,
he
will
direct
the
day-‐to-‐day
work
program
and
be
the
City’s
primary
contact.
He
will
attend
all
meetings,
prepare
all
reports,
and
make
all
needed
presentations.
With
over
24
years
working
within
the
Central
Coast
region,
John
has
unparalleled
experience
for
similar
kinds
of
assignments,
including
controversial
projects
requiring
exceptional
communication
skills.
He
has
a
clear
understanding
of
the
regulatory
framework
of
local,
state,
and
federal
agencies,
and
how
they
interact
for
a
project
such
as
this.
John
is
a
land
use
planner
by
training,
and
an
acknowledged
expert
in
the
application
of
CEQA
as
well
as
other
state
and
federal
environmental
laws.
He
specializes
in
site
analysis.
He
combines
this
technical
background
with
excellent
communication
skills,
which
have
been
honed
managing
comprehensive
and
controversial
projects
such
as
the
City
of
Paso
Robles
General
Plan
Update,
which
won
an
Award
of
Merit
from
the
American
Planning
Association.
He
also
has
worked
with
the
City
of
San
Luis
Obispo
on
many
assignments
over
the
years,
including
as
a
contract
planner
in
the
early
stages
of
the
development
of
the
Orcutt
Area
Specific
Plan.
John
was
also
the
project
manager
for
the
first
San
Luis
Marketplace
EIR,
and
so
is
already
highly
familiar
with
the
Dalidio
property,
including
issues
related
to
the
Airport
Land
Use
Plan.
John
has
managed
difficult
site
studies
for
other
municipal
long-‐range
planning
efforts,
including
the
ongoing
Spanish
Springs
Specific
Plan
in
Pismo
Beach.
He
was
the
contract
planning
director
for
the
City
of
Guadalupe
for
several
years,
and
oversaw
much
of
the
process
that
led
to
the
ultimate
approval
of
the
DJ
Farms
Specific
Plan
for
that
community.
John
authored
an
APA
award-‐winning
report
entitled
Conventional
vs.
Neo-‐Traditional
Development:
A
Comparative
Analysis,
regarding
a
development
on
the
urban
fringe
of
the
City
of
Santa
Maria.
Attachment 1
C8 - 12
John
F.
Rickenbach
Consulting
San
Luis
Ranch
Contract
Planning
Services
City
of
San
Luis
Obispo
- 10 -
C.
COST
ESTIMATE
John
F.
Rickenbach
Consulting
will
provide
contract
planning
services
for
Phase
2
of
the
assignment
in
accordance
with
our
scope
of
work
for
an
estimated
not-‐to-‐exceed
fee
of
up
to
$60,750,
which
assumes
that
an
EIR
will
be
required,
and
that
the
assignment
involves
hiring
and
managing
an
outside
EIR
consultant,
as
well
as
reviewing
their
work.
It
also
includes
the
preparation
of
CEQA
Findings.
This
fee
includes
all
project
management,
technical
work,
meetings,
report
preparation
and
other
tasks
associated
with
the
overall
assignment.
It
also
reflects
John
Rickenbach’s
billing
rate
of
$135
per
hour,
as
shown
on
the
accompanying
spreadsheet.
Our
cost
estimate
is
just
that—an
estimate.
Experience
suggests
that
these
processes
often
take
unanticipated
directions,
and
sometimes
certain
tasks
require
more
(or
less)
effort
than
originally
estimated.
With
that
in
mind,
our
proposed
scope
of
work
and
related
cost
estimate
are
based
on
the
following
assumptions:
1. John
Rickenbach
will
be
the
Project
Manager
and
single
point
of
contact.
2. Our
scope
includes
attendance
at
a
project
kickoff
meeting,
2
public
workshops,
1
EIR
scoping
meeting,
4
public
hearings,
and
up
to
8
additional
meetings
with
City
staff
through
the
process.
We
also
assume
informal
consultation
with
staff
via
email
and
on
the
phone
throughout
the
process.
Public
hearings
would
be
attended
at
time
and
materials
billing
rates.
Additional
meetings
are
possible
at
$135
per
hour
on
a
time
and
materials
basis.
3. The
scope
of
work
does
not
include
any
subconsultant
tasks
or
fees.
If
the
City
chooses
to
engage
any
of
our
optional
subconsultant
services
for
engineering
or
biological
resource
issue
review,
we
can
provide
fee
estimates
consistent
with
the
City’s
desired
services.
4. We
assume
the
City
will
incur
all
printing
costs,
and
that
all
deliverables
will
be
sent
in
electronic
form.
5. If
additional
hours
are
needed
in
the
process,
or
if
additional
time
is
needed
for
meetings
and
coordination
because
of
unforeseen
project
complexities,
we
will
notify
the
City
as
early
as
possible
to
determine
how
best
to
address
these
issues.
If
all
parties
agree,
we
will
request
additional
funding
for
items
not
in
the
original
scope
of
work.
6. We
can
re-‐allocate
portions
of
the
budget
to
different
tasks
if
the
City
determines
that
the
time
is
better
allocated
to
such
tasks.
7. Subsequent
processing
steps,
including
the
LAFCo
process,
cannot
be
known
at
this
time,
and
are
therefore
not
covered
in
this
scope
of
work.
We
can
provide
a
cost
estimate
for
the
LAFCo
annexation
phase
of
the
process
if
requested
by
the
City.
We
intend
to
invoice
the
City
on
a
time-‐and-‐materials
basis,
not
to
exceed
the
total
fee
shown
above.
The
proposed
scope
of
services
and
associated
costs
are
fully
negotiable
to
meet
the
needs
of
the
City.
Additional
work
not
included
within
our
proposed
work
program
will
be
completed
only
upon
written
City
authorization
on
a
time-‐and-‐materials
basis.
This
offer
for
services
is
valid
for
60
days.
Questions
regarding
the
proposal
and
accompanying
cost
estimate
may
be
directed
to
John
Rickenbach
at
805/610-‐1109,
or
at
JFRickenbach@aol.com.
Attachment 1
C8 - 13
John
F.
Rickenbach
Consulting
San
Luis
Ranch
Contract
Planning
Services
City
of
San
Luis
Obispo
- 11 -
City of San Luis Obispo
San Luis Ranch Contract Planning Services
Cost Estimate (Phase 2: Development Review)April 22, 2014
Rickenbach
Tasks CostLabor Hours
$135/hr
PHASE 2. DEVELOPMENT REVIEW PROCESS
1. Coordination Meeting with City Staff $540 4
2. Prepare Schedule to Coordinate Project with LUCE Update $540 4
3. Participate in Public Workshops and Scoping Meeting (2 workshops; 1 scoping meeting)$1,620 12
4. Prepare Initial Study/CEQA Determination $8,100 60
5. Help Develop Possible Alternative Project Concepts for Review $2,160 16
6. EIR Consultant Coordination Process (if EIR needed)
a. Coordinate with Responsible Agencies to Develop EIR Work Scope $1,080 8
b. Prepare EIR Request For Proposals $4,320 32
c. Assist Staff in EIR Consultant Selection $1,080 8
d. Review Administrative Draft EIR $5,400 40
e. Coordinate with City Staff to Release Draft EIR $540 4
f. Coordinate with City staff and CEQA consultant to respond to public input on Draft EIR $4,320 32
g. Review and Coordinate Final EIR $2,160 16
7. Coordinate Fiscal Analysis with City staff and consultant $1,620 12
8. Set Public Hearing Dates $540 4
9. Staff Report Preparation and Review
a. Prepare Project Discussion, Findings and Evidence $5,940 44
b. Prepare CEQA Findings (if not prepared by EIR Consultant)$4,320 32
c. Revise Staff Report based on City Staff input $810 6
10. Present Project at Public Hearings (assume 4)$2,160 16
11. Revise Findings, Evidence or Discussion based on Public Hearing Input $1,620 12
12. Coordinate with City staff and applicant to revise Plan, as needed (if project approved)$3,240 24
13. Ongoing Meetings with City Staff/Project Team as needed (assume 8)$3,240 24
Coordination/Project Management $5,400 40
TOTAL COST ESTIMATE (Phase 2, assuming EIR required):$60,750 450
Attachment 1
C8 - 14