HomeMy WebLinkAboutNHC SLO 2600 Broad Street Closure Report1
Christian, Kevin
From:Clarence Reynolds <c.reynolds@ppcinc.biz>
Sent:Friday, June 18, 2021 2:56 PM
To:Bliss, Matheson
Cc:William Sarten; John Hochleutner
Subject:NHC SLO 2600 Broad Street Closure Report
Attachments:NHC SLO Closure Report pg. 9 mark up.pdf
Follow Up Flag:Follow up
Flag Status:Completed
This message is from an External Source. Use caution when deciding to open attachments, click links, or respond.
Hi Mattie,
I hope this gives you a better idea of how the project proceeded. Unfortunately, the Diesel
Tank Excavation and Trench area have been backfilled so no pictures are available. Please
let me know if you need more detail.
1. Describe the two distinct excavations (diesel tank and concrete structure), the
trenches (noted on 4/6 data table), and soil piles and bins that are also noted on
the data tables. Add additional figures detailing these areas and specific sampling
locations. Diesel Tank Excavation: OEC Lab ID# 2101841-01 through 04 – Tank
Wall Samples were taken at depth of 4’ in the center of each wall. 2101841-05 &
06 Tank Bottom Samples were taken at a depth of 8’ at the inlet and outlet ends
of the tank. These samples were located at the bottom center of the East and
West ends of the excavation approximately 1’ from the East and West walls
respectively. The sample locations can be seen on page 9 of the closure report.
The soil excavated from the diesel tank removal generated a pile approximately 5’
in height, 8’ in length and 4’ in width. Composite samples were taken from the
North, South and West sides of the pile. This was done by taking three equal
amounts of material from halfway up each side of the pile at intervals of about
1’5” and a depth of about 6”. These aliquots were mixed into three composite
samples representing the three sides of the pile. A sample was not taken from the
East side as it was too close to the mouth of the excavation and unsafe. Trenches:
A trench was dug approximately 3’ deep to accommodate a water line. A pile of
soil and brick was generated. It was approximately 3’ in height, 6’ in length and 4’
in width. A composite sample was taken from the pile by taking six equal amounts
of material from half way up the pile (1.5’) at 2’ intervals and a depth of
approximately 6”. These aliquots were combined into a single sample. As the
excavation continued, the trench was segregated into two sections for sampling.
This was done because half the length of the excavated material was composed of
soil and the other length contained brick as well as soil. The length containing only
soil was dubbed “Fire Trench” and the other “Sump Trench”. Originally, samples
2
were taken from the West Wall of the Sump Trench and at the bottom of the
South End of the trench (OEC Lab ID#s 2101841-07,08). After data showed
further excavation was required and carried out, a sample was taken from the
Sump Trench West side (OEC Lab ID# 2103032-01) in the middle of its length
because that is where most of the brick was. A sample was also taken from the
bottom center of the trench (OEC Lab ID# 21020302-03). This Process was
repeated for the Fire Trench with the inclusion of a sample on the East side of the
trench were the material seemed to be consistent along the length of both
trenches. Concrete Excavation: During the excavation of the trench, the outline of
a brick structure was discovered containing lose bricks and soil. As this material
was removed, a concrete slab was uncovered. Brick and soil from this excavation
was placed into several twenty cubic yard bins. This material was sampled by
taking three samples from each bin. Material was taken from the center of each
bin moving left to right at a distance of 3’ apart for each sample (A, B, C). See
OEC Lab ID#s 210508-01 to -15. The concrete slab was removed and it was
discovered that there was hydrocarbon impacted soil underneath it, most likely
from the removed fuel tank. Five samples were taken from the floor of the
excavation. See OEC Lab ID#s 2102742-01 through -05. The sample locations are
as follows: NW Corner @ 8’, NE Corner @8’, SW Corner @ 8’, SE Corner @ 8’ and
the center of the excavation @ 8’. The data for these samples showed the
presence of weathered hydrocarbon and that more material needed to be
removed. Two twenty cubic yard bins of material were excavated and sampled in
the same manner as the other bins. See OEC Lab ID#s 2103212-03 through -08.
Once it was believed that all contaminated material was removed two verification
samples were taken from the excavation floor approximately 4’ East and West
from the center where the highest amount of petroleum had been present. Results
from these samples showed that the petroleum had been removed to an
acceptable level.
2. Reasoning for contaminants of concern (e.g. why weren’t SVOCs, PAHs, etc.
included in testing). These compounds were not considered necessary due to the
nature of the site. There was no indication that they would be present for any
reason considering the location and types of businesses in the area.
3. History of the site, possible uses of the diesel tank and concrete pit, reason for
high lead. Any information on diesel tank closed in place. To the best of our
knowledge, there is no available phase one assessment for this site. Apparently
somewhere close to the site there was a brick factory. The tank was likely used
either for fueling or for waste. The tank had been filled with a concrete slurry.
There was also a thin layer of what appeared to be petroleum on the outside of the
tank. Both the coating and slurry were sampled. See OEC Lab ID#s 2101909-01
and 2102464-01. The tank was then disposed of at the McKittrick Land Fill. The
bricks are possibly left over from a demolished structure, of what kind it is not
clear. The concrete may have been a cap for the fuel contamination underneath it.
Although the chromatographs for the TPH data show a weathered diesel pattern, it
is possible that gasoline range organics may have been present and have
degraded. Due to the presumed age of the site, this may have been leaded
gasoline explaining the presence of lead.
3
4. Depth to groundwater in the area. Approximately 15’ to the NE of the Diesel Tank
Excavation between the former Quik Mart and the building that will be the NHC
SLO, ground water was discovered at a depth of 2’. In the tank excavation, ground
water was discovered at a depth of 5’. No ground water intruded into the second
excavation were the bricks and concrete slab were found.
Best Regards,
Clarence Reynolds
Compliance – CST
P.O. Box 2646 | Orcutt, CA 93457
(805) 925-1947 EXT 352 | Fax: (805) 925-0884 | Cell: (805) 868-9081
Website: www.ppcinc.biz
Attention: During the COVID‐19 pandemic please anticipate a delay in response time to our emails. Safety being our
number one priority requires us to take social distancing measures. We appreciate your patience and understanding
during this time and will respond as soon as possible.