HomeMy WebLinkAbout06-10-2014 B2b Sewer Enterprise Fund ReviewCity of San Luis Obispo, Council Agenda Report, Meeting Date, Item Number
FROM: Carrie Mattingly, Utilities Director
Prepared By: Dave Hix, Utilities Deputy Director, Wastewater
Brigitte Elke, Business Manager
SUBJECT: FISCAL YEAR 2014-15 SEWER ENTERPRISE FUND REVIEW
RECOMMENDATION
1. Review and accept the Fiscal Year (FY) 2014-15 Sewer Enterprise Fund report.
2. Conceptually approve the FY 2014-15 Sewer Enterprise Fund budget, with final action
on June 17, 2014, with the adoption of the FY 2014-15 Financial Plan Supplement
DISCUSSION
Background
The FY 2014-15 budget contained within the 2013-15 Financial Plan provides the basis for the
review of the Sewer Enterprise Fund for this report. All assumptions made during the preparation
of the Financial Plan were reviewed and necessary updates and adjustments incorporated.
As outlined in the FY 2014-15 Sewer Enterprise Fund Analysis, which forecasts the financial
position of the fund through 2020-21, the City will be able to:
1. Continue to deliver safe and reliable wastewater services to the community within the FY
2014-15 adopted sewer rates;
2. Maintain its operation in FY 2014-15 within approved budget levels without any
adjustments;
3. Continue its ongoing level of capital improvement projects to maintain the community’s
wastewater infrastructure assets;
4. Maintain a healthy working capital balance and revenue plan to position the Fund
favorably for financing terms needed for the upcoming Water Resource Recovery
Facility (WRRF) upgrade project.
FY 2014-15 Sewer Enterprise Fund Analysis Report
The FY 2014-15 Sewer Enterprise Fund analysis report (Attachment 1) includes the details of
assumptions used to complete the review, changes in financial position, and an update on major
capital activities.
June 10, 2014
B2b
B2b - 1
Sewer Enterprise Fund Review – FY 2014-15 Page 2
Revenue Update
Overall, revenue projections for FY 2013-14 and 2014-15 are in alignment with the 2013-15
Financial Plan. During a public hearing on June 12, 2013, the City Council adopted sewer
service rates in support of the Fund’s 2013-15 operating budgets and capital investments in
accordance with Proposition 218 requirements.
The adopted sewer rate for 2014-15 reflects a 3% increase, effective July 1, 2014.
Rate Category 2013-14 Rate 2014-15 Rate
Base Fee $7.73 $7.96
Volume Charge $8.52 $8.77
Increase on average household of 7 units* $67.37 $69.35
Average Increase $1.98
* based on average winter water use cap.
Operating Program Update
The Sewer Enterprise Fund includes seven operating programs, all of which are on track with
their work programs within allocated resources. No increases or changes from the assumptions
made in the 2013-15 Financial Plan are recommended for FY 2014-15.
Capital Improvement Program Update
The recommended program will stay within approved overall funding for the fiscal year. Some
projects identified in the 2013-15 approved capital program for 2014-15 are being postponed.
However, construction costs are increasing with bids coming in higher than estimated. Higher
costs are being driven by a variety of reasons, such as site constraints, material costs and a more
competitive bidding environment. Engineer’s estimates have been increased to reflect this
change. The 2013-15 Financial Plan reflected the Madonna Lift Station replacement in 2015-16.
Funding of this facility has been accelerated to 2014-15. Below is a list of projects and changes
recommended to the previously approved funding.
CIP Projects
Original
2014-15
Proposed
2014-15
Proposed Change
Collection System Improvements
Marsh, Higuera, California to Marsh
Jennifer Street Sewerline – 2012-13 CIP
Rachel Street Sewerline
Stafford, Kentucky, Taft Sewerline
$460,000
0
$400,000
$200,000
0
$237,000
$544,000
$656,000
Postpone
Bid cost over estimate
Increased Engineer’s Estimate
Increased Engineer’s Estimate
Total Collection System $1,205,000 $1,582,000
Lift Station Replacements
Madonna Lift Station
Margarita Lift Station
0
$900,000
$520,500
0
Move from 2015-16 to 2014-15
Postpone
Total Lift Station $900,000 $520,500
Total for Amended Projects $2,105,000 $2,102,500
B2b - 2
Sewer Enterprise Fund Review – FY 2014-15 Page 3
Project Highlights
Energy Efficiency Project
Design of the SST (energy efficiency) project is now complete and equipment has been ordered.
Major construction activities will begin later this summer and should be complete by May 2015.
Water Resource Recovery Facility Project
Water Systems Consulting (WSC) has been hired as the Program Manager for the WRRF
Project. Phase One has begun with a variety of plans and studies, including environmental
permitting, infrastructure, regulatory and stakeholder outreach, which will result in a draft
facilities plan in December of 2014 and development of a design RFP in February 2015. The
final facilities plan and design RFP is scheduled to be presented to Council in April 2015. A
community workshop on the facilities plan is scheduled for June 4, 2014 at 6:30 pm at the
Ludwick Center. Phase Two, design, is scheduled to begin in July 2015.
FISCAL IMPACT
While cost estimates for capital projects increased (requiring the re-programming of certain
capital projects) funding required for both capital and operating programs for FY 2014-15
remains the same as projected in the 2013-15 Financial Plan.
ATTACHMENT
1. Fiscal Year 2014-15 Sewer Enterprise Fund Analysis and Exhibits
T:\Council Agenda Reports\2014\2014-06-10\Enterprise Fund Review (Grigsby-Mattingly)\Sewer Enterprise Fund Review
B2b - 3
ATTACHMENT 1
FY 2014-15 Sewer Enterprise Fund Analysis
June 10, 2014
Prepared by the
Utilities Department
B2b - 4
Attachment 1
Page 2
FY 2014-15 Sewer Enterprise Fund
TABLE OF CONTENTS
I. OVERVIEW
II. 2013-15 FINANCIAL PLAN SUPPLEMENT: FY 2014-15 BUDGET
A. Revenue Summary
B. Operating Program Summary
C. Capital Improvement Plan Summary
D. Debt Service Summary
III. MAJOR ACTIVITIES AND PROGRAMS
A. FY 2013-14 Update
B. FY 2014-15 Forecast
EXHIBIT A – FINANCIAL SCHEDULES
A.1 Changes in Financial Position
A.2 Projection Assumptions & Debt Service
A.3 Capital Improvement Plan
EXHIBIT B – SEWER RATE STRUCTURE HISTORY
B2b - 5
Attachment 1
Page 3
FY 2014-15 Sewer Enterprise Fund Analysis
I. OVERVIEW
This report presents the updated financial condition of the Sewer Enterprise Fund for the 2013-
15 Financial Plan Supplement’s 2014-15 operating budget and capital programs. It takes into
consideration the identified needs in the Wastewater Master Plan, regulatory requirements,
infrastructure maintenance, and adopted City financial policies.
II. 2013-15 FINANCIAL PLAN SUPPLEMENT: 2014-15 BUDGET
A. REVENUE SUMMARY
The Sewer Enterprise Fund’s projected revenues are summarized in Table A.
Table A. Revenue Summary
Original Revised Original Revised
BudgetBudget Variance BudgetBudget Variance
Investment & Property Revenue 113,600113,600 0 97,60097,600 0
Sewer Service Charges 14,402,20014,337,200(65,000)14,834,30014,767,300(67,000)
Sales to Cal Poly 882,400882,400 0 908,900929,30020,400
Development Impact Fees 154,400154,400 0 158,300158,300 0
Account Set-up Fees 105,000105,000 0 107,100107,100 0
Industrial User Charges 66,60066,600 0 67,90067,900 0
Connection Charges & Meter Sales 22,30022,300 0 22,70022,700 0
Other Revenues 6,7006,700 0 6,8006,800 0
Total 15,753,20015,688,200(65,000)16,203,60016,157,000(46,600)
2013-14 2014-15
Overall, revenue projections for FY 2013-14 and FY 2014-15 are in alignment with the 2013-15
Financial Plan. FY 2013-14 revenue projections are based upon actuals through March 31, 2014.
FY 2014-15 Sewer Service Charges are projected using the HDR (the department’s rate
consultant) revenue model which is based upon the following:
1. FY 2014-15 monthly sewer rates, adopted as part of the 2013-15 Financial Plan,
2. Winter water use data collected for a three-month period, route-dependent ranging between
mid-November 2013 and mid-March 2014, that establishes the Average Winter Water Use
(AWWU) sewer cap for billing, and
3. Sewer rate analysis that includes a review of all sewer accounts using the most recent 12-
month period.
Current revenue projections are slightly lower than estimated. On February 18, 2014, the City
Council approved the elimination of the Average Daily Attendance rate for schools and
classified schools as non-residential customers going forward. It was estimated that this change
would have a revenue impact of $225,300 annually. The change became effective on March 1,
2014, and will affect revenues in 2014-15, although it appears the impact will be less than
predicted. Beyond FY 2014-15, Sewer Service Charges are estimated using projected sewer
B2b - 6
Attachment 1
Page 4
service rate changes applied to the most recent volume/use data. FY 2014-15 monthly sewer
rates, which reflect a 3% increase effective July 1, 2014, are summarized below.
FY 2014-15 Monthly Sewer Charges
TYPE OF ACCOUNT Monthly Rates
Base Fee
Volume Fee
per unit
Residential – minimum base charge + volume charge
Single family dwelling, including single meter condominiums and townhouses,
per dwelling unit. Total monthly fee capped based on Average Winter Water Use
(AWWU)
$7.96 $8.77
Multi-family dwelling in any duplex, apartment house or rooming house, per
account. Accounts without separate irrigation meter: Total monthly fee capped
based on Average Winter Water Use (AWWU). Account with separate irrigation
meter: No cap.
$7.96 $8.77
Mobile home or trailer park, per account. Accounts without separate irrigation
meter: Total monthly fee capped based on Average Winter Water Use (AWWU).
Account with separate irrigation meter: No cap.
$7.96 $8.77
Non-Residential – minimum base charge + volume charge
All non-residential accounts including Schools, per account $7.96 $8.77
1 unit = 748 Gallons
Each Vehicle Discharging into the City Sewer System
Minimum base fee includes 1,500 gallons discharge. Volume fee per 100 gallons
in excess of initial 1,500 gallons discharged
$207.06 $12.47
per 100 gallons
The following table compares the FY 2013-14 and FY 2014-15 monthly bill for the average
Single Family Residential customer using the calculated AWWU “Sewer Cap” and approved
monthly sewer rates.
Development Impact Fees: Though development activities are increasing, projected FY 2014-
15 Development Impact Fees were maintained as originally estimated in the 2013-15 Financial
Plan in order to keep a conservative approach to this volatile revenue source.
Comparison Average Single Family Residential Sewer Customer Monthly Bill
2013-14 2014-15
AWWU SFR “Sewer Cap”: 6-Units 7-Units
Rates Average Bill Rates Average Bill
Base Charge: $7.73 $7.73 $7.96 $7.96
Volume Charge (Sewer Cap x Rate): $8.52/unit $51.12 $8.77/ unit $61.39
Total $58.85 $69.35
Average Increase $10.50
B2b - 7
Attachment 1
Page 5
B. OPERATING PROGRAM SUMMARY
Wastewater Division operating programs are summarized in Table B. The summary reflects the
operating program base budget amounts for FY 2014-15. No changes were made in any of the
operating programs and the 2013-15 Financial Plan budget assumptions remain valid.
2014-15
BUDGET
Wastewater Collection 906,800
232,600
3,435,900
Water Quality Laboratory 495,500
Wastewater Administration/Engineering 698,300
Wastewater Customer Service (1)298,300
574,500
6,641,900
(1) Customer Service costs are allocated 50/50 between the Sewer and Water Funds
Wastewater Franchise Fees
TOTAL WASTEWATER SERVICES OPERATING PROGRAMS
Water Resource Recovery Facility
Table B. Summary of Operating Programs
Pretreatment
C. CAPITAL IMPROVEMENT PLAN SUMMARY
Capital improvement project expenses are forecast based on infrastructure maintenance and
repair history, individual project budget estimates, and regulatory requirements. Maintaining the
wastewater system infrastructure, including major equipment upgrades, ongoing treatment
processes, technology, and long-term infrastructure upgrade and replacement planning is critical
to providing safe and reliable wastewater services for the community. Wastewater Division
Capital Improvement Plans are summarized in Table C.
B2b - 8
Attachment 1
Page 6
Table C. Capital Improvement Plan
2013-142014-152014-15
BUDGETBUDGET Proposed
Wastewater Collection
Collection System Improvements 562,8431,205,0001,582,000
Calle Joaquin Lift Station 3,300,000
Madonna Lift Station 100,000 0 520,500
Margarita Lift Station 100,000900,000 0
Foothill Lift Station 100,000
Fleet Replacement: Portable Generators (50% share)152,900152,900
1/2 ton Pickup 29,500 00
Hydro-Cleaner 362,300 00
Water Resource Recovery Facility
Major Maintenance 981,348360,000360,000
WRRFEnergy Efficiency
Design 518,325
Construction 9,002,000
WRRF Upgrade
Study 150,000
Design 1,500,0002,000,0002,000,000
Construction Management 2,225,383
4-Wheel Drive Loader 30,200
Compact Pickup Truck 26,800
Fleet Replacement: Service Body Truck 36,80036,800
Administration & Engineering
Street Reconstruction 11,000
Sedan 16,200
Shared - Mobile Equipment Lifts & Safety Stands 13,20013,200
Total Wastewater Services CIP Requests 19,015,8994,667,9004,665,400
Shared Information Technology
Network Switching Infrastructure Replacement 33,50033,500
Office Application Software Replacement 26,0009,0009,000
Total Share of Information Technology CIP 26,00042,50042,500
Carryover from 2012-13 2,981,682
TOTAL SEWER FUND CAPITAL PLAN 22,023,5814,710,4004,707,900
B2b - 9
Attachment 1
Page 7
D. DEBT SERVICE SUMMARY
The Sewer fund’s debt service obligations are summarized in Table D.
Table D. Debt Service Summary
2014-15
Budget
Current
2009 Public Safety Radio System Upgrade $42,600
2009 Public Safety Communications Center $32,500
I-Bank Loan for Tank Farm Lift Station $560,300
Private Placement for Tank Farm Lift Station $185,400
WRRF Energy Efficiency Project $584,500
Total $1,405,300
The Water Resource Recovery Facility (WRRF) Energy Efficiency Project began in 2013-14
with the first debt payment due in 2014-15 as outlined above. The WRRF upgrade project is in
its planning stage, with debt service being programmed in 2017-18.
V. MAJOR ACTIVITIES AND PROGRAMS
A. 2013-14 Updates
1. Laguna Lift Station and Calle Joaquin Lift Station Siphon and Forcemain
Laguna Lift Station construction has been completed and the new station is operating
efficiently requiring minimal amounts of staff time for operations and maintenance.
Calle Joaquin Lift Station, Siphon and Forcemain replacement project is currently at 50%
design, with final design, environmental permitting and land acquisition anticipated to be
completed Fall 2014. Construction is anticipated to commence in late 2014.
2. Regulatory Update
The City has been notified by Central Coast Water Board staff (CCWB), that a revised
National Pollutant Discharge Elimination System (NPDES) permit will be heard by their
Board at its September 25, 2014 meeting. The new permit will require new discharge
limits to meet more stringent nutrient and disinfection by-product standards. The revised
permit will become effective December 1, 2014 giving the City five years to comply with
the new limits. CCWB and City staff continue to discuss the revised permit to determine
the most reasonable requirements for both parties.
B. FY 2014-15 Forecast
1. Water Resource Recovery Facility Energy Efficiency Project
In January 2014 the energy efficiency project kicked off with a ground-breaking
ceremony at the WRRF. Design for all project components has been completed,
equipment ordered, and demolition and installation of new equipment and facilities will
be underway this summer. New cogeneration facilities, filtration, headworks and solids
handling will all be optimized by a new Supervisory Control and Data Acquisition
(SCADA) system. The project is anticipated to reduce the cost of the WRRF upgrade by
B2b - 10
Attachment 1
Page 8
$1.5 million, reduce annual operating costs by $325,000 and help the City meet its
climate action plan goals. Project completion is scheduled for May 2015.
2. Water Resource Recovery Facility Upgrade
In January of this year Water Systems Consulting (WSC) was hired as the WRRF project
program manager to oversee the planning and management of this complicated project.
Phase 1 project planning is designed to allow the acceleration of later portions of the
project such as preliminary and final design, value engineering and bidding for
construction activities. A draft facilities plan is anticipated in December 2014, with
development of the design RFP in 2015. Phase 1 will be completed in April 2015 with
the presentation to Council of the final facility plan and RFP for design services. Design
will begin in July of 2015. This process will ensure timely construction to meet the
WRRF revised NPDES permit. Total project costs are estimated at $64.3 million
including $3.5 million for design and $60.8 million for construction and related services.
B2b - 11
Attachment 1
Page 9
EXHIBIT A
2012 SEWER ENTERPRISE FUND
FINANCIAL SCHEDULES
B2b - 12
Attachment 1
Page 10
EXHIBIT B
SEWER RATE STRUCTURE HISTORY
Current policies to guide rate structure setting:
Comply with legal requirements
Encourage conservation
Ensure revenue adequacy to fully meet system operating and capital needs
Provide equity and fairness between customers
Be easy to understand and administer
Facilitate ongoing review to maintain rate stability
The City Council approved the residential volume-based sewer rate structure effective July 1,
2007 delivering a sewer rate structure with a base fee and volume charge to reflect the individual
customer’s usage and associated sewer charges. The volume based sewer rate structure
encourages water conservation and achieves fairness and equity among residential customer
classes — customers with low use pay less and customers with higher usage pay more. Prior to
2007, the single family residential sewer rate structure was a fixed charge which did not reflect
the individual customer’s water use and associated demand placed on the wastewater system.
With the residential volume-based sewer rate structure, the individual customer’s metered water
use during the winter months, when outdoor irrigation should be turned down or off and water
use should be most reflective of the demand placed on the wastewater system for sewer charges,
is used to establish a “sewer cap”. The water use during the winter months is averaged to
establish the sewer cap. Residential sewer caps are implemented with the first full sewer service
period after July 1st. Sewer charges are based on actual water usage up to the customer’s sewer
cap, which is most reflective of that customer’s demand on the wastewater system.
When a new customer account is activated, single family residential accounts start with an 8-unit
sewer cap and multi-family residential accounts start with a 6-unit sewer cap until the customer
establishes their individual sewer cap based on their average winter water use, as established in
the winter months. Eight units was selected as it is representative of winter water use for new
customers. After an individual cap has been established, a customer will not be charged more
than the cap. Conversely a customer may be charged less if their monthly water usage is below
the cap.
The City’s sewer rate structure includes a minimum base charge plus a volume fee based on the
volume of water used.
B2b - 13
CHANGES IN FINANCIAL POSITION - SEWER FUND
2013-14 2014-15 2015-16 2016-17 2017-18 2018-19 2019-20 2020-21
Revised
Budget Budget Projection Projection Projection Projection Projection Projection
Revenues
Investment and Property Revenues 113,600 97,600 127,100 160,600 58,200 82,000 105,000 88,300
Service Charges
Customer Sales
Sewer Service Charges 14,337,200 14,767,300 15,210,300 15,666,600 15,979,900 16,299,500 16,625,500 16,958,000
Sales to Cal Poly 882,400 929,300 957,200 985,900 1,005,600 1,025,700 1,046,200 1,067,100
Development Impact Fees 154,400 158,300 163,500 168,900 174,800 180,900 187,700 194,800
Account Set-Up Fees 105,000 107,100 110,100 113,200 116,600 120,100 123,700 127,400
Industrial User Charges 66,600 67,900 69,800 71,800 74,000 76,200 78,500 80,900
Connection Charges and Meter Sales 22,300 22,700 23,300 24,000 24,700 25,400 26,200 27,000
Other Revenue 6,700 6,800 7,000 7,200 7,400 7,600 7,800 8,000
Total Revenue 15,688,200 16,157,000 16,668,300 17,198,200 17,441,200 17,817,400 18,200,600 18,551,500
Expenditures
Operating Programs
Public Utilities 7,152,763 6,641,900 6,821,800 7,008,400 7,218,700 7,429,200 7,645,900 7,868,900
General Government 1,609,600 1,291,008 1,323,300 1,356,400 1,397,100 1,439,000 1,482,200 1,526,700
Total Operating Programs 8,762,363 7,932,908 8,145,100 8,364,800 8,615,800 8,868,200 9,128,100 9,395,600
Capital Improvement Plan 22,023,581 4,707,900 4,356,300 62,476,400 1,620,300 1,809,700 5,155,500 875,000
Debt Service 974,500 1,405,300 1,437,820 5,253,344 5,251,263 5,248,677 5,204,885 5,206,887
Total Expenditures 31,760,444 14,046,108 13,939,220 76,094,544 15,487,363 15,926,577 19,488,485 15,477,487
Other Sources (Uses)
Projected Retirement Buyouts
PERS employer rate increase (22,200)(45,500)(46,600)(47,800)(49,000)(50,200)(51,500)
Proceeds from Debt Financing 7,249,000 50,750,000
Cashflow adj
Other Sources (Uses)(38,653)
Total Other Sources (Uses)7,210,347 (22,200)(45,500)50,703,400 (47,800)(49,000)(50,200)(51,500)
Revenues and Other Sources Over (Under)
Expenditures and Other Uses (8,861,897)2,088,692 2,683,580 (8,192,944)1,906,037 1,841,823 (1,338,085)3,022,513
fund balance to adj to CAFR
Working Capital, Beginning of Year 16,937,500 8,075,603 10,164,295 12,847,874 4,654,930 6,560,967 8,402,791 7,064,706
Working Capital, End of Year 8,075,603 10,164,295 12,847,874 4,654,930 6,560,967 8,402,791 7,064,706 10,087,219
Reserve (20% of operating)1,752,500 1,586,600 1,629,000 1,673,000 1,723,200 1,773,600 1,825,600 1,879,100
Rate Stabilization Reserve (5% of sales)761,000 784,800 808,400 832,600 849,300 866,300 883,600 901,300
Capital Reserve for WRF upgrade 1,674,700 2,774,700 6,274,700
Unreserved Working Capital 3,887,403 5,018,195 4,135,774 2,149,330 3,988,467 5,762,891 4,355,506 7,306,819
B2b - 14
Attachment 1
Exhibit A.2
PROJECTION ASSUMPTIONS - SEWER FUND
CATEGORIES 2013-14 2014-15 2015-16 2016-17 2017-18 2018-19 2019-20 2020-21
Utilities Service Fees CPI Projections 1.4%2.0%2.8%2.8%3.0%3.0%3.0%3.0%
Debt Service - State Revolving Fund Loan $0 $0 $0 $0 $0 $0 $0 $0
Debt Service - Energy Conservation Projects $0 $0 $0 $0 $0 $0 $0 $0
Debt Service - 2009 Public Safety Radio System Upgrade $42,600 $42,600 $42,100 $41,800 $41,800 $41,300 $0 $0
Debt Service - 2009 Public Safety Communications Center $32,800 $32,500 $32,500 $32,500 $32,400 $32,400 $32,300 $32,100
Debt Service - I-Bank Loan for Tank Farm Lift Station $561,100 $560,300 $559,400 $558,500 $557,500 $556,600 $555,600 $554,500
Debt Service - Private Placement for Tank Farm Lift Station $185,600 $185,400 $185,100 $184,500 $183,700 $182,700 $181,500 $185,000
Debt Service - Water Reclamation Facility Upgrade $0 $0 $0 $3,817,500 $3,817,500 $3,817,500 $3,817,500 $3,817,500
Debt Service - WRF Energy Efficiency Project (15 Years)$152,400 $584,500 $618,720 $618,544 $618,363 $618,177 $617,985 $617,787
Development Impact Fee Growth Rate 0.25%0.50%0.50%0.50%0.50%0.50%0.75%0.75%
Working Capital Requirement @ 20% of operating expenditures $1,752,500 $1,586,600 $1,629,000 $1,673,000 $1,723,200 $1,773,600 $1,825,600 $1,879,100
Debt Service Coverage at 110% of Net Revenues (2)695%574%581%165%165%167%171%172%
Sewer Service Rate Increase 4.0%3.0%3.0%3.0%2.0%2.0%2.0%2.0%
(1) Development Impact Fee revenue is a based on Resolution No. 9582 (2004) and calculated as follows:
Base year 2011-12 revenue: $151,900
Adjusted base increased by projected CPI and growth $154,400 $158,300 $163,500 $168,900 $174,800 $180,900 $187,700 $194,800
Factors assumed to reduce development impact fee collection: base revenue adjustment for one-time large developments; maps vested prior to
establishment of current development impact fees, and; lower than 1% per year growth.
A study is currently underway to update the Wastewater Development Impact Fees based on current demographics and revised cost estimates for
Master Plan infrastructure projects. At this time, based on preliminary information, it is anticpated that the outcome of this study may include
recommendations for fee revisions to the wastewater impact fees.
(2) State Revolving Fund (SRF) and California Infrastructure and Economic Development Bank (I-Bank) requires overall coverage of 1.1 times maximum
annual debt service for all outstanding debt.
B2b - 15
Attachment 1
Exhibit A.3 CAPITAL IMPROVEMENT PLAN - SEWER FUND
PROJECT DETAIL AND PHASING - PUBLIC UTILITIES
2013-14 2014-15 2015-16 2016-17 2017-18 2018-19 2019-20 2020-21
BUDGET BUDGET PROPOSED PROPOSED PROPOSED PROPOSED PROPOSED PROPOSED
Wastewater Collection
Collection System Improvements 422,843 1,582,000 2,184,600 1,135,000 1,285,000 600,000 1,590,000
Collection System Infrastructure Replacement Strategy
Calle Joaquin Lift Station
Design
Construction 3,000,000
Construction Management 300,000
Madonna Lift Station
Design 100,000 520,500
Construction
Construction Management
Margarita Lift Station
Design 100,000
Construction 800,000
Construction Management 100,000
Foothill Lift Station
Design 100,000
Construction 800,000
Construction Management 100,000
Buckley Lift Station
Design 500,000
Construction 2,000,000
Construction Management 500,000
Marsh Street Siphon 40,000 240,000
Sewerline Repl Rachel 50,000
Sewerline Repl Stafford 50,000
Fleet Particulate Matter Trap Retrofit
Fleet Replacement: 1/2 Ton Pickup 29,500
Fleet Replacement: Hydro-Cleaner 362,300 343,100
Fleet Replacement: Portable Generators (50% share)152,900
Equipment Replacement: Generator (50% share)
Fleet Replacement: CCTV Van 169,100
Fleet Replacement: 1 1/2 Ton Service Trucks 182,700
Fleet Replacement: Portable Sewage Pump 36,900
Fleet Replacement: Caterpillar Mini Escavator (pooled)111,200
Total Collection 4,554,643 2,255,400 3,493,700 2,217,700 1,285,000 1,248,100 4,433,100 -
Water Resource Recovery Facility
Major Maintenance 798,500 360,000 775,000 675,000 280,000 450,000 640,000 875,000
WRRF Energy Efficiency
Design 518,325
Construction 9,002,000
WRRF Upgrade
Study/Environmental 150,000
Design 1,500,000 2,000,000
Construction
Infrastructure 15,590,000
Nutrient Removal 39,460,000
Construction Management 2,225,383 4,500,000
Digester 2 Cleaning 113,098
WRF Sludge Bed 69,750
Fleet Replacement: Service Body Truck 36,800
Fleet Replacement: Utility Trucks (3)54,600
WASTEWATER SERVICES
B2b - 16
Attachment 1
Exhibit A.3 CAPITAL IMPROVEMENT PLAN - SEWER FUND
PROJECT DETAIL AND PHASING - PUBLIC UTILITIES
2013-14 2014-15 2015-16 2016-17 2017-18 2018-19 2019-20 2020-21
BUDGET BUDGET PROPOSED PROPOSED PROPOSED PROPOSED PROPOSED PROPOSEDWASTEWATER SERVICES
Fleet Replacement: Sedan 33,000 33,700
Fleet Replacement: 4-Wheel Drive Loader 30,200
Fleet Replacement: Pickup Truck w/Flat Bed & Crane 104,000
Fleet Replacement: Top-Kick Dump Truck (pooled)0
Fleet Replacement: Compact Pickup Truck 26,800
Fleet Replacement: Decanter Trailer 7,600
Total WRRF 14,434,056 2,396,800 862,600 60,225,000 280,000 561,600 673,700 875,000
Total without CIPs under Debt Financing 5,432,056 5,175,000
Pretreatment
Fleet Replacement: Pickup Truck 25,900
Total Pretreatment 0 0 0 0 0 0 25,900 0
Water Quality Laboratory
Fleet Replacement: Pickup Truck 22,800
Total Quality Laboratory 0 0 0 0 0 0 22,800 0
Administration and Engineering
Street Reconstruction 2013 11,000
Fleet Replacement: Sedan 16,200 33,700
Shared - Mobile Equipment Lifts & Safety Stands 13,200
Total Admin 27,200 13,200 0 33,700 0 0 0 0
1,000,000 1,250,000
Total Wastewater Services CIP Requests 19,015,899 4,665,400 4,356,300 62,476,400 1,565,000 1,809,700 5,155,500 875,000
Total Wastewater CIP without Debt Financing 10,013,899 2,268,600 3,493,700 7,426,400 1,285,000 1,248,100 4,481,800 0
Shared Information Technology
Office Application Software Replacement (4% share)
City Website Upgrade (4% share)
Network Firewalls 8,500
Virtual Private Network (VPN) Replacement 6,200
Network Security Upgrades 5,500
Network Switching Infrastructure Replacement 33,500
Radio Handhelds and Mobile Replacements 46,400
Document Management System 3,800
Office Application Software Replacement 9,000
Enterprise Storage Growth 2,000
Storage Capacity Upgrade and Replacement 8,900
Total Share of Information Technology CIP 26,000 42,500 0 0 55,300 0 0 0
Carryover from 12-13 2,981,682
TOTAL SEWER FUND CAPITAL PLAN 22,023,581 4,707,900 4,356,300 62,476,400 1,620,300 1,809,700 5,155,500 875,000