HomeMy WebLinkAboutDaily report 07-25-2022CANNON CONSTRUCTION MANAGEMENT DIVISION
RESIDENT ENGINEER'S DAILY REPORT
ASSISTANT RESIDENT ENGINEER'S DAILY REPORT Report No:
CEM-4601 (Mod. 6/2011)Date:
M T W T F S Su (Select Day)
Shift Hours:8 Start Stop
8
8 2
2 6
8
8
8
8
4+
4+
5+
RE Hours Onsite Signature Title
Gilberto/Isaac
Cole F.
City Of San Luis Obispo
Tank Farm Road & Orcutt Rd.
Roundabout
Cannon ID 210332
Distribution (All projects): Original local agency project (field office). Reports covering extra work should be filed seperately.
THE RELENTLESS PURSUIT OF THE ELEGANT SOLUTION
July.25,2022
7:00a 7:30p
Location & Description of Work :
Poured stamped concrete at roundabout
EQUIP.
NO.
NO.
MEN
DESCRIPTION
(of Equipment or Labor)
EQUIPMENT AND/OR LABOR
583983622IDLE OR DOWN55F- 75Fsunny
EST. HOURS - ITEM NO.
1 foreman Ruben R.
2 mason Julio C./Sergio C
3 mason/flagger Edgar /Carlos/Blaze
3 mason Christian/Luis /George
Matthew Natividad APWA CP II
2 mason/apprentice
laborer
AC dike machine
Francisco/AbrahamSub Lanscape2
7:00A-1:30P
Sub - " Ccts1
laborers/Berm installersAC Dike Co. 3
CANNON CONSTRUCTION MANAGEMENT DIVISION
RESIDENT ENGINEER'S DAILY REPORT
ASSISTANT RESIDENT ENGINEER'S DAILY REPORT
CEM-4601 (Mod. 6/2011)
Report No:Date:M T W T F S Su (Select Day)
Shift Hours:
Start Stop Temperature:Min:Max:
SIGNATURE TITLE
THE RELENTLESS PURSUIT OF THE ELEGANT SOLUTIONTHE RELENTLESS PURSUIT OF THE ELEGANT SOLUTION
City Of San Luis Obispo
Tank Farm Road & Orcutt Rd.
Roundabout
Cannon ID 210332
Item no. 58 ( Textured Concrete /Truck Apron /Truck Blister )
Rubens crew continue to pour concrete for roundabout stamped concrete as per detail shown on sheet
C1 of approve plans. Reinforcements were verified in compliance with sheet C1 detail of approve plans.
They also formed and poured the acceleration stamped concrete median and also performed the
formwork and prep work for stamped concrete along the OE line median.
Item no. 3 ( Temporary Traffic Control )
Souza flaggers performed one lane traffic control during the concrete pour at the roundabout.
Item no. 98 ( Reclaimed Water Sign )
Sub contractor " CCTS " was on site and installed the reclaimed water signs as shown on irrigation plan
sheet 49 and 50 of approve plans. Installed 12 signs as per plan.
Item no. 36 ( 6" Asphalt Berm City STD 7120 )
Souza Construction hired the services of AC Dike company and installed 2545 LF of AC berm from Sta: OE
57 + 35 to Sta: ON 7 +07 as per construction note 7 of sheet no. 9 of approve plans. 9:00 A -1:30 P
Item no. 22 ( Irrigation )
Sub Contractor Wildbloom Landscaping was on site around 10:00 A and started working on trenching the
P.O.C. at the existing irrigation main. Work was coordinated with Parks department maintenance
personnel Tony and according to Tony, Wildbloom can have access on the meter boxes to shut off the
irrigation main.
Note.
On site meeting with Charlie , Bobby , Bryon and Chris of Central Coast Fence regarding the installation of
the guardrail along the box culvert. According to Bryon, Cole of Souza alredy potholed the flagged PG and
E and that the conduit was never located along the box culvert area. Chris of Central Coast ask the
question if anybody was on site when PG nad E performed the horizontal directional drilling which is being
assumed that method used during the installation of the PG nad E line. Replied to Chris that nobody can
confirm of the horizontal drilling work performed.
CANNON CONSTRUCTION MANAGEMENT DIVISION
RESIDENT ENGINEER'S DAILY REPORT
ASSISTANT RESIDENT ENGINEER'S DAILY REPORT
CEM-4601 (Mod. 6/2011)
Report No:Date:M T W T F S Su (Select Day)
Shift Hours:
Start Stop Temperature:Min:Max:
SIGNATURE TITLE
THE RELENTLESS PURSUIT OF THE ELEGANT SOLUTION
.