HomeMy WebLinkAboutDaily report 07-27-2022CANNON CONSTRUCTION MANAGEMENT DIVISION RESIDENT ENGINEER'S DAILY REPORT ASSISTANT RESIDENT ENGINEER'S DAILY REPORT Report No: CEM-4601 (Mod. 6/2011)Date: M T W T F S Su (Select Day) Shift Hours:8 Start Stop 8 8 2 8 8 8 2 2 4 8 8 8 8 5+ RE Hours Onsite Signature Title Mark M./Steve H. Sub CCTS2 Jose/AngelSub - LWE2 Cat 308 Emin ex Matthew Natividad APWA CP II 2 mason/apprentice laborer Francisco/Abraham/Sub Landscape5 7:00A-3:30P carpenters2 Edgar /Carlos 3 mason Christian/Luis /George 1 foreman Ruben R. 2 mason Julio C./Sergio C 3 mason/flagger July.27,2022 7:00a 7:30p Location & Description of Work : Poured stamped concrete median stamped concrete OE line and 6" curb change order median curb by Spanish Oaks. EQUIP. NO. NO. MEN DESCRIPTION (of Equipment or Labor) EQUIPMENT AND/OR LABOR 58310692,9322ccoIDLE OR DOWN55F- 75F sunny EST. HOURS - ITEM NO. Gilberto/Isaac Cole F. City Of San Luis Obispo Tank Farm Road & Orcutt Rd. Roundabout Cannon ID 210332 Distribution (All projects): Original local agency project (field office). Reports covering extra work should be filed seperately. THE RELENTLESS PURSUIT OF THE ELEGANT SOLUTION CANNON CONSTRUCTION MANAGEMENT DIVISION RESIDENT ENGINEER'S DAILY REPORT ASSISTANT RESIDENT ENGINEER'S DAILY REPORT CEM-4601 (Mod. 6/2011) Report No:Date:M T W T F S Su (Select Day) Shift Hours: Start Stop Temperature:Min:Max: SIGNATURE TITLE THE RELENTLESS PURSUIT OF THE ELEGANT SOLUTIONTHE RELENTLESS PURSUIT OF THE ELEGANT SOLUTION City Of San Luis Obispo Tank Farm Road & Orcutt Rd. Roundabout Cannon ID 210332 Item no. 58 ( Textured Concrete /Truck Apron /Truck Blister ) Rubens crew poured the median stamped concrete at OE line and poured the 6" curb at the median as per CCO by Spanish Oaks. Item no. 3 ( Temporary Traffic Control ) Souza flaggers performed one lane traffic control during the concrete pour at the OE line median from 8:00 A-10:00A Item no. 22 ( Irrigation ) Sub Contractor Wildbloom Landscaping was on site around 10:30 P and continued their work at the irrigation P.O.C. Item no. 92,93 ( Roadside sign -one post-two post ) CCTS was on site today and started the digging for the post signs as per location shown on sheet 44 and 45 of approve plans. Work in progress Item no. ( CCO -Arch footings ) Mark and Steve of Souza was on site today and started the Arch footing foundation work by digging for the beam and etc. Cole was working with them on the mini ex. Work in progress. Item no. 106 ( Lighting System ) LWE electricians was on site and installed the required street light pull box as shown on sheet E1 of approve plans. Jose was also trying to locate the conduit that he installed previously and to be installed at the roundabout with a pullbox for future use. Was not able to locate the conduit. Note. Mentioned to Francisco of Wildbloom that they need to extend the sleeve at T line median to satisfy City STD spec requirements of 18" pass hardscape. CANNON CONSTRUCTION MANAGEMENT DIVISION RESIDENT ENGINEER'S DAILY REPORT ASSISTANT RESIDENT ENGINEER'S DAILY REPORT CEM-4601 (Mod. 6/2011) Report No:Date:M T W T F S Su (Select Day) Shift Hours: Start Stop Temperature:Min:Max: SIGNATURE TITLE THE RELENTLESS PURSUIT OF THE ELEGANT SOLUTION .