HomeMy WebLinkAbout2022-09-10 review of disposal concept (CHA)
Cleath-Harris Geologists, Inc.
75 Zaca Lane, Suite 110
San Luis Obispo, CA 93401
(805) 543-1413
Disposal concept review 1 9/10/2022
September 10, 2022
Dan Garson
Wathen Castanos Homes
735 Tank Farm Road, Suite 100
San Luis Obispo, CA 93401
Subject: Proposed Disposal of Groundwater Inflow to Basin, Avila Ranch Project
Dear Mr. Garson:
Cleath-Harris Geologists has reviewed the proposed conceptual design for a basin drain to
dispose of groundwater that has intruded into the storm drains for the Avila Ranch project , and
then flowed into the basin (RRM Design Group, 8/4/2022). The basin was sized to receive
storm flows and project site surface runoff, and was expected to be dry otherwise. The flow of
intruded groundwater has resulted in significant standing water in Basin A.
Cleath-Harris Geologists’ review pertains to the source of the groundwater and the possible
means of either preventing the intrusion into the storm drains or disposing of the water once it
reaches Basin A.
Shallow Groundwater Conditions
Inflow to the storm drain system for the Avila Ranch project area has been observed where the
storm drains are at or below an elevation of about 98 feet (RRM, August 2 , 2022). Some
variation in groundwater level occurs over the year , which will affect the amount of flow
intruding into the storm drain. This discharge from the groundwater is similar to what happens
in the stream channel.
Under wet conditions, the groundwater level rises above the stream channel invert and results in
a gaining stream in the stream channel coursing through the property. The stream channel bed
drops from an elevation of a bout 110 feet at the northern project property line to about 92 feet at
the intersection of Buckley and Vachell. Sea sonally, the groundwater can be above the invert of
the stream channel during wet periods and below the invert during the dry periods. When CHG
staff walked the creek during our well siting investigation in June 2022, there was no flow in the
creek. A pool of water was observed near the creek crossing (elevation about 102 feet). This
August 23rd, the water level was at about 2 feet below stream channel invert a short distance
upstream of the observed pool (102 foot elevation).
Ground water level elevations are higher to the northeast on the Avila Ranch property. In the
irrigation well on the project area, the groundwater level was measured at 5.5 feet below the top
of casing, or at an elevation of about 99 feet (Cleath-Harris Geologists, June 7, 2021).
Disposal concept review 2 9/10/2022
These existing conditions will result in a varying amount of groundwater flowing into the storm
drains, depending on the season.
Proposed Disposal Concept
The groundwater flow in the storm drains that drain to the basin has been measured at about 30
gallons per minute and has a very low turbidity. The proposed drain would pump this water out
of the basin and into an adjacent area that is designated as a wetland. The Basin A floor at the
lower end of th e basin is at 93 feet elevation, with a subgrade elevation of 89 feet. The adjacent
wetland area is at an elevation of 96 to 97 feet. The adjacent stream bed at the bridge is about 93
feet elevation.
Alternative Options
Alternative options that would lower the shallow groundwater and thereby eliminate flow into
the storm drains were reviewed by the project team.
One of these options was a gravity flow drain in the proximity of the storm drains (RRM, August
23, 2022). This option did not have enough head to result in lowering water lev els below the
storm drain. Therefore, it would not be effective in diverting the groundwater prior to it entering
the storm drain system.
Another option would be to install dewatering wells at various locations. This option was not
feasible due to the large area that would need to be dewater ed.
On- and off-site delivery of the infiltrating groundwater in the storm drains to adjacent
agricultural fields would be effective. It would be a beneficial use and could off-set existing or
future irrigation demands and reduce groundwater production from wells. The demand for the
water may be variable and not be able to handle the continuous flow without storage. A
neighboring property has plans to put in an off-stream reservoir that could receive the water
potentially for the duration of the discharge. Thi s design concept is something that could be
explored but is not within the control of the project team.
Design Considerations
The flow rate for the final design of the proposed disposal concept should take into consideration
the following groundwater conditions:
Flow rate variations from the storm drain outlets
Shallow groundwater that may flow directly into sides and bottom of the basin
The groundwater inflow to the basin could possibly be as high as 100 ga llons per minute.
Disposal concept review 3 9/10/2022
Conclusion
Of the options available to remove the infiltrated groundwater that flows into Basin A, a pumped
sump at the western end of the basin that discharges to the area adjacent to Buckley/Vachell
intersection would be the most effective option at removing the water from the basin. Future use
for irrigation of agriculture may be an option in the future but will require additional
infrastructure and agreements with other parties.
Respectfully Submitted,
Timothy S. Cleath, Certified Hydrogeologist #81
Vice President, Cleath-Harris Geologist
Disposal concept review 4 9/10/2022
References
Cleath-Harris Geologists, June 7, 2021, Pumping Test Results of the Irrigation Well at Avila
Ranch
Cleath-Harris Geologists, August, 25, 2022, Findings from Passive Seismic Analysis at the
Avila Ranch Development
RRM Design Group, August 2, 2022, Avila Ranch Basin Modification to Basin A
RRM Design Group, August 23, 2022, Potholing results to evaluate gravity dewatering
drain.