Loading...
HomeMy WebLinkAboutAvila Ranch BMMP Quarterly Report_2022Q2 Biological Mitigation and Monitoring Plan 2022 Quarter 2 for Avila Ranch Development Phases 1-3 City of San Luis Obispo, California Prepared for Avila Ranch, LLC 735 Tank Farm Road, Suite 240 San Luis Obispo, CA 93401 by ALTHOUSE AND MEADE, INC. BIOLOGICAL AND ENVIRONMENTAL SERVICES 1602 Spring Street Paso Robles, CA 93446 (805) 237-9626 July 2022 838.10 Althouse and Meade, Inc. – 838.10 Biological Mitigation and Monitoring Plan for Avila Ranch Development i 2022 Quarter 2 Table of Contents 1 INTRODUCTION ........................................................................................................ 1 1.1 Permit Background and Purpose ......................................................................... 1 1.2 Location ............................................................................................................... 1 1.3 Contact Information ............................................................................................. 1 2 SUMMARY OF PREVIOUS QUARTERLY REPORTS ............................................... 1 3 CONSTRUCTION ACTIVITIES ................................................................................... 4 3.1 Phase 1 Underground Utilities ............................................................................. 5 3.2 Vertical Construction ........................................................................................... 5 3.3 Sidewalk and Street Construction........................................................................ 6 3.4 Buckley Road Extension ...................................................................................... 6 3.5 Phase 3 and Future Phase 6 Soil Stockpiling ...................................................... 7 3.6 Landscaping ........................................................................................................ 7 3.7 Site Dewatering ................................................................................................... 8 3.8 Erosion Control BMPs ......................................................................................... 8 4 ENFORCEMENT ISSUES .......................................................................................... 9 5 WETLAND MITIGATION MEASURES ....................................................................... 9 5.1 Storm Drain Outfall #2 ......................................................................................... 9 5.2 Corner Wetland Expansion ................................................................................ 10 Table TABLE 1. RESPONSIBLE PARTIES ............................................................................. 1 List of Figures FIGURE 1. UNITED STATES GEOLOGICAL SURVEY TOPOGRAPHIC MAP ............ 2 FIGURE 2. AERIAL PHOTOGRAPH.............................................................................. 3 Althouse and Meade, Inc. – 838.10 Biological Mitigation and Monitoring Plan for Avila Ranch Development 1 2022 Quarter 2 1 INTRODUCTION 1.1 Permit Background and Purpose This summary report has been prepared in accordance with quarterly reporting requirements outlined in Mitigation Measure BIO-1b of the Biological Mitigation and Monitoring Plan (BMMP) for Avila Ranch Development (Project), which states: The Environmental Monitor shall provide quarterly reports to the City regarding construction activities, enforcement issues and remedial measures. This report covers the period of April 1 through June 30, 2022. 1.2 Location Monitoring activities were conducted within the Project area located near the intersection of Buckley Road and Vachell Lane, in the City of San Luis Obispo, California. Project location coordinates are 35.23850°N, 120.66880°W (WGS84) in the Pismo Beach United States Geological Survey (USGS) 7.5-minute topographic quadrangle (Figure 1). A Project aerial photograph is provided as Figure 2. 1.3 Contact Information Contact information for the Project property owner representative, biological consultant, and lead agency is provided in Table 1. TABLE 1. RESPONSIBLE PARTIES Owner Representative Biological Consultant Lead Agency Avila Ranch, LLC Dan Garson 735 Tank Farm Rd., Ste. 240 San Luis Obispo, CA 93401 (805) 595-5440 Althouse and Meade, Inc. LynneDee Althouse LynneDee@alt-me.com Greg Salas Greg@alt-me.com 1602 Spring Street Paso Robles, CA 93446 (805) 237-9626 City of San Luis Obispo Office of Sustainability Robert Hill 990 Palm Street San Luis Obispo, CA 93401 (805) 781-7211 2 SUMMARY OF PREVIOUS QUARTERLY REPORTS This is the ninth BMMP Quarterly Summary Report for the Project. Ground disturbance at the Project was initiated on February 12, 2020 for Phases 1-3. Construction activities have continued through this reporting period. Thus far, work has primarily been focused on Phase 1 of the Project and the Buckley Road extension. Major grading has been completed in these areas. During this reporting period, work continued on the Buckley Road extension, vertical construction of Phase 1 homes, and Phase 1 landscaping. Additionally, work was completed on Phase 1 roads and underground utilities (Figure 2). To date, there have been no compliance issues reported. BIOLOGICALANDENVIRONMENTALSERVICES ALTHOUSEANDMEADE,INC.MDSUSGDWHG MD\,AME\-BB LHJHQG AFWLRQAUHD m Avila Ranch MDSCHQWHU.ƒ:.ƒN SDQLXLVOELVSR,CDOLIRUQLD USGS4XDGUDQJOH3LVPRBHDFK ... MLOH Figure 1. United States Geological Survey Topographic Map SDFUDPHQWR SDQ)UDQFLVFR )UHVQR LRVAQJHOHV LDVVHJDV BIOLOGICAL AND ENVIRONMENTAL SERVICES ALTHOUSE AND MEADE,INC.Map Updated: February 21, 2022 11:26 AM by JBB Legend Action Area Active Phase Inactive Phase ± Avila Ranch Map Center: 120.67218°W 35.23753°N San Luis Obispo, California Imagery Source: USDA NAIP, 05/21/2020 0 500 1,000 Feet Figure 2. Aerial Photograph Higuera Street Buckley Road Vachell Lane L o s Osos Valley Road Tank Farm Road Phase 4 Phase 3 Phase 2 Phase 1 Phase 5 Phase 6 Ph a s e 6 Buckley Ro a d E x t e n s i o n Althouse and Meade, Inc. – 838.10 Biological Mitigation and Monitoring Plan for Avila Ranch Development 4 2022 Quarter 2 3 CONSTRUCTION ACTIVITIES Work activities during the second quarter of 2022 included continued underground utility work in Phase 1, vertical construction, sidewalk and street construction, Buckley Road extension work, soil stockpiling in Phase 3 and future Phase 6, landscaping, site dewatering, and ongoing erosion control BMP upkeep. According to Mitigation Measure BIO-1b of the BMMP, “a CDFW-approved biologist shall be present during all construction occurring within 50 feet of Tank Farm Creek, riparian habitat, drainages, and seasonal or permanent wetlands.” A qualified Environmental Monitor was present for all work conducted within the 50-foot buffer zone. No sensitive species or compliance issues were noted. According to Mitigation Measure BIO-3a of the BMMP, “The City-approved qualified biologist shall conduct training to all construction personnel to familiarize construction crews with sensitive species that have the potential to occur within the Project site.” Worker education was provided to all construction staff prior to the start of work. A log of all trained employees is kept onsite with the Environmental Monitor. According to Mitigation Measure BIO-3b of the BMMP, the Nesting Bird Season is from February 15 to August 15 and “a pre-construction nesting bird survey shall take place within one week of habitat disturbance.” Pre-construction surveys were conducted immediately prior to the start of any vegetation-disturbing activities. During this reporting period, four nests were observed within the work area. These nests included two red-winged blackbird, one song sparrow, and one killdeer. All nests were identified by the Environmental Monitor during clearance surveys for vegetation management activities. In accordance with Mitigation Measure BIO-3b, 50-foot buffers were established around all nests to restrict work activities until nests successfully fledged or became inactive. Once buffers were removed, vegetation management activities resumed in these areas. According to Mitigation Measure BIO-3c of the BMMP, “within 48 hours prior to construction activities within 50 feet of Tank Farm Creek, drainages, and seasonal wetlands, the Project site shall be surveyed for California red-legged frogs.” Pre-construction surveys were conducted immediately prior to the start of any work within the 50-foot buffer zone. No frogs were observed during the surveys, and none have been observed onsite to date. According to Mitigation Measure BIO-3d of the BMMP, “within 48 hours prior to construction activities within 50 feet of Tank Farm Creek, drainages, and seasonal wetlands, the Project site shall be surveyed for western pond turtles.” Pre-construction surveys were conducted immediately prior to the start of any work within the 50-foot buffer zone. No turtles were observed during the surveys, and none have been observed onsite to date. Althouse and Meade, Inc. – 838.10 Biological Mitigation and Monitoring Plan for Avila Ranch Development 5 2022 Quarter 2 3.1 Phase 1 Underground Utilities Trenching for underground utilities, sewer, and storm drains in Phase 1 started on September 23, 2020, and continued through this reporting period. All trenching work areas were previously disturbed by initial site grading work. During this reporting period, work was completed on the installation of the sewer lift station and motor court utilities. Phase 1 underground utility work is now complete. Photo 1. Completed sewer lift station, view west. June 29, 2022. Photo 2. Backfill and grading of Phase 1 motor court utilities. June 29, 2022. 3.2 Vertical Construction Vertical construction of homes commenced on January 31, 2022. Vertical work started with the model homes on Bravo Street and then jumped over to the western end of Earthwood Lane, working eastward. Crews from all trades are currently onsite working on different stages of the home building. Photo 3. Model home progress on Bravo Street. June 29, 2022. Photo 4. View of different stages of home building on Earthwood Lane. June 29, 2022. Althouse and Meade, Inc. – 838.10 Biological Mitigation and Monitoring Plan for Avila Ranch Development 6 2022 Quarter 2 3.3 Sidewalk and Street Construction Construction on the Phase 1 sidewalks and streets began on May 10, 2021. To date, streetlights, sidewalks, gutters, and asphalt have been installed in all of Phase 1. Phase 1 sidewalk and street work was completed during this quarter. Photo 5. Earthwood Lane roundabout paving completed, view south. June 29, 2022. Photo 6. Paving and sidewalks completed on Venture Drive, view west. June 29, 2022. 3.4 Buckley Road Extension On July 23, 2021, work started on the Buckley Road extension from Vachell Lane to South Higuera Street. The large cut for the right of way is complete and the spoils were relocated to future Phase 6 for stockpiling. Buckley Road infrastructure, including storm drains, retaining walls, and sidewalks were the primary focus during this reporting period. Connection to existing roads and paving are scheduled to occur during the next reporting period. Photo 7. Buckley Road extension sidewalk, view west. June 29, 2022. Photo 8. Completed retaining wall, adjacent to South Higuera Street, view northwest. June 29, 2022. Althouse and Meade, Inc. – 838.10 Biological Mitigation and Monitoring Plan for Avila Ranch Development 7 2022 Quarter 2 3.5 Phase 3 and Future Phase 6 Soil Stockpiling Soil stockpiling in future Phases 3 and 6 continued during this reporting period. The soil is coming from onsite operations, as well as import from other sites. Photo 9. Phase 3 soil stockpiling. June 29, 2022. Photo 10. Phase 6 soil stockpiling, adjacent to Buckley Road, view west. June 29, 2022. 3.6 Landscaping Phase 1 landscaping also continued during this reporting period. Work focused on roadside and park landscaping. Oakridge Landscape is the primary contractor for landscaping work. In addition to new landscaping, Oakridge is also responsible for existing vegetation management activities. Primarily, this involves weed-whacking tall vegetation in work areas to eliminate potential nesting bird habitat and clear them for other work activities. Photo 11. Landscaping in stormwater basin adjacent to Park C. June 29, 2022. Photo 12. Landscaping along Earthwood Lane. June 29, 2022. Althouse and Meade, Inc. – 838.10 Biological Mitigation and Monitoring Plan for Avila Ranch Development 8 2022 Quarter 2 3.7 Site Dewatering The irrigation pipeline along the Phase 1 bike path, adjacent to Tank Farm Creek, continued to be used for dewatering the large retention basin in Phase 1. The pipeline extends from the large retention basin, through Phase 2, across the agricultural crossing, and to the borrow pit in Phase 4. Water pumped into the Phase 4 borrow pit was left to evaporate. Photo 13. Water pump used for dewatering at Phase 1 retention basin. June 29, 2022. Photo 14. Irrigation pipeline along Phase 1 bike path. June 29, 2022. 3.8 Erosion Control BMPs Erosion control BMPs were installed and maintained during this reporting period. This work consisted primarily of silt fence installation and maintenance. All BMPs were installed in accordance with the site-specific Erosion Control Plan. Photo 15. Silt fence repairs around the Corner Wetland. June 17, 2022. Photo 16. Silt fence installed around model home parking lot. June 29, 2022. Althouse and Meade, Inc. – 838.10 Biological Mitigation and Monitoring Plan for Avila Ranch Development 9 2022 Quarter 2 4 ENFORCEMENT ISSUES No compliance issues were noted during this reporting period. According to Mitigation Measure BIO-6 of the BMMP, “All work in and within 100 feet of Tank Farm Creek, including work within the creek setback, shall occur outside of the rainy season (April 15th to October 15th, unless approved otherwise by the RWQCB), during periods when the creek channel is dry and water flows are absent.” The RWQCB was contacted in 2020 for approval to continue work within the 100-foot setback beyond October 15th. On November 10, 2020, the RWQCB (Phil Hammer, via email) confirmed that they had no requirements against the work, provided all water quality standards were complied with. Work within the 100-foot setback has continued and no water quality issues have been noted. 5 WETLAND MITIGATION MEASURES 5.1 Storm Drain Outfall #2 Installation of a storm drain outfall was conducted on September 28, 2020. To make room for the outfall, willow trees in the work area were trimmed prior to the start of work, on September 25, 2020. According to Mitigation Measure BIO-2c of the BMMP, “Riparian trees four inches or greater measured at diameter-at-breast- height (DBH) shall be replaced in-kind at a minimum ratio of 3:1 (replaced: removed). Trees measured at 24 inches or greater DBH shall be replaced in-kind at a minimum ratio of 10:1.” One tree meeting the “four inches or greater” criteria was removed and required mitigation. On March 3, 2021, twelve live willow stakes were planted around the banks of the storm drain outlet. Currently, seven of the twelve stakes have been successful. The willow stakes will continue to be monitored for success by the Environmental Monitor. Photo 17. Successful willow stakes on western bank of Outfall #2. June 29, 2022. Photo 18. Successful willow stakes on eastern bank of Outfall #2. June 29, 2022. Althouse and Meade, Inc. – 838.10 Biological Mitigation and Monitoring Plan for Avila Ranch Development 10 2022 Quarter 2 5.2 Corner Wetland Expansion Phases 1 through 3 will result in permanent impact to a portion of one isolated state-regulated wetland in the southwest corner of the property (Corner Wetland), as a result of bike path and road expansion. A small portion (1,832 square feet or 0.04 acre) of the western edge of the approximately 0.29-acre wetland has been permanently removed by the development of a bicycle pathway and expansion of Buckley Road. Per the Project Wetland and Riparian Mitigation and Monitoring Plan (WRMMP) for Phases 1-3, the eastern side of the wetland was expanded on October 6, 2021, to mitigate for the lost portion. The impacts were mitigated at a 1.5:1 ratio of habitat impacted to habitat created, for a total of 2,748 square feet (0.06 acre) of created wetland habitat. Approximately 0.06 acre of adjacent ground was lowered to match the grade of the wetland and the area was seeded, as described by the WRMMP. Revegetation has occurred in this area. The area will continue to be monitored and managed, as described by the WRMMP. Photo 19. Revegetation in wetland expansion area, view south. June 29, 2022. Photo 20. Revegetation in wetland expansion area, view north. June 29, 2022.