LOCATION AND DESCRIPTION OF OPERATION:
Signature:
Start
Stop
Date
Weather: Sunny</
Class
Title: Engineer Inspector 3
Bill Fagundes
DAILY INSPECTION REPORT
Materials: N/A
CADPS Phase 1A
Monterey and Broad Streets
Equipment
Ford F450 Service Truck
GMC Service Truck
Jacob Wilhite
JMC
Colby Fox
Ford F750 Dump Truck
Davey Bowen
Alex Rosas
15:30 AM
Brian Newsom
FM
Lab
Water Truck
Ford F350 Service Truck
Air Compressor
Mini Excavator
Skip Loader
Rincon
Catherine Johnson
Earth Systems Pacific
wackers
Christian Sarabia
Richard Simmer
Sup
Jose Zarate
Ditch Witch Vacuum Trailer
Description of work:
Installation of conduits continued to the curb near the proposed pull boxes in Parking Lot 9. The unmarked 4-inch steel line was removed during trenching. Two unmarked steel lines,
one 8-inch and one 4-inch, were found perpendicular to the trench on the north side of Monterey. JMC brought out a vacuum trailer to excavate around these lines. The trench was
backfilled and compacted approximately 6 feet from the curb. Jose Zarate tested compaction.
I asked Richard and Davey if the number of bends for the AT&T conduit is acceptable for pulling the proposed fiber line, and if not, then changes need to be made prior to moving forward.
Richard informed me that it is acceptable.
Steve, with AT&T, removed the box from the power pole, and all but 3 lines that wrap on the proposed PG&E quadrant. Jake Mohmike was contacted regarding the remaining 3 lines that need
to be moved.
Catherine Johnson was present during excavations.