Good afternoon!
To date, Rincon has provided 9 full days and 2 half days of archaeological monitoring.
Today, Monday 2/13/2023, the crew continued trenching west on Broad Street towards the intersection with Palm Street. They began excavating the trench using a 305.5E2 excavator, but
switched to using hydro vacuum excavation upon reaching the roots of the ficus tree. The crew also began excavating a pit into the sidewalk to locate existing utility lines and to install
new utility boxes. Ground disturbance activities stopped around 1:45 and the monitor left the site at that time.
Tomorrow, Tuesday 2/14/2023, the crew will continue with hydro vacuum excavation around the ficus roots as well as continue excavating the pit and the trench west on Broad Street.
Catherine Johnson, Associate Archaeologist
805-859-9612 Mobile | 805-947-4824 Direct
cjohnson@rinconconsultants.com <mailto:cjohnson@rinconconsultants.com>
<https://www.rinconconsultants.com/>
Ranked 2021 “Best Environmental Services Firm to Work For” by Zweig Group