HomeMy WebLinkAbout6/4/2024 Item 5i, Horn and Kacsinta - Staff Agenda CorrespondenceCity of San Luis Obispo, Council Memorandum
City of San Luis Obispo
Council Agenda Correspondence
DATE: June 4, 2024
TO: Mayor and Council
FROM: Matt Horn, Public Works Director
Prepared by: Madeline Kacsinta, Capital Improvement Program Admin. Manager
VIA: Whitney McDonald, Interim City Manager
SUBJECT: ITEM 5I - 2024-25 ROAD MAINTENANCE RECOVERY ACT (SB1)
FUNDING AND PROJECTS
Staff received the following question, regarding the 2024-25 Road Maintenance Recovery
Act (SB1) funding and the project planned to utilize those funds. The question is shown
below with staff’s response shown in italics:
1) In reviewing the attachments for this item, it appears that the text of the
resolution (Attachment A) does not match the map (Attachment B). Please
clarify the scope of work for the 2024 Roadway Sealing Project.
All roadways included in the 2024 Roadway Sealing Project are included in bold
on Attachment B, Page 193 of the packet. This scope of work is identical to what
Council approved and authorized staff to advertise for construction bids at the May
21, 2024 Council Meeting. Item 5i programs funding for a portion of the work
included in the 2024 Roadway Sealing Project, but not the entire project. The 2024
Roadway Sealing Project is estimated to cost approximately $6.7M and this SB1
Funding is approximately $1.2M. This staff report does not modify the scope of
work included in the 2024 Roadway Sealing Project but only provides the
necessary location information to the California Transportation Commission (CTC)
for tracking purposes.