ORDINANCE NO. 1736 (2024 SERIES)
AN ORDINANCE OF THE CITY COUNCIL OF THE CITY OF SAN LUIS
OBISPO, CALIFORNIA, ADOPTING LOCAL AMENDMENTS TO PART 6
OF THE BUILDING CONSTRUCTION AND FIRE PREVENTION CODE,
2023
WHEREAS, greenhouse gas accumulation in the atmosphere as the result of
human activity is the primary cause of the global climate crisis; and
WHEREAS, in California alone, the initial impacts of climate change have resulted
in unprecedented disasters with tremendous human, economic, and environmental costs
and;
WHEREAS, the Intergovernmental Panel on Climate Change estimates that global
emissions need to be reduced by 45 percent from 2010 levels by 2030, and 100 percent
by 2050 to prevent global catastrophe; and
WHEREAS, the State of California enacted Assembly Bill (AB) 1279 to require
statewide carbon neutrality "as soon as possible," but no later than 2045; and
WHEREAS, City of San Luis Obispo residents and businesses have repeatedly
identified climate action as a top community priority; and
WHEREAS, Resolution 11159 (2020 Series) adopts the City of San Luis Obispo
Climate Action Plan for Community Recovery, which includes a communitywide goal of
carbon neutrality by 2035 and sector specific goal of reducing emissions from existing
buildings by half by 2030; and
WHEREAS, Resolution 11381 (2022 Series) reaffirmed these communitywide and
sector specific goals; and
WHEREAS, the inventoried greenhouse gas emissions in the City of San Luis
Obispo come from a variety of sources, primarily transportation and energy use in
buildings and facilities; and
WHEREAS, in order to achieve carbon neutrality, existing sources of greenhouse
gas emissions need to be substantially reduced or eliminated; and
WHEREAS, Public Resources Code Section 25402.1 (h)(2) allows local agencies
to adopt local amendments that are cost-effective and that result in buildings that use less
energy than would otherwise be required by the California Energy Code; and
Ordinance No. 1736 (2024 Series) Page 2
O 1736
WHEREAS, the California Energy Codes and Standards Statewide Utility
Program, has determined specific modifications to the 2022 State Energy Code for each
climate zone that are cost-effective; and that such modifications will result in designs that
consume less energy than they would under the 2022 State Energy Code; and
WHEREAS, staff has reviewed the “2022 Code Cycle: Custom Cost Effectiveness
Analysis - City of San Luis Obispo” existing building cost-effectiveness study, and finds it
sufficient to illustrate compliance with the requirements set forth under California
Administrative Code Chapter 10-106; and
WHEREAS, based on these studies, the City finds the proposed local
amendments to the 2022 California Energy Code to be cost-effective and consume less
energy than permitted by Title 24, Part 6; and
WHEREAS, the 2022 California Energy Code offers compliance options that were
established through the public rulemaking process of the code update; and
WHEREAS, the Council expressly declares that the proposed amendments to the
Energy Code are reasonably necessary because of local climatic, topological, and
geological conditions; and
WHEREAS, the requirements specified in this Ordinance were reviewed via public
comment and through a publicly noticed public hearing process.
NOW, THEREFORE, BE IT ORDAINED by the Council of the City of San Luis
Obispo as follows:
SECTION 1. Purpose. It is the purpose and intent of this Ordinance to establish
standards for single-family residential retrofits including major additions and alterations
that exceed minimum 2022 Title 24 Part 6 requirements.
SECTION 2. Adoption. The local amendments to Part 6 of the City of San Luis
Obispo Building Construction and Fire Prevention Code, 2023 (SLOMC Section
15.02.060) as specified in Exhibit A, are hereby adopted by the City of San Luis Obispo
to be codified under Chapter 15.02.060 and Chapter 15.04.065. The Council hereby
adopts the recitals herein as separate and additional findings of fact in support of adoption
of the ordinance.
SECTION 3. Severability. If any word, phrase sentence part, section, subsection
or other portion of this amendment or any application thereof to any person or
circumstance is declared void, unconstitutional, or invalid for any reason, then such word,
phrase, sentence, part, section, subsection, or other portion, or the prescribed application
thereof, shall be severable, and the remaining provisions of this amendment, and all
applications thereof, not having been declared void, unconstitutional or invalid, shall
remain in full force and effect.
Ordinance No. 1736 (2024 Series) Page 3
O 1736
SECTION 5. Findings. The City Council finds that each of the changes or
modifications to measures referred to therein are reasonably necessary because of local
climatic, geological, or topographical conditions in the area encompassed by the
boundaries of the City of San Luis Obispo, and the City Council adopts the following
findings in support of local necessity for the changes or modifications:
1. San Luis Obispo is situated along a wildland-urban interface and has been
identified as a Community at Risk from wildfire and is extremely vulnerable to
wildfires and firestorms, and human activities releasing greenhouse gases into
the atmosphere cause increases in worldwide average temperature, drought
conditions, vegetative fuel, and length of fire seasons- contributing to the
likelihood and consequences of fire.
2. The City of San Luis Obispo is situated at the base of a watershed of the Santa
Lucia Mountains and flooding of San Luis, Chorro, Stenner, Old Garden, and
Brizzolara Creeks results in conditions rendering fire department vehicular
traffic unduly burdensome or impossible, as witnessed in major floods that
occurred in 1952, 1961, 1969, 1973, 1978, 1982, 1995, and 2023. Furthermore,
flood conditions described above create the potential for overcoming the ability
of the fire department to aid or assist in fire control, evacuations, rescues and
other emergency task demands inherent in such situations. The resulting
overburdening of fire department personnel may cause a substantial or total
lack of protection against fire for the buildings and structures located in the City
of San Luis Obispo. The afore-described conditions support the imposition of
fire protection requirements greater than those set forth in the California State
Building Standards Code and support the imposition of more restrictive
requirements than set forth in the California Energy Code for the purpose of
reducing the City's contributions to Greenhouse Gas Emissions resulting in a
warming climate and related severe weather events.
3. The aforementioned flood and rain events result in conditions wherein
stormwater can inundate the wastewater treatment system as witnessed in
major floods that occurred in 1952, 1961, 1969, 1973, 1978, 1982, and 1995.
Furthermore, rain events and flood conditions described above create a
condition referred to as Inflow and Infiltration (I/I) that allow rain and flood
waters to flow and/or seep into the wastewater system and overcome the ability
of the wastewater collection system and Water Reclamation Facility (WRF) to
convey and treat sewage. The resulting overburdening of the wastewater
system can result in threats to public health, public and private property and
water quality and violations and fines from the State of California, the
Environmental Protection Agency (EPA) or others. To the extent that climate
change has the potential to make these conditions worse, more restrictive
Energy Code requirements to achieve reduced greenhouse gas emissions are
necessary.
Ordinance No. 1736 (2024 Series) Page 4
O 1736
4. Seasonal climatic conditions during the late summer and fall create numerous
serious difficulties in the control and protection against fire situations in the City
of San Luis Obispo. The hot, dry weather in combination with Santa Lucia
(offshore) winds frequently results in wildland fires in the brush-covered slopes
on the Santa Lucia Mountains, San Luis Mountain, and the Irish Hills areas of
the City of San Luis Obispo. The aforementioned areas surround the City.
When a fire occurs in said areas, such as occurred in 1985 when the Los Pilitas
fire burned six days and entered the City and damaged many structures, the
entirety of local fire department personnel is required to control, monitor, fight
and protect against such fire situations in an effort to protect life and preserve
property and watershed land. The same climatic conditions may result in the
concurrent occurrence of one or more fires in the more populated areas of the
City without adequate fire department personnel to protect against and control
such a situation. Therefore, the above-described findings support the
imposition of measures to increase the efficiency of existing buildings in the
City to reduce greenhouse gas emissions.
5. Failure to address and substantially reduce greenhouse gas emissions creates
an increased risk to the health, safety, and welfare of City residents.
6. The standards imposed by this Ordinance are necessary because of local
climatic, geological, or topographical conditions evidenced above and are cost-
effective, as supported by the “2022 Code Cycle: Custom Cost Effectiveness
Analysis - City of San Luis Obispo” cost effectiveness study prepared by the
California Energy Codes and Standards Statewide Utility Program. Specifically,
the City finds that there are at least five cost effective measure packages:
x Package 1, installing the efficiency measure of R-30 Floor Insulation would
save energy relative to the base code and would achieve a benefit to cost
ratio of 1.4 on an on-bill basis.
x Package 2, installing the efficiency measure of R-19 Floor Insulation would
save energy relative to the base code and would achieve a benefit to cost
ratio of 1.4 on an on-bill basis.
x Package 3 to installing a Heat Pump Water Heater (HPWH), would save
energy relative to the base code and would achieve a benefit to cost ratio
of 1.6 on a “Long-term System Cost” (LSC basis).
x Package 4, Heat Pump Space Heater, would save energy relative to the
base code and would achieve a benefit to cost ratio of 4.2 on an LSC basis.
x Package 5 to install PV + Electric Ready Pre-Wiring would save energy
relative to the base code and would achieve a benefit to cost ratio of 1.4 on
an on-bill basis.
Ordinance No. 1736 (2024 Series) Page 5
O 1736
SECTION 6. CEQA. This ordinance is categorically exempt from CEQA because
it is an action taken by a regulatory agency for the purpose of protecting the environment
(CEQA Guidelines Section 15308). In addition, this ordinance is exempt from CEQA
under the general rule, 15061(b)(3), on the grounds that these standards are more
stringent than the State energy standards, there are no reasonably foreseeable adverse
impacts, and there is no possibility that the activity in question may have a significant
effect on the environment. The following findings are made in support of these
determinations:
1. The purpose of the implementation of a Reach Code is to reduce the amount
of greenhouse gas emissions in the City of San Luis Obispo that are produced
from buildings.
2. The Reach Code approval process requires that the City determines that the
local standards will require buildings to use no more energy than current
statewide requirements. Furthermore, the California Energy Commission
approval process requires that the City make the findings as part of its approval
process. Therefore, the Reach Code standards can only go into effect if they
protect the environment by making buildings more efficient.
SECTION 7. Violations. Violation of the requirements of this Ordinance shall be
considered, at the City’s election, an infraction of the City of San Luis Obispo Municipal
Code punishable by all sanctions prescribed in Chapter 1.12, or an administrative
violation punishable as provided under Chapter 1.24.
SECTION 8. Effective Date. Pending approval by the California Energy
Commission, this Ordinance shall be effective on January 1, 2025.
Ordinance No. 1736 (2024 Series) Page 6
O 1736
SECTION 9. Ordinance Summary. A summary of this ordinance, together with the
names of Council members voting for and against, shall be published at least five (5) days
prior to its final passage, in The New Times, a newspaper published and circulated in this
City. This ordinance shall go into effect at the expiration of thirty (30) days after its final
passage.
INTRODUCED on the 21st day of May 2024, AND FINALLY ADOPTED by the
Council of the City of San Luis Obispo on the 4th day of June 2024, on the following vote:
AYES:
NOES:
Council Member Francis, Marx, and Shoresman
Mayor Stewart
RECUSED: Vice Mayor Pease
___________________________
Mayor Erica A. Stewart
ATTEST:
_______________________
Teresa Purrington
City Clerk
APPROVED AS TO FORM:
_______________________
J. Christine Dietrick
City Attorney
IN WITNESS WHEREOF, I have hereunto set my hand and affixed the official seal of the
City of San Luis Obispo, California, on ______________________.
___________________________
Teresa Purrington,
City Clerk
Ordinance No. 1736 (2024 Series) Page 7
O 1736
Exhibit A
Section 15.02.060
Amend Section 15.020.060 to read as follows:
The City of San Luis Obispo hereby adopts the 2022 California Energy Code as
Part 6 of the San Luis Obispo Building Construction and Fire Prevention Code,
2023. Except as otherwise provided herein, or as later amended in Section
15.04.060 and 15.04.065, or affected by San Luis Obispo Health and Safety Code
Chapter 8.11, Part 6 of the San Luis Obispo Building Construction and Fire
Prevention Code, 2023, shall be as published in the California Energy Code, 2022
Edition, and as copyrighted by the California Building Standards Commission,
California Code of Regulations, Title 24, Part 6, including all of its tables, indices,
appendices, addenda and footnotes. Said California Energy Code is hereby
referred to and by such reference is incorporated herein as if fully set forth.
Section 15.04.065
AMENDMENTS – ENERGY STANDARDS – ADDITIONS AND ALTERATIONS
A. Adoption of Codes and Applicability
The effective date of this ordinance shall be January 1, 2025 and is applicable to
existing single family residential buildings. The amendments contained in
15.04.065 do not apply to repairs to buildings.
B. Add the following definitions to Subchapter 1, Section 100.1(b):
MAJOR ADDITION is any change to an existing building that increases
conditioned floor area by 500 or more square feet in a one-year period.
MAJOR ALTERATION is any construction or renovation to an existing structure
other than a repair or alteration whose work area covers 500 or more square feet
in a one-year period. A project that consists only of roof and/or window
replacement is not considered a Major Alteration.
WORK AREA That portion or portions of a building consisting of all reconfigured
spaces as indicated on the construction documents. Work area excludes other
portions of the building where incidental work entailed by the intended work must
be performed and portions of the building where work not initially intended by the
owner is specifically required by this code.
C. Amend Section 150.0 SINGLE-FAMILY RESIDENTIAL BUILDINGS –
MANDATORY FEATURES AND DEVICES to read as follows:
Single-family residential buildings shall comply with the applicable requirements of
Sections 150.0(a) through 150.0(w).
Ordinance No. 1736 (2024 Series) Page 8
O 1736
D. Add new Section 150(w) to read as follows:
(w) Mandatory Requirements for Existing Building Additions and Alterations.
Existing Building Additions and Alterations shall meet the requirements
of Items 1 through 4 below, as applicable:
1. Major addition. Any Major Addition shall install a set of measures from
the Measure Menu Table, Table 150.0-I to achieve a total score that is
equal to or greater than 8. In addition, all mandatory measures listed
in Table 150.0-I shall be installed. Measure verification shall be
explicitly included as an addendum to the Certificate of Compliance to
be filed pursuant to 2022 Title 24 Section 10-103. Installed measures
shall meet the specifications in Table 150.0-J.
2. Major alteration. Any major alteration shall install a set of measures
from the Measure Menu Table, Table 150.0-I to achieve a total score
that is equal to or greater than 8. In addition, all mandatory measures
listed in Table 150.0-I shall be installed. Measure verification shall be
explicitly included as an addendum to the Certificate of Compliance to
be filed pursuant to 2022 Title 24 Section 10-103. Installed measures
shall meet the specifications in Table 150.0-J.
3. Combination major addition and alteration. Any project that
includes an addition and alteration that has a work area equal to or
greater than 500 square feet shall install a set of measures from the
Measure Menu Table, Table 150.0-I to achieve a total score that is
equal to or greater than 8. In addition, all mandatory measures listed
in Table 150.0-I shall be installed. Measure verification shall be
explicitly included as an addendum to the Certificate of Compliance to
be filed pursuant to 2022 Title 24 Section 10-103. Installed measures
shall meet the specifications in Table 150.0-J.
4. Electric Readiness. Any major addition, major alteration, or
combination major addition and alteration that includes a new electrical
panel and electrical service upgrade to 200A or more shall include
electric readiness components per 150.0(n)1(A)-(B) and 150.0(t)
Exception 1 to Section 150.0(w): The project is the result of a repair as defined
by Title 24 Part 2 Section 202.
Exception 2 to Section 150.0(w): If compliance costs exceed 10% of total project
valuation, or due to conditions specific to the project, it is technically infeasible to
achieve compliance through any available set of measures, the applicant may
request an exemption as set forth below. In applying for an exemption, the burden
is on the applicant to show hardship or infeasibility.
Ordinance No. 1736 (2024 Series) Page 9
O 1736
(1) Application. Based on the following, the applicant shall identify in writing
the specific requirements of the standards for compliance that the
project is unable to achieve and the circumstances that make it a
hardship or infeasible for the project to comply with this chapter. The
applicant may not petition for relief from any requirement of the 2022
California Energy Code (Title 24, Part 6) and referenced standards, or
the 2022 California Green Building Standards (Title 24, Part 11) of the
California Building Standards Code. Circumstances that constitute
hardship or infeasibility shall include one of the following:
i. That the cost of achieving compliance is disproportionate to
the overall cost of the project (i.e., compliance exceeds 10%
of total project cost);
ii. That it is technically infeasible to achieve compliance through
any available set of measures.
iii. That strict compliance with these standards would create or
maintain a hazardous condition(s) and present a life safety
risk to the occupants.
(2) Granting of exemption. If the chief building official determines that it is a
hardship or infeasible for the applicant to fully meet the requirements of this
chapter and that granting the requested exemption will not cause the
building to fail to comply with the 2022 California Energy Code (Title 24,
Part 6) and referenced standards, or the 2022 California Green Building
Standards (Title 24, Part 11) of the California Building Standards Code, the
chief building official shall determine the minimum feasible threshold of
compliance reasonably achievable for the project. If an exemption is
granted, the applicant shall be required to comply with this chapter in all
other respects and shall be required to achieve the threshold of compliance
determined to be achievable by the chief building official.
(3) Denial of exemption. If the chief building official determines that it is
reasonably possible for the applicant to fully meet the requirements of this
chapter, the request shall be denied, and the applicant shall be notified of
the decision in writing. The project and compliance documentation shall be
modified to comply with the standards for compliance.
(4) Appeal. Any aggrieved applicant or person may appeal the
determination of the chief building official regarding the granting or denial of
an exemption or compliance with any other provision of this chapter. An
appeal of a determination of the chief building official shall be filed in writing.
Exception 3 to Section 150.0(w): If the dwelling unit has previously installed
measures from the Measure Menu, Table 150.0-I, and compliance can be
demonstrated to the building official, then these measures shall not be required to
be newly installed.
Ordinance No. 1736 (2024 Series) Page 10
O 1736
Exception 4 to Section 150.0(w): The applicant may request an exemption to any
requirements of this chapter which would impair the historic integrity of any building
listed on a local, state, or federal register of historic structures, as determined by
the chief building official and as regulated by the California Historic Building Code
(Title 24, Part 8). In making a determination of exemption, the chief building official
may require the submittal of an evaluation by an architectural historian or similar
expert.
Exception 5 to Section 150.0(w): An alteration that consists solely of seismic
safety improvements.
Exception 6 to Section 150.0(w): An alteration that consists solely of roof and/or
window projects.
Exception 7 to Section 150.0(w): When an addition or alteration results in the
creation of a new residential unit, the square footage of that unit shall not be
counted towards the 500 square foot “Major” addition, alteration, or addition and
alteration threshold.
D. Add new Table 150.0-I to read as follows:
Table 150.0-I: Measure Menu
Measures
Target Score
8
E1 - LED lamps and Exterior Photocells Mandatory
E2 - Water Heating Package 1
E3 - Air Sealing 1
E4 - R-49 Attic Insulation 2
E5 - Duct Sealing 2
E6 - New Ducts + Duct Sealing 4
E7 - Windows 3
E8 - R-19 Floor Insulation 8
E9 - R-30 Floor Insulation 10
E10 - Heat Pump Water Heater (HPWH) 12
E11 - Heat Pump Space Heater 11
ER1 - Solar PV + Electric Ready Pre-Wire 13
Note: the measures in the Measure Menu table shall conform to the
specifications in Table 150.0-J
O 1736
E. Add new Table 150.0-J to read as follows:
Table 150.0-J: Measure Specifications
ID Measure Specification
Energy Efficiency Measures
E1 Lighting Measures – Replace all interior and exterior screw-in incandescent, halogen, and compact fluorescent lamps with LED lamps.
Install photocell controls on all exterior lighting luminaires consistent with current Title 24 requirements for new single family residential
buildings. Alternative means of exterior lighting timing controls, including smart home devices, may be approved.
E2 Water Heating Package: Add exterior insulation meeting a minimum of R-6 to existing storage water heaters. Insulate all accessible
hot water pipes with pipe insulation a minimum of ¾ inch thick. This includes insulating the supply pipe leaving the water heater,
piping to faucets underneath sinks, and accessible pipes in attic spaces or crawlspaces. Upgrade fittings in sinks and showers to meet
current California Green Building Standards Code (Title 24, Part 11) Section 4.303 water efficiency requirements. Water heaters 20
gallons or less, or water heaters that are not able to add exterior insulation may not take credit for this measure.
E3 Air Sealing: Seal all accessible cracks, holes, and gaps in the building envelope at walls, floors, and ceilings. Pay special attention to
penetrations including plumbing, electrical, and mechanical vents, recessed can light luminaires, and windows. Weather-strip doors if
not already present. Compliance shall be demonstrated with blower door testing conducted by a certified HERS Rater no more than
three years prior to the permit application date that either: a) shows at least a 30 percent reduction from pre-retrofit conditions; or b)
shows that the number of air changes per hour at 50 Pascals pressure difference (ACH50) does not exceed ten for Pre-1978 vintage
buildings, seven for 1978 to 1991 vintage buildings and five for 1992-2010 vintage buildings. If combustion appliances are located
within the pressure boundary of the building, conduct a combustion safety test by a professional certified by the Building Performance
Institute in accordance with the ANSI/BPI-1200-S-2017 Standard Practice for Basic Analysis of Buildings, the Whole House
Combustion Appliance Safety Test Procedure for the Comfortable Home Rebates Program 2020 or the California Community
Services and Development Combustion Appliance Safety Testing Protocol.
E4 R-49 Attic Insulation: Attic insulation shall be installed to achieve a weighted assembly U-factor of 0.020 or insulation installed at the
ceiling level shall have a thermal resistance of R-49 or greater for the insulation alone. Recessed downlight luminaires in the ceiling
shall be covered with insulation to the same depth as the rest of the ceiling. Luminaires not rated for insulation contact must be
replaced or fitted with a fire-proof cover that allows for insulation to be installed directly over the cover. In buildings where existing R-
30 is present and existing recessed downlight luminaires are not rated for insulation contact, insulation is not required to be installed
over the luminaires.
E5 Duct Sealing: Air seal all space conditioning ductwork to meet the requirements of the 2022 Title 24 Section 150.2(b)1E. The duct
system must be tested by a HERS Rater no more than three years prior to the alteration or addition permit application date to verify
the duct sealing and confirm that the requirements have been met. This measure may not be combined with the New Ducts and Duct
Sealing measure in this Table. Buildings without ductwork or where the ducts are in conditioned space may not take credit for this
measure.
E6 New Ducts and Duct Sealing: Replace existing space conditioning ductwork with new R-8 ducts that meet the requirements of 2022
Title 24 Section 150.0(m)11. This measure may not be combined with the Duct Sealing measure in this Table. To qualify, a
preexisting measure must have been installed no more than three years before the alteration or addition permit application date.
E7 Windows: Replace at least 50% of existing windows with high performance windows with an area-weighted average U-factor no
greater than 0.30.
Ordinance No. 1736 (2024 Series) Page 12
O 1736
E8 R-19 Floor Insulation: Raised-floors shall be insulated such that the floor assembly has an assembly U-factor equal to or less than U-
0.037, or shall be insulated between wood framing with insulation having an R-value equal to or greater than R-19.
E9 R-30 Floor Insulation: Raised-floors shall be insulated such that the floor assembly has an assembly U-factor equal to or less than U-
0.028, or shall be insulated between wood framing with insulation having an R-value equal to or greater than R-30.
E10 Heat Pump Water Heater (HPWH): Replace existing electric resistance or natural gas storage water heater with a heat pump water
heater.
E11 Heat Pump Space Heater: Replace all existing gas and electric resistance space heating systems with an electric-only heat pump
system.
Solar PV and Electric-Readiness Measures
ER1 PV and Electric Ready Pre-Wire: Install a solar PV system that meets the requirements of 2022 Title 24 Section 150.1(c)14.
In addition to the solar PV system, Include electric readiness components per 150.0(n)1(A)-(B) and 150.0(t) and one of:
A. Energy Storage Systems (ESS) Ready, as specified in Section 150.0(s), or
B. EV Charger Ready as specified in the California Green Building Code, Title 24, Part 11, Section A4.106.8.1,which otherwise
applies to new construction.
O 1736
F. Modify Section 150.2(a) ENERGY EFFICIENCY STANDARDS FOR ADDITIONS
AND ALTERATIONS TO EXISTING SINGLE FAMILY RESIDENTIAL BUILDINGS to
read as follows:
Additions. Additions to existing single-family residential buildings shall meet the
requirements of Sections 110.0 through 110.9, Sections 150.0(a) through (n), (p),
(q), (w) and either Section 150.2(a)1 or 2.
G. Modify Section 150.2(b) ENERGY EFFICIENCY STANDARDS FOR ADDITIONS
AND ALTERATIONS TO EXISTING SINGLE FAMILY RESIDENTIAL BUILDINGS to
read as follows:
Alterations. Alterations to existing single-family residential buildings or alterations
in conjunction with a change in building occupancy to a single-family residential
occupancy shall meet either Item 1 or 2 below.
1. Prescriptive approach. The altered component and any newly installed
equipment serving the alteration shall meet the applicable requirements of
Sections 110.0 through 110.9 and all applicable requirements of Sections
150.0(a) through (l), 150.0(m)1 through 150.0 (m)10, 150.0(p) through (q), and
150.0(w); and
2. Performance approach. The altered component(s) and any newly installed
equipment serving the alteration shall meet the applicable requirements of
Subsections A, B, and C below.
a. The altered components shall meet the applicable requirements of
Sections 110.0 through 110.9, Sections 150.0(a) through (l), Sections
150.0(m)1 through 150.0 (m)10, Sections 150.0(p) through (q), and
Section 150.0(w). Entirely new or complete replacement mechanical
ventilation systems as these terms are used in Section 150.2(b)1L, shall
comply with the requirements in Section 150.2(b)1L. Altered mechanical
ventilation systems shall comply with the requirements of Section
150.2(b)1M. Entirely new or complete replacement space-conditioning
systems, and entirely new or complete replacement duct systems, as
these terms are used in Sections 150.2(b)1C and 150.2(b)1Diia, shall
comply with the requirements of Sections 150.0(m)12 and 150.0(m)13.