HomeMy WebLinkAboutSubdivision Agreement - check bonds fees 2-12-19 9
EXHIBIT 2 (revised 2-12-19)
TRACT 3095 - FEE AND BOND LIST
3777 Orcutt
Page 1 of 2
Amount Form Date
Received
Bond Release Status
Bonds and Guarantees:
Tiburon Improvements
(FMAP-2241-2015)
$2,837,600 Submitted with
Tract 3066-Phase 2
bond
12/13/18 Can be released upon City acceptance
of improvements, deposit of one-year
warranty surety, and approval of
record drawings. Offsite Water Main Extension
(FMAP-2242-2015/ FMAP-4024-2016)
$775,000
Submitted with
Tract 3063-Phase 1
Off-Site Landscaping
(FMAP-0288-2017)
$175,000 Submitted with
Tract 3063-Phase 1
Tiburon Bridge
(FMAP-4312-2016)
$1,800,000 Submitted with
Tract 3066-Phase 2
bond
12/13/18
Orcutt Frontage Phase 1 Improvements,
including left-turn pocket at Orcutt/Tiburon
intersection per Condition #17
(FMAP-1718-2015)
$730,000 Submitted with
Tract 3066-Phase 2
bond
12/13/18
Tank Farm/Orcutt intersection
improvements or roundabout per OASP
EIR mitigation measures
(FMAP-1718-2015)
$650,000 Submitted with
Tract 3066-Phase 2
bond
12/13/18
Off-site water and sewer mains through
Righetti Tract 3063
(FMAP-2631-2016/FMAP-1718-2015)
$1,400,000 Submitted with
Tract 3063-Phase 1
On-Site Tract 3095 improvements
(FMAP-1202-2017)
$2,196,560 Bond 2/8/19
Labor & Materials for above Tract
3063-Phase 1 and Tract 3066-Phase 2
improvements (50% of total cost of
above improvements)
Submitted with
Tract 3066-Phase 2 bonds
12/13/18 Can be released 90 days after
acceptance of improvements, if no
claims. (Civil Code Section 8412)
Labor & Materials (50% of cost of
improvements) for Tract 3095 On-Site
Improvements
$1,098,280 Bond 2/8/19 Can be released 90 days after
acceptance of improvements, if no
claims. (Civil Code Section 8412)
Tree Preservation Surety for the
existing Sycamore tree on Lot 21
$62,000 Bond 12/11/18 See Exhibit 1 for when bond can be
released.
Monument Guarantee $7,000 CD or Letter of
Credit
1/24/19 Can be released upon verification that
monuments have been set and
surveyor has been paid.
10% Warranty TBD TBD To be
collected
prior to
release of
FP Bond
Can be released one-year after
acceptance of improvements, if no
defects, and approval of record
drawings.
Continued on Page 2
10
EXHIBIT 2
TRACT 3066-Phase 2 - FEE AND BOND LIST
3761 Orcutt
Page 2 of 2
Amount Form Date
Received
Bond Release Status
Fees:
Map Check Fee $17,787.13 Check 11/14/17
Plan Check Fee Deposit
Plan Check Remainder
Total Plan Check Fee
$25,374.43
$6,693.60
$32,068.03
Check
Check
11/14/17
8/29/18
Improvement Plan Inspection Fee $84,450.07 Check 8/29/18
Roadway Maintenance Fee (Condition #24) $2,000 xxx xxx
Park In-Lieu Fee1 To be collected with building permit.
Affordable Housing Requirements See Affordable Housing Agreement
Water Impact Fee1 To be collected with building permit
Wastewater Impact Fee1 To be collected with building permit
Transportation Impact Fee1 To be collected with building permit
1 All Impact Fees are adjusted annually (July 1) based on CPI. Credit given for demolished units.