HomeMy WebLinkAboutARCH-0188-2023 20230420 (Laurel Garden) - Utility LinesJ608
9699
526883
3711
5083
T0734
69708
509598
737484
648130
905034
188530
770146
926954
T730073
T128631
TO SSD
SWITCH 4817
14275
9699
M
526883
LEGEND
EXISTING DESCRIPTIONINSTALL
PRIMARY CABLE: 2-1/0AL EPR 25kV IN NEW 1-4" CONDUIT
SERVICE CABLE:4 RUN(S) OF 1,000A QPX IN 4 OF 7 - 5" CONDUITS
NOTES:09-18-13
14.APPLICANT TO PROVIDE ADEQUATE P.U.E'S AND/OR ROW'S FOR PG&E FACILITIES. ANY ADDITIONAL REQUIRED
RIGHTS OF WAY ARE TO BE SURVEYED AND DOCUMENTED BY PG&E AT THE APPLICANT'S EXPENSE.
CONDUIT, TRENCHING, AND BACKFILL:
1.ALL DIMENSIONS AND LOCATIONS ARE ESTIMATED, APPROXIMATE AND MAY BE SUPERSEDED BY A JOINT
TRENCH DRAWING. REFER TO THE JOINT TRENCH COMPOSITE DRAWING FOR EXACT TRENCH LOCATION
2.MAINTAIN MAXIMUM PRACTICABLE HORIZONTAL CLEARANCE BETWEEN PG&E FACILITIES AND "WET" UTILITIES
(WATER, SEWER, STORM DRAIN, ETC.). THE MIN. ALLOWABLE SEPARATION BETWEEN PG&E FACILITIES AND
ANY PARALLEL "WET" UTILITY IS 3/FT. WITH A PRESENCE OF 1/FT. OF UNDISTURBED EARTH OR THE
INSTALLATION OF A SUITABLE BARRIER. THIS MEASUREMENT IS BETWEEN THE OUTER EDGE OF THE PG&E
FACILITY AND THE OUTER EDGE OF THE PARALLEL "WET" FACILITY. IF 3/FT. CANNOT BE MAINTAINED, A
FORMAL VARIANCE MUST BE OBTAINED FROM PG&E WORK WITH THE PG&E INSPECTOR (REFERENCE PG&E
UO STANDARD S5453).
3.BOX, PAD, AND CONDUIT SIZES AND LOCATIONS SHALL CONFORM TO THE PG&E ELECTRIC CONSTRUCTION
DRAWING.
4.PROVIDE LONG CONDUIT SWEEPS WHERE INDICATED. RECOMMENDED SWEEP RADIUS (10' OF RADIUS PER
INCH OF CONDUIT DIAMETER) EXAMPLE: 4" CONDUIT = 40' RADIUS
5.DO NOT EXCEED 300 DEGREES OF BENDS IN ANY CONDUIT RUN (INCLUDING FEED LOCATION). NOTE:
SECONDARY AND SERVICE RUNS OF 200 FEET OR LESS MAY HAVE UP TO 315 DEGREES OF BENDS (REFERENCE
PG&E DOCUMENT 038193, REV. 7, DATED 6-28-13).
6.MANUFACTURED BENDS OR APPLICATION OF HEAT SHALL NOT BE USED TO OBTAIN LONG CONDUIT SWEEPS.
7.ALL CONDUITS SHALL BE PROVEN AND A POLYESTER PULLING TAPE INSTALLED.
8.MANUFACTURED BENDS ARE NOT TO BE CUT, SHORTENED, OR ALTERED IN ANY WAY.
9.IDENTIFY ENDS OF BURIED CONDUIT WITH AN ELECTRONIC MARKER AND A VERTICAL CONDUIT SCRAP
INSTALLED FROM RIGID CAP TO GROUND LEVEL.
10.CONDUITS ENTERING PRIMARY BOXES SHALL BE AT A RIGHT ANGLE TO THE WINDOW OR WALL.
11.STUB CONDUITS AT RISER POLES IN QUADRANTS AS SHOWN. AT IDENTIFIED POLE LOCATIONS, THE TRENCHING
AGENT IS TO EXCAVATE TO TRENCH DEPTH AND INSTALL A 30" DIAMETER CARDBOARD TUBE. THE RISER
CONDUIT BEND IS TO BE PLACED OUTSIDE AND ADJACENT TO THE TUBE AT THE POLE QUADRANT INDICATED.
BACKFILL AROUND AND INSIDE TUBE WITH CLEAN NATIVE FILL.
12.LS2 STREET LIGHT CONDUIT GOING TO PG&E BOXES OR PEDESTALS NOT DESIGNATED AS P.O.S. (INCLUDING
TRANSFORMERS) WILL NOT BE ACCEPTED OR CONNECTED.
13.ONLY ONE LS2 STREET LIGHT (P.O.S.) CONNECTION PER BOX OR PEDESTAL.
15.CALL 811 (UNDERGROUND SERVICE ALERT) 48 HOURS PRIOR TO EXCAVATION FOR UNDERGROUND UTILITY
LOCATION
MARKING.
16.48 HOUR NOTICE REQUIRED FOR UNDERGROUND INSPECTION.
17.MATERIALS AND WORKMANSHIP SHALL BE FIRST QUALITY IN EVERY RESPECT, PLUMB AND TRUE, AND
ACCORDING TO THE SPECIFIC REQUIREMENTS OF THE DRAWINGS AND THE ABOVE APPLICABLE NOTES AND
SPECIFICATIONS.
18.THE APPLICANT IS TO VERIFY ALL PROPOSED INSTALLATIONS, CONDITIONS & SPECIFICATIONS PRIOR TO
COMMENCING WITH ANY PORTION OF WORK. ANY DISCREPANCIES, DELETIONS OR INCONSISTENCIES ARE TO
BE REPORTED TO THE PG&E REPRESENTATIVE IMMEDIATELY. THE APPLICANT SHALL COMPLY WITH ALL
APPLICABLE SPECIFICATIONS. ANY VARIATIONS FROM PLANS OR SPECIFICATIONS RELIEVES PG&E OF ALL
RESPONSIBILITY FOR THE SUBSTRUCTURE OR DESIGN.
REFER TO ELECTRIC & GAS SERVICE REQUIREMENTS (GREEN BOOK) OR SEPARATE PG&E STANDARD DRAWINGS.
CONTACT YOUR PG&E REPRESENTATIVE FOR COPIES, OR ACCESS. WWW.PGE.COM/GREENBOOK
LAND RIGHTS AND EASEMENTS:
SAFETY AND WORKMANSHIP:
SERVICE CABLE:6 RUN(S) OF 1,000A QPX IN 6 OF 7 - 5" CONDUITS
PRIMARY CABLE: 3-1/0AL EPR 25kV IN NEW 1-4" CONDUIT
PRIMARY CABLE: 3-1100AL EPR 25kV IN NEW 1-6" CONDUIT
VACANT CONDUIT: 1-4"
VACANT CONDUIT:1-6" & 1-4"
JOINTLY OWNED POLE - SIZE AS SHOWN
RISER
OVERHEAD SWITCH
FUSED CUTOUTS | DISCONNECTS
PMI-9TT
PADMOUNTED TRANSFORMER - SIZE AS SHOWN
3' x 5' x 3'6" PRIMARY ENCLOSURE
METER
WORK AGENT RESPONSIBILITIES
TO PERFORM ALL TRENCHING AND EXCAVATION
TO PERFORM JOINT TRENCH COMPOSITE | FORM B
TO PERFORM ALL POLE WORK
TO PERFORM ALL TIE-IN WORK
TO INSTALL ELECTRIC DISTRIBUTION AND SERVICE FACILITIES.
CABLE, TRANSFORMERS, INTERRUPTERS, ETC.PG&E
TO INSTALL ELECTRIC DISTRIBUTION AND SERVICE
SUBSTRUCTURES. CONDUIT, ENCLOSURES, PADS, BOXES, ETC.APPLICANT
APPLICANT
PG&E
PG&E
PG&E
M PRIMARY METER
REMOVAL OF FACILITIES
OVERHEAD TRANSFORMER
PRIMARY CABLE: 2-1/0AL EPR 25kV IN EXISTING 1-4" CONDUIT
WET AND DRY UTILITY CLEARANCES
·THE MINIMUM ALLOWABLE SEPARATION BETWEEN THE EDGE OF THE JOINT
TRENCH AND THE EDGE OF ANY "WET" FACILITY TRENCH IS 3' WITH THE PRESENCE
OF A MINIMUM OF 1' OF UNDISTURBED EARTH OR THE INSTALLATION OF A
SUITABLE BARRIER.
·THE MINIMUM ALLOWABLE SEPARATION BETWEEN THE EDGE OF THE JOINT
TRENCH AND THE EDGE OF ANY "DRY" NON-UTILITY FACILITY TRENCH IS 2' WITH
NO LESS THAN 1' OF UNDISTURBED EARTH OR THE INSTALLATION OF A SUITABLE
BARRIER.
WORK REQUIREMENTS
N/A
N/A
N/AREQUIRED
TRAFFIC CONTROL PLAN / FLAGGING
ENCROACHMENT PERMIT
VEGETATION REMOVAL
REQUIRED
REQUIRED Know what's below.Call before you dig.REMOVAL
5
5
Know what's below.Call before you dig.SCALE: 1" = 5'PMI-9 DETAIL(S): LOC 1-5
SCALE: 1" = 5'SPLICE BOX: LOC 12 SCALE: 1" = 5'T730073 DETAIL: LOC 14 SCALE: 1" = 5'T128631 DETAIL: LOC 16