August 23, 2019 Sent via Email
Thom Jess
Arris Studio Architects
1327 Archer Street, Suite 220
San Luis Obispo, CA 93401
Subject: Completeness Review #1: ARCH-0505-2019 (1150 Laurel Lane): Review of an exterior façade
remodel to an existing warehouse building, the remodel consists of the removal of existing
fabric awnings, the addition of rainscreen panels and metal awnings along the entries, and
new paint throughout.
Dear Thom Jess:
Thank you for the July 29, 2019 submittal for the Laurel Creek Façade Remodel project. We have
reviewed your application and found it to be complete. Preliminary review of your project indicates
that it may be exempt from CEQA. We will immediately begin review of your pr oject to determine
whether it is subject to environmental review under the California Environmental Quality Act
(CEQA). We will also begin an evaluation of the proposed project’s consistency with applicable
State and City regulations and conduct a more detailed analysis of its environmental impacts as
necessary.
Please review the description carefully. If you believe the project description is incorrect or does not
include components that you intend to include as part of the project, please contact us immediately.
We reserve the right to request additional information to clarify any changes or additions that are
made to the project description in response to this letter, as our completeness determination is based
upon the material provided with your application.
Based on our preliminary review of your application, we offer the following advisory statements
which may directly affect the staff recommendation, comments that are not adequately addressed
may become conditions or terms for continuance:
Planning Division
1. The project plans do not identify any site improvements, if any site improvements are proposed
they should be included in the application submittal for consideration. Any plans for site
improvements shall comply with the Community Design Guidelines for Industrial Project
Design.
Utilities Department
2. Provide additional information on location of the existing fire service line feeding the building
and the location of the double check valve assembly.
ARCH-0505-2019 (1150 Laurel Lane)
August 23, 2019
Page 2
Based on the required process steps for this project, we expect to schedule the project hearing
before the Architectural Review Commission (ARC) on October 7, 2019 with a recommendation to
the Director for action tentatively schedule on October 28, 2019. This tentative hearing date
depends upon the course of case processing. Any delays in environmental review or required plan
revisions may cause the tentative hearing date to shift. If we determine that the length of processing
or hearing date will change, we will advise you accordingly. Please be aware that substantial
revisions to submitted information may affect the estimate of time, cost and level of review for your
project.
Please provide seven additional copies of the project plans for the ARC members. If you have any
questions regarding this letter, please call me at (805) 781-7524.
Sincerely,
Kyle Bell
Associate Planner
CC: Chuck Braff
Blue Sky Development
1880 Santa Barbara, Suite 110
San Luis Obispo, CA 93401