HomeMy WebLinkAbout06/06/1988, C-3 - SUBMITTAL OF PLANS AND SPECIFICATIONS FOR ""WATERLINE IMPROVEMENT PROJECT: JENNIFER ST.- ELLA TO GEORGE: GEORGE ST.- JENNIFER TO END; CITY PLAN NO. M-27P."""City of San LUIS OBISPO i .9
Nis COUNCIL AGENDA REPORT STEM NUMBE
FROM:
David F. Romero William T. Hetland Prepared by: Gary Henderson N
Public Works Director Utilities Manager Civil Engineer
SUBJECT
Submittal of Plans and Specifications for "Waterline Improvement Project:
Jennifer St.- Ella to George: George St.- Jennifer to End; City Plan No.
M -27P."
RECOMMENDATION:
Approve Plans and Specifications and Authorize Staff to Advertise for Bids.
BACKGROUND:
The existing waterlines in George Street and Jennifer St. are in a deteriorated
condition, which requires periodic maintenance. The existing waterlines are
only two inch lines, which are substandard. This proposal consists of
replacing 1480 feet of 2 -inch waterline with a 8 -inch waterline.
This project has been given an EIR clearance by the Planning Departmant.
Status: Categorical Exemption.
SIGNIFICANT IMPACT:
Base Bid:
EgC - 8%
Total:
$97,840
7,827
$105,667
This project is included in the Capital Replacement Plan of the 1987/1989
Financial Plan. There was $100,000 allocated for this project.
CONSEQUENCE OF NOT TAKING ACTION:
The substandard condition will remain and the project may be more expensive to
construct at a later date.
ACTION RECOMMENDED:
Approve plans and specifications and authorize staff to advertise for bids.
ACTION TAKEN: Approved As recommended As modified
Denied Continued
Vote:
Plans and specifications available in the Council Office for inspection.
gwh5 /m27p -sr