Loading...
HomeMy WebLinkAboutItem 7c. Tank Farm Roadway Striping Modifications & Authorization to Advertise 2025 Paving Project Item 7c Department: Public Works Cost Center: 5010 For Agenda of: 5/6/2025 Placement: Business Estimated Time: 60 Minutes FROM: Matt Horn, Public Works Director Prepared By: Luke Schwartz, Transportation Manager; Hai Nguyen, Senior Civil Engineer SUBJECT: DISCUSS AND PROVIDE DIRECTION ON TANK FARM ROAD STRIPING MODIFICATIONS AND AUTHORIZE ADVERTISEMENT OF THE 2025 PAVING PROJECT (SPEC. NO. 2000616) FOR CONSTRUCTION RECOMMENDATION 1. Receive staff presentation, provide input and policy direction regarding roadway striping modifications for Tank Farm Road for implementation with the 2025 Paving Project designs; and 2. Authorize the City Engineer to approve final plans and specifications for the 2025 Paving Project, Specification No. 2000616, including incorporation of designs for Tank Farm Road pursuant to City Council direction, prior to advertising the project for construction; and 3. Authorize staff to advertise for bids for the 2025 Paving Project; and 4. Authorize the City Manager to award the construction contract for the 2025 P aving Project pursuant to Section 3.24.190 of the Municipal Code for the bid total, if the lowest responsible bid is within the publicly disclosed funding amount of $7,720,000; 5. Adopt a Draft Resolution entitled, “A Resolution of the City Council of the City of San Luis Obispo, California, Authorizing Appropriation of Capital Projects Reserve Funds to Support the 2025 Paving Project, Specification Number 2000616”; and 6. Authorize the Finance Director to make the following appropriation s and funding transfers to the 2025 Paving Project Account (2000616): a. Appropriate $1,404,530 of Capital Outlay LRM funds from the FY24/25 Capital Reserve of the Capital Outlay Fund; and b. Transfer $2,100,000 of Capital Outlay LRM funds from the Roadway Sealing 2024 Project Account (No. 2000615); and c. Transfer $100,000 of Capital Outlay LRM funds from the Arterials 2023 Project Account (No. 2001065); and d. Transfer $199,200 of Water funds from the Water Valve Cover Adjustments Account (No. 2001005); and e. Transfer $76,800 of Sewer funds from the Sewer Valve Cover Adjustments Account (No. 2000084); and 7. Authorize the City Engineer to issue Contract Change Orders for the 2025 Paving Project up to and in excess of $200,000 if within available project budget, and up to any amended budget subsequently approved by the City Manager per City Purchasing Policy approval thresholds. Page 347 of 625 Item 7c REPORT-IN-BRIEF Staff are requesting City Council authorization to advertise the 2025 Paving Project for construction. In accordance with the City’s Pavement Management Plan, the project includes reconstruction of existing pavement, along with additional improvements such as ADA curb ramp upgrades, replacement of roadway striping, and features that advance the City’s transportation safety and mobility goals. To maximize potential project benefits while maintaining flexibility within the City’s financial constraints, the 2025 Paving Project will be advertised with a Base Bid and two Bid Additive Alternatives. The bid documents will specify that the City intends to award the Base Bid and as many Bid Additive Alternatives as can be funded within the available project budget. The contract is to be awarded based on the lowest base bid price received. The project’s Base Bid includes:  Roadway Reconstruction a. Tank Farm Road (Broad Street to Wavertree) b. Sacramento Drive (Industrial Way to Via Esteban)  Roadway Striping Refresh (no paving work or other improvements) a. Broad Street (Orcutt Road to Tank Farm) b. Santa Rosa & Mill Street Crosswalks c. Madonna Road (US 101 Southbound Ramps to Higuera) d. Prado Road (Higuera to Serra Meadows) e. Tank Farm Road (Santa Fe to Broad Street) The project’s Additive Alternatives include Roadway Reconstruction on: A. Orcutt Road (Tank Farm Road to City/County Line) B. Calle Joaquin (Motel 6 to City/County Line) Typically, staff would include a recommendation for the Council to approve the final plans and specifications concurrently with authorization to advertise for construction. However, specific direction from the Council is needed to guide final design for the Tank Farm Road portion of the project. For this reason, staff is requesting that Council provide design direction for Tank Farm Road, and delegate authority to the City Engineer to approve the final project plans and specifications based on Council input, prior to advertising the project for construction. After reviewing policy recommendations in the City’s General Plan, the ATP, the Draft Vision Zero Action Plan1, input from emergency service providers (including San Luis Obispo Fire Department or “SLO Fire”), and feedback from the City’s Active 1 The Final Vision Zero Action Plan is planned to be presented for City Council approval late summer/early fall of 2025. Page 348 of 625 Item 7c Transportation Committee (ATC) and the community, staff is presenting the following design alternatives for Tank Farm Road (Broad Street to Wavertree Road) for Council consideration:  Tank Farm Alternative 1 (Road Diet) – Proposes a five-lane to three-lane road diet on Tank Farm between Poinsettia Street and Union Pacific Railroad (UPRR) bridge. o Benefits: Greater potential to reduce high vehicle speeds, increase separation between bicyclists/pedestrians and vehicles, and more effectively improve pedestrian crossing exposure. Includes the addition of a new enhanced crosswalk at the Tank Farm/Morning Glory/Sunrose intersection. o Disadvantages: Potential for some increases in driver delay above existing conditions (though not expected to trigger policy or level of service deficiencies), less familiarity for existing road users, and reduced flexibility for future growth or emergency evacuation needs (though not considered a substantive impediment to evacuation by SLO Fire).  Tank Farm Alternative 2 (No Road Diet) – Maintains the existing five-auto-lane configuration on Tank Farm between Broad Street and the UPRR bridge. o Benefits: No change in road configuration, vehicle delays, or driver experience; retains excess road capacity for future growth and emergency evacuations. o Disadvantages: Limited potential to reduce high vehicle speeds, less separation between vehicles and bicycles /pedestrians, and minimal improvement to pedestrian crossing safety. A new crosswalk at Tank Farm/Morning Glory/Sunrose would not be recommended under this alternative. The differences between these alternatives are limited to the western segment of Tank Farm, between Broad Street and the UPRR bridge. To the east of the UPRR Bridge, both designs are identical and include the addition of striped bike lane buffers, radar speed feedback signs, and pedestrian crossing improvements at the Tank Farm/Righetti Ranch Road roundabout but otherwise retain the existing road configuration. Neither of these alternatives include installation of protected bike lanes on Tank Farm . While protected bike lanes are recommended in the ATP, were explored in preliminary concept designs for this project, and are supported by the ATC, staff does not recommend installation of protected bike lanes on Tank Farm at this time based on detailed design review between Public Works and SLO Fire staff, with consideration given to emergency vehicle access and potential evacuation needs, as guided by recent updates to the Cal Fire Hazard Severity Zone Maps. See additional discussion later in this report. As discussed in the Fiscal Impact section of this report, a portion of the funding needed to construct the 2025 Paving Project is expected to be appropriated in Fiscal Year 2025- Page 349 of 625 Item 7c 26. This funding will be identified in the forthcoming 2025 -27 Financial Plan, with construction initiation contingent on approval of the Financial Plan and availability of the 2025-26 funding after July 1, 2025. In addition, staff is recommending that Council authorize the Finance Director appropriate approximately $1.4 million fr om the Fiscal Year 2024-25 Capital Projects Reserve Fund to support project construction. A draft resolution supporting this appropriation is provided as Attachment A. Project construction is slated to begin in late summer/early fall 2025. If the above-listed staff recommendations are approved, the anticipated schedule moving forward would be as follows: i. Council Direction on Tank Farm Road & Authorization to Advertise – May 6, 2025 ii. Project Advertisement (following City Engineer Approval of Plans) – June 2025 iii. Project Bid Opening & Contract Award – July 2025 iv. Start of Construction – Late August/Early September 2025 v. Construction Completion – December 2025 POLICY CONTEXT The 2025 Paving Project directly supports several key City plans, policies, and goals. The project supports the ongoing maintenance of City streets outlined in the Pavement Management Plan. Proposed improvements on Tank Farm Road and Sacramento Drive support several of the recommendations of the City’s Active Transportation Plan (ATP) and the City’s adopted Vision Zero Goal to eliminate severe injury and fatal traffic collisions (Resolution No. 10746 (2016 Series)). The active transportation components of the project also support efforts to achieve the General Plan mode share targets, recommendations of the City’s Climate Action Plan , the current Sustainable Transportation and Climate Action Major City Goal, and the FY 2025-2027 Infrastructure and Sustainable Transportation Major City Goal. General Plan Circulation Element Policy 8.1.4(b) and Safety Element Program OP-7.15 are also relevant to this item, as these policies require that the City ensure traffic management projects accommodate emergency response needs and that the City evaluate emergency response and evacuation needs in high-risk hazard areas, including areas near Fire Very High Hazard Severity Zones. In June 2021, the City Council established the Fund Balance and Reserve Policy (Resolution No 11250, 2021 Series). This policy established the Capital Projects Reserve Fund and committed a reserve of 20% of capital improvement plan budget from the Local Revenue Measure for the purposes of offsetting unanticipated cost increases, unforeseen conditions, and urgent unanticipated projects to provide continued investment in infrastructure maintenance and enhancement. The Capital Projects Reserve funding is requested to fund the project’s construction costs. DISCUSSION Page 350 of 625 Item 7c Background Per the City’s Pavement Maintenance Plan, roadway pavement maintenance projects are implemented each year, generally alternating each year between work within local neighborhood areas and pavement repairs on major arterial streets. Pavement maintenance projects often involve complete removal and replacement of roadway striping and pavement markings, which provides ideal opportunities to incorporate planned safety and complete street2 improvements as part of these larger roadway maintenance efforts. 2025 Paving Project The 2025 Paving Project is structured with a Base Bid and two Additive Alternatives, A and B, to maximize the scope of work within available funding. The project plans and Special Provisions are provided as Attachment B and C of this report. The project’s Base Bid includes pavement maintenance work, striping, curb ramp improvements and complete street features on Tank Farm Road and Sacramento Drive, as well as refreshment of roadway markings on several streets where existing markings are badly faded and beyond what City maintenan ce staff can restore. Base Bid components include:  Roadway Reconstruction a. Tank Farm Road (Broad Street to Wavertree) b. Sacramento Drive (Industrial Way to Via Esteban)  Roadway Striping Refresh (no paving work or other improvements) a. Broad Street (Orcutt Road to Tank Farm) b. Santa Rosa & Mill Street Crosswalks c. Madonna Road (US 101 Southbound Ramps to Higuera) d. Prado Road (Higuera to Serra Meadows) e. Tank Farm Road (Santa Fe to Broad Street) The project’s Additive Alternatives include Roadway Reconstruction on:  Additive Alternate A - Orcutt Road (Tank Farm Road to City/County Line)  Additive Alternate B - Calle Joaquin (Motel 6 to City/County Line) Figure 1 below shows the locations identifies in the 2025 Paving Project for roadway reconstruction. Areas identified to receive striping refresh only are not shown. 2 A complete street is a transportation facility that is planned, designed, operated, and maintained to provide safe mobility for all users, including bicyclists, pedestrians, transit vehicles, trucks, and motorists, appropriate to the function and context of the facility. In California, per the California Complete Streets Act of 2008 (Assembly Bill 1358), all cities and counties are required to include complete streets policies as part of the circulation element of general plans. Page 351 of 625 Item 7c Figure 1: 2025 Paving Project Map Pavement Reconstruction and Maintenance Methodology A pavement analysis conducted in December 2024 confirmed that existing pavement surfaces on Tank Farm, Orcutt, Sacramento, and Calle Joaquin are all structurally deficient and unable to support the current and projected traffic loads. Many sections of these roadways exhibit moderate to severe cracking, rutting in the wheel paths, and potholes, indicating they are nearing the end of their useful life. The pavement management treatments that are proposed to be implemented with this project are Full Depth Hot Mix Asphalt Reconstruction and Full Depth Reclamation. Page 352 of 625 Item 7c Full Depth Hot Mix Asphalt Reconstruction Full-depth Hot Mix Asphalt (HMA) reconstruction is recommended for Orcutt, Sacramento, and Calle Joaquin to restore the roadway to a like -new condition. This process involves milling or grinding the existing pavement to a depth that matches the new asphalt section, creating a smooth and even base for repaving. In some areas, both the surface and base layers may be removed to reach the necessary depth for the new pavement. The reconstructed section is designed to provide long-term durability and support expected traffic loads. Once milling is complete, a fresh layer of asphalt will be placed, resulting in a smooth roadway surface. Full Depth Reclamation Full Depth Reclamation (FDR) is a more comprehensive pavement rehabilitation method that addresses both the surface and base layers of a roadway. This process involves grinding up the existing pavement and mixing it with the underlying base soil to create a stronger, more stable foundation. By recycling the existing materia ls in place, FDR not only corrects structural deficiencies but also offers significant cost and environmental benefits by reducing the need to haul away old pavement. One of the key advantages of FDR is the improved strength of the reconstructed base, which allows for a thinner layer of new, high-quality asphalt on the surface. This can result in substantial cost savings—up to $1 million—by reducing the asphalt section from 14 inches (as required with Full Depth HMA reconstruction) to 8.5 inches. FDR is recommended for Tank Farm Road due to its wider roadway width, which allows for phased construction that helps minimize traffic disruptions. In preparation, staff completed subsurface investigations and confirmed that there are no shallow utilities that would interfere with the pulverization depth. However, FDR is not suitable for all roadway conditions. It is not being considered for Orcutt, Sacramento, and Calle Joaquin due to site -specific constraints. On Sacramento, for example, the roadway is too narrow to accommodate phased construction, and the shallow depth of utility laterals conflicts with the required pulverization depth. In these cases, mill and fill is the more practical and cost-effective approach. Construction Phase Impacts and Mitigations While Full Depth Reclamation (FDR) is a highly effective and cost-efficient method for rehabilitating pavements, it is important to recognize the potential challenges that can arise. The most notable concern is the curing time needed for the treated base l ayer before installing new asphalt, which can extend the project timeline and increase inconveniences during construction. The length of this curing time can vary based on the stabilizing agent used, environmental conditions, and the mix design. For instan ce, cement stabilization typically requires anywhere from 7 to 28 days to achieve full strength, depending on factors such as moisture, temperature, and the mix proportions. In colder conditions, this curing process may take even longer, further extending project timelines. This project is expected to be constructed in late summer / early fall, and the warmer temperatures are expected to help reduce curing timeframes. Page 353 of 625 Item 7c To mitigate the impact on road users during construction, the FDR paving on Tank Farm is proposed to be completed in two phases. During Phase 1, half of the roadway will remain open to traffic on the existing asphalt pavement, allowing for uninterrupted two- way traffic flow, while the other half undergoes FDR treatment. In Phase 2, work will shift to the other half of the roadway, where the asphalt will be pulverized, treated, and paved , with traffic shifting to the side that received the FDR treatment in Phase 1. This phased approach ensures that two-way traffic can continue on at least one side while necessary pavement rehabilitation is carried out on the other side. However, temporary disruptions or lane reductions may occur during the reclamation and curing process. Construction will be phased so that traffic is limited on the treated FDR ba se to the maximum extent possible, with the goal of ensuring that traffic only drives on either the existing HMA or the new HMA. Another factor to be aware of with FDR paving is that a greater amount of dust is often produced during pavement reconstruction during the curing phase of the treated base, especially when lime or other stabilization agents are applied, which can pose concerns for the public. To mitigate these concerns, the City will ensure that the paving contractor implements effective dust control measures during this period to reduce impacts to the community and preserve environmental quality and safety within the vicinity of the construction site. Contractors will be required to submit a Construction Phasing Plan and a Dust Control Plan prior to the start of construction. These plans will outline specific strategies for dust suppression, such as regular watering, the use of dust suppressants, and the installation of physical barriers. By carefully planning and implementing these mitigation measures, the potential impact of dust exposure can be minimized, ensuring the safety and success of the project while minimizing disruptions to the surrounding community. Complete Street Design Elements The 2025 Paving Project includes complete street enhan cements for several streets, which are intended to improve mobility and safety for all road users, as guided by the City’s ATP and Draft Vision Zero Action Plan. In addition to roadway maintenance and striping improvements, this project will include pedestrian curb ramp upgrades at 19 locations on Tank Farm Road, eight (8) locations on Sacramento, and one (1) curb ramp on Orcutt Road to improve accessibility and comply with current ADA requirements. Calle Joaquin (Motel 6 to City/County Line) There are no relevant recommendations in the ATP or notable safety concerns for the segment of Calle Joaquin. Improvements primarily include pavement rehabilitation, restriping, and replacing faded traffic signs and object markers. The only notable change from existing conditions is the addition of striped edge lines for added visibility at night, as there is little streetlighting on this segment of Calle Joaquin. Page 354 of 625 Item 7c Example of Increased Nighttime Visibility with Addition of Edge Lines Sacramento Drive (Industrial Way to Via Esteban) Sacramento Drive is designated as a commercial collector and serves both residential and light industrial uses, including a high level of commercial delivery trucks. The City’s ATP calls for retaining the existing striped bike lanes on Sacramento, and exploring potential for a future pedestrian crossing improvement, such as addition of an all-way stop at Sacramento/Capitolio, which is identified as a Tier 3 (lowest priority) project per the ATP. Public comments received regarding Sacramento Drive in recent years include the following: 1. Concerns with poor pavement condition, particularly within the bike lanes. 2. General complaints regarding high speeds and illegal speeding, including from larger commercial trucks that frequent Sacramento Drive. 3. Concerns with large, parked vehicles/trucks encroaching into southbound bike lane. 4. Concerns with high vehicle speeds and encroachment into the bike lane along the curve in the road north of the paving project limits (note that two community members traveling on foot were tragically killed by a reckless driver along this curve in November 2022). To address these concerns, the following design elements are proposed as part of the 2025 Paving project for Sacramento Drive in addition to pavement reconstruction and ADA curb ramp upgrades: 1. While outside of the paving project limits, plans include sign/striping modifications along the roadway curve north of Via Esteban to reduce illegal speeds and vehicle encroachment into the bike lane. Measures include additional curve warning signage with flashing yellow beacons, addition of striped bikeway buffers, centerline and bike lane line hardening (ceramic “bots dots” pavement markers installed along yellow centerline and bike lane edge stripes) to discourage vehicles encroaching into adjacent lanes. Page 355 of 625 Item 7c 2. Installation of radar speed feedback signs and additional speed limit signs. (Note that the speed limit was recently reduced from 35 to 30 mph from Capitolio to Industrial and is currently posted at 25 mph north of Capitolio). 3. Addition of green bike lane conflict markings at intersections and high-traffic driveways. 4. Striping refinement to narrow auto lane widths (within City Engineering Standards), widen parking lane width next to the southbound bike lane, added width to northbound bike lane, and addition of striped bike lane buffers, where width allows. 5. Moderate expansion of parking restrictions at intersection corners (“daylighting”) to improve sight distance and safety for all road users pursuant to state law and City Engineering Standards. Example of Ceramic Pavement Markers to Reduce Vehicle Departure from Traffic Lanes Consideration for New Pedestrian Crossing or All-Way Stop at Sacramento/Capitolio Staff evaluated the intersection of Sacramento/Capitolio for addition of all-way stop signs, as suggested in the ATP and requested by some community members. However, based on review of traffic volumes, collision history, and site conditions, the intersection does not currently meet the thresholds or “warrants” that need to be satisfied per state engineering standards to legally install an all-way stop. Staff will continue to monitor potential for this modification in the future at this intersection. A planning application is currently under review for a potential private school to be located on Sacramento Drive west of the intersection with Via Esteban. Potential for a new pedestrian crossing is being evaluated as part of this private development project, and if warranted, a new pedestrian crossing would be implemented on Sacramento as a condition of approval of the development with proper features to improve pedestrian access and safety. Further Traffic Calming Considerations on Sacramento Staff initially considered installing speed cushions on Sacramento Drive as part of the 2025 Paving Project as an additional measure to reduce illegal speeding beyond the other features proposed with the current project designs (radar speed signs and addit ional Page 356 of 625 Item 7c speed limit signage). However, staff is recommending that additional physical traffic calming be considered as part of a planned future speed cushion pilot program instead. Staff is planning to implement a pilot program to test the effectiveness and ideal configuration of speed cushions on streets with higher frequency of emergency vehicles, buses or heavy truck activity—streets that would otherwise not be candidates for speed humps or other vertical traffic calming options. Speed cushions are like speed humps, but include cutouts that allow large-axle vehicles, such as fire trucks, ambulances, and buses, to bypass the humps without slowing significantly or risking vehicle damage. The pilot program proposes the use of temporary bolt-down rubber speed cushions to allow staff to test various configurations in coordination with emergency service providers and transit operators to ensure they can be used effectively before installing using permanent materials. The speed cushion pilot program is planned to be implemented during the 2025-27 work program, if sufficient funding is provided to the Neighborhood Traffic Management and/or Vision Zero capital improvement project accounts in the upcoming Financial Plan. Example of Speed Cushion (Future Consideration for Sacramento Dr) Orcutt Road (Tank Farm Rd to City/County Line) Proposed improvements for this roadway primarily include pavement rehabilitation, upgrades to one curb ramp, and replacing existing striping. The ATC did comment on a portion of this roadway that has experienced recent issues with flooding and sediment collection within the bike lane. Staff has identified some significant erosion adjacent to the edge of the roadway along Orcutt Road, which will be remedied as part of this project through grading and soil compaction along the roadway shoulder for improved drainage. Striping Refreshment on Various Streets There are several roadways not planned for resurfacing in the near term where existing pavement markings have deteriorated significantly and beyond what City maintenance staff can repair. These locations have been added to the 2025 Paving Project to refre sh Page 357 of 625 Item 7c pavement markings only, taking advantage of improved pricing and efficiency of adding this work to a larger paving project. No pavement repairs or other improvements are proposed for these streets. These locations include:  Broad Street (Orcutt Road to Tank Farm)  Santa Rosa & Mill Street Crosswalks  Madonna Road (US 101 Southbound Ramps to Higuera)  Prado Road (Higuera to Serra Meadows)  Tank Farm Road (Santa Fe to Broad Street) Tank Farm Road - Existing Conditions & Policy Context Currently, Tank Farm Road has five traffic lanes (two lanes in each direction plus a center median/turn lane) east of Broad Street, before narrowing to three lanes (one lane in each direction plus center median/turn lane) east of the UPRR bridge. Typical street cross sections are illustrated below for reference (note that specific dimensions may vary slightly along these segments compared to illustrative cross section drawings). Figure 2: Existing Tank Farm Road (Broad to UPRR Bridge) Figure 3: Existing Tank Farm Road (Righetti Ranch to Orcutt) The ATP identifies Tank Farm Road as a Tier 1 (highest priority) active transportation corridor, with recommendations to pursue protected bike lanes and pedestrian crossing improvements. The ATP notes that potential auto lane reductions (a “road diet”) should be evaluated to accommodate these improvements, pending further feasibility study. Note that the ATP also encourages development of lower-stress active transportation routes parallel to high traffic volume/speed arterial streets such as Tank Farm, where feasible; however, there are no viable parallel routes existing or planned along this segment of Tank Farm Road. Page 358 of 625 Item 7c Attachment D includes relevant excerpts from the ATP for this segment of Tank Farm Road for reference. While this segment of Tank Farm Road does not have sufficient collision history to be designated as part of the City’s High Injury Network 3, Tank Farm between Broad Street and Righetti Ranch Road is ranked in the Draft Vision Zero Action Plan as having the 11th highest crash rate among city arterial streets, with 15 total collisions and one severe injury collision in the past five years (2019-2023). The most recent severe injury collision involved a pedestrian hit by a vehicle when crossing Tank Farm near the Sunrose/Morning Glory intersection. There was also a severe injury collision involving a pedestrian hit by a vehicle when crossing Tank Farm at Poinsettia in 2014. City staff receives regular comments from community members regarding the following concerns on Tank Farm Road east of Broad Street: 1. General concerns about unsafe/illegal speeding, including requests to lower posted speed limits and add traffic calming (current speed limits are posted as low as legally allowed per the California Vehicle Code).4 2. Concerns about difficulty making left turns from side street intersections due to high vehicle speeds on Tank Farm. 3. Concerns with vehicles failing to yield to pedestrians at existing marked crosswalks on Tank Farm at Poinsettia and at the Righetti Ranch Road roundabout. 4. Requests for the addition of an enhanced pedestrian crossing on Tank Farm between Poinsettia and Righetti Ranch Road. Many of these sentiments are echoed in the public comments receive d in the City’s Online Vision Zero Community Input Map. Considering the history of public concerns, the policy recommendations of the ATP, and data included in the City’s Draft Vision Zero Action Plan regarding collision risk on high- speed, multi-lane arterial streets, staff is recommending that multimodal improvements be considered along Tank Farm Road as part of the 2025 paving project, where appropriate and as funding allows. SLO Fire Review and Input on Tank Farm Road Design Options Preliminary striping plans for the 2025 Paving Project were reviewed with the San Luis Obispo Fire Department (SLO Fire) to ensure that designs are consistent with applicable local and state fire codes and do not present any concerning impediments to emergency response. Tank Farm Road was a primary focus of this review among the streets included 3 The High Injury Network describes the 10% of city road miles where the majority (75%) of fatal and severe injuries occur. See the City’s Traffic Safety webpage and Draft Vision Zero Action Plan for additional details. 4 Posted speed limits on Tank Farm currently range from 35 mph (Broad to Righetti Ranch) to 45 mph (Righetti Ranch to Orcutt), while prevailing speeds range from 42 mph to 45 mph. Where referenced herein, “prevailing speeds” refers to the 85th percentile speed, a commonly used traffic engineering measurement which represents the threshold at which 85 of 100 vehicles are traveling at or below this speed. The California Vehicle Code generally requires speed limits to be set at or near the 85 th percentile speed. Page 359 of 625 Item 7c in the 2025 Paving Project, as Tank Farm serves as a major east -west arterial, a primary emergency response route, and as a likely evacuation route in the case of a wildfire encroaching from the hills east of the City Limits. Public Works and SLO Fire staff reviewed potential striping design alternatives for Tank Farm that include features contemplated in the ATP and Draft Vision Zero Action Plan, such as (a) a potential five-lane to three-lane road diet between Poinsettia and the UPRR Bridge, (b) narrower traffic lane widths, (c) addition of protected bike lanes per the ATP, and (d) potential addition of enhanced pedestrian crossing features. SLO Fire provided the following recommendations to guide final designs: 1. Recommend retaining traffic lane widths >10 feet for greater fire truck clearance, with 11’ as a preferred lane width. Where width is constrained, prioritize width in center turn lane, which may be used to bypass other traffic in an emergency event. 2. Recommend omitting any vertical protected bike lane features, providing greater flexibility for vehicles to pull to the curbside to clear space for emergency vehicles or during an evacuation event. If vertical elements are recommended by the City Council, omit vertical objects within 30’ on either side of any fire hydrants and locate features to maximize roadway clearances. 3. Ensure the most restrictive City Fire Truck can navigate turning movements to/from all driveways and intersections with any street design changes. 4. Pedestrian Refuge Medians – While acknowledging the potential safety benefits of adding raised median refuges at pedestrian crossings5, there is concern that adding this vertical obstruction in the roadway could impede emergency response and/or evacuation needs without sufficient clearance on either side of the median. If two westbound traffic lanes can be retained and a minimum of 20’ cl earance can be provided in the eastbound direction, SLO Fire would be supportive of adding potential refuge islands at pedestrian crossings, pending review of the final design details. (More discussion on this later in the report) Emergency Evacuation Considerations with Potential Road Diet Public Works and City Fire Department staff specifically discussed potential effects that street design changes may pose to evacuation needs in the instance of a large -scale emergency event in the vicinity of Tank Farm Road. The City has not designated formal evacuation routes, as evacuation needs are generally incident -specific. However, evacuation needs are an important consideration when evaluating street design modifications, particularly on arterial streets and primary emergency response routes. While there is no recent history of evacuations in the vicinity of Tank Farm Road and no properties that directly access Tank Farm are currently located within High Fire Hazard Severity Zones, there are properties in the Moderate Severity Zones and areas east of Orcutt Road outside of the City Limit that are identified in the recently updated Cal Fire Hazard maps as High and Very High Fire Hazard Severity Zones (see map below). 5 Per the Federal Highway Administration (FHWA), adding a median pedestrian refuge island to an existing uncontrolled marked crosswalk reduces vehicle vs. pedestrian collisions by 46% on average. Page 360 of 625 Item 7c Figure 4: Cal Fire Hazard Severity Zones Map (Updated March 2025) Traffic congestion during large-scale evacuations tends to occur in areas that already experience heavy traffic during peak periods. In urban street environments, like Tank Farm Road, this is typically at intersections with traffic signals that also provide access to primary regional routes and highways. In the instance of a potential large -scale evacuation along Tank Farm Road, the primary evacuation direction will likely be westbound on Tank Farm Road, and the signalized intersection at Tank Farm and Broad Street (State Route 227) will likely be the primary bottleneck point. No changes are proposed to this intersection as part of the paving project that would reduce traffic capacity compared to existing conditions. Based on SLO Fire’s review, neither of the two proposed alternatives to the specific segment of Tank Farm Road where street design changes are contemplated pose significant concerns to the ability of the neighborhood to evacuate. Whether or not any lane capacity changes are pursued with the 2025 Paving Proj ect, Public Works and SLO Fire staff concur that there is value in developing pre-programmed traffic signal timing plans along city arterial corridors, such as Tank Farm, which could be deployed quickly during an emergency evacuation to prioritize traffic movement away from the incident location. Public Works staff plans to develop these signal timing plans as staffing resources allow. Tank Farm Road Design Alternatives Considering the recommendations of the ATP, Draft Vision Zero Action Plan, community input, and feedback from emergency service representatives, two striping design concepts are presented for Tank Farm Road for Council consideration. The alternatives are intended to advance the City’s transportation safety and mobility goals to the extent feasible, while also accommodating the needs of emergency services. Tank Farm Rd Tank Farm Striping Design Focus Area Page 361 of 625 Item 7c  Alternative 1 (Road Diet) – Proposes a five-lane to three-lane road diet on Tank Farm between Poinsettia Street and UPRR bridge, with additional striped buffered bike lanes and pedestrian crossing improvements at several intersections.  Alternative 2 (No Road Diet) – Maintains the existing five-auto-lane configuration on Tank Farm between Broad Street and the UPRR bridge . This alternative provides an option that prioritizes retaining the existing roadway configuration and traffic capacity to minimize traffic delays, including in the case of a potential large- scale emergency evacuation. Pavement reconstruction and ADA curb ramp upgrades are included under both alternatives and designs east of the UPRR bridge are the same for both design options. Note that both alternatives omit any vertical bikeway separation to preserve roadway clearance and efficiency for emergency vehicle access and evacuation needs. See discussion later in this report for consistency with Active Transportation Committee (ATC) recommendations and ATP policy considerations. Tank Farm Striping Alternative 1 (Road Diet) Design features include: 1. Five-lane to three-lane road diet between Poinsettia and the UPRR bridge, retaining five auto lanes between Broad and Poinsettia near the Marigold Shopping Center. 2. Installation of radar speed feedback signs and additional speed limits signs to encourage lower auto speeds. 3. Pedestrian safety improvements at Tank Farm/Poinsettia, including relocation of crosswalk and existing rectangular rapid flashing beacons (RRFBs) to east leg of intersection for improved visibility and reduce conflicts with turning traff ic. High- visibility crosswalk markings, new streetlighting, advanced warning markings/signage, and striped corner bulbouts to reduce pedestrian crossing distance are also proposed. 4. Addition of a new pedestrian crossing at the Tank Farm/Morning Glory/Sunrose intersection, including hi-visibility crosswalks, new streetlighting, RRFBs, advanced warning markings/signage, and striped corner bulbouts to reduce pedestrian crossing distance are also proposed. 5. Addition of RRFB beacons at the Righetti Ranch Roundabout for crosswalks crossing Tank Farm Road, improving visibility for pedestrians. (Note that vegetation trimming is also scheduled prior to the paving project to improve visibility at this intersection) 6. Striping modifications to the westbound approach of the Tank Farm/Broad Street intersection to convert the existing westbound right-turn lane to a combined through/right-turn lane (reduces vehicle congestion/delays and eliminates need for westbound cyclists to merge across high-speed/volume right turn lane). 7. Addition of green bike lane conflict markings at intersections and high -traffic driveways. Page 362 of 625 Item 7c Figure 5: Alternative 1 - Tank Farm Road Proposed Road Diet Limits Figure 6: Alternative 1 Proposed Tank Farm Road (Broad to Poinsettia) Example Image of Radar Speed Feedback Sign Example Image Rectangular Rapid Flashing Beacon (RRFB) Page 363 of 625 Item 7c Figure 7: Alternative 1 Proposed Tank Farm Road (Poinsettia to UPRR Bridge) Figure 8: Alternative 1 Proposed Tank Farm Road (Righetti Ranch to Orcutt) Attachment E shows preliminary striping plans for Tank Farm Road Alternative 1. Feasibility of Road Diet Proposed with Alternative 1 A traffic operations study was prepared by an outside transportation engineering firm, Kimley Horn, for the road diet proposed in Alternative 1. The analysis evaluates motor vehicle congestion and delays along the segment of Tank Farm Road where lane reductions are proposed (Poinsettia to UPRR bridge), considering both existing and future (Year 20406) traffic conditions. The conclusions of the traffic analysis report are summarized as follows:  The existing (2024) and projected future (2040) traffic volumes on Tank Farm Road are well within the volume thresholds suggested for a viable five-lane to three-lane road diet (see Figure 9 below)  Driver delays/congestion at intersections within the road diet limits would remain within the City’s adopted level of service (LOS) thresholds for existing (2024) conditions with the proposed lane reductions. 6 2040 Conditions traffic forecasts reflect buildout of the City’s General Plan land use growth and transportation circulation improvements, including remaining development within the Orcutt Specific Plan Area and additional growth outside of the city limits pursuant to the SLOCOG Regional Transportation Plan forecasts. Completion of the Prado Road Interchange and Extension to Broad Street are assumed in this scenario, but do not substantively affect future traffic volumes on this segment of Tank Farm Road. Page 364 of 625 Item 7c o The most notable change in driver experience would be an increase in delay of 2-6 seconds per vehicle on average turning left from side streets to Tank Farm Road during AM and PM peak hours.  Under 2040 conditions, all intersections within the road diet limits would operate acceptably, except the Tank Farm/Poinsettia intersection, where the northbound approach would operate at unacceptable LOS E during the PM peak. The traffic study recommends monitoring traffic conditions and installing a northbound left - turn acceleration lane before traffic volumes reach 2040 build-out levels. Staff is recommending including this acceleration lane now as part of the 2025 Paving Project as a pre-emptive measure to avoid potential for future congestion and delays. With this acceleration lane, this intersection would be at acceptable LOS C through 2040 conditions, with less projected delay than if the existing five -lane road configuration were to be retained.  The intersection of Tank Farm/Morning Glory/Sunrose is an appropriate location to add a marked pedestrian crosswalk with the proposed road diet and additional safety features (i.e. bulbouts, warning beacons, safety lighting, etc.). The figure below shows existing and future volumes on Tank Farm compared to Federal Highway Administration (FHWA) recommended thresholds for three-lane road diets. The largest traffic volumes are anticipated for the 2040 PM peak hour, which remain 37% below the Federal Highway Administration’s recommended road diet volume threshold. As noted previously, SLO Fire does not anticipate any significant impacts to typical emergency response or evacuation needs with the proposed road diet, as currently proposed. Figure 9: Tank Farm Rd. Traffic Volumes vs Recommended Road Diet Thresholds Page 365 of 625 Item 7c Tank Farm Striping Alternative 2 (No Road Diet) As discussed in further detail later in this report, staff has received input from some residents expressing opposition to the road diet proposed in Alternative 1, with a preference to retain existing lanes and traffic capacity to minimize potential for ve hicle delays or congestion. The Council may also prefer to retain additional traffic capacity beyond what is currently needed to maintain day-to-day traffic operations as a precautionary strategy to accommodate (a) potential future development growth beyon d current General Plan build-out forecasts, and/or (b) to reduce potential delays in the case of a future large-scale evacuation incident along Tank Farm Road. Alternative 2 is presented to provide the Council with a design option that prioritizes these c onsiderations. Design features include: 1. Retains existing number of traffic lanes on Tank Farm. 2. 11-foot-wide traffic lanes are provided where feasible, per SLO Fire’s preference for efficient emergency vehicle clearance. 3. Striped bike lane buffers provided where width allows for 11 -foot-wide traffic lanes (east of Righetti Ranch) and omitted elsewhere. 4. No curb extensions (bulbouts) at intersections due to insufficient street width. 5. Pedestrian safety improvements at Tank Farm/Poinsettia, including relocation of the existing crosswalk RRFB system to the east leg of intersection for improved visibility and reduce conflicts with turning traffic. High-visibility crosswalk markings, new streetlighting, and advanced warning markings/signage are also proposed. 6. Advance pedestrian warning signage approaching the Tank Farm/Sunrose/Morning Glory intersection and new streetlight installation, but no addition of a marked crosswalk at this location. (see further discussion on this below). 7. Radar speed feedback signs in each direction. 8. Green bike lanes through intersection conflicts. Figure 10: Alternative 2 Proposed Tank Farm Road (Broad to UPRR Bridge) Page 366 of 625 Item 7c Figure 11: Alternative 2 Proposed Tank Farm Road (Righetti Ranch to Orcutt) For the same reasons discussed previously with Alternative 1, no vertical protected bikeway elements are proposed with Alternative 2. Alternative 2 Consideration for Pedestrian Crossing at Tank Farm/Morning Glory/Sunrose While some community members have expressed interest in adding a new pedestrian crossing on Tank Farm between Poinsettia and Righetti Ranch Road—most fittingly at the Tank Farm/Sunrose/Morning Glory intersection—staff does not recommend installing a new crosswalk here with Alternative 2. Based on review of engineering design guidance and transportation safety best practices for uncontrolled crosswalks, it is staff’s opinion that adding an unsignalized marked crosswalk is not the best strategy at a crossing location with traffic speeds over 40 mph and five lanes of traffic (64-foot-wide crossing) without more substantial safety elements. While Alternative 2 could include some safety features, such as high-visibility crosswalk markings, additional lighting, warning signage, and flashing beacons (RRFBs), which could improve the visibility of pedestrians over existing conditions, staff does not recommend adding a marked crosswalk in order to avoid creating a false sense of security for pedestrians, as driver compliance is likely to remain low without further crossing enhancements. For staff to support potential addition of a designated crosswalk at this location, additional safety measures such as a median refuge, raised crosswalks, reducing the number of conflicting traffic lanes, adding bulbouts, or installing a pedestrian hybrid beacon/signal would be needed. Conditions do not currently warrant a pedestrian signal or hybrid beacon installation. See “Alternatives” section of this report for discussion on additional modifications to Alternative 2 that may add potential for a median refuge and crosswalk at this location. Attachment F shows preliminary striping plans for Tank Farm Road Alternative 2. Comparison of Tank Farm Alternative 1 and 2 Table 1: Comparison of Design Alternatives Topic Alternative 1 (Road Diet) Alternative 2 (No Road Diet) Traffic Operations & Emergency  Lane reductions less familiar to existing drivers  More intuitive to existing drivers Page 367 of 625 Item 7c Topic Alternative 1 (Road Diet) Alternative 2 (No Road Diet) Response Considerations  Traffic operates within adopted thresholds, with small increase in vehicle delays above existing configuration and Alt 2 at most intersections  Slight improvement for NBL driver delays at Poinsettia w/ acceleration lane above Alt 2 and existing conditions.  Less excess road capacity preserved for future growth and emergency evacuation (capacity could be restored in future by restriping to restore existing traffic lanes if needed)  Traffic operates within adopted thresholds with fewer vehicle delays than with Alt 1 in general  Preserves extra capacity for additional growth beyond current build-out projections and emergency evacuation Bicycle Facilities  Partially consistent with ATP – wider buffered bike lanes added with more separation from vehicles, but no physical separation  Slightly higher potential to attract new cyclists & increase bike mode share than Alt 2  Mostly inconsistent with ATP, with less improvements to bicycle lane widths and separation from traffic and no physical bikeway separation.  Less potential to attract new riders & increase bike mode share than Alt 1 Pedestrian Crossings  Lane reductions reduce pedestrian exposure & crossing distance, reduces number of veh vs. pedestrian conflict points  Greater potential for driver compliance at crossings  Road diets are proven countermeasure to reduce pedestrian crash rates  Provides new enhanced pedestrian crossing at Tank Farm/Morning Glory/Sunrose  Does not reduce pedestrian exposure & crossing distance  No change in veh. vs. pedestrian conflict points  Less potential to increase driver compliance at crossings  Does not provide a new enhanced pedestrian crossing at Tank Farm/Morning Glory/Sunrose Potential to Reduce  Greater potential to reduce unsafe/illegal vehicle  Some potential to reduce unsafe vehicle speeds by adding radar Page 368 of 625 Item 7c Topic Alternative 1 (Road Diet) Alternative 2 (No Road Diet) Unsafe/Illegal Vehicle Speeds speeds with road diet and radar speed signs speed signs, but less potential than with Alt 1 Costs  Approximately $50,000 higher costs than Alternative 2 by including enhanced pedestrian crossing at Tank Farm/Morning Glory  Approximately $50,000 lower costs than Alternative 1 by omitting enhanced pedestrian crossing at Tank Farm/Morning Glory Previous Council or Advisory Body Action Preliminary plans for the 2025 Paving Project were presented to the Active Transportation Committee (ATC) on November 21, 2024. The ATC staff report is available for reference on the ATC website. The committee was supportive of the design proposal for Tank Farm featuring a road diet as shown herein in Alternative 1; however, the ATC majority voted in favor of including vertical protected bike lane elements on Tank Farm, as recommended in the ATP. Vertical bikeway features are omitted from the current design alternatives presented for Council consideration due to a preference from emergency service providers to preserve roadway clearance for efficient emergency response and evacuation potential. The ATC was also supportive of including buffered bike lanes along Tank Farm between Broad and Poinsettia, which are omitted from current plans, as this would require 10’ traffic lane widths, which are discouraged by emergency response providers for this street. The following summarizes key recommendations from the ATC on the 2025 Paving Project designs and staff responses to each recommendation: Tank Farm Road 1. ATC Recommendation: Include physical bikeway separation, with preference for concrete barriers. o Staff Response: Current design alternatives for Council consideration do not include vertical bikeway separation to preserve roadway clearance for emergency response priorities. If Council were to direct staff to include physical bikeway separation on Tank Farm, staff is not recommending addition of concrete bikeway features at this time—instead rubber flexible elements would be preferred, such as flex posts only or flex posts supplemented with rubber curb stops. This is due to funding constraints, more flexibility for emergency response needs, and an interest to allow for further monitoring and community adaptation to new street design changes before installing higher-cost, rigid features. Page 369 of 625 Item 7c 2. ATC Recommendation: Explore feasibility of center median refuges at Poinsettia and Morning Glory pedestrian crossings. o Staff Response: As discussed previously in section on SLO Fire design coordination, staff is not recommending installation of center median refuges at pedestrian crossings at this time for Alternative 1 or 2. With Alternative 1, there were concerns that addition of a center median may impede the ability of vehicles to use the center turn lane to bypass traffic during an emergency response event or large-scale evacuation westbound on Tank Farm. With Alternative 2, there is no available street width for a median refuge. A potential hybrid design concept is discussed in the “Alternatives” section at the end of this report, which prese nts a design configuration that could include a median pedestrian refuge that is supportable by SLO Fire. 3. ATC Recommendation: Provide gaps in bikeway separation in final plans to allow for flexible passing and merging out of the bike lane for left turns at driveways and intersections. o Staff Response: No vertical bikeway separation is currently proposed with Alternative 1 or 2. If Council chooses to direct staff to revisit potential vertical bikeway elements, staff is supportive of incorporating additional gaps in bikeway separation to improve ability for cyclists to merge and pass other cyclists. Sacramento Drive 4. ATC Recommendation: Consider adding a marked pedestrian crossing at Capitolio intersection or other locations along Sacramento between Orcutt and Industrial. o Staff Response: As noted above, a new pedestrian crossing on Sacramento is currently being evaluated as part of a development proposal for a private school campus near Via Esteban. Staff is recommending that a new crossing be considered as part of this development proposal outside of the 2025 Paving Project scope. No specific design recommendations were provided by the ATC for Calle Joaquin or Orcutt Road beyond the features already proposed by staff and reflected in the current plans for those roadway segments. Design Alternative 2 was not specifically discussed with the ATC in detail but was created subsequently as an additional option for Council consideration in response to feedback from some community members with concerns about potential traffic congestion with a road diet. Staff provided a project status update to the ATC on March 20, 2025, which included a brief update to convey that Tank Farm alternatives with and without a road diet would be presented to the Council for consideration. The ATC did not take any new action on this Page 370 of 625 Item 7c topic at the meeting, but members affirmed the previous committee re commendation supporting the road diet presented in Alternative 1, and a preference for protected bike lane elements as recommended in the ATP. Public Engagement Staff solicited community input on the 2025 Paving Project over the past several months. Direct mailers were sent to all properties within the vicinity notifying community members of the proposed project, planning process and schedule, project website and opportunities to provide in-person input at forthcoming public meetings. Staff received several comments from community members at the November 21, 2024 ATC meeting, and via subsequent emails to staff and City Council, with roughly half of the comments for Tank Farm Road in support of the proposed road diet and features shown in striping Alte rnative 1 to reduce speeds, and half in favor of keeping the existing five-lane street configuration and striping-only bike lanes to maintain current traffic capacity and reduce costs. This divide in public sentiment is a primary reason for requesting Coun cil policy direction for Tank Farm Road designs. Agenda correspondence provided on this item at the November, 2024, ATC meeting is available for review here (see Item 4a correspondence). Notifications were mailed directly to properties within the vicinity of Tank Farm Road ahead of this public hearing on May 6th, 2025, and additional notifications will be provided to community members as project advances to construction. CONCURRENCE Plans for the 2025 Paving Project have been reviewed and refined in coordination with SLO Fire to ensure that these designs are consistent with applicable local and state fire codes and do not present any concerning impediments to emergency response. SLO Fire is supportive of the designs currently presented in Alternative 1 or 2. Following direction from Council from this meeting, staff will provide an additional opportunity for review by SLO Fire Department prior to finalizing the 2025 Paving Project plans for construction. This staff report was reviewed by the City Attorney’s Office, Finance Director, and City Administration prior to publishing. ENVIRONMENTAL REVIEW The 2025 Paving Project qualifies for an Exemption to the California Environmental Quality Act (CEQA) pursuant to State CEQA Guidelines Sections 15301 (Existing Facilities) because the Project consists of the repair and maintenance of existing roadways. In addition, the types of complete street improvements proposed as part of this Project would all be considered categorically exempt from State CEQA Guidelines Sections 15301(Existing Facilities) and are expected to increase access to sustainable transportation modes and potentially reduce vehicle miles traveled (VMT). Therefore, no Page 371 of 625 Item 7c additional environmental review is triggered. A Notice of Exemption will be filed through the Community Development Department upon Council approval of the project. FISCAL IMPACT Budgeted: Yes Budget Year: 2025-26 Funding Identified: Yes Fiscal Analysis: Funding Sources Funding Availability Total Budget Available Current Funding Request Remaining Balance Annual Ongoing Cost General Fund - LRM (No. 2000616) 7/1/2025 $3,960,000 $3,960,000 $0 $ SB1 Fund (No. 2000616) 7/1/2025 $1,277,312 $1,277,312 $0 Capital Reserve Fund (LRM) Current $1,735,907 $1,404,530 $331,377 Roadway Sealing 2024 (Account No. 2000615) (General Fund LRM) Current $2,544,144 $2,100,000 $444,144 Arterials 2023 (Account No. 2001065) (General Fund LRM) Current $169,299 $100,000 $69,299 Water Fund (No. 2001005) Current $228,948 $199,200 $29,748 Sewer Fund (No. 2000084) Current $128,309 $76,800 $51,509 Total $10,043,919 $9,117,842 $926,077 $ Page 372 of 625 Item 7c 2025 Paving Project, Specification No. 2000616 Street Reconstruction and Resurfacing – Annual Asset Maintenance Account (2001001) Water Valve Cover Adjustments (2001005) Sewer MH Cover Adjustments (2000084) Project Total Costs General Fund SB1 Fund Water Fund Sewer Fund Base Bid Construction Estimate 6,212,688 $1,277,312 $166,000 $64,000 $7,720,000 Contingencies 725,342 $0 $33,200 $12,800 $771,342 Construction Management 450,000 $0 $0 $0 $450,000 Materials Testing 100,000 $0 $0 $0 $100,000 Printing & Advertising 1,500 $0 $0 $0 $1,500 Public Relations 75,000 $0 $0 $0 $75,000 Base Bid Total Estimate 7,564,530 1,277,312 199,200 76,800 9,117,842 Additive Alt A Estimate 1,100,000 $0 $0 $0 $1,100,000 Additive Alt B Estimate 550,000 $0 $0 $0 $550,000 Additive Alt A &B Contingencies 200,000 $0 $0 $0 $200,000 Construction Management 100,000 $0 $0 $0 100,000 Materials Testing 50,000 $0 $0 $0 50,000 Printing & Advertising 500 $0 $0 $0 500 Public Relations 25,000 $0 $0 $0 25,000 Additive Alternative Total Estimate 2,025,500 0 0 0 $2,025,500 Total Construction Estimate (Base + Add Alts) 9,590,030 1,277,312 199,200 76,800 11,143,342 Available Project Balance 0 $0 $199,200 $76,800 $276,000 FY 2025-26 Additional Funding on 7/1/2025 $3,960,000 $1,277,312 $0 $0 $5,237,312 Roadway Sealing 2024 (2000615) 2,100,000 $0 $0 $0 $2,100,000 Arterials 2023 (2001065) 100,000 $0 $0 $0 $100,000 CIP Reserve 1,404,530 $0 $0 $0 $1,404,530 Total Funding After 7/1/2025 7,564,530 $1,277,312 $199,200 $76,800 $9,117,842 Page 373 of 625 Item 7c The 2025 Paving Project bid plans and specifications are structured with a Base Bid and two Additive Alternatives, with Additive Alternative A representing work on Orcutt Road east of Tank Farm, and Alternative B representing work on Calle Joaquin. The st rategy is to award the contract with the Base Bid and as many of the Additive Alternatives as funding will allow, up to the Publicly Disclosed amount of $7,720,000 in compliance with Public Contract Code Section 20103.8(c). The total project cost is estimated at $11,143,342, including direct construction costs and contingencies, as well as related soft costs (construction engineering support, materials testing, communications support, etc.). Excluding the Bid Additive Alternatives, the total Base Bid project cost is $9,117,842 (construction, contingency and soft costs). Note that because final designs for Tank Farm Road are pending policy direction from the Council at this hearing, current cost estimates for this component of the project are based on staff’s best approximations and are slightly conservative in nature. A total of $9,117,842 in funding is recommended to support project construction, sourced from the following:  The project’s funding plan relies on approval of a funding request to the 2025 Roadway Paving account (2000616) in the amount of $5,237,312 in fiscal year 2025-26 which is included in the draft 2025-27 Financial Plan. This amount includes $3,960,000 from the General Fund and $1,277,312 from the SB1 Fund7.  An additional $2,100,000 is expected to become available within the Streets Reconstruction and Resurfacing account after the completion of the Roadway Sealing 2024 project (2000615), which is 95% complete and under budget.  An additional $100,000 is expected to become available within the Streets Reconstruction and Resurfacing account with the completion of the Arterials 2023 Project (2001065).  Staff is recommending appropriating $1,404,530 of Local Revenue Measure funds from the Capital Reserve fund to support construction of the Project per the draft Resolution (Attachment A). Approval of this resolution is required to appropriate new undesignated funds from the Capital Projects Reserve Fund.  Where asphalt pavement is replaced, the project will incorporate upgrades to water valve and sewer maintenance hole covers which is funded by the Water Valve Cover Adjustments Account (2001005) in the amount of $199,200 and Sewer Maintenance Hole Cover Adjustments Account (2000084) in the amount of $76,800. 7 Note that the Streets Reconstruction and Resurfacing account (2001001) has a current balance of $17,766. However, it is recommended that this balance remain within the account to support minor pavement failures that may arise throughout the year in lieu of committing 100% of available funds to the 2025 Paving Project. Page 374 of 625 Item 7c This 2025 Paving Project is recommended to be awarded prior to the new fiscal year with work not starting until after July 1, 2025, when the Fiscal Year 2025 -26 funding is available. If funding is not sufficient to support all of this project’s needs, only portions of the contract would be awarded to reflect the work than can be completed within the available budget. In order to allow for project implementation during the summer and early fall months, and to lessen impacts to the traveling public, staff is recommending this project be approved for advertisement now rather than waiting until start of Fiscal Year 2025-26. Project construction will not be initiated unless sufficient funding exists as recommended to support the total project costs. Actual costs will be known when the project ope ns for bid. Fiscal Analysis of Tank Farm Road Striping Alternatives The estimated construction cost for proposed improvements on Tank Farm Road is approximately $5,500,000. Costs would be substantially equal for Alternative 1 and Alternative 2, aside from roughly $50,000 in costs related to pedestrian crossing improvements at the Tank Farm/Morning Glory/Sunset intersection that would be incurred under Alternative 1 only. While the current alternatives for Tank Farm Road do not include vertical bikeway elements, if Council directs staff to pursue designs that include protected bike lanes, there would be further cost implications. If only flex posts were used for protected bikeway separation, an additional $50,000-$75,000 in construction costs would be expected. If additional hardening, such as rubber or concrete curb stops/medians were pursued, the construction costs would increase by at least another $50,000-$100,000 above the costs for flex posts. Ongoing maintenance costs of roughly $30,000 per year would be incurred if protected bike lane features were to be pursued, including roughly $27,000 per year for contract sweeping expenses and roughly $3,000 per year for replacement of damaged bikeway barriers/flex posts. Staff are currently assessing maintenance costs and funding resources closely with development of the 2025-27 Financial Plan. If the Council were to direct staff to advance designs for Tank Farm Road that include vertical bikeway separation, there may not be sufficient funds in the forthcoming 2025-27 operating budget to fund ongoing maintenance costs. Under this scenario, staff would likely need to utilize funds from a capital project account to fund these expenses, such as rem aining contingency funds from the 2025 Paving Project (once complete), remaining funds from other completed CIP projects, or from one of the ATP Implementation capital project accounts. Under this scenario, staff would communicate a funding plan for these ongoing maintenance costs to the Council prior to completion of the 2025 Paving Project. Page 375 of 625 Item 7c ALTERNATIVES Tank Farm Design Alternatives 1. The Council could direct staff to advance an alternative that includes modifications to Alternative 1 or Alternative 2, or combines features from each alternative, such as:  Hybrid Alternative – Road Diet in Eastbound Direction Only i. Preserve existing two (2) traffic lanes in westbound direction for emergency evacuation capacity ii. Road diet to one (1) lane in eastbound direction only from Poinsettia to UPRR bridge (similar to Alternative 1) iii. Use available width from eastbound lane reduction to add bike lane buffers and pedestrian refuges at Tank Farm/Poinsettia and Tank Farm/Morning Glory/Sunrose intersections iv. Concept designs for this Hybrid Alternative are included as Attachment G. Public Works and SLO Fire staff would be supportive of advancing the Hybrid Option (Road Diet Eastbound Only), if preferred by the City Council. Staff’s current recommendation is not to include vertical separation for protected bike lanes on Tank Farm, even with this Hybrid Alternative, to preserve existing roadway clearances for emergency response and evacuation needs and to reduce ongoing maintenance costs. Median refuges at Tank Farm/Poinsettia and Tank Farm/Morning Glory/Sunrose would be feasible and recommended by staff under this alternative and are shown in the design concepts (Attachment G)—medians would not restrict westbound access in the case of an evacuation (two lanes would be retained westbound for evacuation needs). 2. The Council could choose not to recommend a specific design alternative for Tank Farm Road at this time and direct staff to pursue other designs. The Council may ask staff to continue to advance multiple design alternatives or to return with additional alternatives not currently contemplated. This may delay the ability to advance the 2025 Paving Project in time to solicit competitive construction bids. Bidding roadway paving projects in the late spring or early summer can result in lack of competitive bidding, as many roadway contractors are already schedu led for the peak summer road construction season when many other agencies in the region schedule similar paving work. 3. The Council could choose not to support either striping alternative for Tank Farm, directing staff to do neither and simply repave Tank Farm and restore the existing striping configuration with no added features. The Council may direct staff to focus resources only on essential maintenance elements of the paving project for Tank Farm Road, restoring the road configuration and striping to what is currently in place. Further, Council may direct staff to omit other features proposed in the current Page 376 of 625 Item 7c design proposals not related to essential maintenance (pedestrian beacons, new streetlighting, radar speed signs, etc.). This action would not support the recommendations of the adopted ATP or address concerns from residents regarding vehicle speeds and pedestrian crossing safety on Tank Farm Road. Alternatives to Approving Advertisement of the 2025 Paving Project 1. The Council could direct staff to modify design features for other streets included in the 2025 Paving Project other than Tank Farm Road. The City Council may direct staff to modify design elements for Calle Joaquin, Sacramento Drive or Orcutt Road. Staff invites Council input on these details, as long as the recommended design refinements can be accommodated within available funding resources and comply with applicable engineering design standards. 2. Deny authorization to advertise. The City Council may choose not to authorize project advertisement or direct staff to revise and return to Council with an updated bid package at a later date. This would delay advertisement of the project for construction, potentially shifting the project construction schedule into winter months with higher potential for weather delays. ATTACHMENTS A - Draft Resolution Approving Appropriation of Capital Projects Reserve Funds B - 2025 Paving Project Plans (2000616) C - 2025 Paving Project Specifications (2000616) D - Active Transportation Plan Excerpts E - Tank Farm Road Design Alternative 1 (Road Diet) F - Tank Farm Road Design Alternative 2 (No Road Diet) G - Tank Farm Road Hybrid Design Alternative (Eastbound Road Diet Only) Page 377 of 625 Page 378 of 625 R ______ RESOLUTION NO. _____ (2025 SERIES) A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF SAN LUIS OBISPO, CALIFORNIA, AUTHORIZING APPROPRIATION OF CAPITAL PROJECTS RESERVE FUNDS TO SUPPORT THE 2025 PAVING PROJECT, SPECIFICATION NUMBER 2000616 WHEREAS, on May 6, 2025, the City Council authorized advertisement of the 2025 Paving Project and delegated authority to the City Manager to award the construction contract if the lowest responsive bid was within the publicly disclosed funding limit of $7,720,000; and WHEREAS, the project includes roadway reconstruction on Tank Farm Road , from Broad Street to Wavertree Street, reconstruction on Sacramento Drive, from Industrial Way to Via Esteban, and striping in various locations throughout the City; and WHEREAS, two bid alternates are included to be awarded if within the available project budget, which include roadway reconstruction on Orcutt Road and Calle Joaquin; and WHEREAS, proposed improvements on Tank Farm Road, Orcutt Road, and Sacramento Drive support several recommendations in the City’s Active Transportation Plan and the City’s adopted Vision Zero Goal to eliminate severe injury and fatal traffic collisions; and WHEREAS, a pavement analysis conducted in December of 2024 confirmed that Tank Farm Road, Orcutt Road, Sacramento Drive, and Calle Joaquin Road are all structurally deficient and unable to support the current and projected traffic loads; and WHEREAS, to provide sufficient funding to proceed with the 2025 Paving Project, staff is recommending the City Council approve use of $1,404,530 from the FY24/25 Capital Projects Reserve Fund at the close of the 2024-25 Fiscal Year; and WHEREAS, a balance of approximately $1,735,907 is currently available from the FY24/25 Capital Projects Reserve Fund. NOW, THEREFORE, BE IT RESOLVED by the Council of the City of San Luis Obispo as follows: Page 379 of 625 Resolution No. _____ (2025 Series) Page 2 R ______ SECTION 1. The City Council authorizes the Finance Director to appropriate up to $1,404,530 from the Capital Reserve Fund to the 2025 Paving Project, Specification No. 2000616 at the close of the 2024-25 Fiscal Year. Upon motion of _______________________, seconded by _______________________, and on the following roll call vote: AYES: NOES: ABSENT: The foregoing resolution was adopted this _____ day of _____________________ 2025. ___________________________ Mayor Erica A. Stewart ATTEST: __________________________ Teresa Purrington City Clerk APPROVED AS TO FORM: __________________________ J. Christine Dietrick City Attorney IN WITNESS WHEREOF, I have hereunto set my hand and affixed the official seal of the City of San Luis Obispo, California, on ______________________. ___________________________ Teresa Purrington City Clerk Page 380 of 625 Page 381 of 625 Page 382 of 625 Page 383 of 625 Page 384 of 625 Page 385 of 625 Page 386 of 625 Page 387 of 625 Page 388 of 625 Page 389 of 625 Page 390 of 625 Page 391 of 625 Page 392 of 625 Page 393 of 625 Page 394 of 625 Page 395 of 625 Page 396 of 625 Page 397 of 625 Page 398 of 625 Page 399 of 625 Page 400 of 625 Page 401 of 625 Page 402 of 625 Page 403 of 625 Page 404 of 625 Page 405 of 625 Page 406 of 625 Page 407 of 625 Page 408 of 625 Page 409 of 625 Page 410 of 625 Page 411 of 625 Page 412 of 625 Page 413 of 625 Page 414 of 625 Page 415 of 625 Page 416 of 625 SPECIAL PROVISIONS FOR CITY OF SAN LUIS OBISPO 2025 Paving Project Specification No. 2000616 April 2025 PUBLIC WORKS DEPARTMENT ENGINEERING DIVISION 919 Palm Street San Luis Obispo, CA 93401 (805) 781-7200 Page 417 of 625 2025 Paving Project Specification No. 2000616 Approval Date: May 06, 2025 Hai Nguyen May xx, 2025 Brian Nelson May xx, 2025 Page 418 of 625 TABLE OF CONTENTS NOTICE TO BIDDERS ..................................................................................................... I  BID SUBMISSION ...................................................................................................................................... I  BID DOCUMENTS .................................................................................................................................... II  PROJECT INFORMATION........................................................................................................................ II  QUALIFICATIONS .................................................................................................................................... III  AWARD ..................................................................................................................................................... V  ACCOMMODATION .................................................................................................................................. V  BID FORMS .................................................................................................................... A   BID ITEM LIST FOR 2025 PAVING PROJECT, SPECIFICATION NO. 2000616 .................................... A  LIST OF SUBCONTRACTORS ................................................................................................................ G  PUBLIC CONTRACT CODE SECTION 10285.1 STATEMENT .............................................................. H  PUBLIC CONTRACT CODE SECTION 10162 QUESTIONNAIRE ......................................................... H  PUBLIC CONTRACT CODE SECTION 10232 STATEMENT ................................................................. H  LABOR CODE SECTION 1725.5 STATEMENTS ................................................................................... H  NON-COLLUSION DECLARATION .......................................................................................................... J  BIDDER ACKNOWLEDGEMENTS ........................................................................................................... K  QUALIFICATIONS ..................................................................................................................................... L  ATTACH BIDDER'S BOND TO ACCOMPANY BID ................................................................................. M  SPECIAL PROVISIONS .................................................................................................. 1  DIVISION I GENERAL PROVISIONS ....................................................................................................... 1  1 GENERAL ........................................................................................................................................... 1  3 CONTRACT AWARD AND EXECUTION ........................................................................................... 1  4 SCOPE OF WORK ............................................................................................................................. 2  5 CONTROL OF WORK ........................................................................................................................ 2  7 LEGAL RELATIONS AND RESPONSIBILITY TO THE PUBLIC ....................................................... 2  8 PROSECUTION AND PROGRESS ................................................................................................... 4   DIVISION II GENERAL CONSTRUCTION ............................................................................................... 5  12 TEMPORARY TRAFFIC CONTROL ................................................................................................ 5  15 EXISTING FACILITIES ..................................................................................................................... 6  DIVISION IV SUBBASES AND BASES .......................................................................... 6  DIVISION V SURFACINGS AND PAVEMENTS ..................................................................................... 20  39 ASPHALT CONCRETE .................................................................................................................. 20  DIVISION VIII MISCELLANEOUS CONSTRUCTION ............................................................................ 21  73 CONCRETE CURBS AND SIDEWALKS ....................................................................................... 21  77 LOCAL INFRASTRUCTURE .......................................................................................................... 22  DIVISION IX TRAFFIC CONTROL DEVICES......................................................................................... 22  Page 419 of 625 84 MARKINGS ..................................................................................................................................... 22  DIVISION X ELECTRICAL WORK .......................................................................................................... 24  86 ELECTRICAL SYSTEMS ............................................................................................................... 24  DIVISION XIII APPENDICES .................................................................................................................. 24  ADD SECTION 100 APPENDICES ..................................................................................................... 24  APPENDIX A - FORM OF AGREEMENT ....................................................................... 0  APPENDIX B – SEALMASTER SAFE RIDE DATA SHEET ........................................... 3  APPENDIX C – PAVEMENT EVALUATION REPORT ................................................... 4  Page 420 of 625 NOTICE TO BIDDERS i NOTICE TO BIDDERS BID SUBMISSION Sealed bids will be received by the City of San Luis Obispo at the Public Works Administration Office located at 919 Palm Street, San Luis Obispo California, 93401 until 11:00 a.m. on June xx, 2025 at which time they will be publicly opened and read aloud. Public bid opening may be accessed via Microsoft Teams video conference and conference call. In person attendance will be permitted. Use the following link: https://teams.microsoft.com/l/meetup- join/19%3ameeting_YWJmZTY5ZjctNjQxOC00ODk3LWFhMjctODkyOGI2NjkzODRi%4 0thread.v2/0?context=%7b%22Tid%22%3a%22a78b182d-94e4-4507-a9a9- 330dcb148164%22%2c%22Oid%22%3a%22eec32d58-d6a8-4d68-8923- 9cce58e6b2a9%22%7d or join by phone with this number: 1 (209) 645-4165 with Conference ID: 438 062 902# Submit bid in a sealed envelope plainly marked: 2025 Paving Project, Specification No. 2000616 Any bid received after the time and date specified will not be considered and will be returned to the bidder unopened. Bids received by Fax or Email will not be considered. By submission of bid you agree to comply with all instruction and requirements in this notice and the contract documents. All bids must be submitted on the Bid Item List form(s) provided and submitted with all other Bid Forms included in these Special Provisions. Each bid must be accompanied by either a: 1. certified check 2. cashier's check 3. bidder's bond made payable to the City of San Luis Obispo for an amount equal to ten percent of the bid amount as a guaranty. Guaranty will be forfeited to the City San Luis Obispo if the bidder, to whom the contract is awarded, fails to enter into the contract. The City of San Luis Obispo reserves the right to accept or reject any or all bids or waive any informality in a bid. All bids are to be compared based on the City Engineer's estimate of the quantities of work to be done, as shown on the Bid Item List. Page 421 of 625 NOTICE TO BIDDERS NOTICE TO BIDDERS ii Bids will only be accepted from bidders that are licensed in compliance with the provisions of Chapter 9, Division III of Business and Professions Code. The award of the contract, if awarded, will be to the lowest responsive bid submitted by a responsible contractor whose bid complies with the requirements prescribed. If the contract is awarded, the contract will be awarded within 60 calendar days after the opening of the bids. Failure to raise defects in the notice to bidders or bid forms prior to bid opening constitute a waiver of those defects. BID DOCUMENTS A copy of the plans and special provisions may be downloaded, free of charge, from the City’s website at: www.slocity.org/government/department-directory/public-works/public-works-bids- proposals No printed copies are available for purchase at the City office. Standard Specifications and Engineering Standards referenced in the Special Provisions may be downloaded, free of charge, from the City’s website at: www.slocity.org/government/department-directory/public-works/documents- online/construction-documents You are responsible to obtain all issued addenda prior to bid opening. Addenda will be available to download at the City’s website listed above or at the office of the City Engineer. All questions must be submitted through Bidsync and if the City determines that a response is required, the City will post an addendum on Bidsync. Contact the project manager, Hai Nguyen at 805-781-7108 / hnguyen@slocity.org or the Public Works Department at (805) 781-7200 prior to bid opening to verify the number of addenda issued. You are responsible to verify your contact information is correct on the plan holders list located on the City’s website at: www.slocity.org/government/department-directory/public-works/public-works-bids- proposals. PROJECT INFORMATION In general, the project consists of applying slurry seal, striping, pavement markings, and signage to various streets as identified in the project plans. Page 422 of 625 NOTICE TO BIDDERS NOTICE TO BIDDERS iii The project estimated construction cost and contract time established for the project is a follows: BASE BID: $7,720,000 80 working days ADDITIVE ALTERNATIVE “A”: $1,100,000 10 working days ADDITIVE ALTERNATIVE “B”: $550,000 10 working days TOTAL PROJECT BID (BASE BID + ADD ALT. “A” + ADD ALT “B”): $9,370,000 The fixed liquidated damages amount is established at $1,000 per day for failure to complete the work within the contract time. In compliance with section 1773 of the Labor Code, the State of California Department of Industrial Relations has established prevailing hourly wage rates for each type of workman. Current wage rates may be obtained from the Division of Labor at: https://www.dir.ca.gov/oprl/DPreWageDetermination.htm This project is subject to compliance monitoring and enforcement by the Department of Industrial Relations. QUALIFICATIONS You must possess a valid Class A or C12 Contractor's License at the time of the bid opening. You and any subcontractors required to pay prevailing wage must be registered with the Department of Industrial Relations pursuant to Section 1725.5 of the Labor Code. You must have experience constructing projects similar to the work specified for this project. Provide three similar reference projects completed as either the prime or subcontractor. All referenced projects must have been completed within the last five years from this project’s bid opening date. One of the three referenced projects must have been completed under contract with a city, county, state or federal government agency as the prime contractor. Two of the three referenced projects must have included ADA concrete curb ramp and sidewalk construction within the public right of way. All referenced projects must be for roadway construction, including Full Depth Reclamation within the public right of way. If you do not have the necessary Full Depth Reclamation experience, you may elect to subcontract that work. If you elect to subcontract that work, you must provide referenced projects for roadway Page 423 of 625 NOTICE TO BIDDERS NOTICE TO BIDDERS iv construction as the prime and three additional subcontractor referenced projects for Full Depth Reclamation within the public right of way. Failure to provide reference projects as specified in this section and as required on the qualification form is cause to reject a bid as being non-responsive. The City reserves the right to reject any bid based on non-responsiveness if a bidder fails to provide a bid that complies with all bidding instructions. The City reserves the right to reject a responsive bid based on the non-responsibility of the bidder if the Director of Public Works or Designee finds, after providing notice and a hearing to the bidder, that the bidder lacks the 1. knowledge 2. experience, 3. or is otherwise not responsible as defined in Section 3.24 of the San Luis Obispo Municipal Code to complete the project in the best interest of the City. Rejected bidders may appeal this determination. Appeal must comply with the requirements in this Notice to Bidders. It is the City of San Luis Obispo’s intent to award the contract to the lowest responsive bid submitted by a responsible bidder. If in the bidder’s opinion the contract has been or may be improperly awarded, the bidder may protest the contract award. Protests must be filed no later than five working days after either: 1. bid opening date 2. notification of rejected bid. Protest must be in writing and received by the project manager located at: 919 Palm Street San Luis Obispo, CA 93401. Valid protests must contain the following information: 1. the reasons for the protest 2. any supporting documentation 3. the ruling expected by the City to remedy the protest. Any protest not containing all required information will be deemed invalid and rejected. The City will consider additional documentation or other supporting information regarding the protest if submitted in compliance to the specified time limits. Anything submitted after the specified time limit will be rejected and not be considered. The Director of Public Works or Designee may request additional information to be submitted within three days of the request, unless otherwise specified, and will notify the protester of ruling within ten days of determination. Page 424 of 625 NOTICE TO BIDDERS NOTICE TO BIDDERS v If the protester is not satisfied with ruling, the protester may appeal the ruling to the City Council in compliance with Chapter 1.20 of the City of San Luis Obispo Municipal Code. Pursuant to the Public Records Act (Government Code, § 6250, et seq.), the City will make public records available upon request. AWARD The lowest bidder will be determined in compliance with Public Contract Code Section 20103.8(c) with the Publicly Disclosed Funding Amount of $7,720,000 using either:  TOTAL PROJECT BID, if bid for Base Bid + Add. Alt. “A” + Add Alt. “B” is less than $7,720,000; or  BASE BID + ADD. ALT. “A”, if bid for Base Bid + Add. Alt. “A” is less than $7,720,000 and Total Project Bid is greater than $7,720,000; or  BASE BID, if Base Bid is less than $7,720,000 and Base Bid + Add. Alt. “A” is greater than $7,720,000. As a condition to executing a contract with the City, two bonds each equal to one hundred percent of the total contract price are required in compliance with Section 3-1.05 of the Standard Specifications. You may substitute securities for moneys withheld under the contract in compliance with the provisions of the Public Contract Code, Section 10263. ACCOMMODATION If any accommodations are needed to participate in the bid process, please contact Allie Genard at (805) 781-7057 or by Telecommunications Device for the Deaf at (805) 781- 7107. Requests should be made as early as possible in the bidding process to allow time for accommodation. Page 425 of 625 BID FORMS A BID FORMS All bid forms must be completed and submitted with your bid. Failure to submit these forms and required bid bond is cause to reject the bid as nonresponsive. Staple all bid forms together. THE UNDERSIGNED, agrees that they have carefully examined: 1. the location of the proposed work 2. the plans and specifications 3. read the accompanying instructions to bidders and propose to furnish all: 4. materials 5. labor to complete all the required work satisfactorily in compliance with 6. plans 7. specifications 8. special provisions for the prices set forth in the bid item list: BID ITEM LIST FOR 2025 PAVING PROJECT, SPECIFICATION NO. 2000616 Item Item Unit of Estimated Item Price Total No. SS(1) Description Measure Quantity (in figures) (in figures) BASE BID ITEMS 1 7, 12 TRAFFIC CONTROL PLAN AND IMPLEMENTATION LS 1 -------------- 2 7 COMPLY WITH NIGHT WORK PERMIT LS 1 -------------- 3 20 TREE TRIMMING LS 1 -------------- 4 30 POTHOLING ON TANK FARM LS 1 -------------- 5 77 WATER SERVICE REPAIR ALLOWANCE EA 5 6 30 CONSTRUCTION PHASING PLAN (FDR) LS 1 -------------- 7 30 DUST CONTROL PLAN (FDR) LS 1 -------------- 8 15, 73 CURB RAMP TANK FARM AND BROAD NE LS 1 -------------- 9 15, 73 CURB RAMP TANK FARM AND TETRA TECH SE LS 1 -------------- 10 15, 73 CURB RAMP TANK FARM AND MARIGOLD NW LS 1 -------------- 11 15, 73 CURB RAMP TANK FARM AND MARIGOLD NE LS 1 -------------- 12 15, 73 CURB RAMP TANK FARM AND MARIGOLD ALLEY NW LS 1 -------------- 13 15, 73 CURB RAMP TANK FARM AND MARIGOLD ALLEY NE LS 1 -------------- 14 15, 73 CURB RAMP TANK FARM AND HOLLYHOCK NW LS 1 -------------- Page 426 of 625 BID FORMS BID FORMS B Item Item Unit of Estimated Item Price Total No. SS(1) Description Measure Quantity (in figures) (in figures) 15 15, 73 CURB RAMP TANK FARM AND HOLLYHOCK NE LS 1 -------------- 16 15, 73 CURB RAMP TANK FARM AND POINSETTIA NW LS 1 -------------- 17 15, 73 CURB RAMP TANK FARM AND POINSETTIA NE LS 1 -------------- 18 15, 73 CURB RAMP TANK FARM AND POINSETTIA SW LS 1 -------------- 19 15, 73 CURB RAMP TANK FARM AND POINSETTIA SE LS 1 -------------- 20 15, 73 CURB RAMP TANK FARM AND SUNROSE NW LS 1 -------------- 21 15, 73 CURB RAMP TANK FARM AND SUNROSE NE LS 1 -------------- 22 15, 73 CURB RAMP TANK FARM AND MORNING GLORY SW LS 1 -------------- 23 15, 73 CURB RAMP TANK FARM AND MORNING GLORY SE LS 1 -------------- 24 15, 73 CURB RAMP TANK FARM AND BROOKPINE SW LS 1 -------------- 25 15, 73 CURB RAMP TANK FARM AND BROOKPINE SE LS 1 -------------- 26 15, 73 CURB RAMP TANK FARM AND WAVERTREE SW LS 1 -------------- 27 15, 73 CURB RAMP TANK FARM AND WAVERTREE SE LS 1 -------------- 28 15, 73 CURB RAMP SACRAMENTO AND RICARDO NE LS 1 -------------- 29 15, 73 CURB RAMP SACRAMENTO AND INDUSTRIAL NW LS 1 -------------- 30 15, 73 CURB RAMP SACRAMENTO AND INDUSTRIAL NE LS 1 -------------- 31 15, 73 CURB RAMP SACRAMENTO AND VIA ESTEBAN NW LS 1 -------------- 32 15, 73 CURB RAMP SACRAMENTO AND VIA ESTEBAN NE LS 1 -------------- 33 15, 73 CURB RAMP SACRAMENTO AND VIA ESTEBAN SW LS 1 -------------- 34 15, 73 CURB RAMP SACRAMENTO AND CAPITOLIO NW LS 1 -------------- 35 15, 73 CURB RAMP SACRAMENTO AND CAPITOLIO SE LS 1 -------------- 36 37 COLD PLANE (13.5 INCHES) SQYD 10,454 37 37 COLD PLANE (8.5 INCHES) SQYD 26,668 38 37 PULVERIZATION (FDR) SQYD 26,668 39 37 LIME TREATMENT (FDR) SQYD 26,668 40 39 3/4 MIX HOT MIX ASPHALT TON 14,953 41 39 1/2 MIX HMA COURSE TON 5,046 42 84 BLUE HYDRANT MARKERS PER CITY STD 7920 EA 26 Page 427 of 625 BID FORMS BID FORMS C Item Item Unit of Estimated Item Price Total No. SS(1) Description Measure Quantity (in figures) (in figures) 43 15 UPGRADE/ADJUST COMMUNICATIONS MANHOLE TO FINISHED GRADE EA 4 44 15 UPGRADE/ADJUST COMMUNICATIONS VAULT TO FINISHED GRADE EA 3 45 15 UPGRADE/ADJUST GAS VALVE TO FINISHED GRADE EA 2 46 15 UPGRADE/ADJUST MONUMENT TO FINISHED GRADE EA 14 47 15 REPLACE STORM DRAIN INLET EA 1 48 15 UPGRADE/ADJUST STORM DRAIN MANHOLE TO FINISHED GRADE EA 4 49 15 UPGRADE/ADJUST SANITARY SEWER MANHOLE OR CLEANOUT TO FINISHED GRADE EA 4 50 15 REBUILD SANITARY SEWER MANHOLE FRAME AND COVER EA 13 51 15 UPGRADE/ADJUST WATER VALVE TO FINISHED GRADE EA 83 52 86 SOLAR FLASHING YELLOW BEACON EA 4 53 86 REINSTALL RAPID RECTANGULAR FLASHING BEACON SYSTEM W/ NEW POST AND PUSH BUTTONS - TANK FARM & POINSETTIA LS 1 -------------- 54 86 RAPID RECTANGULAR FLASHING BEACON SYSTEM - TANK FARM & MORNING GLORY LS 1 -------------- 55 86 RAPID RECTANGULAR FLASHING BEACON SYSTEM TANK FARM & RIGHETTI RANCH LS 1 -------------- 56 86 RAPID RECTANGULAR FLASHING BEACON SYSTEM SANTA BARBARA & HIGH LS 1 -------------- 57 86 RAPID RECTANGULAR FLASHING BEACON SYSTEM MONTEREY & TORO LS 1 -------------- 58 84 6" WHITE LF 904 59 84 6" YELLOW LF 227 60 84 8" YELLOW LF 285 61 84 12" WHITE LF 2,629 62 84 12" YELLOW LF 1,914 Page 428 of 625 BID FORMS BID FORMS D Item Item Unit of Estimated Item Price Total No. SS(1) Description Measure Quantity (in figures) (in figures) 63 84 24" WHITE LF 1,311 64 84 DETAIL 2 LF 498 65 84 DETAIL 9 LF 1,506 66 84 DETAIL 22 LF 3,690 67 84 DETAIL 25 LF 1,887 68 84 DETAIL 27B LF 1,884 69 84 DETAIL 29 LF 4,141 70 84 DETAIL 32 LF 1,582 71 84 DETAIL 38 LF 2,335 72 84 DETAIL 39 LF 3,016 73 84 DETAIL 39A LF 3,778 74 84 DETAIL 40 LF 389 75 84 12" WHITE PAINT LF 874 76 84 DETAIL 9 PAINT LF 15,836 77 84 DETAIL 22 PAINT LF 2,662 78 84 DETAIL 24 PAINT LF 1,672 79 84 DETAIL 29 PAINT LF 371 80 84 DETAIL 32 PAINT LF 4,733 81 84 DETAIL 38 PAINT LF 2,112 82 84 DETAIL 39 PAINT LF 12,412 83 84 DETAIL 39A PAINT LF 1,326 84 84 DETAIL 40 PAINT LF 113 85 84 DETAIL 41 PAINT LF 120 86 84 BIKE BUFFER LF 8,262 87 84 BIKE BUFFER WITH PAVEMENT MARKERS LF 653 88 84 GREEN BIKE LANE CASE 2 LF 2,161 89 84 GREEN BIKE LANE CASE 3 LF 896 90 84 RED CURB LF 292 91 84 BOTS DOTS EA 242 92 82 FLEX POSTS EA 70 93 82 REMOVE (E) POST EA 9 94 82 12' PUNCH POST EA 17 95 82 14' PUNCH POST EA 3 96 86 INSTALL NEW STREETLIGHT EA 2 97 82 R1-1 SIGN EA 3 98 82 R2-1 (35) SIGN EA 1 99 82 R2-1 (35) SIGN EA 1 100 82 R2-1 (35) SIGN EA 1 101 82 R9-3 SIGN EA 9 Page 429 of 625 BID FORMS BID FORMS E Item Item Unit of Estimated Item Price Total No. SS(1) Description Measure Quantity (in figures) (in figures) 102 82 R9-3B(R) SIGN EA 4 103 82 R9-3B(L) SIGN EA 4 104 82 R10-15 SIGN EA 1 105 82 MODIFIED R10-15 SIGN EA 1 106 82 R26 SIGN EA 12 107 82 R81(CA) SIGN EA 2 108 82 R81B(CA) SIGN EA 1 109 82 W1-1a(R)(25) SIGN EA 1 110 82 W1-8(L) SIGN EA 4 111 82 W1-8(R) SIGN EA 4 112 82 W4-2 SIGN SIGN EA 1 113 82 W8-6 SIGN EA 1 114 82 W9-1 SIGN EA 1 115 82 W11-2 SIGN EA 2 116 82 W16-9P SIGN EA 3 117 82 RADAR SPEED FEEDBACK SIGN EA 6 118 82 STREET NAME SIGNS EA 7 119 84 WHITE PAINT PAVEMENT MARKINGS/LEGENDS (ARROWS, WORDS, SYMBOLS, ETC.) SQFT 1,473 120 84 WHITE PAVEMENT MARKINGS/LEGENDS (ARROWS, WORDS, SYMBOLS, ETC.) SQFT 1,721 Base Bid $ ADDITIVE ALTERNATIVE A BID ITEMS 121 7, 12 TRAFFIC CONTROL PLAN AND IMPLEMENTATION LS 1 -------------- 122 7 COMPLY WITH NIGHT WORK PERMIT LS 1 -------------- 123 20 TREE TRIMMING LS 1 -------------- 124 15, 73 CURB RAMP ORCUTT AND SPANISH OAKS SW LS 1 -------------- 125 37 COLD PLANE (8.5 INCHES) SQYD 8,767 126 39 3/4 MIX HOT MIX ASPHALT TON 2,860 127 39 1/2 MIX HMA COURSE TON 1,192 128 39 HMA DIKE LF 2,815 129 20 REGRADE, RECOMPACT AND INSTALL JUTE NETTING SQFT 7,108 130 84 BLUE HYDRANT MARKERS PER CITY STD 7920 EA 1 Page 430 of 625 BID FORMS BID FORMS F Item Item Unit of Estimated Item Price Total No. SS(1) Description Measure Quantity (in figures) (in figures) 131 15 UPGRADE/ADJUST MONUMENT TO FINISHED GRADE EA 1 132 84 DETAIL 22 LF 1,666 133 84 DETAIL 24 LF 38 134 84 DETAIL 29 LF 181 135 84 DETAIL 38 LF 112 136 84 DETAIL 39 LF 3,702 Additive Alternative A $ ADDITIVE ALTERNATIVE B BID ITEMS 137 7, 12 TRAFFIC CONTROL PLAN AND IMPLEMENTATION LS 1 -------------- 138 7 COMPLY WITH NIGHT WORK PERMIT LS 1 -------------- 139 20 TREE TRIMMING LS 1 -------------- 140 37 COLD PLANE (6 INCHES) SQYD 6,611 141 39 3/4 MIX HOT MIX ASPHALT TON 1,438 142 39 1/2 MIX HMA COURSE TON 719 143 84 BLUE HYDRANT MARKERS PER CITY STD 7920 EA 1 144 84 DETAIL 22 LF paint for CL? 145 84 DETAIL 39 LF 3,822 146 84 DETAIL 22 PAINT LF 1,856 147 82 DELINEATOR CLASS 1 TYPE E EA 8 148 82 R26 SIGN EA 9 149 82 W1-8(L) SIGN EA 6 150 82 W14-1 SIGN EA 1 Additive Alternative B Base Bid Total $ Additive Alternative “A” Total $ Additive Alternative “B” Total $ Total Project Bid = (Base Bid + Add. Alternative A + Add. Alternative B) $ Company Name: (1) refers to section in the Standard Specifications, with modifications in the Special Provisions, that describe required work. * Bid item exempt from Section 9-1.06B and 9-1.06C of the Standard Specifications. The unit price will not be adjusted regardless of the final bid item quantity. (S) Specialty item per Section 5-1.13A SUBCONTRACTING, General of the Standard Specifications Page 431 of 625 BID FORMS BID FORMS G LIST OF SUBCONTRACTORS Pursuant to Section 4100 of the Public Contracts Code and section 2-1.33C of the standard specifications, the Bidder is required to furnish the following information for each Subcontractor performing more than 1/2 percent (0.5%) of the total base bid. Do not list alternative subcontractors for the same work. Subcontracting must not total more than fifty percent (50%) of the submitted bid except as allowed in section 5-1.13 of the standard specifications. For Streets & Highways projects, subcontractors performing less than ten thousand dollars ($10,000) worth of work need not be mentioned. Subcontractors required to pay prevailing wage, must be registered with the Department of Industrial Relations pursuant to Labor Code section 1725.5 to be listed. NOTE: If there are no subcontractors, write “NONE” and submit with bid. Name Under Which Subcontractor is Licensed License Number DIR Public Works Registration Number Address and Phone Number of Office, Mill or Shop Specific Description of Subcontract % of Total Base Bid Attach additional sheets as needed. Page 432 of 625 BID FORMS BID FORMS H PUBLIC CONTRACT CODE SECTION 10285.1 STATEMENT In compliance with Public Contract Code Section 10285.1 (Chapter 376, Stats. 1985), the bidder hereby declares under penalty of perjury under the laws of the State of California that the bidder, or any subcontractor to be engaged by the bidder, has ____, has not ____ been convicted within the preceding three years of any offenses referred to in that section, including any charge of fraud, bribery, collusion, conspiracy, or any other act in violation of any state or federal antitrust law in connection with the bidding upon, award of, or performance of, any public works contract, as defined in Public Contract Code Section 1101, with any public entity, as defined in Public Contract Code Section 1100, including the Regents of the University of California or the Trustees of the California State University. The term "bidder" is understood to include any partner, member, officer, director, responsible managing officer, or responsible managing employee thereof, as referred to in Section 10285.1. NOTE: The bidder must place a check mark after "has" or "has not" in one of the blank spaces provided. The above Statement is part of the Bid. Signing this Bid on the signature portion constitute signature of this Statement. Bidders are cautioned that making a false certification may subject the certifier to criminal prosecution. PUBLIC CONTRACT CODE SECTION 10162 QUESTIONNAIRE In compliance with Public Contract Code Section 10162, the Bidder must complete, under penalty of perjury, the following questionnaire: Has the bidder, any officer of the bidder, or any employee of the bidder who has a proprietary interest in the bidder, ever been disqualified, removed, or otherwise prevented from bidding on, or completing a federal, state, or local government project because of a violation of law or a safety regulation? Yes No If the answer is yes, attach a letter explaining the circumstances PUBLIC CONTRACT CODE SECTION 10232 STATEMENT In compliance with Public Contract Code Section 10232, you hereby state under penalty of perjury, that no more than one final unappealable finding of contempt of court by a federal court has been issued against you within the immediately preceding two-year period because of your failure to comply with an order of a federal court which orders you to comply with an order of the National Labor Relations Board. LABOR CODE SECTION 1725.5 STATEMENTS The bidder has delinquent liability to an employee or the state for any assessment of back wages or related damages, interest, fines, or penalties pursuant to any final judgment, order, or determination by a court or any federal, state, or local administrative agency, including a confirmed arbitration award. Any judgment, order, or determination that is Page 433 of 625 BID FORMS BID FORMS I under appeal is excluded, provided that the contractor has secured the payment of any amount eventually found due through a bond or other appropriate means. Yes No The bidder is currently debarred under Section 1777.1 or under any other federal or state law providing for the debarment of contractors from public works. Yes No NOTE: The above Statements and Questionnaire are part of the Bid. Signing this Bid on the signature portion constitute signature of this Statement and Questionnaire. Bidders are cautioned that making a false certification may subject the certifier to criminal prosecution. Page 434 of 625 BID FORMS BID FORMS J NON-COLLUSION DECLARATION I, , declare that I am of , the party making the foregoing bid that the bid is not made in the interest of, or on behalf of, any undisclosed person, partnership, company, association, organization, or corporation; that the bid is genuine and not collusive or sham; that the bidder has not directly or indirectly induced or solicited any other bidder to put in a false or sham bid, and has not directly or indirectly colluded, conspired, connived, or agreed with any bidder or anyone else to put in a sham bid, or that anyone refrained from bidding; that the bidder has not in any manner, directly or indirectly, sought by agreement, communication, or conference with anyone to fix the bid price of the bidder or any other bidder, or to fix any overhead, profit, or cost element of the bid price, or of that of any other bidder, or to secure any advantage against the public body awarding the contract of anyone interested in the proposed contract; that all statements contained in the bid are true; and, further, that the bidder has not, directly or indirectly, submitted his or her bid price or any breakdown thereof, or the contents thereof, or divulged information or data relative thereto, or paid, and will not pay, any fee to any corporation, partnership, company association, organization, bid depository, or to any member or agent thereof to effectuate a collusive or sham bid. Executed on , 20 , in __ I declare under penalty of perjury under the laws of the State of California that the foregoing is true and correct. (Signature and Title of Declarant) (SEAL) Subscribed and sworn to before me this _______day of _________, 20_____ Notary Public Company Name:____________________ Page 435 of 625 BID FORMS BID FORMS K BIDDER ACKNOWLEDGEMENTS By signing below, the bidder acknowledges and confirms that this bid is based on the information contained in all contract documents, including the notice to bidders, plans, specifications, special provisions, and addendum number(s) . (Note: You are responsible to verify the number of addenda prior to the bid opening.) The undersigned further agrees that in case of default in executing the required contract, with necessary bonds, within eight days, (not including Saturdays, Sundays, and legal holidays), after having received a mailed notice that the contract is ready for signature, the proceeds of the check or bond accompanying his bid will become the property of the City of San Luis Obispo. Licensed in accordance with an act providing for the registration of contractors, License No. , Expiration Date . The above statement is made under penalty of perjury, and any bid not containing this information "will be considered non-responsive and will be rejected” by the City. Signature of Bidder (Print Name and Title of Bidder) DIR– Public Works Registration No: Business Name (DBA): Owner/Legal Name: Indicate One: Sole-proprietor  Partnership Corporation List Partners/Corporate Officers: Name Title Name Title Name Title Business Address Street Address Mailing Address City, State, Zip Code Phone Number Fax Number Email Address Date Page 436 of 625 BID FORMS BID FORMS L QUALIFICATIONS Failure to furnish complete reference information ON THIS FORM, as specified in this project’s Notice to Bidders and indicated below, is cause to reject the bid. Additional information may be attached but is not a substitute for this form. Reference Number 1 Customer Name & Contact Individual Telephone & Email Project Name (Site Address): Did this project include roadway construction/ reconstruction within the public right of way. Yes □ No □ Describe the services provided and how this project is similar to that which is being bid: Date project completed: Was this contract for a public agency? Yes □ No □ Reference Number 2 Customer Name & Contact Individual Telephone & Email Project Name (Site Address): Did this project include roadway construction/ reconstruction within the public right of way. Yes □ No □ Describe the services provided and how this project is similar to that which is being bid: Date project completed: Was this contract for a public agency? Yes □ No □ Reference Number 3 Customer Name & Contact Individual Telephone & Email Project Name (Site Address): Did this project include roadway construction/ reconstruction within the public right of way. Yes □ No □ Describe the services provided and how this project is similar to that which is being bid: Date project completed: Was this contract for a public agency? Yes □ No □ Page 437 of 625 BID FORMS BID FORMS M ATTACH BIDDER'S BOND TO ACCOMPANY BID Know all men by these presents: That we ____________________________________________, AS PRINCIPAL, and _______________________________________________________, AS SURETY, are held and firmly bound unto the City of San Luis Obispo in the sum of: ____________________________________________________ Dollars (_____________) to be paid to said City or its certain attorney, its successors and assigns; for which payment, well and truly to be made, we bind ourselves, our heirs, executors and administrators, successors or assigns, jointly and severally, firmly by these presents: THE CONDITION OF THIS OBLIGATION IS SUCH, that if the certain bid of the above bounden ______________________________________________________________________ to construct ___________________________________________________________________ (insert name of street and limits to be improved or project) dated _____________________ is accepted by the City of San Luis Obispo, and if the above bounden _______________________________________________________, his heirs, executors, administrators, successors, and assigns shall duly enter into and execute a contract for such construction and shall execute and deliver the two bonds described within ten (10) days (not including Saturdays, Sundays, or legal holidays) after the above bounden, ______________________________________________________, has received notice by and from the said City of San Luis Obispo that said contract is ready for execution, then this obligation shall become null and void; otherwise, it shall be and remain in full force and virtue. IN WITNESS WHEREOF, we hereunto set our hands and seals this ___ day of ______, 20____. Bidder Principal: Signature Date Title: Surety: Bidder's signature is not required to be notarized. Surety's signature must be notarized. Equivalent form may be substituted (Rev. 6-30-14) Page 438 of 625 SPECIAL PROVISIONS 1 SPECIAL PROVISIONS ORGANIZATION Special provisions are under headings that correspond with the main section heading of the Standard Specifications. Each special provision begins with a revision clause that describes or introduces a revision to the Standard Specifications. Any paragraph added or deleted by a revision clause does not change the paragraph number of the Standard Specifications for any other reference to a paragraph of the Standard Specifications. DIVISION I GENERAL PROVISIONS 1 GENERAL Add to Section 1-1.01 GENERAL: The work must be done in compliance with the City of San Luis Obispo, Department of Public Works: 1. 2025 Paving Project Special Provisions 2. City of San Luis Obispo Standard Specifications and Engineering Standards – 2020 edition 3. State of California, Department of Transportation Standard Specifications and Standard Plans – 2015 edition In case of conflict between documents, governing ranking must comply with section 5- 1.02 of the City of San Luis Obispo’s Standard Specifications. Failure to comply with the provisions of these sections is a material breach of contract: 1. Sections 5 through 8 of the Standard Specifications 2. Section 12 through 15 of the Standard Specifications 3. Section 77-1 of the Standard Specifications 4. Section 81 of the Standard Specifications 5. authorized working hours 6. OSHA compliance 3 CONTRACT AWARD AND EXECUTION Add Section 3-1.18B CONTRACT EXECUTION, Caltrans Encroachment Permit: Compliance with Caltrans Encroachment permit and traffic control shall conform to the provisions of Section 12 “Temporary Traffic Control”, of the Standard Specifications and these Special Provisions. Measurement and Payment The lump sum contract price paid to comply with Caltrans Encroachment Permit shall include full compensation for furnishing all labor, materials, tools, equipment, personnel, and for doing all the work involved to comply with all Caltrans encroachment permit requirements. Page 439 of 625 SPECIAL PROVISIONS SPECIAL PROVISIONS 2 4 SCOPE OF WORK Add to Section 4-1.03 WORK DESCRIPTION: Comply with the provisions of Sections 3, 7, 12, 13, 15, 20, 37, 39, 73, 77, 82, 84, 86 and 90 for general, material, construction, and payment specifics. Add Section 4-1.03A WORK DESCRIPTION, Project Specific Signage: Maintain Revenue Enhancement Funding signage in work area. Return Revenue Enhancement Funding signs at the end of the project or upon the Engineer’s request. The Engineer will furnish Sales Tax signs mounted to moveable Barricades. Maintain Sales Tax signage in work area. Return Sales Tax signs at the end of the project or upon the Engineer’s request. Sales Tax signs are stored at the City’s corporation Yard at 25 Prado Road. The contractor is responsible to load and transport from City Corporation Yard to job site and return them when the project is completed under direction of project inspector. 5 CONTROL OF WORK Add to Section 5-1.20B(5) COORDINATION WITH OTHER ENTITIES, Permits, Licenses, Agreements, and Certifications - Comply with Local, State and Federal Regulations: The City applied for an encroachment permit from the State of California, Department of Transportation for work within and affecting Caltrans public right of way. The Contractor is required to obtain and pull the pending permit, comply with all conditions, and pay all associated fees. 7 LEGAL RELATIONS AND RESPONSIBILITY TO THE PUBLIC Add to Section 7-1.03B PUBLIC CONVENIENCE, Traffic Control Plan WORK HOUR RESTRICTIONS Unless stated otherwise below, work hours are 7:00 a.m. to 4:00 p.m. (Monday through Friday) at all the affected streets. Paving and pulverization operations on Tank Farm between Broad and Poinsettia must be completed at night. Two-way traffic circulation with minimum 10’ travel lanes must be retained on Tank Farm, Orcutt and Sacramento between 7:00 a.m. and 9:00 p.m. Night work permit will be necessary if above limitations are not feasible to perform aspects of work. The contractor must not work two consecutive shifts, day and night, unless approved by the Engineer. Page 440 of 625 SPECIAL PROVISIONS SPECIAL PROVISIONS 3 Full Depth Reclamation (FDR) PHASING The FDR work on Tank Farm must be performed in two phases to maintain traffic flow:  Phase 1: During this phase, half of the roadway must remain open to traffic while the other half is closed for pulverization, treatment, and repaving. The portion of the roadway to be worked on must be properly barricaded and signed to redirect traffic. The contractor must ensure that the open half of the roadway is fully accessible to vehicles at all times during Phase 1, with clear signage and traffic control measures in place to guide drivers safely around the work zone.  Phase 2: The work must shift to the other half of the roadway, where the asphalt will be pulverized, treated, and repaved. Similar to Phase 1, the contractor must ensure that at least one side of the roadway remains open to traffic during this phase as well. Temporary lane reductions or disruptions may occur during both phases as necessary to accommodate the construction process. The contractor must carefully manage the traffic flow throughout both phases to minimize disruptions, with ongoing efforts to ensure that one lane in each direction is always open to traffic during the project. CURB RAMPS Where curb ramp improvements are proposed at multiple corners of the intersection, the contractor shall provide a phasing plan showing schedule for demolition and construction of ramps in a manner that retains pedestrian access on at least one side of the street at all times. The construction phasing approach for these ramps shall be approved to the satisfaction of the Engineer. CHANGEABLE MESSAGE SIGNS Two (2) changeable message signs (CMS) must be installed and operational 1 week prior to the start of construction and be maintained throughout the duration of the project at locations approved by the Engineer upon review of the submitted Traffic Control Plan. Changeable message sign shall be programmed for two flashes with the messages to be approved by the Engineer. WORK IN CALTRANS RIGHT-OF-WAY Unless otherwise approved by Caltrans and the Engineer, work within Caltrans Right of Way must be performed between the hours of 9:00 a.m. to 3:00 p.m. (Monday through Thursday) and 9:00 a.m. to 2:00 p.m. Friday. NIGHT WORK Night work is permitted separately. Night work shall comply with the restrictions set forth in the permit by the City of San Luis Obispo Community Development. It is the contractor’s Page 441 of 625 SPECIAL PROVISIONS SPECIAL PROVISIONS 4 responsibility to keep track of the Night Work Permit expiration date. Requests to extend the Night Work Permit must be submitted to the Engineer at least 5 weeks prior to the permit expiration date. Night work is defined as work between the hours of 7:00 P.M. and 7:00 A.M (Sunday through Thursday). Night work will not be allowed on Friday, and Saturday. Prior to commencing the project, the contractor must notify businesses and residences within 300 feet of the worksite about proposed night work. Any portable or fixed equipment that produces noise (such as generators, concrete saws, jack hammers, etc.) must be equipped with sound blankets, temporary sound barriers, or other attenuating devices so as to limit impacts to adjoining properties. When not in use, equipment must be kept in its lowest (quietest) idling state or switched off to limit noise impacts. Any portable lighting must be shielded and/or directed away from adjacent properties. Loudspeakers or other similar forms of communication is prohibited. Contractor will provide lighting for all operations, no exceptions are to be made. Any contractor personnel working outside the lights will be directed to return to a lighted area or the operation must be stopped. All contractor work vehicles, including heavy equipment, backhoes, trenching machines must have two working headlights and taillights. Vehicles without appropriate lighting will be kept from working until they are brought to compliance. Illumination level of 10-foot candles is required for all nighttime operations, which will normally be achieved with light plants or balloon lights. All lighting fixtures must be mounted and directed in manner precluding glare to approaching traffic. TRAFFIC CONTROL PLAN Provide traffic control plan and traffic control application at or before the preconstruction meeting. Traffic control plan must be drawn to scale. Traffic control application may be obtained on the City’s website: www.slocity.org/government/department-directory/public-works/documents- online/construction-documents Upon approval of the traffic control plan, the City will issue a no-fee Encroachment Permit. Permittee is responsible to comply with all conditions of the traffic control plan. Complete work using due diligence to restore free flowing of traffic. 8 PROSECUTION AND PROGRESS Page 442 of 625 SPECIAL PROVISIONS SPECIAL PROVISIONS 5 Add to Section 8-1.01A GENERAL, Order of Work: Unless otherwise approved by the Engineer, roadway restriping work on the following streets must be scheduled as the first phase of work:  Madonna Road  Prado Road  Broad Street  Tank Farm Road (west of Broad Street)  Santa Rosa Street & Mill Street intersection Below is the required sequence of work for installation of Rapid Rectangular Flashing Beacon systems, signs and striping, unless otherwise approved by the Engineer. 1. Unless otherwise approved by the Engineer, the contractor must reinstall the existing flashing beacon system at the Tank Farm/Poinsettia intersection no later than two weeks following completion of curb ramp improvements at this intersection. A temporary crosswalk must be marked in traffic-rated paint in conjunction with reinstallation of this beacon system, unless otherwise approved. 2. Unless otherwise approved by the Engineer, new crosswalk markings at the Tank Farm/Morning Glory/Sunrose intersection shall not be installed until the new flashing beacon system(s) are installed and operational. 3. Contractor will furnish and install all equipment needed for intended operation of Rapid Rectangular Flashing Beacon system. Contractor shall provide beacon system equipment submittals for City review and approval prior to procurement. 4. Contractor is responsible for coordination with beacon system manufacturer’s representative(s) as needed to provide intended operation of beacon systems. Replace the 1st paragraph in Section 8-1.02A SCHEDULE, General with: Provide a Level 1 schedule for this work. A one week look ahead schedule shall be provided to the Engineer before commencing the following week’s work. This requirement shall be completed in order to continue construction work. DIVISION II GENERAL CONSTRUCTION 12 TEMPORARY TRAFFIC CONTROL Add to Section 12-6.01 TEMPORARY PAVEMENT DELINEATION, General with: You will be assessed Liquidated Damages in the amount of $500 per calendar day for each day’s failure to complete temporary striping and pavement markings. Replace Section 12-6.04 PAYMENT with: The lump sum price paid for “Temporary Striping and Pavement Markings” include payment for the following:  Temporary striping and pavement markings to match proposed lane configuration after the roadway paving. Page 443 of 625 SPECIAL PROVISIONS SPECIAL PROVISIONS 6 15 EXISTING FACILITIES Add to Section 15-1.04 PAYMENT The contract price paid per square yard of cold plane shall be based on the actual area of surface cold planed irrespective of the number of passes required to obtain the required depth of the grind as shown on the Plans and shall include full compensation for furnishing all labor, materials, tools, equipment, and incidentals, and doing all work involved in cold planning asphalt concrete surfacing and disposing of planed material as specified in the Standard Specification and these special provisions and as shown on the Plans, and no additional compensation will be allowed therefore. DIVISION IV SUBBASES AND BASES Replace Section 30-4 FULL DEPTH RECLAMATION – CEMENT with: Section 30-4 FULL DEPTH RECLAMATION - LIME AND CEMENT 30-4.01 GENERAL 30-4.01A Summary Section 30-4 includes specifications for constructing a base using full-depth reclamation – lime and cement (FDR). FDR consists of: 1. Pulverizing existing asphalt concrete pavement and underlying materials 2. Mixing with water and lime 3. Mixing with water and cement 4. Spreading, grading, and compacting the mixture 5. Applying asphaltic emulsion 30-4.01B Definitions OMC: Optimum moisture content determined under California Test 216 lot: 1,000 sq yd of FDR 30-4.01C Submittals 30-4.01C(1) General At least 20 days before starting FDR work, submit: 1. Quality Control (QC) plan per 30-4.01C(2) 2. Certificate of Compliance for Quicklime (with each delivery) 3. Certificate of Compliance for Portland Cement (with each delivery) 30-4.01C(2) Quality Control Plan The QC plan must describe the organization, responsible parties, and procedures you will use for: 1. QC including sampling, testing, and reporting Page 444 of 625 SPECIAL PROVISIONS SPECIAL PROVISIONS 7 2. Determining upper and lower action limits when corrective actions are needed 3. Implementing corrective actions 4. Ensuring FDR pulverizing, mixing, compacting, grading, and finishing activities are coordinated The QC plan must include copies of the forms that will be used to provide the required inspection records and sampling and testing results. The form for recording and reporting the QC measurements must show the cement and water proportions. The QC plan must include a contingency plan that describes the corrective actions you will take in the event of equipment break down. The corrective actions must include repairing and reopening the roadway to traffic using minor HMA under section 39. 30-4.01C(3) Mix Design The FDR mix design is provided by the City. Refer to Appendix D. 30-4.01C(4) Test Strip Submit a summary of the determinations made from the test strip. 30-4.01C(5) Quality Control Reporting For each lot, submit a report daily that includes the following items based on the frequencies specified in section 30-4.01D(4): 1. General Information: 1.1. Lot number 1.2. Location description 1.3. Beginning and ending stations 1.4. Lane number and offset from centerline 1.5. Weather: 1.5.1. Ambient air temperature before starting daily FDR activities including time of temperature reading 1.5.2. Road surface temperature before starting daily FDR activities including time of temperature reading 2. Calculated lime application rate in lb/sq yd and percent dry weight of FDR 3. Calculated cement application rate in lb/sq yd and percent of dry weight of FDR 4. For FDR processing: 4.1. Depth of cut 4.2. Average forward speed 5. FDR quality control test results for: 5.1. Gradation 5.2. Moisture content 5.3. Unconfined compressive strength 5.4. In-place wet density 5.5. Relative compaction Page 445 of 625 SPECIAL PROVISIONS SPECIAL PROVISIONS 8 6. For asphalt emulsion used on finished FDR surface: 6.1. Emulsion type 6.2. Emulsion application rate in gal/sq yd 6.3. Emulsion dilution as the weight ratio of added water to asphaltic emulsion 7. Note on the daily report the station limits of any unsuitable materials locations and when the Engineer was notified Update each day's submitted report within 24 hours of obtaining test results. Consolidate all lots completed in a day in one report with each lot reported separately. 30-4.01C(6) Asphaltic Emulsion With each dilution of asphaltic emulsion used for finishing under section 30-4.03H, submit: 1. Weight ratio of water to bituminous material in the original asphaltic emulsion 2. Weight of asphaltic emulsion before diluting 3. Weight of added water 4. Final dilution weight ratio of water to asphaltic emulsion 30-4.01D Quality Control and Assurance 30-4.01D(1) General Schedule a preoperation conference at a mutually agreed time at the job site to meet with the Engineer. Discuss the project specifications and methods of performing each item of the work. Items discussed must include the processes for: 1. Mix design requirements 2. Production 3. Compacting 4. Grading 5. Finishing 6. Implementing the approved QC plan 7. Implementing the contingency plan 8. QC sampling and testing 9. Acceptance criteria Preoperation conference attendees must sign an attendance sheet provided by the Engineer. The preoperation conference must be attended by your: 1. Project superintendent 2. Project manager 3. QC manager 4. Workers and your subcontractor's workers, including: 4.1. Foremen 4.2. Ground supervisors 4.3. Representative from testing lab Page 446 of 625 SPECIAL PROVISIONS SPECIAL PROVISIONS 9 Do not start FDR activities, including test strips, until the listed personnel have attended a preoperation conference. Relative compaction must be determined under California Test 231 and the following: 1. Test in 0.50-foot depth intervals from the bottom of the FDR layer regardless of the layer thickness 2. Correction for oversize material does not apply 3. The asphalt concrete surfacing and underlying base materials shall be pulverized such that 100 percent of the material will pass a two-inch sieve and a minimum of 90-percent will pass a one and one-half-inch (1 ½) sieve. 4. Use the laboratory wet test maximum density closest in proximity to the lot to determine relative compaction. If the relative compaction for a lot is less than 97 percent, perform California Test 216 and California Test 226 for each noncompliant lot and recalculate the relative compaction Divide the area to receive FDR into lots of FDR produced except the test strip is the 1st lot and must be at least 2,000 sq yd. A quantity of FDR placed at the end of a work shift greater than 500 sq yd is considered 1 lot. If a quantity of FDR placed at the end of a work shift is less than 500 sq yd, you may either count this quantity as 1 lot or include the test results for quality control in the previous lot. For any lot including the test strip, stop FDR activities and immediately inform the Engineer whenever: 1. Any test result shown in the QC Requirements table or the FDR Acceptance Criteria Testing table does not comply with the specifications 2. Visual inspection shows evidence of: 2.1. Poor dispersion or dry spots 2.2. Segregation, raveling, and loose material 2.3. Variance of more than 0.05 foot measured from the lower edge of a 12- foot straightedge 2.4. Nonuniform surface texture throughout the work limits 2.5. Repaired areas If FDR activities are stopped, before resuming activities: 1. Notify the Engineer of the adjustments you will make 2. Remedy or replace the noncompliant lot until it complies with specifications 3. Construct a new test strip of FDR with proposed adjustments demonstrating ability to comply with the specifications 4. Obtain authorization 30-4.01D(2) Mix Design Sampling and Testing The Mix Design is provided in Appendix D. The lime content must be 1.0-percent by dry weight of FDR. The cement content must be 3.0 percent by dry weight of FDR. For estimating purposes, use a with a dry unit weight of 130 lb /cu ft. except an increase or decrease in the cement content may be Page 447 of 625 SPECIAL PROVISIONS SPECIAL PROVISIONS 10 ordered based on the mix design. During progress of the work, if you encounter an isolated area that requires more lime or cement than described in the mix design for that area, notify the Engineer before applying. 30-4.01D(3) Test Strip On the 1st day of FDR activities and using the same equipment and materials that will be used during production, construct a test strip of at least 1,500 feet in a single lane width to determine the: 1. Equipment, materials, and processes can produce FDR in compliance with the specifications 2. Effect of varying the FDR machine's forward speed and drum rotation rate on the consistency of the pulverized material 3. Optimal proportions of lime, cement, and water. Changes to the mix design must be authorized. 4. Rolling method and sequence can comply with the compaction and finishing specifications 5. Application rate of asphaltic emulsion for opening to traffic The Engineer tests each test strip under section 30-4.01D(5). Do not proceed with FDR activities until the Engineer informs you the test strip is acceptable. If QC or Engineer's acceptance test results are not available, you may proceed at your own risk. 30-4.01D(4) Quality Control, Sampling, and Testing Designate a ground supervisor whose sole purpose is to monitor the FDR activities, advise project personnel, and interface with the quality control testing personnel. The ground supervisor must not have any sampling or testing duties. Take samples under California Test 125. Perform sampling and testing for each test strip and at the specified frequency for the quality characteristics shown in the following table: Page 448 of 625 SPECIAL PROVISIONS SPECIAL PROVISIONS 11 Quality Control Requirements Quality characteristic Test method Minimum sampling and testing frequency Requirement Sampling location Maximum reporting time allowance Water sulfates a (ppm, max) California Test 417 1 per source 1,300 Source Before work starts Water chlorides a (ppm, max) California Test 422 1 per source 650 Source Gradation (%, passing)b Sieve Size 3 inch 2 inch 1-1/2 inch California Test 202 Test strip and 1 per lot 100 95–100 85–100 Loose mix after pulverizing and mixing 24 hours Moisture content (%) California Test 226 Test strip and 2 per day c Mix design ± 2 percentage points Loose mix after pulverizing and mixing d 24 hours Unconfined compressive strength (psi) ASTM D 1633e Test strip and 1 per 2 lots Specified in section 30- 4.01D(2) Loose mix after pulverizing and mixing d 24 hours after testing specimens Laboratory maximum wet density (lf/cu ft) California Test 216 Test strip and 2 per day Use for relative compaction calculation Same location as a California Test 231 test 24 hours Relative compaction (%, min) (wet density) f California Test 231 Test strip and 1 per lot 97 Compacted mix 24 hours Page 449 of 625 SPECIAL PROVISIONS SPECIAL PROVISIONS 12 a Only required for non-potable water sources. b Remove solids larger than 3 inches. c If test fails, minimum test frequency is 1 per lot d Sample immediately after mixing is complete e Method A, except: 1. Test specimens must be compacted under ASTM D 1557, Method A or B. 2. Test specimens must be cured by sealing each specimen with 2 layers of plastic at least 4-mil thick. The plastic must be tight around the specimen. Seal all seams with duct tape to prevent moisture loss. Sealed specimens must be placed in an oven for 7 days at 100 ± 5 degrees F. At the end of the cure period, specimens must be removed from the oven and air-cooled. Duct tape and plastic wrap must be removed before capping. Specimens must not be soaked before testing. f Verify the moisture content reading made under California Test 231 with California Test 226. Measure and record the actual cut depth at both ends of the pulverizing drum at least once every 300 feet along the cut length. Take measurements in the Engineer's presence. 30-4.01D(5) Acceptance Criteria FDR acceptance is based on: 1. Visual inspection for the following: 1.1. Segregation, raveling, and loose material 1.2. Variance of more than 0.05 foot measured from the lower edge of a 12- foot straightedge 1.3. Uniform surface texture throughout the work limits 1.4. Repaired areas 2. Compliance with the quality characteristics shown in the following table: Page 450 of 625 SPECIAL PROVISIONS SPECIAL PROVISIONS 13 FDR Acceptance Criteria Testing Quality Characteristic Test Method Requirement Lime application rate (lb/sq yd) Calibrated tray or equal Mix design rate ± 5% Cement application rate (lb/sq yd) Calibrated tray or equal Mix design rate ± 5% Relative compaction (%, min, wet density) California Test 231 97 Thickness (ft) a Core measurements ±0.05 of the thickness shown a Take 4- or 6-inch diameter cores from random locations the Engineer selects. The Engineer may require 3 locations per lot; coring more than 3 locations per lot is change order work. At time of coring, submit cores to the Engineer for measurement. 30-4.02 MATERIALS 30-4.02A General Not Used 30-4.02B Lime Lime shall be quicklime conforming to the chemical requirements in ASTM C977 except it shall have a minimum of 90 percent available calcium oxide. Quicklime shall be supplied from a single source. Hydrated lime (dry or slurry), air slaked, by-product or water lime will not be permitted. Quicklime shall be protected from moisture until application and be sufficiently dry to flow freely when handled and added. Quicklime, when delivered to the work site shall conform to the following grading requirements when tested in accourdance with ASTM C136 (dry sieving only) Sieve Size: 3/8 inch. Percent Passing: 98-100 A Certificate of Compliance and a certified weighmaster ticket showing the shipping weight shall be submitted to the Engineer with each delivery. 30-4.02C Cement Cement must be Type II or Type V portland cement specified in ASTM C 150/150M. Pozzolanic material shall not be substituted for Portland Cement. 30-4.02D Water Notify the Engineer if a water source other than potable water is used and perform testing for chlorides and sulfates. Page 451 of 625 SPECIAL PROVISIONS SPECIAL PROVISIONS 14 30-4.02E Mixed Material The pulverized mixture of asphalt concrete and underlying material, lime, and cement must comply with the grading requirements for the sieve sizes shown in the following table: FDR Gradation Sieve Size Percentage Passing 3" 100 2" 100 1.5" 90-100 The moisture content at the time of mixing must comply with the mix design within 2 percentage points. 30-4.02F Asphaltic Emulsion Asphaltic emulsion must be Grade SS1h or CSS1h. For dilution, the weight ratio of water added to asphaltic emulsion must not exceed 1 to 1. 30-4.02G Core Backfill Material Material to fill cored holes for thickness measurements must be packaged rapid- hardening cementitious material under ASTM C 928, Type R2 or R3. 30-4.03 CONSTRUCTION 30-4.03A General Do not start FDR activities if the ambient air temperature is below 40 degrees F or the road surface is below 40 degrees F. If the ambient air temperature falls below 40 degrees F during FDR activities, you may only compact and finish FDR. Before starting daily FDR activities, sweep the FDR area constructed the previous day to remove loose material. 30-4.03B Equipment Do not interrupt traffic while servicing FDR equipment. The FDR machine must have independent and interlocked systems for water and must include the following: 1. Digital electronic controller system 2. Pumping system 3. Spray bar system Storage equipment for water must not leak and must be attached to the FDR machine with a tow bar and hose. Page 452 of 625 SPECIAL PROVISIONS SPECIAL PROVISIONS 15 Grading and compacting equipment must be self-propelled and reversible. The frequency and amplitude of vibrating rollers must be adjustable and exceed a force of 15 tons in vibratory mode. Grading equipment must be a motor grader with automatic grade controls for profile elevation and cross slope. 30-4.03C Surface Preparation Before FDR activities start, prepare the existing roadway surface by: 1. Clearing foreign matter including vegetation 2. Removing standing water 3. Referencing the profile and cross slope 4. Marking the proposed longitudinal cut lines on the existing pavement as follows: 4.1. Cut lines must coincide with points where the existing cross slope changes, approximately at the centerline and edge of traveled way 4.2. Cut lines must indicate the sequence of the cuts If excess material is to be stored adjacent to the shoulder, clear and dispose of the weeds, grass, and debris from the area. 30-4.03D Pulverizing Do not leave a wedge where the pulverizing drum cuts into the existing material. The 1st cut width must use the full width of the pulverizing drum. Subsequent cuts must overlap at least 4 inches. Do not leave a gap of unpulverized material between cuts. If an overlap is more than 4 inches, immediately adjust. If an overlap is less than 4 inches, immediately back up and pulverize the deviation along the correct cut line. Mark the existing pavement where the center of the pulverizing drum stops. Start the following cut on this alignment at least 2 feet behind the mark. If you encounter unstable subgrade or rocks greater than 4 inches in the roadway section, notify the Engineer. The Engineer determines the extent of the problem and the corrective measures to be taken. 30-4.03E Spreading Materials Do not spread lime before pulverizing. Lime shall be in a dry state at the time of spreading. Lime shall not be spread while the atmospheric temperature is below 35 degrees Fahrenheit or wind conditions are such that blowing lime will have an adverse effect on traffic or adjacent property. No traffic other than the reclaimer or other related construction equipment shall be allowed to pass over the spread lime until completion of the initial mixing. Spread lime uniformly over the full roadway surface width. The spread rate must be the mix design rate or the ordered rate in lb/sq yd ± 5 percent. Spread cement uniformly. Do not spread cement more than 30 minutes before mixing. Do not apply dry cement in windy conditions that will result in dust outside the FDR area. The spread rate must be the mix design rate or the ordered rate in lb/sq yd ± 5 percent. Page 453 of 625 SPECIAL PROVISIONS SPECIAL PROVISIONS 16 30-4.03F Mixing 30-4.03F(1) General Requirements The overlap requirements in section 30-4.03D apply to mixing. With each cut, adjust the amount of water proportionally to the actual cut width. If an overlap is less than 4 inches, immediately back up and pulverize the deviation along the correct line without adding water or cement. Water must be injected through the pulverizing machine. The injection rate of mixing water must be sufficient to produce the FDR material mixing moisture content described in the mix design. Mark where the center of the pulverizing drum stops. Start the following cut on this alignment at least 2 feet behind the mark. 30-4.03F(2) Lime Mixing After spreading has been completed, the lime shall be mixed with the pulverized base material to the depth below the bottom of the asphalt concrete pavement to be constructed, as shown on the Plans. Mixing shall be performed a minimum of 2 times. At least one of the 2 mixing operations shall be performed while introducing water into the pulverized base material-lime mixture through operation of the metering/pump device on the reclaimer. Water shall be added as necessary to provide a moisture content of at least 3 percent above the optimum moisture content of the pulverized base material-lime mixture. Any remaining untreated pulverized base material around or attached to manholes, valves, vaults, survey monuments or other structures; adjacent or attached to curbs and gutters; or in areas inaccessible by the reclaimer shall be removed to the depth mixed, and replaced with the pulverized base material-lime mixture. 30-4.03F(3) Mellowing and Final Mixing (Lime) The pulverized base material-lime mixture shall be allowed to cure or “mellow” in an un- compacted state for a period of no less than 16 hours unless otherwise specified in the mix design or approved by the Engineer. During the mellowing periods, the moisture content of the mixture shall be maintained above the optimum moisture content. In no case shall initial and final mixing be performed in the same day. After the required mellowing period and prior to spreading cement, the pulverized base material-lime mixture shall be re-mixed. Mixing operation shall be performed in such a manner as to produce a uniformly blended mixture of lime, water, and pulverized base material free of streaks and pockets of lime. Subsequent to the addition of water, sufficient passes of the reclaimer shall be made as necessary to produce a uniformly treated material. Uniformity will be determined initially by sampling and testing at variable depths and locations within the mixture. The number of passes required may be adjusted based upon subsequent sampling and testing. The depth of mixing shall not vary more than 0.1 foot from the specified depth at any point. Mixing to a depth that exceeds the specified depth by 10 percent or more shall be Page 454 of 625 SPECIAL PROVISIONS SPECIAL PROVISIONS 17 considered as evidence of an inadequate amount of lime and additional lime shall be added at the Contractor’s expense. No color reaction of the treated material, exclusive of 1 inch or larger clods, when tested with the standard phenolphthalein alcohol indicator, will be considered evidence of inadequate mixing. Final mixing shall continue until the pulverized base material-lime mixture, exclusive of rock or aggregate, conforms to the following gradation when testing in accordance with ASTM C136: Sieve Size: 1 inch. Percent Passing: 98 min. Sieve Size: No. 4. Percent Passing: 65 min. 30-4.03F(4) Cement Mixing Mixing shall be performed in a series of passes parallel to the centerline of the roadway such that transverse and longitudinal construction joints are minimized. The full depth of the pulverized base material shall be mixed with cement a minimum of 2 times. At least 1 of the 2 mixing shall be done with introducing water into the pulverized base material through the metering device on the reclaimer. Water shall be added to the pulverized base material during mixing to provide a moisture content not less than 1 percentage point below nor more than 2 percentage points above the optimum moisture content of the pulverized base material mixture. Any remaining untreated material around or attached to manholes, valves, vaults, survey monuments or other structures; adjacent or attached to curbs and gutters; or in areas inaccessible by the reclaimer shall be removed to the depth mixed, and replaced with lime and cement base material mixture. Before compacting, remove solids larger than 3 inches in any dimension by hand. 30-4.03G Compacting and Grading Immediately after pulverizing and mixing, compact FDR to the minimum relative compaction. Do not allow more than 2 hours between final mixing of the pulverized material with cement and completion of compaction with vibratory steel drum rollers. During grading and final compaction with vibratory steel drum rollers, add water to maintain the mixing moisture content as described in the mix design. If the established grade will cause noncompliance with the thickness requirements, notify the Engineer. 30-4.03H Finishing The finished FDR surface must not vary more than 0.05 foot from the lower edge of a 12-foot straight edge laid in directions parallel and perpendicular to the centerline. Immediately after compaction, apply water and roll with pneumatic-tired rollers or steel drum roller with no vibration. The finished surface must be free of ruts, bumps, indentations, segregation, raveling, and any loose material. Page 455 of 625 SPECIAL PROVISIONS SPECIAL PROVISIONS 18 Keep the compacted surface damp by lightly watering until asphaltic emulsion is applied. During the period from 48 to 72 hours after compaction, microcrack the surface by applying 3 single passes with a 12-ton vibratory steel drum roller at maximum amplitude travelling from 2 to 3 mph, regardless of whether asphaltic emulsion has been applied. Apply a coat of asphaltic emulsion to the finished surface when it is damp but free of standing water. The application rate of asphaltic emulsion must be from 0.15 to 0.25 gal/sq yd. Do not water after applying asphaltic emulsion. Do not open to traffic without authorization. While open to traffic and before placing HMA, maintain the FDR surface free of ruts, bumps, indentations, raveling, and segregation. Repair damaged FDR material with minor HMA. Take cores to determine the finished FDR thickness before placing HMA. If a core indicates FDR thickness is less than the specified thickness by more than 0.05 foot, core in the vicinity of the noncompliant core to determine the extent of the deficient thickness. Remove the FDR material deficient in thickness by cold planing to a depth of 0.2 foot below the finished FDR grade. Replace the planed FDR with the HMA specified for the project and compact under the method compaction specifications in section 39- 1.03. Immediately before placing HMA, apply asphaltic emulsion at a rate from 0.03 to 0.05 percent residual binder content. Do not place HMA until authorized. 30-4.04 Curing Time The contractor must account for the curing time required for the treated base layer during the Full Depth Reclamation (FDR) process. The curing period for cement or lime stabilization additives must be observed as per the specified requirements. The curing time must be based on the stabilizing agent, environmental conditions, and mix design. The contractor must anticipate potential delays due to curing time, which may range from 7 to 28 days, and plan the project timeline accordingly. In colder conditions, curing times may extend beyond this range. 30-4.05 Dust Control The contractor must implement dust control measures during the curing phase of the treated base, particularly when lime or cement stabilization agents are used. Prior to the start of construction, the contractor must submit a Construction Phasing Plan and a Dust Control Plan for approval. These plans must detail specific strategies for dust suppression, including, but not limited to, regular watering, the use of dust suppressants, and the installation of physical barriers. The contractor must ensure that dust control measures are effectively implemented throughout the duration of the project to minimize health and environmental impacts. Page 456 of 625 SPECIAL PROVISIONS SPECIAL PROVISIONS 19 30-4.06 Utility Verification and Protection  Bridge Crossing at Tank Farm and Hollyhock: Shallow utilities exist at the bridge crossing on Tank Farm at Hollyhock. The contractor must pothole and verify the depth of all existing utilities within 20 feet of the bridge to ensure proper coordination of the work. The contractor must also take necessary precautions to avoid damaging the bridge during grinding operations to remove the Hot Mix Asphalt (HMA) surface. The depth of the existing HMA surface over the bridge is approximately 3 inches, and the contractor must limit grinding operations to avoid damage to the bridge structure. After grinding, the contractor must remove and replace the HMA to meet the existing profile and cross-section of the roadway.  Traffic Signal Conduits at Broad and Tank Farm Intersection: Traffic signal conduits exist at the intersection of Broad and Tank Farm. The contractor must locate these conduits and verify their depth prior to performing any work in the area to prevent damage to the signal infrastructure.  8" Water Main Crossing Tank Farm from Sunrose and Morning Glory: The contractor must pothole and verify the exact depth of the 8" water main crossing Tank Farm from Sunrose to Morning Glory. The contractor must take all necessary precautions to protect this utility during construction and ensure that no damage occurs.  No Pulverization within 12 Inches of Existing Utilities: No pulverization work is allowed within 12 inches vertically of any existing utilities. In areas with shallow utilities, the contractor will only be required to complete an 8.5-inch mill and fill operation to protect these utilities. The contractor must ensure that the milling depth in such areas does not exceed this limit to prevent damage to existing infrastructure. 30-4.07 Payment Full depth reclamation– lime and cement is measured by the square yardage of FDR. The contract price for Full Depth Reclamation with lime and cement includes full compensation for furnishing all labor, materials, tools, equipment, and incidentals, and for doing the work involved in all pulverizing and mixing of the existing pavement; for spreading and mixing lime and cement, compacting and trimming to the proper grade, for all microcracking, curing, protection and sealing, and furnishing and applying asphaltic emulsion, all as shown on the plans as specified in the Standard Specifications and these special provisions and as directed by the engineer. Lime for Full Depth Reclamation shall be paid for by the ton separately from Full Depth Reclamation. Cement for Full Depth Reclamation shall be paid for by the ton separately from Full Depth Reclamation. Page 457 of 625 SPECIAL PROVISIONS SPECIAL PROVISIONS 20 The quantity of lime and cement is subject to increased or decreased compensation and will be the difference between the specified theoretical quantity of lime and cement and the quantity of lime and cement used. Potholing of utilities, as required for verification of utility depths and protection of existing infrastructure, will be paid for by the lump sum potholing bid item as specified in the bid item list. Additionally, no extra compensation will be allowed for any intermittent operations, delays, or adjustments to paving activities that may arise due to the shallow depth of utilities identified through the potholing process. The contractor is responsible for planning and executing the work to minimize disruptions but will not be entitled to any compensation beyond the lump sum bid item for potholing activities. In addition, the contractor will be liable for repairing any utilities damaged during paving operations if they fail to accurately identify the location of existing utilities. DIVISION V SURFACINGS AND PAVEMENTS 39 ASPHALT CONCRETE Add to Section 39-1.0A GENERAL, Summary Contractor must phase milling and pavement operations such that public traffic is not directed to traverse milled surfaces, including remaining asphalt or base material. Contractor must submit phasing plan for review and approval. Add to Section 39-1.02B MATERIALS, Tack Coat All vertical edges and surfaces to be paved against shall be tack coated. These include, but are not limited to, curb faces, gutter lips, swale edges, cross gutter edges, and asphalt concrete edges. Replace Section 39-1.02F MATERIALS, Reclaimed Asphalt Pavement (RAP) with: Asphalt concrete with 25% RAP may be used for paving operations. Add to Section 39-1.03 HOT MIX ASPHALT DESIGN REQUIREMENTS Mix voids to be targeted at 4.0%. TSR to be minimum 70 in accordance with CTM 371. Add to Section 39-6 Payment Payment to remove and replace hot mix asphalt dike shall include full compensation for furnishing all labor, materials, tools, equipment and incidentals, and for doing all work involved in removing the existing HMA dike and replacing the dike, complete and in place, as specified in the Standard Specifications and these Special Provisions and as directed by the engineer. Page 458 of 625 SPECIAL PROVISIONS SPECIAL PROVISIONS 21 DIVISION VIII MISCELLANEOUS CONSTRUCTION 73 CONCRETE CURBS AND SIDEWALKS Add to Section 73-1.03 CONSTRUCTION You must meet with the Engineer for an average of 1.5 hours total per ramp to complete the following coordination tasks: 1. Before saw-cutting to agree on the limits of demolition and removal. 2. After formwork is set, to verify that grades meet those stated on the Plans. 3. Upon completion of new curb ramp installation to verify finished grades. Curb ramps have been designed to comply with the current Caltrans Standard Plan detail RSP A88A and City Std. 4440. Field modifications to the design plans, if approved by the Engineer, must meet the dimensional and slope requirements of Standard Plan RSP A88A. When measuring the ADA facility’s dimensions and slopes, consider the required dimension or slope to have been met if the recorded individual measurements comply with the following: • Dimensional measurement does not exceed ½-inch from the dimension shown, i.e. ½-inch less than a minimum dimension, or ½-inch greater than a maximum dimension. • Slope measurement does not exceed 0.2 percent from the slope shown. You must give the City a 24-hour notice for inspection of formwork before pouring the concrete. You must calibrate all levels used in construction at the beginning of each work day. You must ensure that new ramp flowlines do not create any "ponding" areas. You cannot saw-cut and demolish more than 2 corners at any given intersection in order to allow pedestrian travel. Curb ramp spandrel design may vary from Engineering Standards, as directed by the Engineer, in order to accommodate ramp landing. You are responsible for storing existing signs and boxes for reuse. Add to Section 73-1.04 PAYMENT As shown on the bid item list, each new Curb Ramp will be paid in lump sum for all work shown on the plans for the individual corner/section. The lump sum price includes all work shown on the Plans, as specified in the Standard Specifications and these Special Provisions. It also includes work for: 1. public notices 2. layout 3. elevation control 4. saw-cutting Page 459 of 625 SPECIAL PROVISIONS SPECIAL PROVISIONS 22 5. demolition 6. removal and disposal of demolished material 7. formwork 8. installation of ramps, driveway, sidewalk, pavers, curb and gutter. 9. furnishing and installation of new signs, post and sleeves 10. furnishing and installation of guide rail edge protection 11. temporary cold mix 12. adjustment of existing utility boxes, covers, vaults, etc. 13. removal of existing traffic signal detector boxes 14. removal of existing and installation of new traffic signal pull boxes 15. removal of existing and installation of new water meter boxes 16. removal of existing and installation of new sidewalk underdrain 17. tree protection and tree well installation 18. repair of existing irrigation systems, if damaged & modifications as needed 19. landscape replacement, if applicable 20. protection of existing utilities and restoration of existing improvements 21. protection and restoration of existing benchmarks and survey monuments 22. cleanup Payment for varying widths of “paveouts” shown on plans are included in the applicable Curb Ramp lump sum price. Remove and replace AC over PCC pavement per Eng. Std. 4110 & 6020. Full compensation for concrete cross gutters is paid on a square footage basis as shown in the bid item list and is identified as the portion of the cross gutter between gutter spandrels. “Additional Allowance Bid Items” are intended for field changes and additions to work shown on the plans. The intent of the additional items is to provide additional payment to conform specified work to existing field conditions on a per unit price basis. Sections 9 - 1.06B and 9-1.06C are waived for these bid items and you are advised that these bid items may be increased, decreased or deleted in their entirety without any additional compensation. 77 LOCAL INFRASTRUCTURE Add to Section 77-1.01 EXCAVATION AND RESTORATION, GENERAL; Protection and restoration of survey monuments and benchmarks must comply with Section 5-1.26 and 5-1.36. DIVISION IX TRAFFIC CONTROL DEVICES 84 MARKINGS Add to Section 84-2.01A GENERAL, Summary with: Traffic Striping to be applied shall be per Caltrans Revised Standard Plans 2015. Page 460 of 625 SPECIAL PROVISIONS SPECIAL PROVISIONS 23 See Section 84-2.04 of the City Standard Specifications for payment of traffic striping. Contractor shall layout all temporary and permanent striping and get approval from the Engineer prior to installing. Unless otherwise approved by the Engineer, contractor shall install temporary reflective tape to any existing crosswalks prior to opening to traffic. New crosswalk markings shall not be installed until all crosswalk warning signage and flashing beacon systems (if applicable) are installed and operational. Otherwise, temporary signage must be installed to convey “CROSSWALK CLOSED” to the satisfaction of the engineer. Replace Section 84-2.03C CONSTRUCTION, Application of Stripes and Markings with: Final Stripes and Pavement Markings must not begin before 5 calendar days and completed no later than 15 calendar days after placement of asphalt concrete. You must provide the Engineer a minimum two working day notice to review, modify and approve striping layout prior placing the final striping. Unless prior approval is obtained for the Engineer, you will be assessed Liquidated Damages in the amount of $500 per calendar day for each day’s failure to complete striping and pavement markings within this specified time. New stripes and markings must be protected from damage until completely dry. Curb markings must be paint not thermoplastic. Add to Section 84-2.04 Payment with: Bike lane buffer is measured along the linear foot and accounts for all striping and cross hatching regardless of width of buffer. Details containing white pavement markings and green pavement paint (bicycle turn box, greenback sharrow, etc.) will be paid per detail and no additional compensations will be allowed. Green bike lane markings (Case 1, 2, & 3) paid by the linear foot include bike lane symbol, green pavement coating, white markings and striping and no additional compensation will be allowed. Unless otherwise mentioned above, green bike lane coating is measured by the square foot for the area applied. Add Section 84-6 BIKE LANE MARKINGS Add Section 84-6.01 Bike Lane Coatings: Bike lane coating must be SealMaster Safe Ride (Appendix B) or City-approved equal. Page 461 of 625 SPECIAL PROVISIONS SPECIAL PROVISIONS 24 Prior to installation of green bike lane coating, the contractor shall submit a color sample and manufacturer specifications to the City for approval. Per manufacturer's specifications, SealMaster Safe Ride installation must include application of two coats minimum, with three coats provided at high traffic/wear locations (at intersection conflict areas). Replace Section 84-9.04 EXISTING MARKINGS, Payment Full compensation for work specified in Section 84 and applicable Engineering Standards is included in the payment for other bid items unless a bid item of work is shown on the Bid Item List. DIVISION X ELECTRICAL WORK 86 ELECTRICAL SYSTEMS Add Section 86-1.08 RRFB PAYMENT: As shown on the bid item list, installation of the Rapid Rectangular Flashing Beacon (RRFB) systems will be paid by Lump Sum per the limits shown on the plans at each intersection. The lump sum unit price must include furnishing and installation of all equipment needed for the operation of beacon system as shown on the plans and specified in the Standard Specifications and these Special Provisions. Unless otherwise indicated on plans, each beacon system includes, but is not limited to: 1. Solar engine kit 2. Beacon light bars 3. Battery system 4. Pushbuttons 5. Pushbutton frame and sign placards 6. Mounting hardware 7. Electrical conductors/wiring Punch posts and signage to be installed at each beacon location are included as individual bid items. DIVISION XIII APPENDICES ADD SECTION 100 APPENDICES Add Section 100-1.01 GENERAL: 1. Appendix A - Form of Agreement 2. Appendix B - SealMaster Safe Ride Data Sheet 3. Appendix C – Pavement Evaluation Report 4. Appendix D - Full Depth Reclamation Mix Design Page 462 of 625 APPENDIX APPENDIX 0 APPENDIX A - FORM OF AGREEMENT THIS AGREEMENT, made on _____________, by and between the City of San Luis Obispo, a municipal corporation and charter city, San Luis Obispo County, California (hereinafter called the Owner) and COMPANY NAME (hereinafter called the Contractor). WITNESSETH: That the Owner and the Contractor for the consideration stated herein agree as follows: ARTICLE 1, SCOPE OF WORK: The Contractor shall perform everything required to be performed, shall provide and furnish all of the labor, materials, necessary tools, expendable equipment, and all utility and transportation services required to complete all the work of construction of NAME OF PROJECT, SPEC NO. in strict compliance with the plans and specifications therefor, including any and all Addenda, adopted by the Owner, in strict compliance with the Contract Documents hereinafter enumerated. It is agreed that said labor, materials, tools, equipment, and services shall be furnished and said work performed and completed under the direction and supervision and subject to the approval of the Owner or its authorized representatives. ARTICLE II, CONTRACT PRICE: The Owner shall pay the Contractor as full consideration for the faithful performance of this Contract, subject to any additions or deductions as provided in the Contract Documents, the contract prices as follows: Item No. Item Unit of Measure Estimated Quantity Item Price (in figures) Total (in figures) 1. 2. 3. BID TOTAL: $ .00 Payments are to be made to the Contractor in compliance with and subject to the provisions embodied in the documents made a part of this Contract. Should any dispute arise respecting the true value of any work omitted, or of any extra work which the Contractor may be required to do, or respecting the size of any payment to the Contractor, during the performance of this Contract, said dispute shall be decided by the Owner and its decision shall be final, and conclusive. Page 463 of 625 APPENDIX APPENDIX 1 ARTICLE III, COMPONENT PARTS OF THIS CONTRACT: The Contract consists of the following documents, all of which are as fully a part thereof as if herein set out in full, and if not attached, as if hereto attached: 1. Notice to Bidders and Information for Bidders 2. Standard Specifications and Engineering Standards 3. Special Provisions, any Addenda, Plans and Contract Change Orders 4. Caltrans Standard Specifications and Standard Plans 2015 5. Accepted Bid and Bid Bond 6. List of Subcontractors 7. Public Contract Code Sections 10285.1 Statement 8. Public Contract Code Section 10162 Questionnaire 9. Public Contract Code Section 10232 Statement 10. Labor Code Section 1725.5 Statements 11. Bidder Acknowledgements 12. Qualifications 13. Non-collusion Declaration 14. Agreement and Bonds 15. Insurance Requirements and Forms ARTICLE IV INDEMNIFICATION: The Contractor shall indemnify, defend with legal counsel approved by City, and hold harmless City, its officers, officials, employees and volunteers from and against all liability, loss, damage, expense, cost (including without limitation reasonable legal counsel fees, expert fees and all other costs and fees of litigation) of every nature arising out of or in connection with the Contractor’s negligence, recklessness or willful misconduct in the performance of work hereunder or its failure to comply with any of its obligations contained in this Agreement, except such loss or damage which is caused by the sole or active negligence or willful misconduct of the City. Should conflict of interest principles preclude a single legal counsel from representing both the City and the Contractor, or should the City otherwise find the Contractor’s legal counsel unacceptable, then the Contractor shall reimburse the City its costs of defense, including without limitation reasonable legal counsel fees, expert fees and all other costs and fees of litigation. The Contractor shall promptly pay any final judgment rendered against the City (and its officers, officials, employees and volunteers) with respect to claims determined by a trier of fact to have been the result of the Contractor’s negligent, reckless or wrongful performance. It is expressly understood and agreed that the foregoing provisions are intended to be as broad and inclusive as is permitted by the law of the State of California and will survive termination of this Agreement. The Contractor obligations under this section apply regardless of whether such claim, charge, damage, demand, action, proceeding, loss, stop notice, cost, expense, judgment, civil fine or penalty, or liability was caused in part or contributed to by an Indemnitee. However, without affecting the rights of the City under any provision of this agreement, the Contractor shall not be required to indemnify and hold harmless the City for liability attributable to the active negligence of City, provided such active negligence is determined by agreement between the parties or by the findings of a court of competent jurisdiction. In Page 464 of 625 APPENDIX APPENDIX 2 instances where the City is shown to have been actively negligent and where the City’s active negligence accounts for only a percentage of the liability involved, the obligation of the Contractor will be for that entire portion or percentage of liability not attributable to the active negligence of the City. ARTICLE V. It is further expressly agreed by and between the parties hereto that should there be any conflict between the terms of this instrument and the bid of said Contractor, then this instrument shall control and nothing herein shall be considered as an acceptance of the said terms of said bid conflicting herewith. IN WITNESS WHEREOF, the parties to these presents have hereunto set their hands this year and date first above written. CITY OF SAN LUIS OBISPO A Municipal Corporation __________________________________ Whitney McDonald, City Manager APPROVED AS TO FORM CONTRACTOR: Name of Company ________________________________ By:________________________________ J. Christine Dietrick City Attorney Name of CAO/President Its: CAO/PRESIDENT (2nd signature required if Corporation): By:________________________________ Name of Corporate Officer Its: ____________________ Page 465 of 625 APPENDIX APPENDIX 3 APPENDIX B – SEALMASTER SAFE RIDE DATA SHEET Page 466 of 625 Page 467 of 625 Page 468 of 625 Page 469 of 625 Page 470 of 625 Page 471 of 625 Page 472 of 625 Page 473 of 625 APPENDIX APPENDIX 4 APPENDIX C – PAVEMENT EVALUATION REPORT Page 474 of 625 3$9(0(17(9$/8$7,21 6(59,&(6 for &,7<2)6$1/8,62%,632 5RDGZD\3DYLQJ3URMHFW 9DULRXV6WUHHWV Page 475 of 625 December 4, 2024 Project No. 240140 Hai Nguyen, PE City of San Luis Obispo 919 Palm Street San Luis Obispo, CA 93401-3218 Subject: Deflection Analysis for the 2025 Roadway Paving Project in the City of San Luis Obispo Dear Hai: In accordance with your request, we have completed the pavement deflection analysis for the subject project and are herein providing our findings and recommendations. INTRODUCTION Our field work consisted of deflection testing using our falling weight pavement deflection testing device in general accordance with CTM 356, coring to measure the existing pavement thickness, and a visual condition survey. This work was performed by Brett Long, Carlos Cardona, and Justin Custer of PEI’s staff. Visual evaluations were performed by Steven Holm of PEI’s engineering staff. The traffic indexes used in this analysis were provided by the City of San Luis Obispo. We have summarized our analysis on the deflection summary sheets for the street segments following this report. Included on the summary sheets is the coring data for existing pavement thickness, visual condition survey, deflection test results analysis, and rehabilitation recommendations. ANALYSIS The rehabilitation alternatives have been designed using structural requirements from the deflection analysis contained in CTM 356, reflective cracking criteria, and the visual condition survey. Reflection cracking requirements are determined as a minimum of one-half the bonded layer section per current Caltrans recommendations for reflective cracking. Engineering judgment and experience has been used in applying these criteria to the individual street segments. The rehabilitation alternatives evaluated in this analysis include HMA and RHMA overlays, milling and replacement with HMA, and Partial Depth Recycling (PDR). Reconstruction alternatives are also provided including Full Depth Reclamation (FDR), Full Depth HMA, and HMA over aggregate base. Page 476 of 625 Hai Nguyen, PE December 4, 2024 Project No. 240140 Page 2 OVERLAYS The recommended overlays must meet both the structural requirements from the deflection analysis and reflective cracking requirements. The minimum recommended overlay thickness is 1-3/4 inches to ensure that the HMA can be properly compacted. For HMA overlays, typically a HMA leveling course is recommended if pavement fabric is placed. The leveling course provides a uniform surface and fills cracks to ensure the fabric is bonded properly to the overlay. Pavement fabric is not typically recommended unless needed to reduce the overlay thickness required for reflective cracking. PEI recommends placing a leveling course under RHMA overlays. The leveling course helps provide a uniform surface for placing the RHMA to ensure the thickness of the RHMA overlay. Minimum thickness for RHMA overlays is critical for compaction. MILLING AND REPLACEMENT Milling and replacement is generally recommended when overlay requirements for reflective cracking exceed 3-1/2 inches and are structurally adequate by deflection. Overlays which exceed 3-1/2 inches are not usually feasible due to geometric constraints. Mill and replacement alternatives allow for resurfacing the pavement to match the existing profile. This alternative can also reduce the lift thickness to meet reflective cracking requirements if the pavement is structurally adequate. The expected pavement life for milling and replacing is like an overlay. Milling and replacement is a green alternative also, because asphalt suppliers use the removed asphalt in Rap (recycled asphalt pavement) mixes if fabric is not present. PEI does not recommend Milling and Replacement when the pavement is less than 5 inches thick. Construction traffic can cause significant failures in pavements that are milled and leave less than 3 inches. PARTIAL DEPTH RECYCLING (PDR) PDR is an option when pavements are structurally adequate or slightly structurally deficient. It can be especially useful when pavements are thick (greater than 6 inches). PDR helps reduce crack history in thicker pavement and provides a green approach by using existing materials. PDR consists of either an emulsion process or a foaming process. The cold foam process can include mixing aggregate base with asphalt concrete. Page 477 of 625 Hai Nguyen, PE December 4, 2024 Project No. 240140 Page 3 RECONSTRUCTION Reconstruction can consist of various alternatives including Full Depth HMA, HMA over aggregate base, or Full Depth Reclamation (FDR). Full Depth HMA is the fastest for construction but typically has higher costs than other reconstruction alternatives. FDR HMA can be a cost-effective approach but takes much longer to construct than HMA. HMA over aggregate base has a lower cost than Full Depth HMA but has significant impact on the public due to the slower construction process. FDR involves treating the existing base and soil with either cement or lime depending on the makeup of the materials. FDR is a green alternative because it uses existing materials and reduces the amount of imported materials. PROJECT ANALYSIS AND DESIGN OVERVIEW The street segments that were evaluated for this project are as follows: Location 1: x Calle Joaquin – Motel 6 to City Limits x Industrial Way – Broad Street to East End x Sacramento Drive – Via Esteban to Industrial Way Location 2: x Tank Farm Road – South Higuera to East City Limits x Tank Farm Road – West City Limits to Broad Street x Tank Farm Road – Broad Street to Righetti Ranch Road x Tank Farm Road – Righetti Ranch Road to Wavertree Street x Orcutt Road – Spanish Oaks Drive to City Limits Location 3: x Broad Street – Sweeney Lane to Tank Farm Road Location 4: x Foothill Boulevard – California Boulevard to City Limits These roadways are classified as arterials with higher design traffic indexes (9.5). Most of the R-values tested were less than 20. The recommendations for each section vary based on existing structural section thicknesses and structural requirements by deflection analysis. Page 478 of 625 Hai Nguyen, PE December 4, 2024 Project No. 240140 Page 4 PEI evaluated multiple alternatives for rehabilitating the pavements. The estimated design life of each recommended alternative is provided in the following table: Proposed Treatment Expected Service Life HMA and RHMA Overlays 7-12 years Milling and Replacement 7-12 years Partial Depth Recycling (PDR) 7-12 years Full Depth Reclamation (FDR) 15-20 years Full Depth HMA 15-20 years HMA Over Aggregate Base 15-20 years Each alternative should be evaluated by the design engineer for cost, constructability, and impact on the public during construction. The Deflection Summary Sheets following this report provide the coring data, deflection data, and visual condition evaluations used in PEI’s analysis. The recommended repair strategies have been provided for rehabilitation alternatives. Following the summary sheets are the deflection data print outs, R-values and photos. MATERIALS AND CONSTRUCTION HMA recommended for leveling courses less than 1 inch should be constructed using 3/8-inch maximum HMA or #4 mix. The leveling course should be rolled and compacted with an 8 to 12 ton pneumatic-tire roller. HMA with thicknesses of 1 to 2 inches should be constructed using 1/2-inch maximum HMA. HMA layer thicknesses greater than 2 inches can be constructed with either 1/2 or 3/4-inch maximum HMA. RHMA should be constructed with 3/8 inches maximum aggregate for overlays less than 2 inches and 1/2-inch maximum size aggregate for overlays greater than or equal to 2 inches. All HMA and RHMA work should be placed in accordance with Caltrans 2010 Section 39 using the standard process or Caltrans 2018 Section 39 that is modified for City/County work. Page 479 of 625 Page 480 of 625 CALLE JOAQUIN Motel 6 near Los Osos Valley Road to City Limits Page 481 of 625 Deflection and Structural Summary Project No. 240140 2025 Roadway Paving Project Client: City of San Luis Obispo Calle Joaquin Motel 6 (S/O Los Osos Valley Road) to City Limits (Near KSBY 6) CORING LOG STRUCTURAL REQUIREMENTS (by Deflection Analysis) REFLECTIVE CRACKING REQUIREMENTS *(Required overlay by reflective cracking is half the existing AC thickness - if pavement fabric is used then these criteria can be reduced by 1-1/4 inch with at least a minimum overlay requirement of 1-3/4 inch) VISUAL CONDITIONS The pavement exhibits block shrinkage cracking and moderate to severe alligator cracking. Numerous areas of alligator cracking have progressed to base failures in both directions. There is also some subsidence cracking along the pavement edge. Previous maintenance includes pavement repairs and slurry sealing. ANALYSIS The existing pavement consists of 5 to 6-1/2 inches of asphalt concrete over 7 to 10 inches of aggregate base. There is 4 to 5 inches of a sandy subbase underneath the aggregate base. PEI could not identify if pavement fabric was present in the asphalt concrete layer. The native soils are brown sandy clays with R-values ranging from 13 to 15. Core No. Location HMA Layer (Inches) Fabric (Yes/No) AB Layer (Inches) ASB Layer (Inches) R-value 1 SB – 470’ from COP @ Motel 6 5 No 10 4 15 2 NB – 875’ from COP @ Motel 6 6-1/2 No 8 5 --- 3 SB -- 1250’ from COP @ Motel 6 6 No 7 4 13 4 NB -- 1700’ from COP @ Motel 6 5 No 7 5 --- Direction Traffic Index (TI) Tolerable 80th Percentile HMA Overlay Requirement (Inches) NB 9.5 13.0 41.2 6-1/2 SB 9.5 13.0 35.1 5-3/4 HMA Overlay Requirement (Inches)* Pavement Fabric Required (Yes or No) 1-3/4 Yes Page 482 of 625 Deflection and Structural Summary Project No. 240140 2025 Roadway Paving Project Client: City of San Luis Obispo Based on the deflection analysis, the pavement is structurally deficient by 6-1/2 inches of HMA. For this pavement, PEI is providing recommendations for full depth reclamation (FDR) and reconstruction with Full Depth HMA or HMA over aggregate base. Overlaying with HMA and RHMA, milling and replacement and partial depth recycling (PDR) are not recommended because of structural deficiency. RECOMMENDATIONS Overlay Options Overlaying with HMA and RHMA are not recommended because of structural deficiency. Milling and Replacement Option Milling and replacement is not recommended because of structural deficiency. Partial Depth Recycling Option (PDR) Partial depth recycling (PDR) is not recommended because of structural deficiency. FDR Option We recommend uniformly pulverizing 16 inches of existing asphalt concrete, aggregate base, and native soil, removing 8 inches of pulverized material, treating the remaining pulverized material and subbase with cement to a depth of 16 inches and placing 8 inches of new HMA in 3 lifts. This recommendation is based on an unconfined compressive strength (UCS) of 300 psi. Reconstruction Options Full Depth HMA We recommend removing to a depth of 14 inches and placing 14 inches of HMA in 5 lifts. HMA over Aggregate Base We recommend removing to a depth of 23 inches, installing a SEG fabric, placing 16-1/2 inches of aggregate base and 6-1/2 inches of HMA in 2 lifts. Both reconstruction alternatives could develop unstable grade from construction traffic during the construction process. Stabilization allowances should be included if one of these alternatives is chosen. As previously discussed in the report, rehabilitation alternatives may have different anticipated service lives. The design engineer should evaluate each alternative based on cost, constructability, and impact on the public. Page 483 of 625 10/24/24 Page 1 Road: Survey Date: From: Thickness: To: Traffic Index: Lane/Line: Project Number: Deflection Data Analysis Deflection Readings (Equivalent Deflectometer Units) No. of Tests Low Mean High Std. Dev. 20 10.95 29.57 61.28 13.78 Road Surface Thickness Traffic Index 0.50 9.50 Structural Design Tolerable 80th Percentile 90th Percentile % Reduction GE Deficient 13.00 41.15 47.21 68.41 1.03 HMA Overlay 0.54 (805) 781-2265 (916) 209-8300 PAVEMENT ENGINEERING INCORPORATED City of San Luis Obispo Motel 6 (S/O Los Osos Valley Concord Redding San Luis Obispo Sacramento (877) 240-0468 (530) 224-4535 NB 10/16/24 0.50 9.50 240140 Calle Joaquin City Limits (Near KSBY 6) Page 484 of 625 10/24/24 Page 2 Road: Survey Date: From: Thickness: To: Traffic Index: Lane/Line: Project Number: Calle Joaquin City Limits (Near KSBY 6) Motel 6 (S/O Los Osos Valley NB 10/16/24 0.50 9.50 240140 PAVEMENT ENGINEERING INCORPORATED City of San Luis Obispo Concord Redding San Luis Obispo Sacram ento (877) 240-0468 (530) 224-4535 (805) 781-2265 (916) 209-8300 113' from City Limits 206' from City Limits 302' from City Limits 409' from City Limits 504' from City Limits 606' from City Limits 705' from City Limits 828' from City Limits 934' from City Limits 1039' from City Limits 1117' from City Limits 1217' from City Limits 1306' from City Limits 1420' from City Limits 1506' from City Limits 1608' from City Limits 1700' from City Limits 1801' from City Limits 1909' from City Limits 1971' from City Limits 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 0 102030405060708090100 Te s t P o i n t Deflectometer Deflection Page 485 of 625 Date: Client: Interval: Road: Survey Date: From: Thickness: To: Traffic Index: Lane/Line Project Number: Test Points DynaflectConditions Deflection Exclude 1 10.95 10.950 2 16.30 16.300 3 35.88 35.880 4 36.54 36.540 5 26.10 26.100 6 13.85 13.850 7 15.32 15.320 8 23.15 23.150 9 29.92 29.920 10 43.56 43.560 11 11.45 11.450 12 38.45 38.450 13 39.15 39.150 14 61.28 61.280 15 28.66 28.660 16 26.70 26.700 17 38.15 38.150 18 11.39 11.390 19 36.91 36.910 20 47.67 47.670 Concord (877) 240-0468 Redding (530) 224-4535 San Luis Obispo (805) 781-2265 Sacramento (916) 209-8300 10/16/24 0.50 9.50 240140 PAVEMENT ENGINEERING INCORPORATED Comments City Limits (Near KSBY 6) Motel 6 (S/O Los Osos Valley Rd) NB 10/24/2024 City of San Luis Obispo Calle Joaquin 100' 934' from City Limits 1039' from City Limits 504' from City Limits 1506' from City Limits 1608' from City Limits 409' from City Limits 705' from City Limits 1117' from City Limits 1217' from City Limits 1306' from City Limits 1420' from City Limits 828' from City Limits 113' from City Limits 206' from City Limits 302' from City Limits 1700' from City Limits 1801' from City Limits 606' from City Limits 1909' from City Limits 1971' from City Limits Page 486 of 625 10/24/24 Page 1 Road: Survey Date: From: Thickness: To: Traffic Index: Lane/Line: Project Number: Deflection Data Analysis Deflection Readings (Equivalent Deflectometer Units) No. of Tests Low Mean High Std. Dev. 20 6.12 26.26 49.89 10.55 Road Surface Thickness Traffic Index 0.50 9.50 Structural Design Tolerable 80th Percentile 90th Percentile % Reduction GE Deficient 13.00 35.12 39.76 62.99 0.91 HMA Overlay 0.48 SB 10/16/24 0.50 9.50 240140 Calle Joaquin Motel 6 (S/O Los Osos Valley (805) 781-2265 (916) 209-8300 PAVEMENT ENGINEERING INCORPORATED City of San Luis Obispo City Limits (Near KSBY 6) Concord Redding San Luis Obispo Sacramento (877) 240-0468 (530) 224-4535 Page 487 of 625 10/24/24 Page 2 Road: Survey Date: From: Thickness: To: Traffic Index: Lane/Line: Project Number: PAVEMENT ENGINEERING INCORPORATED City of San Luis Obispo Concord Redding San Luis Obispo Sacram ento (877) 240-0468 (530) 224-4535 (805) 781-2265 (916) 209-8300 Calle Joaquin Motel 6 (S/O Los Osos Valley City Limits (Near KSBY 6) SB 10/16/24 0.50 9.50 240140 117' from Motel 6 223' from Motel 6 324' from Motel 6 410' from Motel 6 522' from Motel 6 624' from Motel 6 731' from Motel 6 831' from Motel 6 903' from Motel 6 1017' from Motel 6 1137' from Motel 6 1224' from Motel 6 1320' from Motel 6 1423' from Motel 6 1511' from Motel 6 1620' from Motel 6 1718' from Motel 6 1816' from Motel 6 1898' from Motel 6 1958' from Motel 6 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 0 102030405060708090100 Te s t P o i n t Deflectometer Deflection Page 488 of 625 Date: Client: Interval: Road: Survey Date: From: Thickness: To: Traffic Index: Lane/Line Project Number: Test Points DynaflectConditions Deflection Exclude 1 23.60 23.600 2 11.52 11.520 3 27.67 27.670 4 25.35 25.350 5 40.43 40.430 6 49.89 49.890 7 41.56 41.560 8 6.12 6.120 9 15.77 15.770 10 21.83 21.830 11 26.61 26.610 12 25.95 25.950 13 17.07 17.070 14 20.16 20.160 15 32.60 32.600 16 35.15 35.150 17 35.06 35.060 18 25.04 25.040 19 21.52 21.520 20 22.39 22.390 522' from Motel 6 1511' from Motel 6 1620' from Motel 6 410' from Motel 6 731' from Motel 6 1137' from Motel 6 1224' from Motel 6 1320' from Motel 6 1423' from Motel 6 831' from Motel 6 117' from Motel 6 223' from Motel 6 324' from Motel 6 1718' from Motel 6 1816' from Motel 6 624' from Motel 6 1898' from Motel 6 1958' from Motel 6 903' from Motel 6 1017' from Motel 6 10/24/2024 City of San Luis Obispo Calle Joaquin 100' PAVEMENT ENGINEERING INCORPORATED Comments Motel 6 (S/O Los Osos Valley Rd) City Limits (Near KSBY 6) SB Concord (877) 240-0468 Redding (530) 224-4535 San Luis Obispo (805) 781-2265 Sacramento (916) 209-8300 10/16/24 0.50 9.50 240140 Page 489 of 625 Laboratory No.:L244050 Project No.:240140 Sample Date:November 20, 2024 Report Date:November 27, 2024 Client:City of San Luis Obispo Project Name:Pavement Evaluation Services for 2025 Roadway Paving Project Sample Description:Brown Sandy Clay Sample Location:C1, Calle Joaquin Specimen No. 1 2 3 Moisture Content (%) 17.0 18.0 18.5 Dry Density (PCF) 120.4 118.7 117.7 Resistance Value (R) 24 10 0 Exudation Pressure (PSI) 389 259 157 Expansion Pressure 87 39 0 17.0 RESISTANCE VALUE AT 300 P.S.I. 15 Reviewed By: Materials Engineer Brandon Rodebaugh RESISTANCE (R) VALUE TEST ASTM D 2844 As Received Moisture Content (%) 0 10 20 30 40 50 60 70 80 90 100 0100200300400500600700800 Re s i s t a n c e V a l u e Exudation Pressure (P.S.I.) Resistance Value Test 300 P.S.I. Page 490 of 625 Laboratory No.:L244050 Project No.:240140 Sample Date:November 20, 2024 Report Date:November 27, 2024 Client:City of San Luis Obispo Project Name:Pavement Evaluation Services for 2025 Roadway Paving Project Sample Description:Brown Sandy Clay Sample Location:C3, Calle Joaquin Specimen No. 1 2 3 Moisture Content (%) 19.2 18.2 19.8 Dry Density (PCF) 115.7 118.1 115.2 Resistance Value (R) 10 22 0 Exudation Pressure (PSI) 266 405 164 Expansion Pressure 43 87 0 19.2 RESISTANCE VALUE AT 300 P.S.I. 13 Reviewed By: Materials Engineer Brandon Rodebaugh RESISTANCE (R) VALUE TEST ASTM D 2844 As Received Moisture Content (%) 0 10 20 30 40 50 60 70 80 90 100 0100200300400500600700800 Re s i s t a n c e V a l u e Exudation Pressure (P.S.I.) Resistance Value Test 300 P.S.I. Page 491 of 625 Calle Joaquin @ COP by Motel 6 looking North Photo 1 Calle Joaquin @ COP by Motel 6 looking South Photo 2 Page 492 of 625 Calle Joaquin @ 700’ S/O COP looking North Photo 3 Calle Joaquin @ 700’ S/O COP looking South Photo 4 Page 493 of 625 Calle Joaquin @ 500’ N/O KSBY looking North Photo 5 Calle Joaquin @ 500’ N/O KSBY looking South Photo 6 Page 494 of 625 Calle Joaquin @ KSBY looking North Photo 7 Calle Joaquin @ KSBY looking South Photo  Page 495 of 625 ORCUTT ROAD Spanish Oaks Drive to City Limits Page 496 of 625 Deflection and Structural Summary Project No. 240140 2025 Roadway Paving Project Client: City of San Luis Obispo Orcutt Road Spanish Oaks Drive to East City Limits CORING LOG STRUCTURAL REQUIREMENTS (by Deflection Analysis) REFLECTIVE CRACKING REQUIREMENTS *(Required overlay by reflective cracking is half the existing AC thickness - if pavement fabric is used then these criteria can be reduced by 1-1/4 inch with at least a minimum overlay requirement of 1-3/4 inch) VISUAL CONDITIONS The pavement exhibits moderate block shrinkage cracking and alligator cracking. Some areas of alligator cracking have progressed to base failures, predominantly in the travel lanes. The Southbound lane appears to be in worse condition. Previous maintenance includes pavement repairs. Core No. Location HMA Layer (Inches) Fabric (Yes/No) Treated Base Layer (inches) AB Layer (Inches) R-value 1 EB – 425’ from Spanish Oaks 6 No 15 7 --- 2 WB –760’ from Spanish Oaks 5 No 9 14 --- 3 EB –1250’ from Spanish Oaks 4 No 8 14 --- 4 WB –1575’ from Spanish Oaks 6 No 0 16 18 Direction Traffic Index (TI) Tolerable 80th Percentile HMA Overlay Requirement (Inches) EB 9.5 13.0 13.0 0 WB 9.5 13.0 10.6 0 HMA Overlay Requirement (Inches)* Pavement Fabric Required (Yes or No) 5-1/4 Yes Page 497 of 625 Deflection and Structural Summary Project No. 240140 2025 Roadway Paving Project Client: City of San Luis Obispo ANALYSIS The existing pavement consists of 4 to 6 inches of asphalt concrete, 0 to 15 inches of treated base, and 7 to 16 inches of aggregate base. PEI could not identify if pavement fabric was present in the asphalt concrete layer. The native soil is brown sandy clay with an R-value of 18. Based on the deflection analysis, the pavement is structurally adequate. For this pavement, PEI is providing recommendations for milling and replacement, partial depth recycling (PDR), full depth reclamation (FDR) and reconstruction with Full Depth HMA or HMA over aggregate base. Overlaying is not recommended because of the high reflective cracking requirement. RECOMMENDATIONS Overlay Options Overlaying is not recommended because of the high reflective cracking requirement. Milling and Replacement Option HMA We recommend milling off 3-1/2 inches of the existing pavement, 10-inch pavement repairs of base failures, placing a 1-inch HMA leveling course, pavement fabric, and a 2-1/2-inch HMA overlay. RHMA We recommend milling off 2 inches of the existing pavement, 6-inch pavement repairs of base failures and placing a 2-inch RHMA overlay. This alternative may leave thinner asphalt in some areas. An allowance should be included for additional pavement repairs since construction traffic may cause failure in the thinner remaining asphalt layer. Partial Depth Recycling Option (PDR) We recommend partial depth recycling to a depth of 3-1/2 inches and placing a 2-1/2-inch HMA or RHMA overlay. FDR Option We recommend uniformly pulverizing 16 inches of existing asphalt concrete, aggregate base, and native soil, removing 7-1/2 inches of pulverized material, treating the remaining pulverized material and native soil with cement/lime to a depth of 14-1/2 inches and placing 7-1/2 inches of new HMA in 3 lifts. This recommendation is based on an unconfined compressive strength (UCS) of 300 psi. *** ***Careful consideration should be given when recommending FDR for this section because of the existing treated layer. Page 498 of 625 Deflection and Structural Summary Project No. 240140 2025 Roadway Paving Project Client: City of San Luis Obispo Reconstruction Options Full Depth HMA We recommend removing to a depth of 14 inches and placing 14 inches of HMA in 5 lifts. HMA over Aggregate Base We recommend removing to a depth of 23 inches, installing a SEG fabric, placing 16-1/2 inches of aggregate base and 6-1/2 inches of HMA in 2 lifts. Both reconstruction alternatives could develop unstable grade from construction traffic during the construction process. Stabilization allowances should be included if one of these alternatives is chosen. As previously discussed in the report, rehabilitation alternatives may have different anticipated service lives. The design engineer should evaluate each alternative based on cost, constructability, and impact on the public. Page 499 of 625 10/24/24 Page 1 Road: Survey Date: From: Thickness: To: Traffic Index: Lane/Line: Project Number: Deflection Data Analysis Deflection Readings (Equivalent Deflectometer Units) No. of Tests Low Mean High Std. Dev. 18 3.85 8.93 19.99 4.85 Road Surface Thickness Traffic Index 0.50 9.50 Structural Design Tolerable 80th Percentile 90th Percentile % Reduction GE Deficient 13.00 13.00 15.14 0.03 0.00 HMA Overlay 0.00 EB 10/16/24 0.50 9.50 240140 Orcutt Road Spanish Oaks Drive (805) 781-2265 (916) 209-8300 PAVEMENT ENGINEERING INCORPORATED City of San Luis Obispo East City Limits Concord Redding San Luis Obispo Sacramento (877) 240-0468 (530) 224-4535 Page 500 of 625 10/24/24 Page 2 Road: Survey Date: From: Thickness: To: Traffic Index: Lane/Line: Project Number: PAVEMENT ENGINEERING INCORPORATED City of San Luis Obispo Concord Redding San Luis Obispo Sacram ento (877) 240-0468 (530) 224-4535 (805) 781-2265 (916) 209-8300 Orcutt Road Spanish Oaks Drive East City Limits EB 10/16/24 0.50 9.50 240140 137' from Spanish Oaks Drive 207' from Spanish Oaks Drive 326' from Spanish Oaks Drive 424' from Spanish Oaks Drive 534' from Spanish Oaks Drive 632' from Spanish Oaks Drive 723' from Spanish Oaks Drive 826' from Spanish Oaks Drive 913' from Spanish Oaks Drive 1021' from Spanish Oaks Drive 1134' from Spanish Oaks Drive 1248' from Spanish Oaks Drive 1318' from Spanish Oaks Drive 1419' from Spanish Oaks Drive 1539' from Spanish Oaks Drive 1625' from Spanish Oaks Drive 1806' from Spanish Oaks Drive 1822' from Spanish Oaks Drive 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 0 102030405060708090100 Te s t P o i n t Deflectometer Deflection Page 501 of 625 Date: Client: Interval: Road: Survey Date: From: Thickness: To: Traffic Index: Lane/Line Project Number: Test Points DynaflectConditions Deflection Exclude 1 3.85 3.850 2 4.03 4.030 3 5.03 5.030 4 4.02 4.020 5 9.66 9.660 6 8.05 8.050 7 4.54 4.540 8 5.06 5.060 9 4.41 4.410 10 7.81 7.810 11 13.34 13.340 12 6.94 6.940 13 11.25 11.250 14 10.29 10.290 15 19.99 19.990 16 17.59 17.590 17 13.32 13.320 18 11.52 11.520 534' from Spanish Oaks Drive 1539' from Spanish Oaks Drive 1625' from Spanish Oaks Drive 424' from Spanish Oaks Drive 723' from Spanish Oaks Drive 1134' from Spanish Oaks Drive 1248' from Spanish Oaks Drive 1318' from Spanish Oaks Drive 1419' from Spanish Oaks Drive 826' from Spanish Oaks Drive 137' from Spanish Oaks Drive 207' from Spanish Oaks Drive 326' from Spanish Oaks Drive 1806' from Spanish Oaks Drive 1822' from Spanish Oaks Drive 632' from Spanish Oaks Drive 913' from Spanish Oaks Drive 1021' from Spanish Oaks Drive 10/24/2024 City of San Luis Obispo Orcutt Road 100' PAVEMENT ENGINEERING INCORPORATED Comments Spanish Oaks Drive East City Limits EB Concord (877) 240-0468 Redding (530) 224-4535 San Luis Obispo (805) 781-2265 Sacramento (916) 209-8300 10/16/24 0.50 9.50 240140 Page 502 of 625 10/24/24 Page 1 Road: Survey Date: From: Thickness: To: Traffic Index: Lane/Line: Project Number: Deflection Data Analysis Deflection Readings (Equivalent Deflectometer Units) No. of Tests Low Mean High Std. Dev. 18 3.44 7.70 14.96 3.42 Road Surface Thickness Traffic Index 0.50 9.50 Structural Design Tolerable 80th Percentile 90th Percentile % Reduction GE Deficient 13.00 10.57 12.08 0.00 0.00 HMA Overlay 0.00 WB 10/16/24 0.50 9.50 240140 Orcutt Road East City Limits (805) 781-2265 (916) 209-8300 PAVEMENT ENGINEERING INCORPORATED City of San Luis Obispo Spanish Oaks Drive Concord Redding San Luis Obispo Sacramento (877) 240-0468 (530) 224-4535 Page 503 of 625 10/24/24 Page 2 Road: Survey Date: From: Thickness: To: Traffic Index: Lane/Line: Project Number: PAVEMENT ENGINEERING INCORPORATED City of San Luis Obispo Concord Redding San Luis Obispo Sacram ento (877) 240-0468 (530) 224-4535 (805) 781-2265 (916) 209-8300 Orcutt Road East City Limits Spanish Oaks Drive WB 10/16/24 0.50 9.50 240140 108' from East City Limits 234' from East City Limits 312' from East City Limits 402' from East City Limits 500' from East City Limits 623' from East City Limits 718' from East City Limits 815' from East City Limits 913' from East City Limits 1014' from East City Limits 1093' from East City Limits 1211' from East City Limits 1333' from East City Limits 1436' from East City Limits 1538' from East City Limits 1627' from East City Limits 1703' from East City Limits 1806' from East City Limits 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 0 102030405060708090100 Te s t P o i n t Deflectometer Deflection Page 504 of 625 Date: Client: Interval: Road: Survey Date: From: Thickness: To: Traffic Index: Lane/Line Project Number: Test Points DynaflectConditions Deflection Exclude 1 12.70 12.700 2 12.05 12.050 3 14.96 14.960 4 13.19 13.190 5 8.63 8.630 6 8.47 8.470 7 7.11 7.110 8 5.35 5.350 9 6.61 6.610 10 4.89 4.890 11 6.33 6.330 12 4.65 4.650 13 6.44 6.440 14 5.86 5.860 15 4.69 4.690 16 4.31 4.310 17 3.44 3.440 18 8.85 8.850 500' from East City Limits 1538' from East City Limits 1627' from East City Limits 402' from East City Limits 718' from East City Limits 1093' from East City Limits 1211' from East City Limits 1333' from East City Limits 1436' from East City Limits 815' from East City Limits 108' from East City Limits 234' from East City Limits 312' from East City Limits 1703' from East City Limits 1806' from East City Limits 623' from East City Limits 913' from East City Limits 1014' from East City Limits 10/24/2024 City of San Luis Obispo Orcutt Road 100' PAVEMENT ENGINEERING INCORPORATED Comments East City Limits Spanish Oaks Drive WB Concord (877) 240-0468 Redding (530) 224-4535 San Luis Obispo (805) 781-2265 Sacramento (916) 209-8300 10/16/24 0.50 9.50 240140 Page 505 of 625 Laboratory No.:L243996 Project No.:240140 Sample Date:November 13, 2024 Report Date:November 21, 2024 Client:City of San Luis Obispo Project Name:Pavement Evaluation Services for 2025 Roadway Paving Project Sample Description:Brown Sandy Clay Sample Location:C4, Orcutt Road Specimen No. 1 2 3 Moisture Content (%) 15.5 16.5 17.0 Dry Density (PCF) 120.6 118.6 118.0 Resistance Value (R) 28 14 1 Exudation Pressure (PSI) 405 265 164 Expansion Pressure 87 43 0 15.5 RESISTANCE VALUE AT 300 P.S.I. 18 Reviewed By: Materials Engineer Brandon Rodebaugh RESISTANCE (R) VALUE TEST ASTM D 2844 As Received Moisture Content (%) 0 10 20 30 40 50 60 70 80 90 100 0100200300400500600700800 Re s i s t a n c e V a l u e Exudation Pressure (P.S.I.) Resistance Value Test 300 P.S.I. Page 506 of 625 Orcutt Road @ East City Limits (COP) looking South Photo 1 Orcutt Road @ East City Limits looking North Photo 2 Page 507 of 625 Orcutt Road @ 1,035’ N/O East City Limits looking South Photo 3 Orcutt Road @ 1,035’ N/O East City Limits looking North Photo 4 Page 508 of 625 Orcutt Road @ Spanish Oaks Drive looking South Photo 5 Orcutt Road @ Spanish Oaks Drive looking North Photo 6 Page 509 of 625 SACRAMENTO DRIVE Via Esteban to Industrial Way Page 510 of 625 Deflection and Structural Summary Project No. 240140 2025 Roadway Paving Project Client: City of San Luis Obispo Sacramento Drive Via Esteban to Industrial Way CORING LOG STRUCTURAL REQUIREMENTS (by Deflection Analysis) REFLECTIVE CRACKING REQUIREMENTS *(Required overlay by reflective cracking is half the existing AC thickness - if pavement fabric is used then these criteria can be reduced by 1-1/4 inch with at least a minimum overlay requirement of 1-3/4 inch) VISUAL CONDITIONS The pavement exhibits moderate block shrinkage cracking and moderate to severe alligator cracking. Several areas of alligator cracking have progressed to base failure, predominantly in the travel lanes. The cracking is more severe in the Northbound lane. Previous pavement maintenance includes pavement repairs and crack sealing. Core No. Location HMA Layer (Inches) Fabric (Yes/No) AB Layer (Inches) R-value 1 NB – 450’ from Industrial Way 8-1/2 No 0 19 2 SB – 750’ from Industrial Way 7-3/4 No 0 - 3 NB – 1,300’ from Industrial Way 8-1/2 No 0 19 4 SB – 750’ from Industrial Way 7 No 0 - 5 NB – 2,100’ from Industrial Way 3-1/4 No 13 17 Direction Traffic Index (TI) Tolerable 80th Percentile HMA Overlay Requirement (Inches) NB 9.5 13.0 29.0 4-3/4 SB 9.5 13.0 18.3 1-1/2 HMA Overlay Requirement (Inches)* Pavement Fabric Required (Yes or No) 2-3/4 Yes Page 511 of 625 Deflection and Structural Summary Project No. 240140 2025 Roadway Paving Project Client: City of San Luis Obispo ANALYSIS The existing pavement consists of 3-1/4 to 8-1/2 inches of asphalt concrete over 0 to 13 inches of aggregate base. PEI could not identify if pavement fabric was present in the asphalt concrete layer. The native soils are brown sandy clays with R-values ranging from 17 to 19. Based on the deflection analysis, the pavement is structurally deficient by 4-3/4 inches of HMA in the Northbound lane. For this pavement, PEI is providing recommendations for full depth reclamation (FDR) and reconstruction with Full Depth HMA or HMA over aggregate base. Overlaying, milling and replacement, and partial depth recycling (PDR) are not recommended because of structural deficiency. RECOMMENDATIONS Overlaying is not recommended because of structural deficiency. Milling and Replacement Option Milling and replacement is not recommended because of structural deficiency. Partial Depth Recycling Option (PDR) Partial depth recycling (PDR) is not recommended because of structural deficiency. FDR Option We recommend uniformly pulverizing 16 inches of existing asphalt concrete, aggregate base, and native soil, removing 7-1/2 inches of pulverized material, treating the remaining pulverized material and native soil with cement/lime to a depth of 14-1/2 inches and placing 7-1/2 inches of new HMA in 3 lifts. This recommendation is based on an unconfined compressive strength (UCS) of 300 psi. Reconstruction Options Full Depth HMA We recommend removing to a depth of 13-1/2 inches and placing 13-1/2 inches of HMA in 5 lifts. HMA over Aggregate Base We recommend removing to a depth of 23 inches, installing a SEG fabric, placing 16-1/2 inches of aggregate base and 6-1/2 inches of HMA in 2 lifts. Both reconstruction alternatives could develop unstable grade from construction traffic during the construction process. Stabilization allowances should be included if one of these alternatives is chosen. Page 512 of 625 Deflection and Structural Summary Project No. 240140 2025 Roadway Paving Project Client: City of San Luis Obispo As previously discussed in the report, rehabilitation alternatives may have different anticipated service lives. The design engineer should evaluate each alternative based on cost, constructability, and impact on the public. Page 513 of 625 10/24/24 Page 1 Road: Survey Date: From: Thickness: To: Traffic Index: Lane/Line: Project Number: Deflection Data Analysis Deflection Readings (Equivalent Deflectometer Units) No. of Tests Low Mean High Std. Dev. 25 2.19 19.11 45.94 11.81 Road Surface Thickness Traffic Index 0.58 9.50 Structural Design Tolerable 80th Percentile 90th Percentile % Reduction GE Deficient 13.00 29.03 34.23 55.22 0.75 HMA Overlay 0.39 NB 10/16/24 0.58 9.50 240140 Sacramento Drive Industrial Way (805) 781-2265 (916) 209-8300 PAVEMENT ENGINEERING INCORPORATED City of San Luis Obispo Via Esteban Concord Redding San Luis Obispo Sacramento (877) 240-0468 (530) 224-4535 Page 514 of 625 10/24/24 Page 2 Road: Survey Date: From: Thickness: To: Traffic Index: Lane/Line: Project Number: PAVEMENT ENGINEERING INCORPORATED City of San Luis Obispo Concord Redding San Luis Obispo Sacram ento (877) 240-0468 (530) 224-4535 (805) 781-2265 (916) 209-8300 Sacramento Drive Industrial Way Via Esteban NB 10/16/24 0.58 9.50 240140 110' from Industrial Way 218' from Industrial Way 323' from Industrial Way 409' from Industrial Way 518' from Industrial Way 620' from Industrial Way 706' from Industrial Way 817' from Industrial Way 915' from Industrial Way 1025' from Industrial Way 1129' from Industrial Way 1215' from Industrial Way 1307' from Industrial Way 1407' from Industrial Way 1514' from Industrial Way 1626' from Industrial Way 1716' from Industrial Way 1811' from Industrial Way 1915' from Industrial Way 2017' from Industrial Way 2139' from Industrial Way 2212' from Industrial Way 2316' from Industrial Way 2413' from Industrial Way 2482' from Industrial Way 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 0 102030405060708090100 Te s t P o i n t Deflectometer Deflection Page 515 of 625 Date: Client: Interval: Road: Survey Date: From: Thickness: To: Traffic Index: Lane/Line Project Number: Test Points DynaflectConditions Deflection Exclude 1 8.11 8.110 2 15.62 15.620 3 31.09 31.090 4 45.94 45.940 5 8.83 8.830 6 9.32 9.320 7 16.61 16.610 8 25.06 25.060 9 16.42 16.420 10 18.62 18.620 11 14.06 14.060 12 14.49 14.490 13 2.19 2.190 14 15.64 15.640 15 8.44 8.440 16 6.67 6.670 17 8.22 8.220 18 36.05 36.050 19 37.48 37.480 20 29.80 29.800 21 14.37 14.370 22 4.89 4.890 23 33.62 33.620 24 32.22 32.220 25 24.00 24.000 518' from Industrial Way 2212' from Industrial Way 1514' from Industrial Way 1626' from Industrial Way 409' from Industrial Way 706' from Industrial Way 1129' from Industrial Way 1215' from Industrial Way 1307' from Industrial Way 1407' from Industrial Way 817' from Industrial Way 110' from Industrial Way 218' from Industrial Way 323' from Industrial Way 1716' from Industrial Way 1811' from Industrial Way 620' from Industrial Way 1915' from Industrial Way 2017' from Industrial Way 2139' from Industrial Way 2316' from Industrial Way 2413' from Industrial Way 2482' from Industrial Way 915' from Industrial Way 1025' from Industrial Way 10/24/2024 City of San Luis Obispo Sacramento Drive 100' PAVEMENT ENGINEERING INCORPORATED Comments Industrial Way Via Esteban NB Concord (877) 240-0468 Redding (530) 224-4535 San Luis Obispo (805) 781-2265 Sacramento (916) 209-8300 10/16/24 0.58 9.50 240140 Page 516 of 625 10/24/24 Page 1 Road: Survey Date: From: Thickness: To: Traffic Index: Lane/Line: Project Number: Deflection Data Analysis Deflection Readings (Equivalent Deflectometer Units) No. of Tests Low Mean High Std. Dev. 24 5.66 13.22 32.70 6.03 Road Surface Thickness Traffic Index 0.58 9.50 Structural Design Tolerable 80th Percentile 90th Percentile % Reduction GE Deficient 13.00 18.28 20.94 28.89 0.22 HMA Overlay 0.12 (805) 781-2265 (916) 209-8300 PAVEMENT ENGINEERING INCORPORATED City of San Luis Obispo Industrial Way Concord Redding San Luis Obispo Sacramento (877) 240-0468 (530) 224-4535 SB 10/16/24 0.58 9.50 240140 Sacramento Drive Via Esteban Page 517 of 625 10/24/24 Page 2 Road: Survey Date: From: Thickness: To: Traffic Index: Lane/Line: Project Number: Sacramento Drive Via Esteban Industrial Way SB 10/16/24 0.58 9.50 240140 PAVEMENT ENGINEERING INCORPORATED City of San Luis Obispo Concord Redding San Luis Obispo Sacram ento (877) 240-0468 (530) 224-4535 (805) 781-2265 (916) 209-8300 118' from Via Esteban 235' from Via Esteban 309' from Via Esteban 424' from Via Esteban 530' from Via Esteban 617' from Via Esteban 718' from Via Esteban 826' from Via Esteban 908' from Via Esteban 1021' from Via Esteban 1142' from Via Esteban 1233' from Via Esteban 1319' from Via Esteban 1433' from Via Esteban 1514' from Via Esteban 1612' from Via Esteban 1724' from Via Esteban 1822' from Via Esteban 1923' from Via Esteban 2011' from Via Esteban 2115' from Via Esteban 2208' from Via Esteban 2320' from Via Esteban 2416' from Via Esteban 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 0 102030405060708090100 Te s t P o i n t Deflectometer Deflection Page 518 of 625 Date: Client: Interval: Road: Survey Date: From: Thickness: To: Traffic Index: Lane/Line Project Number: Test Points DynaflectConditions Deflection Exclude 1 17.38 17.380 2 7.15 7.150 3 21.56 21.560 4 16.67 16.670 5 17.63 17.630 6 13.26 13.260 7 10.86 10.860 8 12.80 12.800 9 15.54 15.540 10 12.54 12.540 11 8.09 8.090 12 8.48 8.480 13 10.67 10.670 14 7.17 7.170 15 11.72 11.720 16 20.38 20.380 17 14.98 14.980 18 15.25 15.250 19 32.70 32.700 20 11.18 11.180 21 10.94 10.940 22 8.04 8.040 23 6.54 6.540 24 5.66 5.660 Concord (877) 240-0468 Redding (530) 224-4535 San Luis Obispo (805) 781-2265 Sacramento (916) 209-8300 10/16/24 0.58 9.50 240140 PAVEMENT ENGINEERING INCORPORATED Comments Via Esteban Industrial Way SB 10/24/2024 City of San Luis Obispo Sacramento Drive 100' 2320' from Via Esteban 2416' from Via Esteban 908' from Via Esteban 1021' from Via Esteban 530' from Via Esteban 2208' from Via Esteban 1514' from Via Esteban 1612' from Via Esteban 424' from Via Esteban 718' from Via Esteban 1142' from Via Esteban 1233' from Via Esteban 1319' from Via Esteban 1433' from Via Esteban 826' from Via Esteban 118' from Via Esteban 235' from Via Esteban 309' from Via Esteban 1724' from Via Esteban 1822' from Via Esteban 617' from Via Esteban 1923' from Via Esteban 2011' from Via Esteban 2115' from Via Esteban Page 519 of 625 Laboratory No.:L243740 Project No.:240140 Sample Date:October 23, 2024 Report Date:November 4, 2024 Client:City of San Luis Obispo Project Name:Pavement Evaluation Services for 2025 Roadway Paving Project Sample Description:Brown Sandy Clay Sample Location:C1, Sacramento Drive Specimen No. 1 2 3 Moisture Content (%) 16.8 17.8 18.3 Dry Density (PCF) 118.5 117.4 116.1 Resistance Value (R) 30 15 2 Exudation Pressure (PSI) 406 265 165 Expansion Pressure 87 43 0 16.8 RESISTANCE VALUE AT 300 P.S.I. 19 Reviewed By: Materials Engineer Brandon Rodebaugh RESISTANCE (R) VALUE TEST ASTM D 2844 As Received Moisture Content (%) 0 10 20 30 40 50 60 70 80 90 100 0100200300400500600700800 Re s i s t a n c e V a l u e Exudation Pressure (P.S.I.) Resistance Value Test 300 P.S.I. Page 520 of 625 Laboratory No.:L243740 Project No.:240140 Sample Date:October 23, 2024 Report Date:November 4, 2024 Client:City of San Luis Obispo Project Name:Pavement Evaluation Services for 2025 Roadway Paving Project Sample Description:Brown Sandy Clay Sample Location:C3, Sacramento Drive Specimen No. 1 2 3 Moisture Content (%) 17.8 18.9 19.4 Dry Density (PCF) 118.6 116.8 115.6 Resistance Value (R) 31 14 1 Exudation Pressure (PSI) 389 260 160 Expansion Pressure 87 43 0 17.8 RESISTANCE VALUE AT 300 P.S.I. 19 Reviewed By: Materials Engineer Brandon Rodebaugh RESISTANCE (R) VALUE TEST ASTM D 2844 As Received Moisture Content (%) 0 10 20 30 40 50 60 70 80 90 100 0100200300400500600700800 Re s i s t a n c e V a l u e Exudation Pressure (P.S.I.) Resistance Value Test 300 P.S.I. Page 521 of 625 Laboratory No.:L243740 Project No.:240140 Sample Date:October 23, 2024 Report Date:November 4, 2024 Client:City of San Luis Obispo Project Name:Pavement Evaluation Services for 2025 Roadway Paving Project Sample Description:Brown Sandy Clay Sample Location:C5, Sacramento Drive Specimen No. 1 2 3 Moisture Content (%) 17.4 18.4 18.9 Dry Density (PCF) 119.3 117.3 116.3 Resistance Value (R) 28 14 1 Exudation Pressure (PSI) 408 270 168 Expansion Pressure 87 48 0 17.4 RESISTANCE VALUE AT 300 P.S.I. 17 Reviewed By: Materials Engineer Brandon Rodebaugh RESISTANCE (R) VALUE TEST ASTM D 2844 As Received Moisture Content (%) 0 10 20 30 40 50 60 70 80 90 100 0100200300400500600700800 Re s i s t a n c e V a l u e Exudation Pressure (P.S.I.) Resistance Value Test 300 P.S.I. Page 522 of 625 Sacramento Drive @ Via Esteban looking North Photo 1 Sacramento Drive @ Via Esteban looking South Photo  Page 523 of 625 Sacramento Drive @ Capitolio Way looking North Photo  Sacramento Drive @ Capitolio Way looking South Photo  Page 524 of 625 Sacramento Drive @ Ricardo Court looking North Photo  Sacramento Drive @ Ricard Court looking South Photo  Page 525 of 625 Sacramento Drive @ UPS Facility looking North Photo  Sacramento Drive @ UPS Facility looking South Photo  Page 526 of 625 Sacramento Drive @ Industrial Way looking North Photo  Sacramento Drive @ Industrial Way looking South Photo 1 Page 527 of 625 TANK FARM ROAD South Higuera Street to City Limits and City Limits to Wavertree Street Page 528 of 625 Deflection and Structural Summary Project No. 240140 2025 Roadway Paving Project Client: City of San Luis Obispo Tank Farm Road South Higuera Street to East City Limits CORING LOG STRUCTURAL REQUIREMENTS (by Deflection Analysis) REFLECTIVE CRACKING REQUIREMENTS *(Required overlay by reflective cracking is half the existing AC thickness - if pavement fabric is used then these criteria can be reduced by 1-1/4 inch with at least a minimum overlay requirement of 1-3/4 inch) Core No. Location HMA Layer (Inches) Fabric (Yes/No) AB Layer (Inches) R-value 1 WB2 – 440’ from East City Limits 4-1/4 N 22+ - 2 WB1 – 780’ from East City Limits 5 N 18 - 3 WB2 – 1300’ from East City Limits 7 N 16 20 4 WB1 – 1690’ from East City Limits 5 N 11 9 5 EB2 – 415’ from South Higuera Street 4-1/4 N 15 - 6 EB1 – 850’ from South Higuera Street 6 N 14 - 7 EB2 – 1250’ from South Higuera Street 4-1/2 N 10 - 8 EB1 – 1700’ from South Higuera Street 10 N 3 - Direction Traffic Index (TI) Tolerable 80th Percentile HMA Overlay Requirement (Inches) EB1 9.5 13.0 18.2 1-1/2 EB2 9.5 15.0 15.4 0 WB1 9.5 15.0 17.2 1/4 WB2 9.5 14.0 22.1 2-1/4 HMA Overlay Requirement (Inches)* Pavement Fabric Required (Yes or No) 1-3/4 Yes Page 529 of 625 Deflection and Structural Summary Project No. 240140 2025 Roadway Paving Project Client: City of San Luis Obispo VISUAL CONDITIONS Pavement exhibits slight block shrinkage cracking and moderate to severe alligator cracking. Some areas of alligator cracking have progressed to base failure. The segment between Old Windmill Lane and Innovation Way appears to have been paved within the last 5 years and pavement exhibits slight longitudinal cracking. Previous maintenance includes pavement repairs and crack sealing. ANALYSIS The existing pavement consists of 4-1/4 to 10 inches of asphalt concrete over 3 to 22+ inches of aggregate base. PEI could not identify if pavement fabric was present in the asphalt concrete layer. The native soil is a brown silty clay with R-values ranging from 9 to 20. Based on the deflection analysis, the pavement is structurally deficient by 2-1/4 inches of HMA. For this pavement, PEI is providing recommendations for overlaying with HMA and RHMA, full depth reclamation (FDR) and reconstruction with Full Depth HMA or HMA over aggregate base. Milling and replacement and partial depth recycling (PDR) are not recommended because of the structural deficiency. RECOMMENDATIONS Overlay Options HMA We recommend 6-inch pavement repairs of base failures, placing a 1/2-inch HMA leveling course, pavement fabric and placing a 1-3/4-inch HMA overlay. RHMA We recommend 6-inch pavement repairs of base failures, placing a 1/2-inch HMA leveling course and a 1-3/4-inch RHMA overlay. The pavement should be evaluated for the base failures present. If the amount of base failure exceeds 10%, then placing overlays may not be cost effective. Milling and Replacement Option Milling and replacement is not recommended because of structural deficiency. Partial Depth Recycling Option (PDR) Partial Depth Recycling (PDR) is not recommended because of structural deficiency. FDR Option We recommend uniformly pulverizing 16 inches of existing asphalt concrete, aggregate base, and native soil, removing 8-1/2 inches of pulverized material, treating the remaining pulverized material and native soil with cement/lime to a depth of 16 inches and placing 8-1/2 inches of Page 530 of 625 Deflection and Structural Summary Project No. 240140 2025 Roadway Paving Project Client: City of San Luis Obispo new HMA in 3 lifts. This recommendation is based on an unconfined compressive strength (UCS) of 300 psi. Reconstruction Options Full Depth HMA We recommend removing to a depth of 14 inches and placing 14 inches of HMA in 5 lifts. HMA over Aggregate Base We recommend removing to a depth of 23 inches, installing a SEG fabric, placing 16-1/2 inches of aggregate base and 6-1/2 inches of HMA in 2 lifts. Both reconstruction alternatives could develop unstable grade from construction traffic during the construction process. Stabilization allowances should be included if one of these alternatives is chosen. As previously discussed in the report, rehabilitation alternatives may have different anticipated service lives. The design engineer should evaluate each alternative based on cost, constructability, and impact on the public. Page 531 of 625 10/24/24 Page 1 Road: Survey Date: From: Thickness: To: Traffic Index: Lane/Line: Project Number: Deflection Data Analysis Deflection Readings (Equivalent Deflectometer Units) No. of Tests Low Mean High Std. Dev. 19 4.46 10.61 45.46 9.08 Road Surface Thickness Traffic Index 0.67 9.50 Structural Design Tolerable 80th Percentile 90th Percentile % Reduction GE Deficient 13.00 18.24 22.23 28.72 0.22 HMA Overlay 0.12 (805) 781-2265 (916) 209-8300 PAVEMENT ENGINEERING INCORPORATED City of San Luis Obispo East City Limits Concord Redding San Luis Obispo Sacramento (877) 240-0468 (530) 224-4535 EB1 10/16/24 0.67 9.50 240140 Tank Farm Road South Higuera Street Page 532 of 625 10/24/24 Page 2 Road: Survey Date: From: Thickness: To: Traffic Index: Lane/Line: Project Number: Tank Farm Road South Higuera Street East City Limits EB1 10/16/24 0.67 9.50 240140 PAVEMENT ENGINEERING INCORPORATED City of San Luis Obispo Concord Redding San Luis Obispo Sacram ento (877) 240-0468 (530) 224-4535 (805) 781-2265 (916) 209-8300 149' from South Higuera 226' from South Higuera 304' from South Higuera 416' from South Higuera 513' from South Higuera 627' from South Higuera 668' from South Higuera 818' from South Higuera 910' from South Higuera 1014' from South Higuera 1114' from South Higuera 1213' from South Higuera 1330' from South Higuera 1432' from South Higuera 1517' from South Higuera 1610' from South Higuera 1691' from South Higuera 1816' from South Higuera 1917' from South Higuera 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 0 102030405060708090100 Te s t P o i n t Deflectometer Deflection Page 533 of 625 Date: Client: Interval: Road: Survey Date: From: Thickness: To: Traffic Index: Lane/Line Project Number: Test Points DynaflectConditions Deflection Exclude 1 5.82 5.820 2 6.26 6.260 3 7.04 7.040 4 4.68 4.680 5 5.63 5.630 6 4.46 4.460 7 6.24 6.240 8 11.60 11.600 9 12.57 12.570 10 6.64 6.640 11 45.46 45.460 12 17.68 17.680 13 10.09 10.090 14 12.89 12.890 15 9.06 9.060 16 8.96 8.960 17 10.20 10.200 18 6.51 6.510 19 9.77 9.770 Concord (877) 240-0468 Redding (530) 224-4535 San Luis Obispo (805) 781-2265 Sacramento (916) 209-8300 10/16/24 0.67 9.50 240140 PAVEMENT ENGINEERING INCORPORATED Comments South Higuera Street East City Limits EB1 10/24/2024 City of San Luis Obispo Tank Farm Road 100' 910' from South Higuera Street 1014' from South Higuera Street 513' from South Higuera Street 1517' from South Higuera Street 1610' from South Higuera Street 416' from South Higuera Street 668' from South Higuera Street 1114' from South Higuera Street 1213' from South Higuera Street 1330' from South Higuera Street 1432' from South Higuera Street 818' from South Higuera Street 149' from South Higuera Street 226' from South Higuera Street 304' from South Higuera Street 1691' from South Higuera Street 1816' from South Higuera Street 627' from South Higuera Street 1917' from South Higuera Street Page 534 of 625 10/24/24 Page 1 Road: Survey Date: From: Thickness: To: Traffic Index: Lane/Line: Project Number: Deflection Data Analysis Deflection Readings (Equivalent Deflectometer Units) No. of Tests Low Mean High Std. Dev. 14 8.54 12.98 16.98 2.89 Road Surface Thickness Traffic Index 0.38 9.50 Structural Design Tolerable 80th Percentile 90th Percentile % Reduction GE Deficient 15.00 15.40 16.67 2.61 0.01 HMA Overlay 0.01 (805) 781-2265 (916) 209-8300 PAVEMENT ENGINEERING INCORPORATED City of San Luis Obispo East City Limits Concord Redding San Luis Obispo Sacramento (877) 240-0468 (530) 224-4535 EB2 10/16/24 0.38 9.50 240140 Tank Farm Road South Higuera Street Page 535 of 625 10/24/24 Page 2 Road: Survey Date: From: Thickness: To: Traffic Index: Lane/Line: Project Number: Tank Farm Road South Higuera Street East City Limits EB2 10/16/24 0.38 9.50 240140 PAVEMENT ENGINEERING INCORPORATED City of San Luis Obispo Concord Redding San Luis Obispo Sacram ento (877) 240-0468 (530) 224-4535 (805) 781-2265 (916) 209-8300 100' from South Higuera 218' from South Higuera 316' from South Higuera 418' from South Higuera 526' from South Higuera 526' from South Higuera 604' from South Higuera 762' from South Higuera 842' from South Higuera 918' from South Higuera 1013' from South Higuera 1118' from South Higuera 1208' from South Higuera 1294' from South Higuera 1 2 3 4 5 6 7 8 9 10 11 12 13 14 0 102030405060708090100 Te s t P o i n t Deflectometer Deflection Page 536 of 625 Date: Client: Interval: Road: Survey Date: From: Thickness: To: Traffic Index: Lane/Line Project Number: Test Points DynaflectConditions Deflection Exclude 1 11.39 11.390 2 13.31 13.310 3 16.98 16.980 4 16.64 16.640 5 10.16 10.160 6 10.17 10.170 7 8.54 8.540 8 12.32 12.320 9 13.44 13.440 10 10.43 10.430 11 10.74 10.740 12 16.70 16.700 13 14.24 14.240 14 16.61 16.610 Concord (877) 240-0468 Redding (530) 224-4535 San Luis Obispo (805) 781-2265 Sacramento (916) 209-8300 10/16/24 0.38 9.50 240140 PAVEMENT ENGINEERING INCORPORATED Comments South Higuera Street East City Limits EB2 10/24/2024 City of San Luis Obispo Tank Farm Road 100' 842' from South Higuera Street 918' from South Higuera Street 526' from South Higuera Street 418' from South Higuera Street 604' from South Higuera Street 1013' from South Higuera Street 1118' from South Higuera Street 1208' from South Higuera Street 1294' from South Higuera Street 762' from South Higuera Street 100' from South Higuera Street 218' from South Higuera Street 316' from South Higuera Street 526' from South Higuera Street Page 537 of 625 10/24/24 Page 1 Road: Survey Date: From: Thickness: To: Traffic Index: Lane/Line: Project Number: Deflection Data Analysis Deflection Readings (Equivalent Deflectometer Units) No. of Tests Low Mean High Std. Dev. 19 6.77 13.03 25.39 4.93 Road Surface Thickness Traffic Index 0.42 9.50 Structural Design Tolerable 80th Percentile 90th Percentile % Reduction GE Deficient 15.00 17.18 19.35 12.67 0.05 HMA Overlay 0.03 WB1 10/16/24 0.42 9.50 240140 Tank Farm Road East City Limits (805) 781-2265 (916) 209-8300 PAVEMENT ENGINEERING INCORPORATED City of San Luis Obispo South Higuera Street Concord Redding San Luis Obispo Sacramento (877) 240-0468 (530) 224-4535 Page 538 of 625 10/24/24 Page 2 Road: Survey Date: From: Thickness: To: Traffic Index: Lane/Line: Project Number: PAVEMENT ENGINEERING INCORPORATED City of San Luis Obispo Concord Redding San Luis Obispo Sacram ento (877) 240-0468 (530) 224-4535 (805) 781-2265 (916) 209-8300 Tank Farm Road East City Limits South Higuera Street WB1 10/16/24 0.42 9.50 240140 122' from East City Limits 216' from East City Limits 329' from East City Limits 429' from East City Limits 525' from East City Limits 630' from East City Limits 728' from East City Limits 817' from East City Limits 924' from East City Limits 1020' from East City Limits 1122' from East City Limits 1213' from East City Limits 1360' from East City Limits 1432' from East City Limits 1518' from East City Limits 1628' from East City Limits 1746' from East City Limits 1817' from East City Limits 1895' from East City Limits 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 0 102030405060708090100 Te s t P o i n t Deflectometer Deflection Page 539 of 625 Date: Client: Interval: Road: Survey Date: From: Thickness: To: Traffic Index: Lane/Line Project Number: Test Points DynaflectConditions Deflection Exclude 1 8.05 8.050 2 12.41 12.410 3 12.77 12.770 4 13.35 13.350 5 14.02 14.020 6 25.39 25.390 7 13.87 13.870 8 12.11 12.110 9 6.77 6.770 10 8.69 8.690 11 10.17 10.170 12 10.97 10.970 13 9.62 9.620 14 8.83 8.830 15 9.60 9.600 16 11.88 11.880 17 17.10 17.100 18 20.25 20.250 19 21.75 21.750 525' from East City Limits 1518' from East City Limits 1628' from East City Limits 429' from East City Limits 728' from East City Limits 1122' from East City Limits 1213' from East City Limits 1360' from East City Limits 1432' from East City Limits 817' from East City Limits 122' from East City Limits 216' from East City Limits 329' from East City Limits 1746' from East City Limits 1817' from East City Limits 630' from East City Limits 1895' from East City Limits 924' from East City Limits 1020' from East City Limits 10/24/2024 City of San Luis Obispo Tank Farm Road 100' PAVEMENT ENGINEERING INCORPORATED Comments East City Limits South Higuera Street WB1 Concord (877) 240-0468 Redding (530) 224-4535 San Luis Obispo (805) 781-2265 Sacramento (916) 209-8300 10/16/24 0.42 9.50 240140 Page 540 of 625 10/24/24 Page 1 Road: Survey Date: From: Thickness: To: Traffic Index: Lane/Line: Project Number: Deflection Data Analysis Deflection Readings (Equivalent Deflectometer Units) No. of Tests Low Mean High Std. Dev. 19 7.23 16.64 28.68 6.44 Road Surface Thickness Traffic Index 0.47 9.50 Structural Design Tolerable 80th Percentile 90th Percentile % Reduction GE Deficient 14.00 22.05 24.88 36.50 0.36 HMA Overlay 0.19 WB2 10/16/24 0.47 9.50 240140 Tank Farm Road East City Limits (805) 781-2265 (916) 209-8300 PAVEMENT ENGINEERING INCORPORATED City of San Luis Obispo South Higuera Street Concord Redding San Luis Obispo Sacramento (877) 240-0468 (530) 224-4535 Page 541 of 625 10/24/24 Page 2 Road: Survey Date: From: Thickness: To: Traffic Index: Lane/Line: Project Number: PAVEMENT ENGINEERING INCORPORATED City of San Luis Obispo Concord Redding San Luis Obispo Sacram ento (877) 240-0468 (530) 224-4535 (805) 781-2265 (916) 209-8300 Tank Farm Road East City Limits South Higuera Street WB2 10/16/24 0.47 9.50 240140 103' from East City Limits 219' from East City Limits 373' from East City Limits 414' from East City Limits 514' from East City Limits 622' from East City Limits 731' from East City Limits 826' from East City Limits 920' from East City Limits 1012' from East City Limits 1114' from East City Limits 1197' from East City Limits 1352' from East City Limits 1430' from East City Limits 1523' from East City Limits 1623' from East City Limits 1716' from East City Limits 1808' from East City Limits 1864' from East City Limits 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 0 102030405060708090100 Te s t P o i n t Deflectometer Deflection Page 542 of 625 Date: Client: Interval: Road: Survey Date: From: Thickness: To: Traffic Index: Lane/Line Project Number: Test Points DynaflectConditions Deflection Exclude 1 8.82 8.820 2 10.32 10.320 3 21.94 21.940 4 12.33 12.330 5 10.46 10.460 6 13.39 13.390 7 18.94 18.940 8 21.12 21.120 9 22.59 22.590 10 19.34 19.340 11 28.68 28.680 12 25.39 25.390 13 22.14 22.140 14 21.74 21.740 15 11.43 11.430 16 18.92 18.920 17 13.07 13.070 18 7.23 7.230 19 8.22 8.220 514' from East City Limits 1523' from East City Limits 1623' from East City Limits 414' from East City Limits 731' from East City Limits 1114' from East City Limits 1197' from East City Limits 1352' from East City Limits 1430' from East City Limits 826' from East City Limits 103' from East City Limits 219' from East City Limits 373' from East City Limits 1716' from East City Limits 1808' from East City Limits 622' from East City Limits 1864' from East City Limits 920' from East City Limits 1012' from East City Limits 10/24/2024 City of San Luis Obispo Tank Farm Road 100' PAVEMENT ENGINEERING INCORPORATED Comments East City Limits South Higuera Street WB2 Concord (877) 240-0468 Redding (530) 224-4535 San Luis Obispo (805) 781-2265 Sacramento (916) 209-8300 10/16/24 0.47 9.50 240140 Page 543 of 625 Laboratory No.:L243752 Project No.:240140 Sample Date:October 23, 2024 Report Date:November 5, 2024 Client:City of San Luis Obispo Project Name:Pavement Evaluation Services for 2025 Roadway Paving Project Sample Description:Brown Sandy Clay Sample Location:C3, Tank Farm Specimen No. 1 2 3 Moisture Content (%) 14.4 15.4 15.9 Dry Density (PCF) 121.3 119.4 118.0 Resistance Value (R) 32 15 1 Exudation Pressure (PSI) 404 264 164 Expansion Pressure 87 39 0 14.4 RESISTANCE VALUE AT 300 P.S.I. 20 Reviewed By: Materials Engineer Brandon Rodebaugh RESISTANCE (R) VALUE TEST ASTM D 2844 As Received Moisture Content (%) 0 10 20 30 40 50 60 70 80 90 100 0100200300400500600700800 Re s i s t a n c e V a l u e Exudation Pressure (P.S.I.) Resistance Value Test 300 P.S.I. Page 544 of 625 Laboratory No.:L243714 Project No.:240140 Sample Date:October 23, 2024 Report Date:November 1, 2024 Client:City of San Luis Obispo Project Name:Pavement Evaluation Services for 2025 Roadway Paving Project Sample Description:Brown Clay Sample Location:C4, Tank Farm Specimen No. 1 2 3 Moisture Content (%) 18.2 19.2 19.8 Dry Density (PCF) 113.0 110.6 109.7 Resistance Value (R) 18 6 0 Exudation Pressure (PSI) 396 261 159 Expansion Pressure 91 48 0 18.2 RESISTANCE VALUE AT 300 P.S.I. 9 Reviewed By: Materials Engineer Brandon Rodebaugh RESISTANCE (R) VALUE TEST ASTM D 2844 As Received Moisture Content (%) 0 10 20 30 40 50 60 70 80 90 100 0100200300400500600700800 Re s i s t a n c e V a l u e Exudation Pressure (P.S.I.) Resistance Value Test 300 P.S.I. Page 545 of 625 Deflection and Structural Summary Project No. 240140 2025 Roadway Paving Project Client: City of San Luis Obispo Tank Farm Road West City Limits to Broad Street CORING LOG STRUCTURAL REQUIREMENTS (by Deflection Analysis) REFLECTIVE CRACKING REQUIREMENTS *(Required overlay by reflective cracking is half the existing AC thickness - if pavement fabric is used then these criteria can be reduced by 1-1/4 inch with at least a minimum overlay requirement of 1-3/4 inch) Core No. Location HMA Layer (Inches) Fabric (Yes/No) AB Layer (Inches) R-value 9 EB1 – 450’ from West City Limits 7-1/2 No 19 - 10 EB2 – 850’ from West City Limits 6 No 13 12 11 EB1 – 1300’ from West City Limits 7 No 7 - 12 EB2 – 1800’ from West City Limits 6 No 8 22 13 WB1 – 475’ from Broad Street 9-1/2 No 6 - 14 WB1 – 1550’ from Broad Street 8 No 0 - Direction Traffic Index (TI) Tolerable 80th Percentile HMA Overlay Requirement (Inches) EB1 9.5 13.0 15.3 1/2 EB2 9.5 13.0 17.7 1-1/4 WB 9.5 13.0 16.0 3/4 HMA Overlay Requirement (Inches)* Pavement Fabric Required (Yes or No) 2-1/4 Yes Page 546 of 625 Deflection and Structural Summary Project No. 240140 2025 Roadway Paving Project Client: City of San Luis Obispo VISUAL CONDITIONS Pavement exhibits slight block shrinkage cracking and moderate to severe alligator cracking. Some areas of alligator cracking have progressed to base failure. The Eastbound direction appears to be in worse condition than the Westbound direction. Previous maintenance includes pavement repairs. ANALYSIS The existing pavement consists of 6 to 9-1/2 inches of asphalt concrete over 0 to 19 inches of aggregate base. PEI could not identify if pavement fabric was present in the asphalt concrete layer. The native soils are brown silty clays with R-values ranging from 12 to 22. Based on the deflection analysis, the pavement is structurally deficient by 1-1/4 inches of HMA. For this pavement, PEI is providing recommendations for overlaying with HMA and RHMA, milling and replacement, Partial depth recycling (PDR), full depth reclamation (FDR) and reconstruction with Full Depth HMA or HMA over aggregate base. RECOMMENDATIONS Overlay Options HMA We recommend 8-inch pavement repairs of base failures, placing a 3/4-inch HMA leveling course, pavement fabric and placing a 1-3/4-inch HMA overlay. RHMA We recommend 8-inch pavement repairs of base failures, placing a 1/2-inch HMA leveling course and a 1-3/4-inch RHMA overlay. The pavement should be evaluated for the base failures present. If the amount of base failure exceeds 10%, then placing overlays may not be cost effective. Milling and Replacement Option HMA We recommend milling off 2-1/2 inches of the existing pavement, 7-inch pavement repairs of base failures and placing a 2-1/2-inch HMA overlay. RHMA We recommend milling off 2-1/2 inches of the existing pavement, 7-inch pavement repairs of base failures and placing a 2-1/2-inch RHMA overlay. Partial Depth Recycling Option (PDR) We recommend partial depth recycling to a depth of 3 inches, 5-inch pavement repairs of base failures, and placing a 2-1/2-inch HMA or RHMA overlay. Page 547 of 625 Deflection and Structural Summary Project No. 240140 2025 Roadway Paving Project Client: City of San Luis Obispo FDR Option We recommend uniformly pulverizing 16 inches of existing asphalt concrete, aggregate base, and native soil, removing 8 inches of pulverized material, treating the remaining pulverized material and native soil with cement/lime to a depth of 16 inches and placing 8 inches of new HMA in 3 lifts. This recommendation is based on an unconfined compressive strength (UCS) of 300 psi. Reconstruction Options Full Depth HMA We recommend removing to a depth of 14 inches and placing 14 inches of HMA in 5 lifts. HMA over Aggregate Base We recommend removing to a depth of 23 inches, installing a SEG fabric, placing 16-1/2 inches of aggregate base and 6-1/2 inches of HMA in 2 lifts. Both reconstruction alternatives could develop unstable grade from construction traffic during the construction process. Stabilization allowances should be included if one of these alternatives is chosen. As previously discussed in the report, rehabilitation alternatives may have different anticipated service lives. The design engineer should evaluate each alternative based on cost, constructability, and impact on the public. Page 548 of 625 Deflection and Structural Summary Project No. 240140 2025 Roadway Paving Project Client: City of San Luis Obispo Tank Farm Road Broad Street to Righetti Ranch Road CORING LOG STRUCTURAL REQUIREMENTS (by Deflection Analysis) Core No. Location HMA Layer (Inches) Fabric (Yes/No) AB Layer (Inches) R-value 31 WB2 – 420’ from Righetti Ranch Road 3-1/4 No 17 19 32 WB1 – 1000’ from Righetti Ranch Road 5 No 12 - 33 WB2 – 14500’ from Righetti Ranch Road 7 No 13 14 34 WB1 – 2000’ from Righetti Ranch Road 6 No 11 - 35 WB2 – 2350’ from Righetti Ranch Road 6 No 10 19 36 WB1 – 2800’ from Righetti Ranch Road 5-1/2 No 10-1/2 - 37 EB2 – 440’ from Righetti Ranch Road 4-1/2 No 9 - 38 EB1 – 950’ from Righetti Ranch Road 4-1/4 No 12 - 39 EB2 – 1500’ from Righetti Ranch Road 5-1/4 No 15 - 40 EB1 – 1960’ from Righetti Ranch Road 4 No 13 - 41 EB1 – 2600’ from Righetti Ranch Road 3 No 15 - Direction Traffic Index (TI) Tolerable 80th Percentile HMA Overlay Requirement (Inches) EB1 9.5 17.0 22.8 1-1/4 EB2 9.5 15.0 17.6 1/2 WB1 9.5 14.0 20.3 1-3/4 WB2 9.5 14.0 18.7 1-1/4 Page 549 of 625 Deflection and Structural Summary Project No. 240140 2025 Roadway Paving Project Client: City of San Luis Obispo REFLECTIVE CRACKING REQUIREMENTS *(Required overlay by reflective cracking is half the existing AC thickness - if pavement fabric is used then these criteria can be reduced by 1-1/4 inch with at least a minimum overlay requirement of 1-3/4 inch) VISUAL CONDITIONS Pavement exhibits block shrinkage cracking and moderate to severe alligator cracking. Some areas of alligator cracking have progressed to base failure. Previous maintenance includes pavement repairs. ANALYSIS The existing pavement consists of 3 to 7 inches of asphalt concrete over 9 to 17 inches of aggregate base. PEI could not identify if pavement fabric was present in the asphalt concrete layer. The native soils are brown sandy clays with R-values ranging from 14 to 19. Based on the deflection analysis, the pavement is structurally deficient by 1-3/4 inches of HMA. For this pavement, PEI is providing recommendations for overlaying with HMA and RHMA, full depth reclamation (FDR) and reconstruction with Full Depth HMA or HMA over aggregate base. Milling and replacement and partial depth recycling (PDR) are not recommended because of the thinner existing asphalt concrete layer and structural deficiency. RECOMMENDATIONS Overlay Options HMA We recommend 6-inch pavement repairs of base failures and placing a 2-1/2-inch HMA overlay. RHMA We recommend 6-inch pavement repairs of base failures, placing a 1/2-inch HMA leveling course and a 1-3/4-inch RHMA overlay. The pavement should be evaluated for the base failures present. If the amount of base failure exceeds 10%, then placing overlays may not be cost effective. Milling and Replacement Option Milling and replacement is not recommended because of the thinner existing pavement layer and structural deficiency. Partial Depth Recycling Option (PDR) Partial Depth Recycling (PDR) is not recommended because of structural deficiency. HMA Overlay Requirement (Inches)* Pavement Fabric Required (Yes or No) 1-3/4 Yes Page 550 of 625 Deflection and Structural Summary Project No. 240140 2025 Roadway Paving Project Client: City of San Luis Obispo FDR Option We recommend uniformly pulverizing 16 inches of existing asphalt concrete, aggregate base, and native soil, removing 8 inches of pulverized material, treating the remaining pulverized material and native soil with cement/lime to a depth of 15 inches and placing 8 inches of new HMA in 3 lifts. This recommendation is based on an unconfined compressive strength (UCS) of 300 psi. Reconstruction Options Full Depth HMA We recommend removing to a depth of 13-1/2 inches and placing 13-1/2 inches of HMA in 5 lifts. HMA over Aggregate Base We recommend removing to a depth of 23 inches, installing a SEG fabric, placing 16-1/2 inches of aggregate base and 6-1/2 inches of HMA in 2 lifts. Both reconstruction alternatives could develop unstable grade from construction traffic during the construction process. Stabilization allowances should be included if one of these alternatives is chosen. As previously discussed in the report, rehabilitation alternatives may have different anticipated service lives. The design engineer should evaluate each alternative based on cost, constructability, and impact on the public. Page 551 of 625 Deflection and Structural Summary Project No. 240140 2025 Roadway Paving Project Client: City of San Luis Obispo Tank Farm Road Righetti Ranch Road to Wavertree Street CORING LOG STRUCTURAL REQUIREMENTS (by Deflection Analysis) REFLECTIVE CRACKING REQUIREMENTS *(Required overlay by reflective cracking is half the existing AC thickness - if pavement fabric is used then these criteria can be reduced by 1-1/4 inch with at least a minimum overlay requirement of 1-3/4 inch) VISUAL CONDITIONS Pavement exhibits block shrinkage cracking and moderate to severe alligator cracking. Some areas of alligator cracking have progressed to base failure. Previous maintenance includes pavement repairs. ANALYSIS The existing pavement consists of 3 to 4 inches of asphalt concrete over 14 to 17-1/2 inches of aggregate base. PEI could not identify if pavement fabric was present in the asphalt concrete layer. The native soils are brown sandy clays with R-values ranging from 16 to 17. Core No. Location HMA Layer (Inches) Fabric (Yes/No) AB Layer (Inches) R-value 20 WB – 300’ from Wavertree Street 3 N 15 16 21 EB – 600’ from Wavertree Street 3-1/4 N 17-1/2 - 22 WB – 1100’ from Wavertree Street 4 N 14 17 23 EB – 1600’ from Wavertree Street 3-1/2 N 16-1/2 - Direction Traffic Index (TI) Tolerable 80th Percentile HMA Overlay Requirement (Inches) EB 9.5 18.0 21.4 1/2 WB 9.5 17.0 24.9 1-3/4 HMA Overlay Requirement (Inches)* Pavement Fabric Required (Yes or No) 2 No Page 552 of 625 Deflection and Structural Summary Project No. 240140 2025 Roadway Paving Project Client: City of San Luis Obispo Based on the deflection analysis, the pavement is structurally adequate. For this pavement, PEI is providing recommendations for overlaying with HMA and RHMA, full depth reclamation (FDR) and reconstruction with Full Depth HMA or HMA over aggregate base. Milling and replacement and partial depth recycling (PDR) are not recommended because of thinner existing asphalt concrete layer and structural deficiency. RECOMMENDATIONS Overlay Options HMA We recommend 4-inch pavement repairs of base failures and placing a 2-inch HMA overlay. RHMA We recommend 4-inch pavement repairs of base failures, placing a 1/2-inch HMA leveling course and a 1-3/4-inch RHMA overlay. The pavement should be evaluated for the base failures present. If the amount of base failure exceeds 10%, then placing overlays may not be cost effective. Milling and Replacement Option Milling and replacement is not recommended because of the thinner existing asphalt concrete layer and structural deficiency. Partial Depth Recycling Option (PDR) Partial depth recycling (PDR) is not recommended because of structural deficiency. FDR Option We recommend uniformly pulverizing 16 inches of existing asphalt concrete, aggregate base, and native soil, removing 7-1/2 inches of pulverized material, treating the remaining pulverized material and native soil with cement/lime to a depth of 14-1/2 inches and placing 7-1/2 inches of new HMA in 3 lifts. This recommendation is based on an unconfined compressive strength (UCS) of 300 psi. Reconstruction Options Full Depth HMA We recommend removing to a depth of 13-1/2 inches and placing 13-1/2 inches of HMA in 5 lifts. HMA over Aggregate Base We recommend removing to a depth of 23 inches, installing a SEG fabric, placing 16-1/2 inches of aggregate base and 6-1/2 inches of HMA in 2 lifts. Page 553 of 625 Deflection and Structural Summary Project No. 240140 2025 Roadway Paving Project Client: City of San Luis Obispo Both reconstruction alternatives could develop unstable grade from construction traffic during the construction process. Stabilization allowances should be included if one of these alternatives is chosen. As previously discussed in the report, rehabilitation alternatives may have different anticipated service lives. The design engineer should evaluate each alternative based on cost, constructability, and impact on the public. Page 554 of 625 10/24/24 Page 1 Road: Survey Date: From: Thickness: To: Traffic Index: Lane/Line: Project Number: Deflection Data Analysis Deflection Readings (Equivalent Deflectometer Units) No. of Tests Low Mean High Std. Dev. 19 2.50 9.93 21.41 6.42 Road Surface Thickness Traffic Index 0.60 9.50 Structural Design Tolerable 80th Percentile 90th Percentile % Reduction GE Deficient 13.00 15.32 18.15 15.16 0.07 HMA Overlay 0.04 EB1 10/16/24 0.60 9.50 240140 Tank Farm Road West City Limits (805) 781-2265 (916) 209-8300 PAVEMENT ENGINEERING INCORPORATED City of San Luis Obispo Broad Street Concord Redding San Luis Obispo Sacramento (877) 240-0468 (530) 224-4535 Page 555 of 625 10/24/24 Page 2 Road: Survey Date: From: Thickness: To: Traffic Index: Lane/Line: Project Number: PAVEMENT ENGINEERING INCORPORATED City of San Luis Obispo Concord Redding San Luis Obispo Sacram ento (877) 240-0468 (530) 224-4535 (805) 781-2265 (916) 209-8300 Tank Farm Road West City Limits Broad Street EB1 10/16/24 0.60 9.50 240140 125' from West City Limits 226' from West City Limits 326' from West City Limits 424' from West City Limits 501' from West City Limits 642' from West City Limits 729' from West City Limits 817' from West City Limits 940' from West City Limits 1026' from West City Limits 1140' from West City Limits 1216' from West City Limits 1325' from West City Limits 1445' from West City Limits 1526' from West City Limits 1644' from West City Limits 1706' from West City Limits 1809' from West City Limits 1857' from West City Limits 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 0 102030405060708090100 Te s t P o i n t Deflectometer Deflection Page 556 of 625 Date: Client: Interval: Road: Survey Date: From: Thickness: To: Traffic Index: Lane/Line Project Number: Test Points DynaflectConditions Deflection Exclude 1 3.83 3.830 2 7.60 7.600 3 8.10 8.100 4 8.87 8.870 5 6.13 6.130 6 2.50 2.500 7 3.36 3.360 8 7.94 7.940 9 2.83 2.830 10 5.19 5.190 11 4.79 4.790 12 14.19 14.190 13 20.55 20.550 14 14.86 14.860 15 20.40 20.400 16 21.41 21.410 17 18.68 18.680 18 7.63 7.630 19 9.83 9.830 501' from West City Limits 1526' from West City Limits 1644' from West City Limits 424' from West City Limits 729' from West City Limits 1140' from West City Limits 1216' from West City Limits 1325' from West City Limits 1445' from West City Limits 817' from West City Limits 125' from West City Limits 226' from West City Limits 326' from West City Limits 1706' from West City Limits 1809' from West City Limits 642' from West City Limits 1857' from West City Limits 940' from West City Limits 1026' from West City Limits 10/24/2024 City of San Luis Obispo Tank Farm Road 100' PAVEMENT ENGINEERING INCORPORATED Comments West City Limits Broad Street EB1 Concord (877) 240-0468 Redding (530) 224-4535 San Luis Obispo (805) 781-2265 Sacramento (916) 209-8300 10/16/24 0.60 9.50 240140 Page 557 of 625 10/24/24 Page 1 Road: Survey Date: From: Thickness: To: Traffic Index: Lane/Line: Project Number: Deflection Data Analysis Deflection Readings (Equivalent Deflectometer Units) No. of Tests Low Mean High Std. Dev. 12 7.68 14.01 21.72 4.39 Road Surface Thickness Traffic Index 0.50 9.50 Structural Design Tolerable 80th Percentile 90th Percentile % Reduction GE Deficient 13.00 17.70 19.63 26.54 0.20 HMA Overlay 0.11 EB2 10/16/24 0.50 9.50 240140 Tank Farm Road West City Limits (805) 781-2265 (916) 209-8300 PAVEMENT ENGINEERING INCORPORATED City of San Luis Obispo Broad Street Concord Redding San Luis Obispo Sacramento (877) 240-0468 (530) 224-4535 Page 558 of 625 10/24/24 Page 2 Road: Survey Date: From: Thickness: To: Traffic Index: Lane/Line: Project Number: PAVEMENT ENGINEERING INCORPORATED City of San Luis Obispo Concord Redding San Luis Obispo Sacram ento (877) 240-0468 (530) 224-4535 (805) 781-2265 (916) 209-8300 Tank Farm Road West City Limits Broad Street EB2 10/16/24 0.50 9.50 240140 830' from West City Limits 908' from West City Limits 1017' from West City Limits 1105' from West City Limits 1230' from West City Limits 1310' from West City Limits 1420' from West City Limits 1534' from West City Limits 1633' from West City Limits 1728' from West City Limits 1816' from West City Limits 1903' from West City Limits 1 2 3 4 5 6 7 8 9 10 11 12 0 102030405060708090100 Te s t P o i n t Deflectometer Deflection Page 559 of 625 Date: Client: Interval: Road: Survey Date: From: Thickness: To: Traffic Index: Lane/Line Project Number: Test Points DynaflectConditions Deflection Exclude 1 20.82 20.820 2 7.68 7.680 3 8.87 8.870 4 16.71 16.710 5 16.79 16.790 6 21.72 21.720 7 10.27 10.270 8 14.04 14.040 9 14.22 14.220 10 13.02 13.020 11 12.87 12.870 12 11.06 11.060 1230' from West City Limits 1105' from West City Limits 1420' from West City Limits 1816' from West City Limits 1903' from West City Limits 1534' from West City Limits 830' from West City Limits 908' from West City Limits 1017' from West City Limits 1310' from West City Limits 1633' from West City Limits 1728' from West City Limits 10/24/2024 City of San Luis Obispo Tank Farm Road 100' PAVEMENT ENGINEERING INCORPORATED Comments West City Limits Broad Street EB2 Concord (877) 240-0468 Redding (530) 224-4535 San Luis Obispo (805) 781-2265 Sacramento (916) 209-8300 10/16/24 0.50 9.50 240140 Page 560 of 625 10/24/24 Page 1 Road: Survey Date: From: Thickness: To: Traffic Index: Lane/Line: Project Number: Deflection Data Analysis Deflection Readings (Equivalent Deflectometer Units) No. of Tests Low Mean High Std. Dev. 29 6.18 17.90 35.48 5.85 Road Surface Thickness Traffic Index 0.31 9.50 Structural Design Tolerable 80th Percentile 90th Percentile % Reduction GE Deficient 17.00 22.82 25.40 25.51 0.18 HMA Overlay 0.09 (805) 781-2265 (916) 209-8300 PAVEMENT ENGINEERING INCORPORATED City of San Luis Obispo Righetti Ranch Road Concord Redding San Luis Obispo Sacramento (877) 240-0468 (530) 224-4535 EB1 10/16/24 0.31 9.50 240140 Tank Farm Road Broad Street Page 561 of 625 10/24/24 Page 2 Road: Survey Date: From: Thickness: To: Traffic Index: Lane/Line: Project Number: Tank Farm Road Broad Street Righetti Ranch Road EB1 10/16/24 0.31 9.50 240140 PAVEMENT ENGINEERING INCORPORATED City of San Luis Obispo Concord Redding San Luis Obispo Sacram ento (877) 240-0468 (530) 224-4535 (805) 781-2265 (916) 209-8300 135' from Broad Street 247' from Broad Street 317' from Broad Street 404' from Broad Street 512' from Broad Street 617' from Broad Street 713' from Broad Street 764' from Broad Street 902' from Broad Street 1011' from Broad Street 1125' from Broad Street 1225' from Broad Street 1389' from Broad Street 1413' from Broad Street 1531' from Broad Street 1629' from Broad Street 1761' from Broad Street 1853' from Broad Street 1939' from Broad Street 2025' from Broad Street 2138' from Broad Street 2228' from Broad Street 2333' from Broad Street 2448' from Broad Street 2533' from Broad Street 2626' from Broad Street 2708' from Broad Street 2827' from Broad Street 2920' from Broad Street 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 0 102030405060708090100 Te s t P o i n t Deflectometer Deflection Page 562 of 625 Date: Client: Interval: Road: Survey Date: From: Thickness: To: Traffic Index: Lane/Line Project Number: Test Points DynaflectConditions Deflection Exclude 1 18.83 18.830 2 13.60 13.600 3 6.18 6.180 4 17.41 17.410 5 17.40 17.400 6 19.81 19.810 7 11.95 11.950 8 22.65 22.650 9 15.96 15.960 10 24.36 24.360 11 23.34 23.340 12 16.24 16.240 13 15.11 15.110 14 18.33 18.330 15 13.09 13.090 16 15.39 15.390 17 12.41 12.410 18 18.87 18.870 19 18.45 18.450 20 24.28 24.280 21 15.04 15.040 22 12.86 12.860 23 13.68 13.680 24 15.48 15.480 25 21.62 21.620 26 30.01 30.010 27 35.48 35.480 28 18.57 18.570 29 12.81 12.810 Concord (877) 240-0468 Redding (530) 224-4535 San Luis Obispo (805) 781-2265 Sacramento (916) 209-8300 10/16/24 0.31 9.50 240140 PAVEMENT ENGINEERING INCORPORATED Comments Broad Street Righetti Ranch Road EB1 10/24/2024 City of San Luis Obispo Tank Farm Road 100' 2827' from Broad Street 2920' from Broad Street 2333' from Broad Street 2448' from Broad Street 2533' from Broad Street 2626' from Broad Street 902' from Broad Street 1011' from Broad Street 512' from Broad Street 2228' from Broad Street 1531' from Broad Street 1629' from Broad Street 404' from Broad Street 713' from Broad Street 1125' from Broad Street 1225' from Broad Street 1389' from Broad Street 1413' from Broad Street 764' from Broad Street 135' from Broad Street 247' from Broad Street 317' from Broad Street 1761' from Broad Street 1853' from Broad Street 2708' from Broad Street 617' from Broad Street 1939' from Broad Street 2025' from Broad Street 2138' from Broad Street Page 563 of 625 10/24/24 Page 1 Road: Survey Date: From: Thickness: To: Traffic Index: Lane/Line: Project Number: Deflection Data Analysis Deflection Readings (Equivalent Deflectometer Units) No. of Tests Low Mean High Std. Dev. 24 9.15 14.16 22.50 4.11 Road Surface Thickness Traffic Index 0.41 9.50 Structural Design Tolerable 80th Percentile 90th Percentile % Reduction GE Deficient 15.00 17.61 19.42 14.82 0.07 HMA Overlay 0.04 (805) 781-2265 (916) 209-8300 PAVEMENT ENGINEERING INCORPORATED City of San Luis Obispo Righetti Ranch Road Concord Redding San Luis Obispo Sacramento (877) 240-0468 (530) 224-4535 EB2 10/16/24 0.41 9.50 240140 Tank Farm Road Broad Street Page 564 of 625 10/24/24 Page 2 Road: Survey Date: From: Thickness: To: Traffic Index: Lane/Line: Project Number: Tank Farm Road Broad Street Righetti Ranch Road EB2 10/16/24 0.41 9.50 240140 PAVEMENT ENGINEERING INCORPORATED City of San Luis Obispo Concord Redding San Luis Obispo Sacram ento (877) 240-0468 (530) 224-4535 (805) 781-2265 (916) 209-8300 144' from Broad Street 211' from Broad Street 329' from Broad Street 440' from Broad Street 532' from Broad Street 620' from Broad Street 708' from Broad Street 763' from Broad Street 870' from Broad Street 916' from Broad Street 1012' from Broad Street 1122' from Broad Street 1219' from Broad Street 1320' from Broad Street 1442' from Broad Street 1551' from Broad Street 1621' from Broad Street 1769' from Broad Street 1824' from Broad Street 1919' from Broad Street 2013' from Broad Street 2113' from Broad Street 2231' from Broad Street 2342' from Broad Street 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 0 102030405060708090100 Te s t P o i n t Deflectometer Deflection Page 565 of 625 Date: Client: Interval: Road: Survey Date: From: Thickness: To: Traffic Index: Lane/Line Project Number: Test Points DynaflectConditions Deflection Exclude 1 16.80 16.800 2 10.31 10.310 3 9.78 9.780 4 16.75 16.750 5 18.35 18.350 6 20.17 20.170 7 9.15 9.150 8 12.65 12.650 9 16.21 16.210 10 18.39 18.390 11 21.74 21.740 12 12.56 12.560 13 9.99 9.990 14 11.79 11.790 15 11.50 11.500 16 22.50 22.500 17 10.52 10.520 18 9.86 9.860 19 10.01 10.010 20 12.72 12.720 21 18.37 18.370 22 14.90 14.900 23 13.42 13.420 24 11.36 11.360 Concord (877) 240-0468 Redding (530) 224-4535 San Luis Obispo (805) 781-2265 Sacramento (916) 209-8300 10/16/24 0.41 9.50 240140 PAVEMENT ENGINEERING INCORPORATED Comments Broad Street Righetti Ranch Road EB2 10/24/2024 City of San Luis Obispo Tank Farm Road 100' 2231' from Broad Street 2342' from Broad Street 870' from Broad Street 916' from Broad Street 532' from Broad Street 2113' from Broad Street 1442' from Broad Street 1551' from Broad Street 440' from Broad Street 708' from Broad Street 1012' from Broad Street 1122' from Broad Street 1219' from Broad Street 1320' from Broad Street 763' from Broad Street 144' from Broad Street 211' from Broad Street 329' from Broad Street 1621' from Broad Street 1769' from Broad Street 620' from Broad Street 1824' from Broad Street 1919' from Broad Street 2013' from Broad Street Page 566 of 625 10/24/24 Page 1 Road: Survey Date: From: Thickness: To: Traffic Index: Lane/Line: Project Number: Deflection Data Analysis Deflection Readings (Equivalent Deflectometer Units) No. of Tests Low Mean High Std. Dev. 18 8.21 15.73 36.17 6.76 Road Surface Thickness Traffic Index 0.28 9.50 Structural Design Tolerable 80th Percentile 90th Percentile % Reduction GE Deficient 18.00 21.41 24.39 15.94 0.08 HMA Overlay 0.04 (805) 781-2265 (916) 209-8300 PAVEMENT ENGINEERING INCORPORATED City of San Luis Obispo Wavertree Street Concord Redding San Luis Obispo Sacramento (877) 240-0468 (530) 224-4535 EB 10/16/24 0.28 9.50 240140 Tank Farm Road Righetti Ranch Road Page 567 of 625 10/24/24 Page 2 Road: Survey Date: From: Thickness: To: Traffic Index: Lane/Line: Project Number: Tank Farm Road Righetti Ranch Road Wavertree Street EB 10/16/24 0.28 9.50 240140 PAVEMENT ENGINEERING INCORPORATED City of San Luis Obispo Concord Redding San Luis Obispo Sacram ento (877) 240-0468 (530) 224-4535 (805) 781-2265 (916) 209-8300 162' from Righetti Ranch Rd 229' from Righetti Ranch Rd 332' from Righetti Ranch Rd 417' from Righetti Ranch Rd 511' from Righetti Ranch Rd 612' from Righetti Ranch Rd 789' from Righetti Ranch Rd 820' from Righetti Ranch Rd 908' from Righetti Ranch Rd 1005' from Righetti Ranch Rd 1119' from Righetti Ranch Rd 1216' from Righetti Ranch Rd 1330' from Righetti Ranch Rd 1417' from Righetti Ranch Rd 1516' from Righetti Ranch Rd 1607' from Righetti Ranch Rd 1706' from Righetti Ranch Rd 1816' from Righetti Ranch Rd 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 0 102030405060708090100 Te s t P o i n t Deflectometer Deflection Page 568 of 625 Date: Client: Interval: Road: Survey Date: From: Thickness: To: Traffic Index: Lane/Line Project Number: Test Points DynaflectConditions Deflection Exclude 1 9.40 9.400 2 12.40 12.400 3 16.69 16.690 4 12.43 12.430 5 15.07 15.070 6 36.17 36.170 7 15.48 15.480 8 8.21 8.210 9 12.11 12.110 10 14.80 14.800 11 22.56 22.560 12 13.58 13.580 13 8.75 8.750 14 12.90 12.900 15 10.98 10.980 16 22.28 22.280 17 22.87 22.870 18 16.53 16.530 Concord (877) 240-0468 Redding (530) 224-4535 San Luis Obispo (805) 781-2265 Sacramento (916) 209-8300 10/16/24 0.28 9.50 240140 PAVEMENT ENGINEERING INCORPORATED Comments Righetti Ranch Road Wavertree Street EB 10/24/2024 City of San Luis Obispo Tank Farm Road 100' 908' from Righetti Ranch Road 1005' from Righetti Ranch Road 511' from Righetti Ranch Road 1516' from Righetti Ranch Road 1607' from Righetti Ranch Road 417' from Righetti Ranch Road 789' from Righetti Ranch Road 1119' from Righetti Ranch Road 1216' from Righetti Ranch Road 1330' from Righetti Ranch Road 1417' from Righetti Ranch Road 820' from Righetti Ranch Road 162' from Righetti Ranch Road 229' from Righetti Ranch Road 332' from Righetti Ranch Road 1706' from Righetti Ranch Road 1816' from Righetti Ranch Road 612' from Righetti Ranch Road Page 569 of 625 10/24/24 Page 1 Road: Survey Date: From: Thickness: To: Traffic Index: Lane/Line: Project Number: Deflection Data Analysis Deflection Readings (Equivalent Deflectometer Units) No. of Tests Low Mean High Std. Dev. 19 2.33 9.15 38.15 8.18 Road Surface Thickness Traffic Index 0.73 9.50 Structural Design Tolerable 80th Percentile 90th Percentile % Reduction GE Deficient 13.00 16.02 19.62 18.85 0.10 HMA Overlay 0.05 (805) 781-2265 (916) 209-8300 PAVEMENT ENGINEERING INCORPORATED City of San Luis Obispo West City Limits Concord Redding San Luis Obispo Sacramento (877) 240-0468 (530) 224-4535 WB 10/16/24 0.73 9.50 240140 Tank Farm Road Broad Street Page 570 of 625 10/24/24 Page 2 Road: Survey Date: From: Thickness: To: Traffic Index: Lane/Line: Project Number: Tank Farm Road Broad Street West City Limits WB 10/16/24 0.73 9.50 240140 PAVEMENT ENGINEERING INCORPORATED City of San Luis Obispo Concord Redding San Luis Obispo Sacram ento (877) 240-0468 (530) 224-4535 (805) 781-2265 (916) 209-8300 138' from Broad Street 244' from Broad Street 333' from Broad Street 426' from Broad Street 519' from Broad Street 619' from Broad Street 711' from Broad Street 799' from Broad Street 928' from Broad Street 1025' from Broad Street 1142' from Broad Street 1234' from Broad Street 1321' from Broad Street 1425' from Broad Street 1527' from Broad Street 1616' from Broad Street 1720' from Broad Street 1825' from Broad Street 1933' from Broad Street 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 0 102030405060708090100 Te s t P o i n t Deflectometer Deflection Page 571 of 625 Date: Client: Interval: Road: Survey Date: From: Thickness: To: Traffic Index: Lane/Line Project Number: Test Points DynaflectConditions Deflection Exclude 1 13.28 13.280 2 15.43 15.430 3 14.99 14.990 4 38.15 38.150 5 8.30 8.300 6 9.15 9.150 7 12.97 12.970 8 5.62 5.620 9 4.37 4.370 10 4.89 4.890 11 4.04 4.040 12 11.61 11.610 13 6.78 6.780 14 6.54 6.540 15 4.55 4.550 16 3.57 3.570 17 3.63 3.630 18 3.57 3.570 19 2.33 2.330 Concord (877) 240-0468 Redding (530) 224-4535 San Luis Obispo (805) 781-2265 Sacramento (916) 209-8300 10/16/24 0.73 9.50 240140 PAVEMENT ENGINEERING INCORPORATED Comments Broad Street West City Limits WB 10/24/2024 City of San Luis Obispo Tank Farm Road 100' 928' from Broad Street 1025' from Broad Street 519' from Broad Street 1527' from Broad Street 1616' from Broad Street 426' from Broad Street 711' from Broad Street 1142' from Broad Street 1234' from Broad Street 1321' from Broad Street 1425' from Broad Street 799' from Broad Street 138' from Broad Street 244' from Broad Street 333' from Broad Street 1720' from Broad Street 1825' from Broad Street 619' from Broad Street 1933' from Broad Street Page 572 of 625 10/24/24 Page 1 Road: Survey Date: From: Thickness: To: Traffic Index: Lane/Line: Project Number: Deflection Data Analysis Deflection Readings (Equivalent Deflectometer Units) No. of Tests Low Mean High Std. Dev. 30 5.83 15.11 29.19 6.14 Road Surface Thickness Traffic Index 0.46 9.50 Structural Design Tolerable 80th Percentile 90th Percentile % Reduction GE Deficient 14.00 20.26 22.97 30.91 0.26 HMA Overlay 0.14 (805) 781-2265 (916) 209-8300 PAVEMENT ENGINEERING INCORPORATED City of San Luis Obispo Broad Street Concord Redding San Luis Obispo Sacramento (877) 240-0468 (530) 224-4535 WB1 10/16/24 0.46 9.50 240140 Tank Farm Road Righetti Ranch Road Page 573 of 625 10/24/24 Page 2 Road: Survey Date: From: Thickness: To: Traffic Index: Lane/Line: Project Number: Tank Farm Road Righetti Ranch Road Broad Street WB1 10/16/24 0.46 9.50 240140 PAVEMENT ENGINEERING INCORPORATED City of San Luis Obispo Concord Redding San Luis Obispo Sacram ento (877) 240-0468 (530) 224-4535 (805) 781-2265 (916) 209-8300 143' from Righetti Ranch Rd 239' from Righetti Ranch Rd 314' from Righetti Ranch Rd 402' from Righetti Ranch Rd 515' from Righetti Ranch Rd 612' from Righetti Ranch Rd 712' from Righetti Ranch Rd 804' from Righetti Ranch Rd 904' from Righetti Ranch Rd 1017' from Righetti Ranch Rd 1116' from Righetti Ranch Rd 1210' from Righetti Ranch Rd 1330' from Righetti Ranch Rd 1412' from Righetti Ranch Rd 1512' from Righetti Ranch Rd 1616' from Righetti Ranch Rd 1725' from Righetti Ranch Rd 1835' from Righetti Ranch Rd 1905' from Righetti Ranch Rd 2005' from Righetti Ranch Rd 2127' from Righetti Ranch Rd 2205' from Righetti Ranch Rd 2317' from Righetti Ranch Rd 2423' from Righetti Ranch Rd 2519' from Righetti Ranch Rd 2647' from Righetti Ranch Rd 2719' from Righetti Ranch Rd 2813' from Righetti Ranch Rd 2902' from Righetti Ranch Rd 2979' from Righetti Ranch Rd 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 0 102030405060708090100 Te s t P o i n t Deflectometer Deflection Page 574 of 625 Date: Client: Interval: Road: Survey Date: From: Thickness: To: Traffic Index: Lane/Line Project Number: Test Points DynaflectConditions Deflection Exclude 1 8.32 8.320 2 8.48 8.480 3 29.19 29.190 4 21.39 21.390 5 16.70 16.700 6 16.28 16.280 7 16.93 16.930 8 14.83 14.830 9 18.63 18.630 10 16.99 16.990 11 15.72 15.720 12 11.76 11.760 13 20.32 20.320 14 7.94 7.940 15 14.68 14.680 16 13.94 13.940 17 16.67 16.670 18 14.49 14.490 19 13.48 13.480 20 24.34 24.340 21 24.96 24.960 22 6.37 6.370 23 20.40 20.400 24 23.88 23.880 25 5.83 5.830 26 7.42 7.420 27 6.65 6.650 28 7.26 7.260 29 13.60 13.600 30 15.80 15.800 Concord (877) 240-0468 Redding (530) 224-4535 San Luis Obispo (805) 781-2265 Sacramento (916) 209-8300 10/16/24 0.46 9.50 240140 PAVEMENT ENGINEERING INCORPORATED Comments Righetti Ranch Road Broad Street WB1 10/24/2024 City of San Luis Obispo Tank Farm Road 100' 2813' from Righetti Ranch Road 2902' from Righetti Ranch Road 2979' from Righetti Ranch Road 2317' from Righetti Ranch Road 2423' from Righetti Ranch Road 2519' from Righetti Ranch Road 2647' from Righetti Ranch Road 904' from Righetti Ranch Road 1017' from Righetti Ranch Road 515' from Righetti Ranch Road 2205' from Righetti Ranch Road 1512' from Righetti Ranch Road 1616' from Righetti Ranch Road 402' from Righetti Ranch Road 712' from Righetti Ranch Road 1116' from Righetti Ranch Road 1210' from Righetti Ranch Road 1330' from Righetti Ranch Road 1412' from Righetti Ranch Road 804' from Righetti Ranch Road 143' from Righetti Ranch Road 239' from Righetti Ranch Road 314' from Righetti Ranch Road 1725' from Righetti Ranch Road 1835' from Righetti Ranch Road 2719' from Righetti Ranch Road 612' from Righetti Ranch Road 1905' from Righetti Ranch Road 2005' from Righetti Ranch Road 2127' from Righetti Ranch Road Page 575 of 625 10/24/24 Page 1 Road: Survey Date: From: Thickness: To: Traffic Index: Lane/Line: Project Number: Deflection Data Analysis Deflection Readings (Equivalent Deflectometer Units) No. of Tests Low Mean High Std. Dev. 26 6.57 14.34 24.28 5.19 Road Surface Thickness Traffic Index 0.46 9.50 Structural Design Tolerable 80th Percentile 90th Percentile % Reduction GE Deficient 14.00 18.70 20.98 25.14 0.18 HMA Overlay 0.09 WB2 10/16/24 0.46 9.50 240140 Tank Farm Road Righetti Ranch Road (805) 781-2265 (916) 209-8300 PAVEMENT ENGINEERING INCORPORATED City of San Luis Obispo Broad Street Concord Redding San Luis Obispo Sacramento (877) 240-0468 (530) 224-4535 Page 576 of 625 10/24/24 Page 2 Road: Survey Date: From: Thickness: To: Traffic Index: Lane/Line: Project Number: PAVEMENT ENGINEERING INCORPORATED City of San Luis Obispo Concord Redding San Luis Obispo Sacram ento (877) 240-0468 (530) 224-4535 (805) 781-2265 (916) 209-8300 Tank Farm Road Righetti Ranch Road Broad Street WB2 10/16/24 0.46 9.50 240140 401' from Righetti Ranch Rd 503' from Righetti Ranch Rd 622' from Righetti Ranch Rd 712' from Righetti Ranch Rd 836' from Righetti Ranch Rd 909' from Righetti Ranch Rd 1022' from Righetti Ranch Rd 1117' from Righetti Ranch Rd 1223' from Righetti Ranch Rd 1325' from Righetti Ranch Rd 1415' from Righetti Ranch Rd 1511' from Righetti Ranch Rd 1627' from Righetti Ranch Rd 1731' from Righetti Ranch Rd 1818' from Righetti Ranch Rd 1908' from Righetti Ranch Rd 2019' from Righetti Ranch Rd 2120' from Righetti Ranch Rd 2203' from Righetti Ranch Rd 2316' from Righetti Ranch Rd 2400' from Righetti Ranch Rd 2500' from Righetti Ranch Rd 2607' from Righetti Ranch Rd 2701' from Righetti Ranch Rd 2819' from Righetti Ranch Rd 2928' from Righetti Ranch Rd 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 0 102030405060708090100 Te s t P o i n t Deflectometer Deflection Page 577 of 625 Date: Client: Interval: Road: Survey Date: From: Thickness: To: Traffic Index: Lane/Line Project Number: Test Points DynaflectConditions Deflection Exclude 1 20.78 20.780 2 23.31 23.310 3 9.76 9.760 4 14.26 14.260 5 9.12 9.120 6 14.47 14.470 7 14.48 14.480 8 12.11 12.110 9 12.97 12.970 10 8.47 8.470 11 8.83 8.830 12 8.41 8.410 13 15.55 15.550 14 19.55 19.550 15 8.81 8.810 16 17.20 17.200 17 18.28 18.280 18 18.22 18.220 19 12.22 12.220 20 19.09 19.090 21 8.67 8.670 22 6.57 6.570 23 24.28 24.280 24 19.91 19.910 25 18.69 18.690 26 8.94 8.940 836' from Righetti Ranch Road 2500' from Righetti Ranch Road 1818' from Righetti Ranch Road 1908' from Righetti Ranch Road 712' from Righetti Ranch Road 1022' from Righetti Ranch Road 1415' from Righetti Ranch Road 1511' from Righetti Ranch Road 1627' from Righetti Ranch Road 1731' from Righetti Ranch Road 1117' from Righetti Ranch Road 401' from Righetti Ranch Road 503' from Righetti Ranch Road 622' from Righetti Ranch Road 2019' from Righetti Ranch Road 2120' from Righetti Ranch Road 909' from Righetti Ranch Road 2203' from Righetti Ranch Road 2316' from Righetti Ranch Road 2400' from Righetti Ranch Road 2607' from Righetti Ranch Road 2701' from Righetti Ranch Road 2819' from Righetti Ranch Road 2928' from Righetti Ranch Road 1223' from Righetti Ranch Road 1325' from Righetti Ranch Road 10/24/2024 City of San Luis Obispo Tank Farm Road 100' PAVEMENT ENGINEERING INCORPORATED Comments Righetti Ranch Road Broad Street WB2 Concord (877) 240-0468 Redding (530) 224-4535 San Luis Obispo (805) 781-2265 Sacramento (916) 209-8300 10/16/24 0.46 9.50 240140 Page 578 of 625 10/24/24 Page 1 Road: Survey Date: From: Thickness: To: Traffic Index: Lane/Line: Project Number: Deflection Data Analysis Deflection Readings (Equivalent Deflectometer Units) No. of Tests Low Mean High Std. Dev. 18 8.69 19.97 28.49 5.86 Road Surface Thickness Traffic Index 0.29 9.50 Structural Design Tolerable 80th Percentile 90th Percentile % Reduction GE Deficient 17.00 24.89 27.47 31.70 0.27 HMA Overlay 0.14 (805) 781-2265 (916) 209-8300 PAVEMENT ENGINEERING INCORPORATED City of San Luis Obispo Righetti Ranch Road Concord Redding San Luis Obispo Sacramento (877) 240-0468 (530) 224-4535 WB 10/16/24 0.29 9.50 240140 Tank Farm Road Wavertree Street Page 579 of 625 10/24/24 Page 2 Road: Survey Date: From: Thickness: To: Traffic Index: Lane/Line: Project Number: Tank Farm Road Wavertree Street Righetti Ranch Road WB 10/16/24 0.29 9.50 240140 PAVEMENT ENGINEERING INCORPORATED City of San Luis Obispo Concord Redding San Luis Obispo Sacram ento (877) 240-0468 (530) 224-4535 (805) 781-2265 (916) 209-8300 132' from Wavertree Street 221' from Wavertree Street 315' from Wavertree Street 414' from Wavertree Street 547' from Wavertree Street 626' from Wavertree Street 727' from Wavertree Street 824' from Wavertree Street 919' from Wavertree Street 1021' from Wavertree Street 1136' from Wavertree Street 1229' from Wavertree Street 1325' from Wavertree Street 1413' from Wavertree Street 1531' from Wavertree Street 1627' from Wavertree Street 1736' from Wavertree Street 1818' from Wavertree Street 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 0 102030405060708090100 Te s t P o i n t Deflectometer Deflection Page 580 of 625 Date: Client: Interval: Road: Survey Date: From: Thickness: To: Traffic Index: Lane/Line Project Number: Test Points DynaflectConditions Deflection Exclude 1 21.98 21.980 2 23.90 23.900 3 28.49 28.490 4 23.99 23.990 5 22.50 22.500 6 20.10 20.100 7 20.88 20.880 8 22.94 22.940 9 20.63 20.630 10 10.11 10.110 11 21.18 21.180 12 24.20 24.200 13 26.82 26.820 14 21.08 21.080 15 20.20 20.200 16 11.78 11.780 17 8.69 8.690 18 9.99 9.990 Concord (877) 240-0468 Redding (530) 224-4535 San Luis Obispo (805) 781-2265 Sacramento (916) 209-8300 10/16/24 0.29 9.50 240140 PAVEMENT ENGINEERING INCORPORATED Comments Wavertree Street Righetti Ranch Road WB 10/24/2024 City of San Luis Obispo Tank Farm Road 100' 919' from Wavertree Street 1021' from Wavertree Street 547' from Wavertree Street 1531' from Wavertree Street 1627' from Wavertree Street 414' from Wavertree Street 727' from Wavertree Street 1136' from Wavertree Street 1229' from Wavertree Street 1325' from Wavertree Street 1413' from Wavertree Street 824' from Wavertree Street 132' from Wavertree Street 221' from Wavertree Street 315' from Wavertree Street 1736' from Wavertree Street 1818' from Wavertree Street 626' from Wavertree Street Page 581 of 625 Laboratory No.:L243714 Project No.:240140 Sample Date:October 24, 2024 Report Date:November 1, 2024 Client:City of San Luis Obispo Project Name:Pavement Evaluation Services for 2025 Roadway Paving Project Sample Description:Brown Clay Sample Location:C10, Tank Farm Specimen No. 1 2 3 Moisture Content (%) 20.4 19.3 20.9 Dry Density (PCF) 115.0 116.5 114.5 Resistance Value (R) 9 23 0 Exudation Pressure (PSI) 270 403 165 Expansion Pressure 43 91 0 20.4 RESISTANCE VALUE AT 300 P.S.I. 12 Reviewed By: Materials Engineer Brandon Rodebaugh RESISTANCE (R) VALUE TEST ASTM D 2844 As Received Moisture Content (%) 0 10 20 30 40 50 60 70 80 90 100 0100200300400500600700800 Re s i s t a n c e V a l u e Exudation Pressure (P.S.I.) Resistance Value Test 300 P.S.I. Page 582 of 625 Laboratory No.:L243752 Project No.:240140 Sample Date:October 24, 2024 Report Date:November 5, 2024 Client:City of San Luis Obispo Project Name:Pavement Evaluation Services for 2025 Roadway Paving Project Sample Description:Brown Silty Clay Sample Location:C12, Tank Farm Specimen No. 1 2 3 Moisture Content (%) 19.6 18.6 20.2 Dry Density (PCF) 114.6 116.7 113.2 Resistance Value (R) 17 35 2 Exudation Pressure (PSI) 264 406 166 Expansion Pressure 43 87 0 19.6 RESISTANCE VALUE AT 300 P.S.I. 22 Reviewed By: Materials Engineer Brandon Rodebaugh RESISTANCE (R) VALUE TEST ASTM D 2844 As Received Moisture Content (%) 0 10 20 30 40 50 60 70 80 90 100 0100200300400500600700800 Re s i s t a n c e V a l u e Exudation Pressure (P.S.I.) Resistance Value Test 300 P.S.I. Page 583 of 625 Laboratory No.:L243752 Project No.:240140 Sample Date:October 24, 2024 Report Date:November 5, 2024 Client:City of San Luis Obispo Project Name:Pavement Evaluation Services for 2025 Roadway Paving Project Sample Description:Brown Silty Clay Sample Location:C35, Tank Farm Specimen No. 1 2 3 Moisture Content (%) 14.1 15.1 15.6 Dry Density (PCF) 120.2 119.6 117.7 Resistance Value (R) 33 16 1 Exudation Pressure (PSI) 416 276 173 Expansion Pressure 91 43 0 14.1 RESISTANCE VALUE AT 300 P.S.I. 19 Reviewed By: Materials Engineer Brandon Rodebaugh RESISTANCE (R) VALUE TEST ASTM D 2844 As Received Moisture Content (%) 0 10 20 30 40 50 60 70 80 90 100 0100200300400500600700800 Re s i s t a n c e V a l u e Exudation Pressure (P.S.I.) Resistance Value Test 300 P.S.I. Page 584 of 625 Laboratory No.:L243714 Project No.:240140 Sample Date:October 24, 2024 Report Date:November 1, 2024 Client:City of San Luis Obispo Project Name:Pavement Evaluation Services for 2025 Roadway Paving Project Sample Description:Brown Silty Clay Sample Location:C33, Tank Farm Specimen No. 1 2 3 Moisture Content (%) 17.8 18.8 19.4 Dry Density (PCF) 117.4 116.1 115.1 Resistance Value (R) 23 10 0 Exudation Pressure (PSI) 389 260 158 Expansion Pressure 87 43 0 17.8 RESISTANCE VALUE AT 300 P.S.I. 14 Reviewed By: Materials Engineer Brandon Rodebaugh RESISTANCE (R) VALUE TEST ASTM D 2844 As Received Moisture Content (%) 0 10 20 30 40 50 60 70 80 90 100 0100200300400500600700800 Re s i s t a n c e V a l u e Exudation Pressure (P.S.I.) Resistance Value Test 300 P.S.I. Page 585 of 625 Laboratory No.:L243752 Project No.:240140 Sample Date:October 23, 2024 Report Date:November 5, 2024 Client:City of San Luis Obispo Project Name:Pavement Evaluation Services for 2025 Roadway Paving Project Sample Description:Brown Silty Clay Sample Location:C31, Tank Farm Specimen No. 1 2 3 Moisture Content (%) 15.4 16.4 17.0 Dry Density (PCF) 119.5 118.3 117.5 Resistance Value (R) 32 15 1 Exudation Pressure (PSI) 407 270 168 Expansion Pressure 91 48 0 15.4 RESISTANCE VALUE AT 300 P.S.I. 19 Reviewed By: Materials Engineer Brandon Rodebaugh RESISTANCE (R) VALUE TEST ASTM D 2844 As Received Moisture Content (%) 0 10 20 30 40 50 60 70 80 90 100 0100200300400500600700800 Re s i s t a n c e V a l u e Exudation Pressure (P.S.I.) Resistance Value Test 300 P.S.I. Page 586 of 625 Laboratory No.:L243714 Project No.:240140 Sample Date:October 24, 2024 Report Date:November 1, 2024 Client:City of San Luis Obispo Project Name:Pavement Evaluation Services for 2025 Roadway Paving Project Sample Description:Brown Clay Sample Location:C20 Tank Farm Specimen No. 1 2 3 Moisture Content (%) 17.6 16.5 18.1 Dry Density (PCF) 117.7 120.8 117.8 Resistance Value (R) 13 25 4 Exudation Pressure (PSI) 260 425 187 Expansion Pressure 52 104 4 17.6 RESISTANCE VALUE AT 300 P.S.I. 16 Reviewed By: Materials Engineer Brandon Rodebaugh RESISTANCE (R) VALUE TEST ASTM D 2844 As Received Moisture Content (%) 0 10 20 30 40 50 60 70 80 90 100 0100200300400500600700800 Re s i s t a n c e V a l u e Exudation Pressure (P.S.I.) Resistance Value Test 300 P.S.I. Page 587 of 625 Laboratory No.:L243714 Project No.:240140 Sample Date:October 24, 2024 Report Date:November 1, 2024 Client:City of San Luis Obispo Project Name:Pavement Evaluation Services for 2025 Roadway Paving Project Sample Description:Brown Clay Sample Location:C22, Tank Farm Specimen No. 1 2 3 Moisture Content (%) 18.4 17.6 19.0 Dry Density (PCF) 117.9 120.3 118.0 Resistance Value (R) 15 26 4 Exudation Pressure (PSI) 277 413 178 Expansion Pressure 52 104 0 18.4 RESISTANCE VALUE AT 300 P.S.I. 17 Reviewed By: Materials Engineer Brandon Rodebaugh RESISTANCE (R) VALUE TEST ASTM D 2844 As Received Moisture Content (%) 0 10 20 30 40 50 60 70 80 90 100 0100200300400500600700800 Re s i s t a n c e V a l u e Exudation Pressure (P.S.I.) Resistance Value Test 300 P.S.I. Page 588 of 625 Tank Farm Road @ Wavertree Street lookingEast Photo  Tank Farm Road @ Wavertree Street looking West Photo  Page 589 of 625 Tank Farm Road @ Brookpine Drive lookingEast Photo  Tank Farm Road @ Brookpine Drive looking West Photo  Page 590 of 625 Tank Farm Road @ 430’ S/O Brookpine Drive looking East Photo  Tank Farm Road @ 430’ S/O Brookpine Drive looking :Hst Photo  Page 591 of 625 Tank Farm Road EB @ Railroad Overpass looking East Photo  Tank Farm Road EB @ Railroad Overpass looking West Photo  Page 592 of 625 Tank Farm Road WB @ Railroad Overpass looking East Photo  Tank Farm Road WB @ Railroad Overpass looking West Photo 1 Page 593 of 625 Tank Farm Road EB @ Hollyhock Way looking East Photo 1 Tank Farm Road EB @ Hollyhock Way looking West Photo 1 Page 594 of 625 Tank Farm Road WB @ Hollyhock Way looking East Photo 1 Tank Farm Road WB @ Hollyhock Way looking West Photo  Page 595 of 625 Tank Farm Road EB @ Poinsettia Street looking East Photo  Tank Farm Road EB @ Poinsettia Street looking West Photo  Page 596 of 625 Tank Farm Road WB @ Poinsettia Street looking East Photo  Tank Farm Road WB @ Poinsettia Street looking West Photo  Page 597 of 625 Tank Farm Road EB @ Broad Street looking West Photo  Tank Farm Road EB @ Broad Street looking East Photo 2 Page 598 of 625 Tank Farm Road WB @ Broad Street looking East Photo 2 Tank Farm Road WB @ Broad Street looking East Photo 2 Page 599 of 625 Tank Farm Road EB @ Broad Street looking East Photo 2 Tank Farm Road EB @ Broad Street looking West Photo  Page 600 of 625 Tank Farm Road WB @ Broad Street looking East Photo  Tank Farm Road WB @ Broad Street looking West Photo  Page 601 of 625 Tank Farm Road EB @ 350’ W/O Broad Street looking East Photo  Tank Farm Road EB @ 350’ W/O Broad Street looking West Photo  Page 602 of 625 Tank Farm Road WB @ 350’ W/O Broad Street looking East Photo  Tank Farm Road WB @ 350’ W/O Broad Street looking West Photo 3 Page 603 of 625 Tank Farm Road @ West City Limits looking East Photo 3 Tank Farm Road @ West City Limits looking West Photo 3 Page 604 of 625 1 101 101 Reservior Canyon Natural Reserve Irish Hills Natural Reserve Laguna Lake Natural Reserve Southw o o d D r Flo r a S t Slack St Fe r r i n i R d Oliv e S t G r o v e S t Murray St Guerra D r Ironbark St D a l i d i o C a r m e l S t B e a c h S t Bish o p S t McCollum St Syd ney S t Tangle wood Dr Fuller R d Fredericks St Li n c o l n S t Diab l o D r R o c k v i e w P l Suburban Rd G a r d e n S t Tibu ron W a y Lau r e l L n B u l l o c k L n W C r e e k R d Va che l l Ln Pi n n a c l e s R d Wo odbridg eSt A u g u s t a S t Palm S t Mou n t B i s h o p R d Loomis S t S a c r a m e n t o D r High St Islay S t B r o a d S t Pacifi c S t Mill St San L u i s D r G r a n d A v e P o i n s e t t i a S t WFoo t hill B l v d B l u e G r a n i t e L n Mont e r e y S t M ars hSt Pism o S t Ocea n a i r e D r SH i gu e r aSt Madon n a R d C a l i f o r n i a B l v d M o u n t L o w e R d Main i n i R a n c h R d E Foothill Blvd O c o n n o r W a y Tank F a r m R d R e s e r v o i r C a n y o n R d O r c u t t R d L o s O s o s V a l l e y R d California Polytechnic State University 010.5 Miles Proposed Bicycle/Pedestrian Grade-Separated Crossing Proposed Bicycle/Pedestrian Major Crossing Improvement Anholm Neighborhood Greenway Broad St / Santa Barbra Corridor Foothill Blvd Higuera St/Marsh St Los Osos Valley Rd Madonna Rd/ Oceanaire NG/South St Mill/Morro/ Railroad Safety Trail Prado/Dilidio Proposed Bicycle/Pedestrian Minor Crossing Improvement Tier 1 Bicycle and Pedestrian Project Corridors San Luis Obispo Sources: City of San Luis Obispo *See Ch. 5 for proposed bikeway and crossing types. School Park or Open Space Rail Trails Tank Farm Rd Page 605 of 625 Islay Hill Open Space South Hills Natural Reserve Rigetti Hill Open Space Sout h w o o d D r Ma l v a Aero D r Me a d o w S t Sage St Stoneridge Dr Cll C r o t a l o Caudill St Clarion Ct Mc M i l l a n A v e Ga r i b a l d i A v e Capito l i o W a y Hopkins L n Farmhouse Ln Corrida Dr Woo d s i d e D r Fer n w o o d D r Mitchell Dr Junipero W a y F l o r a S t Ironbark S t Hansen Ln Aug u s t a S t Prado Rd Wa v e r t r e e S t Lawrence Dr S e q u o i a D r Tanglewood D r Fuller R d Goldenrod Ln Indust r i a l W a y R o c k v i e w P l Tibu r o n W a y Lau r e l L n B u l l o c k L n Jo h n s o n A v e Ho o v e r Woodbridge S t Spa n i s h O a k s D r S a c r a m e n t o D r Sa n t a F e R d P o i n s e t t i a S t Tank F a rm R d O r c u t t R d 0 0.50.25 Miles Sources: City of San Luis Obispo School Park or Open Space Rail Trails San Luis Obispo Shared-Use Path Bicycle Lane Protected Bicycle Lane Neighborhood Greenway Proposed Bicycle/Pedestrian Grade-Separated Crossing Proposed Bicycle/Pedestrian Major Crossing Improvement Proposed Bicycle/Pedestrian Minor Crossing Improvement Tier 1 Bicycle and Pedestrian Project Corridors - Southeast Page 606 of 625 Appendix A ATP Tier 1 Project List Corridor User Type ID Location Cross Street A Notable Constraints% Ridership Potential NotesCross Street B Miles Ped/Bike Grade‐Separated Crossing I‐4Lawrence Dr or Francis 36 Ped/bike bridge over UPRR  tracks Requires UPRR coordination &  right‐of‐way Ped/Bike Crossing Improvement (Major) J‐17 Pepper St Monterey St 36 Long‐term plan is a ped/bike  bridge. Interim solution may  include RRFB & median  refuge/diverter Requires UPRR coordination &  right‐of‐way Ped/Bike Crossing Improvement (Major) J‐64 California Blvd Taft St 36 Planned roundabout Bike Protected Bike Lane 261 Dalidio/Prado Madonna Rd Elks Ln 0.47 17 South side of Prado  (Madonna to Froom) will be  a shared‐use path Bike Protected Bike Lane 261 Prado Rd Elks Ln Serra Meadows Rd 0.71 17 Bike Bike Lane 104 Prado Rd Serra Meadows Rd Broad St 1.03 17 Ped/Bike Shared‐Use Path 105 Prado Rd (North  Side) Serra Meadows Rd Broad St 1.09 17 Ped/Bike Shared‐Use Path 106 Prado Rd (South  Side) Serra Meadows Rd Broad St 0.86 17 Ped/Bike Shared‐Use Path 127 Dalidio Dr Madonna Rd ‐0.3 17 Ped/Bike Crossing Improvement (Major) I‐2Prado Rd Damon‐Garcia Sports  Field 17 Potential ped/bike  undercrossing Bike Protected Bike Lane 33 Tank Farm Rd S. Higuera St Horizon Ln 0.46 11 Ped/Bike Shared‐Use Path 64,157,267 Tank Farm Rd (North  Side) Horizon Ln Santa Fe Rd 0.94 11 Requires roadway widening and  right‐of‐way Bike Protected Bike Lane 31, 32 Tank Farm Rd Santa Fe Rd Orcutt Rd 1.33 11 May required auto lane  reduction. Ped Crossing Improvement (Minor) J‐13 Tank Farm Rd Poinsettia St 11 Potential RRFB & median  refuge Ped/Bike Crossing Improvement (Major) J‐65 Tank Farm Rd Orcutt Road 11 Planned roundabout Project ID numbers correspond to mapping in the Public Viewer http://slocity.maps.arcgis.com/apps/webappviewer/index.html?id=d0c9ddaa42a444bda8d5940e05891eb7 Tank Farm Road Prado/Dalidio Project ID numbers correspond to mapping in the Public Viewer http://slocity.maps.arcgis.com/apps/webappviewer/index.html?id=d0c9ddaa42a444bda8d5940e05891eb7 Page 4 Page 607 of 625 Page 608 of 625 Page 609 of 625 Page 610 of 625 Page 611 of 625 Page 612 of 625 Page 613 of 625 Page 614 of 625 Page 615 of 625 Page 616 of 625 Page 617 of 625 Page 618 of 625 Page 619 of 625 Page 620 of 625 Page 621 of 625 Page 622 of 625 Page 623 of 625 Page 624 of 625 Page 625 of 625 2025 Paving Project & Tank Farm Rd Design Alternatives City Council Presentation MAY 6, 2025 Project Overview 2 BASE BID •Tank Farm Rd •Sacramento Dr •Safety Striping Refresh •Broad Street •Santa Rosa / Mill Crosswalks •Madonna •Prado Road •Tank Farm Road BID ADDITIVE ALTERNATIVE A •Orcutt Road BID ADDITIVE ALTERNATIVE B •Calle Joaquin Planning Context 3 Tank Farm Road 4 Existing Conditions & Planning Context 5Existing Tank Farm Road (Broad to UPRR Bridge) Existing Conditions & Planning Context 6Existing Tank Farm Road (Righetti Ranch to Orcutt) Existing Issues & Concerns 7 1.Unsafe/illegal vehicle speeds 2.Difficulty making left turns on to Tank Farm 3.Ped Crossing Concerns – Failure to yield to pedestrians within x-walks crossing Tank Farm at Poinsettia, Righetti Ranch Roundabout 4.Requests for pedestrian crossing enhancements between Poinsettia and Righetti Rd Planning Context 8 ATP •Tier 1 Project - Protected bike lanes & potential road diet proposed •Proposed ped crossing improvements between Poinsettia and Righetti Ranch Rd TRAFFIC SAFETY/VISION ZERO ACTION PLAN •Not on High -Injury Network, but 11th highest crash rate arterial street •15 collisions in past 5 years –1 severe injury ped collision at Morning Glory –1 severe injury ped collision at Poinsettia in 2014 –No bike collisions in past 5 years –Pattern, of minor solo veh collisions at Righetti Ranch Roundabout due to high/ unsafe entry speeds and DUI Tank Farm Design Alternatives 9 •Alternative 1 – Road Diet •Alternative 2 – No Road Diet •Hybrid Alternative – Road Diet Eastbound Only Emergency Response & Evacuation Considerations 10 Cal Fire – Fire Hazard Safety Zones 2009-2 0 11 2025 Emergency Response & Evacuation Considerations 11 Emergency Response & Evacuation Review Findings & Recommendations: 1.As currently proposed, none of the current design alternatives would pose significant concerns to ability to evacuate via Tank Farm Road 2.No vertical protected bikeway features recommended to preserve road clearance for potential evacuation 3.Provide traffic lane widths wider than minimum City Standard (10’) where possible 4.Develop special traffic signal timing plans for Broad (SR 227)/ Tank Farm intersection to clear traffic during evacuation Common Features to All Alternatives 12 1.Pavement reconstruction & ADA curb ramps 2.New streetlights at Poinsettia & Morning Glory intersections 3.Radar speed feedback signs 4.Green bike lanes at conflict areas 5.Restripe WB right turn lane at Tank Farm/ Broad from right -turn only to shared thru/ right lane 6.Tank Farm East of UPRR Bridge – Same design for all Alts Tank Farm Improvements – Ea st of UPRR 13 Proposed: Tank Farm Road (Righetti Ranch to Orcutt) Tank Farm Improvements – Ea st of UPRR 14 Tank Farm & Righetti Ranch Roundabout Alternative 1: Road Diet 15 Alternative 1: Road Diet 16Proposed: Tank Farm Road (Broad to Poinsettia) Alternative 1: Road Diet 17Proposed: Tank Farm Road (Broad to Poinsettia) 18 19 20 Alternative 1: Road Diet 21 Pros & Cons of Alternative 1 22 Pros 1.Road Diets reduce crashes by 19%-47% 2.RRFBs increase driver yield rate by up to 98%, reduce ped crashes by 47% 3.Eliminate “multiple threat” ped collision risk 4.Reduce illegal speeding – cuts collision frequency and severity for all users 5.Retains acceptable traffic operations & emergency evacuation flexibility 6.Can be “undone” relatively easily in future, if needed Cons 1.New configuration may require learning curve for drivers 2.Less excess road capacity for future growth and potential large -scale evacuation, but not considered significant concern as proposed Alternative 2: No Road Diet 23Proposed Tank Farm Road (Broad to UPRR Bridge) 24 25 Pros & Cons of Alternative 2 26 Pros 1.Retains existing road configuration & familiarity for road users 2.Reduced construction cost compared to Alt 1 ($50K less by omitting ped crossing at Morning Glory/ Sunset) 3.Retains excess traffic capacity for future growth and/ or large -scale emergency evacuation 4.Some benefits over existing conditions with addition of radar speed feedback signs, green bike lane markings in conflict areas, etc. Cons 1.Less potential to reduce high-end vehicle speeds 2.Less potential to improve road safety, particularly for pedestrian crossings 3.No designated ped crossing between Poinsettia and Righetti Ranch Rd 4.Less separation between vehicles and pedestrians/bicycles ATC Inp ut 27 1.Detailed review of 2025 Paving Project in November 2024, project update in March 2025 2.Key Comments/ Recommendations: Sacramento: a)Reduce vehicle speeds b)Add pedestrian crossing along Sacramento Tank Farm: a)Support road diet b)Prefer protected bike lanes – preference for concrete/rigid materials for bikeway separation & openings for passing/ left turns c)Prefer median refuges at pedestrian crossings d)Slow speeds entering Righetti Ranch Rd Roundabout & improve ped crossing visibility Public Input 28 Outreach & Noticing: a)Project website b)Direct mailers sent to all properties along Sacramento and Tank Farm Rd ahead of each public meeting c)In -person meeting at November 2024 ATC meeting d)News releases, email list, social media updates e)Input from previous outreach as part of ATP and Vision Zero Action Plan Key Comments/ Recommendations: a)Roughly 50/ 50 split for/ against road diet on Tank Farm b)Support for more robust pedestrian crossing measures, such as raised median refuges at Poinsettia and Morning Glory c)Suggestions for rumble strips along Tank Farm Project Costs & Funding 29 GENERAL FUND (Streets R&R)$6,160,000 GENERAL FUND (CIP Re se rve )$1,404,530 S B1 FUND $ 1,2 7 7 ,3 12 WATER FUND $199,200 SEWER FUND $76,800 AVAILABLE FUNDING $9,117,842 BASE BID TO TAL ESTIMATE $ 9 ,117 ,8 4 2 ADDITIVE ALTERNATIVE A $1,351,585 ADDITIVE ALTERNATIVE B $673,915 TOTAL PROJECT ESTIMATE $11,143,34 Project Cost Funding •May 2025 – Update designs based on Council input; City Engineer to approve final plans and specifications •June -July 2025 – Solicit construction bids & award construction contract •August/September 2025 – Start construction •January/February 2026 – Complete construction 30 Next Steps & Schedule Recommendation 31 1.Receive staff presentation, provide input and policy direction regarding roadway striping modifications for Tank Farm Road for implementation with the 2025 Paving Project designs; and 2.Authorize the City Engineer to approve final plans and specifications for the 2025 Paving Project, Specification No. 2000616, including incorporation of designs for Tank Farm Road pursuant to City Council direction, prior to advertising the project for construction; and 3.Authorize staff to advertise for bids for the 2025 Paving Project; and 4.Authorize the City Manager to award the construction contract for the 2025 Paving Project pursuant to Section 3.24.190 of the Municipal Code for the bid total, if the lowest responsible bid is within the publicly disclosed funding amount of $7,720,000; and 5.Adopt a draft resolution entitled “A Resolution of the City Council of the City of San Luis Obispo, California, Authorizing Appropriation of Capital Projects Reserve Funds to Support the 2025 Paving Project, Specification Number 2000616”; and, Recommendation 3 6.Authorize the Finance Director to make the following appropriations and funding transfers to the 2025 Paving Project Account (2000616): a. Appropriate $1,404,530 of Capital Outlay LRM funds from the FY24/ 25 Capital Reserve of the Capital Outlay Fund; and b. Transfer $2,100,000 of Capital Outlay LRM funds from the Roadway Sealing 2024 Project Account (No. 2000615); and, c. Transfer $100,000 of Capital Outlay LRM funds from the Arterials 2023 Project Account (No. 2001065); and, d. Transfer $199,200 of Water funds from the Water Valve Cover Adjustments Account (No. 2001005); and, e.Transfer $76,800 of Sewer funds from the Sewer Valve Cover Adjustments Account (No. 2000084); and 7.Authorize the City Engineer to issue Contract Change Orders for the 2025 Paving Project up to and in excess of $200,000 if within available project budget, and up to any amended budget subsequently approved by the City Manager per City Purchasing Policy approval thresholds. Questions? Tank Farm Design Alternatives 35 •Alternative 1 – Road Diet •Alternative 2 – No Road Diet •Hybrid Alternative – Road Diet Eastbound Only Protected Bike Lane Considerations 36 1.Emergency services recommend no vertical bikeway elements to preserve clearance for emergency vehicle access and capacity for potential large-scale evacuation on Tank Farm 2.If directed by Council, staff recommendation is for flexible materials (i.e. flex posts) – lower costs, opportunity for driver adjustments, maximizes clearance for emergency access & evacuation •Converting striped bike lanes to protected lanes, even with rubber flex posts only, reduces veh vs. bicycle crash rates by up to 53%, reduces crash rates for all users (FHWA) 3.Cost Implications •+$50,000-$-75,000 in construction costs for flex posts; +$150,000-$175,000 for more rigid materials •+$30,000 per year in maintenance costs Road Maintenance Elements 3 Sacramento Drive, Orcutt Road, and Calle Joaquin •Mill and Fill Asphalt •9 ADA curb ramp upgrades Tank Farm Road •Full Depth Reclamation (FDR) •19 ADA curb ramp upgrades Key Steps with FDR 3 1. Pulverization: Existing pavement and base are ground up. 2. Mixing: Additives like cement and lime are mixed in. 3. Compaction: Compacted to form a strong base. 4. Surface Course: A new asphalt section is applied. FDR Benefits / Challenges 3 Benefits 1.Lower Costs 2. Less Hauling 3. Environmentally Friendly Challenges 1.Project Duration 2.Phased Construction Planning 3.Dust Control Needs 4.Site Suitability Madonna Road Full Depth Reclamation (2017) Sacramento Drive 4 Existing Issues and Planning Context 41 1.ATP: –Striped (Class II) bike lanes –Potential ped crossing (all-way stop at Sacramento/Capitolio ) 2.Safety/Vision Zero : Fatal ped collision along curve in 2022 due to driver negligence. No other high collision rate locations 3.Poor pavement condition 4.High traffic speeds 5.Parked vehicles encroaching into bike lane 6.Safety concerns at roadway curve north (unsafe speeds, vehicles cutting corner & encroaching into bike lane) Proposed Improvements 4 1.Reconstruct pavement 2.ADA curb ramp upgrades 3.Safety improvements along roadway curve 4.Radar speed feedback signs & additional speed limit signs 5.Red curb (“Daylighting”) to improve sight lines at intersections & driveways 6.Increase bike lane widths & add buffers (where width allows) 7.Green bike lane markings through conflict areas Proposed Improvements 4 Further Tra ffic Ca lming Opportunities 4 Future Speed Cushion Pilot Program Pedestrian Crossing Considerations 4 •Sacramento & Capitolio intersection does not meet warrants for All-Way Stop Control •No ped collision history or locations with concentrated crossing demand •Development proposal currently under review for new private school on Sacramento near Via Esteban. •Pedestrian crossing likely to be recommended as condition of approval for new school Orcutt Road 4 1.Roadway Repaving and restriping 2.Minor drainage improvements 3.No changes to roadway configuration Ca lle Joa quin 4 Proposed Improvements: 1.Reconstruct pavement 2.Replace existing striping & add edge stripes for added visibility 3.Replace faded road signs & object markers 48Proposed: Tank Farm Road (Poinsettia to UPRR Bridge) Hybrid Alterna tive: Roa d Diet EB Only 49 50 Pros & Cons of Hybrid Alternative 51 Pros 1.Retains existing 2 -lane vehicle capacity in WB direction, most likely evacuation route 2.Greater potential to reduce speeds and improve safety than Alt 2 (No Road Diet) 3.Provides opportunity for raised ped median refuges, which improves ped crossing safety, particularly crossing dual WB traffic lanes. Cons 1.Less potential to reduce high-end vehicle speeds than with Alt 1 2.Less potential to improve road safety, particularly for pedestrian crossings than with Alt 1 3.Less separation between vehicles and pedestrians/bicycles than with Alt 1 Alternatives to Staff Recommendations 52 Tank Farm Design Alternatives 1.Hybrid Alterna tive – Road Diet Eastbound Only 2.Other Design Outside of Current Staff Alts 3.No Change/ Maintenance Only – Pave and restore existing striping configuration, no added features Alternatives to Staff Recommendations 53 2025 Paving Project Alternatives 1.Modify design features for other (non-Tank Farm) streets in 2025 Paving Project 2.Deny Authorization to Advertise – Defer project and/ or return at future date