HomeMy WebLinkAboutOrcutt Associates LLC Settlement AgreementSETTLEMENT AGREEMENT AND GENERAL RELEASE OF CLAIMS This Settlement Agreement ("Agreement") is entered into this 2 day of January, 2019 (the "Effective Date") by the City of San Luis Obispo, a municipal corporation and charter city ("City") and Orcutt Associates, LLC, a California limited liability company ("Orcutt Associates") (City and Orcutt Associates are collectively referred to herein as the "Parties"). Recitals WHEREAS, Orcutt Associates is the developer of the residential project at the intersection of Orcutt Road and Sacramento Drive (the "Project"); WHEREAS, as part of the Project, Orcutt Associates constructed certain traffic and pedestrian improvements including, but not limited to: Curb, gutter, sidewalk and other frontage improvements (the "Frontage Improvements") on Orcutt Road along what is commonly known as the "Tickell Property;" and 2. Intersection improvements at Laurel Lane and Orcutt Road (the "Intersection Improvements"). In connection with these improvements, the City and Orcutt Associates executed a Reimbursement Agreement dated November 20, 2007, which was later amended by agreement on July 22, 2011 (the "Reimbursement Agreement"). The Reimbursement Agreement required the City to exercise its "best efforts" in securing payment from future development in the "Benefitted Property/Parcels" identified in the Reimbursement Agreement. The Tickell Property is included in the Benefitted Property/Parcel area. The Reimbursement Agreement also required the City to reimburse Orcutt Associates $339,065 (subject to annual adjustment for inflation) for Intersection Improvements, with such amount to be paid by the City from Public Facilities Financing Plan transportation impact fees ("TIF") collected from future development in the Benefitted Property/Parcel area. WHEREAS, on February 5, 2018, the City's Architectural Review Commission ("ARC") approved a project on the Tickell Property commonly referred to as the "Twin Creeks" project; the applicant was New Heritage Family Limited Partnership ("New Heritage"). The Twin Creeks approval included a condition of approval requiring New Heritage to pay a fee in the amount of $381,061.77 (the "Frontage Fee Payment") as reimbursement for the Frontage Improvements. Under the Reimbursement Agreement, the City was entitled to $256,287.96 of this payment with the balance owed to Orcutt Associates. New Heritage appealed the ARC's approval on the basis that the Frontage Fee Payment was an unlawful exaction based on a variety of legal theories. WHEREAS, on May 8, 2018, the City entered into a settlement agreement with New Heritage regarding certain fees the City was imposing on the Twin Creeks Project including the Frontage 1 Initials: / Fee Payment. Under the settlement agreement, New Heritage agreed to pay City $256,287.96 of the $381,061.77 for the Frontage Fee Payment. WHEREAS, Orcutt Associates claims that the City's agreement to settle with New Heritage pursuant to the May 8, 2018 settlement agreement constituted a breach of the Reimbursement Agreement and a breach of the implied covenant of good faith and fair dealing associated with such agreement (the "Claim"). WHEREAS, City disagrees and denies any liability for the Claim; WHEREAS, by this Settlement Agreement, the Parties desire to resolve the Claim. Agreement NOW, THEREFORE, in consideration of the mutual promises and covenants contained herein and other good and valuable consideration, the sufficiency of which is hereby acknowledged, and intending to be legally bound hereby, the Parties hereby agree as follows: A. Recitals. The recitals above are true and correct and are incorporated herein by this reference. Capitalized terms not defined herein shall have the same meaning as defined in the Reimbursement Agreement. B. Reimbursement of Frontage Improvements. Within thirty days of City's receipt of $35,000 or more of the Frontage Fee Payment from New Heritage, or any successor owner of the Twin Creeks project, City shall pay to Orcutt Associates the sum of $35,000. C. Reimbursement of the Intersection Improvements. City acknowledges that the reimbursable amount for the Intersection Improvements as of the Effective Date is $412,812, which the parties agree includes all inflation adjustments through that date. Additional inflation adjustments based on CPI-U shall be applied yearly, on the anniversary of the Effective Date and in accordance with the Reimbursement Agreement, to any portion remaining unpaid at that time ("Annual Inflation Adjustment"). City shall reimburse Orcutt Associates for the Intersection Improvements in accordance with the Reimbursement Agreement, as amended, and supplemented as follows: i. City anticipates that the first TIF that will be paid to the City for projects located within the Benefitted Property/Parcels will be for building permits for the Taylor Subdivision, Tract 3044 and Vesting Tentative Parcel Map No. 2017-0115, as depicted in Exhibit A hereto (collectively the "Taylor Subdivision"). City has calculated that each single-family residence within the Taylor Subdivision will have an estimated TIF of $17,185 which is eligible to be used for reimbursement for the Intersection Improvements under the Reimbursement Agreement. City and Orcutt Associates agree that the Excel spreadsheet attached hereto as Exhibit B (the "Spreadsheet"), fairly allocates the distribution of potential future TIF from the Taylor Subdivision as between any credits the developer of the Taylor Subdivision 2 Initials: / is eligible to receive, City credits, and reimbursement payments to Orcutt Associates for the Intersection Improvements. ii. Reimbursement payments by the City to Orcutt Associates for the Intersection Improvements shall be made on a quarterly basis, starting April 1, 2019, and, as set forth in the Spreadsheet, shall consist of 70 percent of TIF collected by the City for the Intersection Improvements during that quarter. iii. The City shall provide an updated version of the Spreadsheet to Orcutt Associates along with each quarterly payment. If no payment is due in a quarter, either because the City has received no fee payments or otherwise, the City shall so notify Orcutt Associates. iv. If the Twin Creeks project pays TIF or other fair -share fees for the Intersection Improvements to the City, City shall pay Orcutt Associates $10,746.75 from those fees with the next quarterly payment, and the Spreadsheet shall be revised to deduct that amount from the final payment due to Orcutt Associates. V. If any other project within the Benefitted Property/Parcels pays TIF or other fair - share fees for the Intersection Improvements to the City, City shall pay Orcutt 70% of those collected fees with the next quarterly payment, and the Spreadsheet shall be revised to deduct that amount from the final payment(s) due to Orcutt. vi. The Spreadsheet shall be updated on an annual basis, to incorporate the Annual Inflation Adjustment, with respect to all remaining payments. D. Release. Orcutt Associates and City hereby, on behalf of themselves and their partners, successors -in -interest and assigns, irrevocably and unconditionally release and discharge each other from any and all lawsuits, claims, actions, demands or other legal responsibilities of any kind regarding the Claim, including, without limitation, any related attorneys' fees or legal costs. Orcutt Associates and the City expressly acknowledge that this Release includes any and all claims that Orcutt Associates or City asserted or could have asserted based upon or related to the Claim. E. Release of Unknown Claims. With respect to the release specified in Paragraph D, Orcutt Associates and City hereby waive any and all rights or benefits that any of them may have under Section 1542 of the Civil Code of the State of California, which provides: "A GENERAL RELEASE DOES NOT EXTEND TO CLAIMS WHICH THE CREDITOR DOES NOT KNOW OR SUSPECT TO EXIST IN HIS OR HER FAVOR AT THE TIME OF EXECUTING THE RELEASE, WHICH IF KNOWN BY HIM OR HER MUST HAVE MATERIALLY AFFECTED HIS OR HER SETTLEMENT WITH THE DEBTOR." Orcutt Associates and City acknowledge that they understand the effects of this waiver pursuant to Civil Code Scction 1542, and that they are represented by legal counsel and have been advised of this release by their counsel. 3 Initials: _ / F. Miscellaneous 1. Legal Advice, Authority to Execute Agreement. The Parties represent and warrant that they understand that they have the right to be represented by counsel and expressly acknowledge that they have had the opportunity to review this Agreement with their chosen counsel. The Parties represent that they fully understand the terms of this Agreement and agree to be bound by its contents. The Parties further represent that they have full authority to enter this Agreement and do so of their own accord. 2. Enforcement. In any action or proceeding to enforce or interpret the terms of this Agreement or otherwise arising out of the Agreement, the prevailing party shall be entitled to recover reasonable attorney's fees. 3. Entire Agreement. This Agreement constitutes the entire agreement between the Parties with regard to the subject matter set forth herein and supersedes any and all prior and contemporaneous agreements, negotiations, correspondence, understandings and communications of the Parties, whether oral or written, respecting the subject matter of this Agreement. 4. Compromise of Claims. It is expressly understood that this Agreement is in full accord and satisfaction of disputed claims, and this Agreement will not be deemed an admission of liability or responsibility of either Party hereto for any purpose. 5. Amendment. Neither this Agreement, nor any of its provisions, may be amended, waived, modified, or terminated except by an instrument in writing signed by the Parties, and then only to the extent set forth in such writing. 6. Severability. If any provision of this Agreement is deemed to be invalid, void, or illegal by a court of competent jurisdiction, such provision shall be construed and amended in a manner which would permit its enforcement, to the extent feasible, but in no event shall the validity of such provision affect, impair, or invalidate any other provision of this Agreement, and the remainder of this Agreement shall remain in full force and effect. 7. Governing Law. This Agreement shall be construed in accordance with the laws of the State of California, without regard to choice -of -law principles. 8. No Third-i'arty Beneficiaries. This Agreement does not create, and will not be construed to create, any rights enforceable by any person who is not a Party to this Agreement. 9. Interpretation. This Agreement is the product of negotiation and preparation by and among each Party hereto and its respective counsel. Accordingly, this Agreement will not be deemed prepared or drafted by one Party or another, and should be construed accordingly. 4 Initials: 10. Cooperation. Each Party agrees to make good faith, reasonable efforts to effectuate the purposes of this Agreement. 11. (Iaptions/l lea(iin(_)s. All captions and headings in this Agreement are inserted solely for convenience and shall not be deemed to restrict or limit the meaning of the text. 12. Execution of Agreement. This Agreement may be executed in multiple counterparts, each of which shall be deemed an original, and all of which shall constitute one document to be effective as of the Effective Date. Signatures that have been transmitted by facsimile or electronic mail shall be deemed to be original signatures for the purposes of this Agreement. Photocopies of this Agreement shall have the same effect as the original and may be used in lieu of the original for any purpose. [Signatures on following page.] 5 Initials: IN WITNESS WHEREOF, the Parties have executed this Agreement as of the last date indicated below. Orcutt Associates, LLC A California Limited Liability Company By Sonia H. Chin Send all notices herein to: Sonia H. Chin Orcutt Associates, LLC 11452 El Camino Real, Suite 120 San Diego, CA 92130 With a copy to: Donald Sobelman Downey Brand LLP 455 Market Street, Suite 1500 San Francisco, CA 94105 City of San Luis Obispo du"�YL'� �- 1.) Teresa Purrington, City Clerk as to form: J. hristinc Dietrick, City Attorney Send all notices herein to: City Attorney 990 Palm Street San Luis Obispo, CA 93401 6 Initials: / 1 Luz I3J 'Cl Alp I s "a II n I' V hT44 'NCE 7720' PER R5 Exhibit A TRACT 3044 A 5'JBE1—CS OF A PORTION OF ICT 125 OF THE EONURBAN TRAC' AS RECORDED IN BOOP 1• PACE 92 OF RECORD OF SURVEYS AND PJRTHEP. DESCRIBED AS PARCEL I (COA'_ O-ODB6) OF CERTIFICATE OF COMPLIANCE RECORDED 45 DOCUMENT NO 1012-002861 OF 'OFFICIAL RECORDS ALL FILED IN THE CFFICE OF THE SAN LUTE OBI5P0 COLINTI• REcokD�R. lNS IN THE CITY OF rF F CAI i DISP 0, COUNTY OF SAN LDIc ^E CITY ETA FORM L01T 123 100_ LS — _ 7- S- 9 GStyL c _ n Lem i _ � • ..irn •1t r1u lr I _ ...• 'T=U DETAIL h 1 � •• t�l a l a ✓t � / o /� y �/f iv ior�` - ��4m• .r31 I I �I I i � Ix..,. Ia PATE ' r , • ) 1 j'-i Ill EA.MEI.i MEI 1 , n LOT 46 A,IF II I 1 41 N5E'J: e'c'E 35D'-'YYY �In P1,. T1 I 1`� 1 NseO� E nas � I II I Im Ii. a wF/4MG u ATO 1 PER DED1Cr.AT DOCUMENTT ( 1D', :'-U22363 L•- I. .: 31' PRIVATE 'SLOPE EASEMENT n wS 1 OFPEF 0% DEDICATION L F\-� _ LOT 47 60 ? - -1 ' FUF STREET P'JR'O:rs 1� q PER THIS MAP - I Ij UFnA►N'1( EA'Sg11DR 1 I LOT 34 SF LOT 3.5 I J } LOT 36 -24 z SF Ig I T LOT 37 1�I 3 e.I 1 LOT 35 I T LOT 3942�2 SF a 1 - II �ii V• y76K I —LSr3E I '.I I J 1 \ DETAIL A � N r LOT 40 1 .,^. 5F I 1 1 LOT 46 .I sF I{a,� �I _ �w4V i III Ili' 3 eD r �or•rc aw• I •s NlA-L243-E aA9•—' J y�,yrl :.� Im ^ LOT 45 I LOT 42 I_ 1l :i w— ri l;= • 3780 SF I 15FRIVAIE _ tiaY W(IIp1T ='PRIVATE DRAINAGE - l — �1 —.MW'�Q•Yy(,� I EASEMT _ MJeT�'Ir. 1 IL1iVZUi I ^ .I W LOT �N_— _—___ ` I� G3OT4 —�� 1 m CT 3C66-P 1fli7 - � RIGHT GF WAY PER_kACT 30 66-PHASE I TFA F 30E5—F'Hk--- -LEx1STINO RIONI OF WAY (3'J—MLA—c4 J I ZJ 2JD111 ^1'191V PER DOCUMENT I III® LEGEND SET 5/8' RE— W/ CAP STAMPED LS 5139 13 SET II" IRON FIFE W-TAG STAMPED LS 5139 SET BRASS IF IN MONUMENT WELL STAMPED 1111.1 d,AS$ CAP Si,,—D LS J739 IN MONUMENT LVEII PER 3.-A'9-59 UNLESS NOTED OTHERLWSE SET 5,i8- PESAR 6-CAP STAMPED LS 5139 W 0 OFFSET :=_E_ MAIL D ON SHEET 4) .< SET LEAD AND TACA STAMPED LS 5111 FC' MONUMENT ',S NOTED NOE YDEYARD RETAN',NG WALL MAINTENANCE AND ""SAS' EASE N ENT PILE PUBLIC UTILIT'i EASENEN'T P A.E PUBLIC PEDESTRIAN ACCESS EASEMENT LAE � ARLD ACCES, LASEMLNI STE STREET TREE E15EINENT M MEPSUREC CF CALCULATED FPOM FAD) RADIAL BEARIN( ROW FIGHT OF WAI -c FOUND .-9*16fA BOUNDARY ............. C: Y LUIS BOUNDARY - ArtWrl( — - - GRTNS IMt•TT yn( '-;REFIT UNE — — 1r,NT OF WA INE REFERENCES BASIS OF BEARINGS Rt 105-LS-61 1'11E BASIS OF 5-ARING5 101• Trill PRO.;ECT IS DETERMINED FC _6-G9-4I RJ 108-LS-5t BETWEEN FRO FOUND MCNJMENiS PUBLISHED IN THE CITY OF SAN LU15 OBRPO 20U7 HORIZON•AL CONTROL NETWORI, POINT 62DS Rb 'OD 201^_-OO2d61 FOUND 14AIL IN 15 INCH IP.CN PIPE IN MONUMENT WELL IN THE CEN -ERLINE INIERSECNCN 0- JOHNSON AND OR—T. RJ 94-LS-9• N-_'291%" a. E-5774674 730A AND POINT eD97, PIN IN R6 49-PI,'.-52 CONCRETE IN RONOMENT W!_L T THE CENTERLINE INTERSECTION OF TANI, FAFM AND ORCUT- N-?E87643845 F-5-7797060a• BEARING N1C'51•14"W CALIFORNIA COORDINATE <YSTEM ZONE 5, EPOCH 1911 35 NA083 � on i I Illyi iMOt 1 S> -I• UEsp CA 53401 CA B05 SI4.7-07 1 9ECEM13ER 14 :018 SHEET 4 OF 5 51EET5 1 LEGEND r1K�.ya ..j�� / FD 1/2• REBAR '1 1 SET S/6• RE-P W/ I- STAMPED IS 5,3A �� -- _ _ —I ` � ' I° "R�^E 2i&3]• PEP. F1 HELD FOR LINE. LLL </"_l f1F '_I �'i TRUE GORrv[R JE-R` N5E'0?•9 - - I ❑ SET th' IRON PIPE w-i,tG STAMPED IS `_�t 3S CERRD CABRO1f1 LANE AD REEAR AND CAP [AU ILLEVIBLL FEN Rla, a�l - - t-, FT _• ORASO CAP IN ICNLMENT WEL SEE DETAIL C STAMPED LSJ,39 BRASS CAP STAMPED L' 5139 1N MONJMENT N Sf' , .T J - ,— SOD _ _ -a•pp" _:• _ AV PER 3i-MB-55 UI ILE55 NOTED O1HE� SE 24 Y . .6t -_•^-I a r3[ Ea'ISPNC PG,YF. SET 5/E' FEBAF W-CAE STAAIPEJ LS Sl i9 __ FAIEIEI- PER l d ^ OFFSET (SEE DETAIL D ON SHEET a) _ ~ IA D E - _ I x SET '_EAU PnID TACO: ST.:MPEC IS 5139 e LOT 33 I ��•. �S T '-� -: M' D E I I I 1 _ , �52 oR s7a fD MONUMExr As NOTE[ - LOT S M D E_'1 TI 9 iiI LOTS LOT 2 I LOT 3 LOT 4 I LOT 5 I $ LOT 6 $ LOT 7 I LOT 6 r 4 L-2 y `� i�_a � � M D E SmEYARD RETAINNc NAI I. NANTENANCE AND S1D0•U•AI f..00 II i]3.9 SF 373A 4- .'. r,+A :F }TJA Sc 37TA. SF ?' SF I` DRAINAGE EATEN 7 ! C I $ I Ak Ir DEDIIAIILN P L E PUauc UTILITY EASEIAE.NT iREEi -IIFPOSEPcE PUBLIC PEDESTRIAN AC_AS5 EASEMENT 'LOT 32 p ( c NDE . MOE 7s3aYPER THIS IAAP ¢\I'I f.Yl PSPESHAVED ACCESS EASEMENT STE STREET TREE EASEMENT --•.se� 9 �RSICF CALCU,ATEG FROM ___ae ]3 _ .s 7= _-_� ` - ;RAci RADIAL BEARING N - 1 LOT 31 - —41 RC. R,GHr , wAy 373B OF IC' E �S PD FILING n sTE. �. ` — J SEE DETAIA� �1. -, .y / S EPSEAIENI _ ' \•[ 3.�YJ 1 "C 1 C - I P F B 4 E PUBLIC PEDESTRIAN 51C, CLE ACCESS —dJ 0?'- .t 00=y-J�-=�Df1i'L97411oll' �p� —{dap• •33 'l �[ �, ACCESc uENIAI.. DF:J:1T:'. RELINOUISHMENi _ I 0: RIGHTS OF N£HICULAF HGP.ESS A EGRESS — — T, — — .—--LO T 30IF LOT m`—, mr. OT sf OT sF OT s- LOT 12 r. OT fl1 _ _ _ _ _ SLOT 1oLOT 15I BLOT 13 $ ••••••' n � 'rr. LagT NrNow rDIS9CENTLRLIJE CI001T SFOI E1 STNG ROPS IY LINE LOT 29 . ,'pJ1Lf�� ...'.,1 — 4ael[R>ti738 SFLOT 16 pl-Mµ I = MFE+I A'4D� I _ I _ TA I RIGHT JF 'N JxE W 23B SF [ 3WD.T ...) • 1/6[ - - -- - - EASEMENT C +DE • r0C IaPL, + I .�L�+�w+IRT� — }- aTr I .:-0G •- a. GD' --ai DTi RA•DC'tD•r 11, :4 til.N... J-•,6.7 nnr3il•EBAR H Y31. RW G I t"/Y I 'ROE 21807" PER R, 'M� f0— _ !ate I LOT 19 ~ C•��� -RC[ 2to'UY PER R: u. W e - O 0Uf $ HELD FOR LINE, TRUE CORNER 1•3E�AI� � 1 1 tia4 t1[ -- �-• 637e sF FA ECEL 'l_ SEARS HIS 'oo 16-E 122 IOrldY--df i 11 _I ��'I11 v ov[ 1 } Codl G—OG�S 1— — -r I - II ♦ �T[ r3&,J 1 1 IHYLL'OC 4H+E ANI: 1.11 IU;.L r_ —UlC7U'r— 2012-007_361 OFFER RF RFOICAnnN PEF 3 -� LOT 27_ I z — — —� ti +4 DOCUMENT 2I1)mSIDt 373d IF yy I p LOT $ [.•.DKMi IF -_ EASEMENT - DRAINAGE 1 [p LOT 26 — I I? LOT 21 7 1 + 6126 IFLOT o 25 -( 3 P A E 24 .a I ,l1 LOT 22 ` — < — is m 211 G$ �, t :.3.— trj I a LOT 23 h3e3 e,c9 ,F- - ,es.a' m �Vl�if\ ism N ./ PoFcel LIr1c lab(e Length lL•:•. . I- 8518 5-111,11" 14 E- 5763803'E cDD m�,m3t-w ,aeT 7 s,31236•w Id 1] 576 "�_'1E N17N]]] 37' SS3'02'J] W -5CO E <blli•t n695 Si15>'I D"E / ' / INK' P � DET IL C Naa \ I '• \ �� r 1 � co , •\ I • OI 'I I I P / 1C6J !i NS A SUBOIESION OF A PCATION OF Lcf 125 OF THE SUBURBAN TFA01 AS RECORDED IN BCON 1. PAGE 92 OF RECORD CF $ JEYS AND FURTHER DESCRIBED AS PARCEL '. (COA1 10-DO86) OF CERTIFICATE OF COMPLI INCE RECGRDED AS DOCUM:NT NO. 20,2-00366I OF OFFICIAL RECORDS. ALL FILED IN !HE OFFICE OF IHE SAN LUGS D815PD LIEN IY RECIRGER. LYING IN THE UTY IF SA 1 LUI$ 0611P0, F.CILINTY OF SAN LUIS LI�Iz d LI u` L3 TJ 13 LG IS - - _ 'W'- PEi1K1 RIaY ;p Ek15TLY0 RIGHT OF WAr i l36'—P/1s-4 1 i AI— — �- ` Carinon BASIS OF BEARINGS REFERENCES► THE BFSII OF BEARINGS FOR THIS PPOJECT IS DETERMINED RI 105-LE-6, HTWEEN TNO FOUND MONUMENT$ PUBLISHED IN THE CITY OG SAN 15 OBISPO 2007 HORIZONTAL CONTROL IETWORN. POINT 8208: R3 108_LS-51 'DUNE NAIL IIJ , 5 MOTIF IR F PIPE IN NOM1'UMENT WELL IN THE 'I/ tCSO $ou,H.00 Dri+e H4 U. 2012-R02B61 Son was O6.111. CA 93a01 CEM1'TERVN- INTERSECTION OF JIMNSON AND ORC'JFT, I I I I I AOS SJJ ]a07 -'_CRETE IN M NLUENTE-57148)<,] A AND POINT RLIW PIIJ IN RE SI_L$- 51 CONCRETE A MON D ENT TT AT IH=' CEN tERLINE IN:ERSEC IIDN P,6 a9-'RAI-52TEr DECEMBER la. ;DI8 SHEET 5 OF 5 SHEETS OF TANK FARM AND RING N N-22676a38C3 E-5]7>97B,e69. BEARING N36'3:. NA CALIFORNIA COORDINATE , INCH -aO FEET NTS. SYS cN. ZONE 5. EPOCH t591.35. NADd3. ST /- 2017-05 LEGEND J.JLJ EXISTING ppoaosEn is VESTING TENTATIVE PARCEL MAP = = = ==== z A DIVISION OF LOT 48 TRACT 3044 - TAYLOR RANCH CITY OF SAN LUIS OBISPO, CALIFORNIA -"- AYLOR RANCH µ"weRi °°0 �a _ TRACT 3044 6Y " } i DEVELOPER. < w. ns vow xoun # # ' obi,9Qa a ENONEER/SURVEYOR, Q C � ! smm aim Iss".e= ww a...fx V ,'! SITEMEA. 7 m ea.tr wt UTB.IT—,Ohl aevaw .•1. o R ��;�' SUBDIVUfION MAP PNASNO. '� �� ;,`,I, � o � a �•f FLOOD YAPPINO.� µ cr PxcaEx," I p 71,- er lie) a000 AIRPORT I n� Ll VICINITY MAP o. `e .w =I BENCHMARK/BASIS OF ELEVATION. �"'� ""� �� ��" • rxE xEnnu oxnx ra, rxE axVE,- xrru+c xu. axrma nLU x­2 rmEomwsz cuax°x.�n"of_TN a rvR. r PROGRESS 1— .xo ,wxs«. xuE x.Hxc . wsuwm .cFvxnw of s. Qa — now! SET Ll Li BASNi OF BEARNOB. ioxs s cPea ,e9� cs Z a ' / +"4 ••••M• s.s,sxa Iae: (x�e`s�`�ocm�o �.r�� c sm�m;o _ _ r"zo11111E�µpwis �x. uqY� �a9,m....E-. wcr. bs y f REFERENCE DOCUIENTB _ °an orun°xi nn -Dn �:rxa"var so,s minor°I" Ot ` TAYLOR x •� omeAx�sc u o OEOTECXNICALssPEcCFICAr1oM6 \����L_, /y'� R'u" ` 'Fg SECTION AND DETAIL NUMBERING SYSTEM �—I.2 o Vl�l^dig cti o rs"no.Ec ss zo,i°E .rI� mm�. Y / /5to EETw ar a. ox..w«c -T. :vuwi cncx — a a w EARTHWORK a / /*G� ttti0 Ii1 gvn T is'"�s sE�ox �c� r�iVfesy •y ~ F .. ox r Y �, inxnx�,c" a �._: >w .. /' '�/• oa FlEo"ar` . TM u F Pn.r�. �.aoo �. , j� oz o `w _"a"� 1111 QE) a°Er A /'/ I/ G►g` pig/ SHEET INDEXr.o a Flu .xn xCL—.x—A. / � •oomoxu e.vonr vEawxm iE sw� xxs ` l w/• SHEET T SHEET NUMBER ias swmxxxa w nu 1! �, N ' p TRACT 3063 PARSONS > wM'IT ,�✓ sccnwz PROJECT SITE t t ® Co L� CL it m k rn LANDS OF HALL 1 TRACT 3Od3 1327 OR 992 1 1( 1 >° ` 1 , T 1 m1 0 _ r �_ •FAers�,ci- - � I I \, �`, ♦`, ��� \, �., �, \, \., ♦♦ .• .ore '\ 1 LANDS \ PA�tCFL I r 1 \\ - PRATT ,\ S O 5 1JJ—,of 2065 OR , 1 1 I 1 \\I\ �• 1 1 339 1�AL.T 3D44 1 , i , • I)�iiJrLv �1 tI 1 1 i 1 `\ `♦ i - _��-ems---- - I - �� , a y �r %S PARCcL11 `\ tl♦ I i e o' ° .� fIP� AL 10-POSE ` ! I 1 \ \\ ,��`♦ � it 1 i� � t. I i li 11 i 11 �\ \\ `Z ��.♦` O . =Zit. 1 1 1 11 ; \\ ♦\ OjI J�\ ♦ .• II PROGRESS Y 11I 1 1 1 `� \\ ♦♦ ♦j T PARCEL 2 HANDS 0 01 '\ ,1\ gP� `� 1 t COAL EANDERSO , \ `♦ _ 1-� 10-CO8E 1 374 OR 4 , `♦ ♦` 1 1 1 1 \ ♦♦ ` - 1 za N - E 1 1 1 � ♦ .� �� a� O LANDS OF FIAtA a z 1785/OR/547 �� TRACT 305E PHASE oF 1 i (35—MB-41) PARCEL LEGAL DESCRIPTION ---- ._, `�\ ° N 1 1 l i l I Au TYT ft. RWop ory.= r w f 11 eT S- WS mv*. STATE O 4+0n/A . IOIT d IAtm I a co', To-mo AS 1-0 vAAtn a Do,= O TR WI 1 1 Z KCOImD w SM . of I-= W %AA AAA SL CA q[ M M omo[ O TiE [X..T. \ RComo d TK cojS AW or Slu6 40sm STATE of CYIOCF. _ - _-__-_ - / i SHEET // , _ mum PA.F� MM[[ sw "I-aL r--1 , --1 '—figI 1 1 1 � 1 Ls LOT LOT LOT ]6 LOT 3 O LOT 40 1� Lm LOT LT a 1 $i .® Co 6g �g LOT r 9 11 • ' L3 1 c ' LOT LOT , LOT 1.1 ' 7 9T ' 11 �► l/1 IRACT 3X4 PIIAS I I LOT LOT LOT i tot I BY SUWTANTIAL - —� a 14 13 12 , 11 i a �1 WITIMMNCE Dunau om".4 — NUr A PA= cu LOT Lo, 0. 1 I LOT 1 13 111111111 I PROJECT STATISTICS LOT TYPE LOTS AREA (ACRES) I R-2: MEDIUM DENSITY RESIDENTIAL 47 4.98 11 R-2: MEDIUM DENSITY RESIDENTIAL 6 0.54 II R-3: MEDUIM-HIGH DENSITY RESIDENTIAL 1 2.27 RIGHT-OF-WAY 2.21 PROGRESS SET C3 7 O� o r M 1 1 1 1 ?al� ORAE - n on+oe A rs +Ioat r.. nma tw �yl - RAMCM Ma7Y ROAD UCTWN - STA 220D TO 901aAA 1 ur rl�r• _� �.ee s.. .ws son 1 w cra ... r .un1 wt IUD eAsau Doll - sTown ava aa. Ie1iwl lar 4 R � I I df[£- .I�I w I �w FAM C&IM LAW STCTlD11 s...w � - .� oac w• wrw IIm ole , ra.s.�. S RAMGN MOM ROW SEC" STA 20+W - 22+W C 2 . - 000ae —1 �•. VROOAESS 8ET C4 izRACF 30 CEPRO GERKLD IANE r--77-777-7 a rVe 1 1L.�etN�Raeius oNto n owo •ar ,L 'ARC FAac�� ] � II ---- � �I II II I� I� II ww � II I 1 _ L a: ® �e H� 3Y c o ; Im 3�B 0 I/ % �! 100 1!f Ka li Xb S7! s0 fl0 700 se a 3 eR its PROGRESS SET Z Z< J o a F- 3 o Q nF Z 3 z < OONMR>JMON NOTO c� Nz z �s v`vi.z""f"'o�° off.,wrz ow m.n gym. i�o�w, p �.E , �. owu..o �owwo ,o �� ro. n SHEET C 6 i $i i b �9 6 � HHHH 1 � DMA Cl nTF1nw s i IIIIIII _ _ � IIIIIII I __ 1 _ ' � �=�•tt p- III 0 I I I � '-' � � •tr. �ft / (IIIIIII f3 IJ I LI _ 1 [1 1 PROGRESS 1 pt � BET L� p w�n�ie q.na V, 1 ' DMA -Al a z 1 i i s ozEE 3 1 m eF � Exhibit B TAYLOR TRACT 3044 FEE CREDITS FOR OASP PEEP IMPROVEMENTS IMMM Maximum allowed OASP PEEP improvements to be constructed by Tract 3044 $45,000 Total remaining credits allowed or reimbursement due Tract3044 by others $0 Maximum allowed reimbursement due City Total remaining reimbursement due City Maximum allowed reimbursement due Orcutt Associates Total remaining reimbursement due Orcutt Associates $179,603 ($273,390) $412,812 $0 NOTE 1: OAS P TIE estimate per 2018 PEEP update for one bus stop NOTE 2: $339,065 was advanced by Orcutt Associates for Laurel/Orcutt improvements per the Tract 2707 credits and reimbursements spreadsheet plus a CPI increase from October 2007 to September 2018 of 21 75%as provided to the City by Orcutt Associate NOTE 3: City is owed $179,603 for amount fronted by City to cover OASP share of the Broad/South improvements. City is first in line for reimbursement