COUNCIL CONSIDERATION OF THE FOLLOWING CONTRACT PAY ESTIMATES
S. Brett Whitaker Est . #3 S 7.291 .08
MISSION PLAZA WALKWAY
AND PATIO KIOSK
M-02Y & M-03Y
Madonna Construction Est. #4 S 125,397.21
HIGUERA ST. WIDENING PROJECT- C.C.O. #1 - 2,695.00
MADONNA ROAD TO MCCRACKEN'S TIRE C.C.O. #2 735.04
CP K-25B C.C.O. #3 374 .65
C.C.O. #4 131 .08
C.C.O. #5 - 9,922.72
C.C.O. #6 - 92. 25
Development Service. Inc. Est. #3 $ 6,999.30
Bus Passenger Waiting Shelter: Est. #4 FINAL 1 ,374 . 70 ( 11/7%88)
Madonna Road
CP M-38R
Union Asphalt, Inc. Est. #1 S 153,651 .47
STREET RECONSTRUCTION AND
RESURFACING PROJECT, VARIOUS
LOCATIONS
CP M-08A
Christoff Technical Services Est. #1 S 39,990.87
WATERLINE IMPROVEMENT PROJECT,
JENNIFER ST. , ELLA TO GEORGE ST. ,
JENNIFER TO END
CP M-27P