HomeMy WebLinkAbout05/21/1991, 6 - PLANS AND SPECIFICATIONS FOR CRACK REPAIR PROJECT FOR PALM STREET AND MARSH STREET PARKING STRUCTURES, CITY PLAN NO. R-39D Original Agenda report-"- mm 5/7/91 meeting. /
MffT1NG DATE '
city of san gats owpo
COUNCIL AGENDA REPORT IT6vl NUMBER.
FROM:
David F. Romero, Public Works Director
SUBJECT:
Plans and specifications for crack repair project for Palm Street
and Marsh Street parking structures, City Plan No. R-39D
CAO RECOMMENDATION:
By motion, approve the plans and specifications for crack repair for
the Palm Street and Marsh Street parking structures and authorize
solicitation of bids and awarding of contract if lowest responsible bid
is within Engineer's estimate
BACKGROUND:
At its meeting of March 19, 1991, the City Council considered plans and
specifications for sealing a number of cracks in the walls of the two
parking structures. Council was concerned that these cracks
represented some level of failure of the parking structure, or improper
workmanship, and requested that staff obtain additional information
justifying the need for this work. Attached are letters from Conrad
and Associates, the original design consultant; Fred Schott and
Associates, a local structural engineering firm hired to investigate
the cracks on the Marsh Street structure; and Applied Engineering, a
local engineering firm hired to investigate the Palm Street structure.
All three of the consultants recommend epoxy injection of the cracks so
as to prevent corrosion of the reinforcing steel. All three indicated
that these are primarily surface cracks and not structural in nature.
Conrad indicates that these cracks are not uncommon in this type of
structure. None of the consultants indicate, nor does the staff
believe, that the cracks are a result of improper workmanship. Even if
improper workmanship could be proven, the contractor guarantee is for
one year and it is now more than two years since the Palm Street
structure was accepted. 94% of the crack sealing will take place at
the Palm Street structure.
DISCUSSION:
Staff believes that this kind of cracking is inherent with this design
of structure and that it still must be protected or face the risk of
ultimate failure of the parking structure due to corrosion.
ALTERNATIVES:
1. The project could be delayed until a later date, with a probable
increase in cost and probable corrosion damage to the steel.
2. The project could be reduced by eliminating the Marsh Street
structure from the contract, since these cracks are very, very
minor and are generally closed during the warmer weather thus
minimizing the rain water penetration to the steel.
,��r��'�►fullllllllll� ������ll city of San tins OBlspo
1 1111 .0 COUNCIL AGENDA REPORT
Crack Sealing
Page Two
3. Conduct work with City forces. If the contract approach is not
approved, staff will have to attempt the epoxy injection with its
own forces. Staff would rent equipment and materials locally and
attempt to do the job. However, we are not expert in this type of
operation and are not likely to do as good a job as a contractor
specializing in this work.
4. Do nothing. Staff does not feel that the option of doing nothing
is a viable one, since the structures would ultimately be subject
to failure because of lack of proper maintenance.
FISCAL IMPACT:
The Engineer's estimate for the project is $42,000. This is a new
project and monies have not been allocated for this repair work in the
current budget. Funds will have to be allocated from the undesignated
fund balance of the parking program. As reflected in the recent mid-
year budget review, adequate balances are projected at year end to fund
this project. However, the long-term financial status of the parking
system continues to be a concern, and any unprogrammed outlay reduces
the funds available for future capital purchases, such as acquisition
of a third parking site.
i
i
I
Attachments: Council Agenda Report, 3/19/81
Conrad letter, April 10, 1991
Fred Schott letter, September 28, 1990
Applied Engineering letter, November 9, 1990
Page from specifications
I
NOTE: Plans and Specifications are on file in the City Clerk's Office.
i
i
i
I
I
crackseal/dfr#28
p�l��►B��Ilulllllllll`�IIUIII "J r ME ING DATE:
�p�ml Cl o san �Uis oB�spo � / s- �
COUNCIL AGENDA REPORT ITEM NUMBER:
FROM:
Dave Romero Wayne Peterson Prepared by: Reith Opalewski
Public Works City Engineer Parking Manager
SUW:
Plans and Specifications for Crack Repair Project for Palm Street
and Marsh Street Parking Structures.
CAO RECOMMENDATION:
By motion, approve the plans and specifications for crack repair
for the Palm Street and Marsh Street Parking Structures and
authorize soliciting of bids and awarding of contract if lowest
responsible bid is within Engineer's estimate.
BACKGROUND:
Since the completion of the Palm Street Parking Structure in March
1988, there have been a number of structural cracks in the walls
and floors. This is common with structures of this construction.
These cracks are easily penetrated by water which is causing
deterioration of the concrete and metal reinforcement in the walls
and floors. If allowed to continue unchecked, this water
penetration could cause serious damage and costly reconstruction to
the structure. There have been similar cracks in the floor area of
the new Marsh Street facility, but to a lesser degree.
DISCUSSION:
Through an epoxy injection system the floors and walls of both
structures can be sealed to prevent further water damage.
Approximately 3100 linear feet will have to sealed in the Palm
Structure and 200 linear feet in the Marsh Structure. This
application process in the most cost-effective and can be done with
a minimum of disruption to the operations of each structure.
The life expectancy of this project is unknown because of the
nature of post-tension concrete contruction. Periodic inspections
will be required to determine if additional repairs are needed.
CONCURRENCES:
The Engineering and Parking Divisions concur with the
recommendation to epoxy seal the walls and floors.
FISCAL II4PACT:
The Engineer's estimate for the project is $42, 000. This is a new
project and monies have not been allocated for this repair work in
CTL / Of San L ,.,S OBISPO
COUNCIL AGENDA REPORT
Council Agenda Report
Page Two
the current budget. Funds will have to be allocated from the
undesignated fund balance of the parking program. As reflected in
the recent mid-year budget review, adequate balances are projected
at year end to fund this project. However, the long-term financial
status of the parking system continues to be a concern, and any
unprogrammed outlay reduces the funds available for future capital
purchases, such as acquisition of a third parking site.
ALTERNATIVES:
1. Delay the project to a later date j
2. Reduce the scope of the project i
3. Cancel the project
PROS AND CONS
I
It is possible to postpone the project, especially in light of our
limited rainfall. However, any additional moisture from
condensation or light rain will only accelerate the concrete
deterioration. The longer we wait, the more costly for future
repairs. Repairing only part of the cracks or completing only one
structure would be less expensive in the short-term, but more
costly in the long-term since the bidding and contract process j
would have to be repeated. Cancelling the project would be short
sighted and only cause more serious problems in the future.
Approved:
I
City Administrative Officer
I
tt ey
I .. I
City Finance Director
!
Public Works Director
I
(l/ — 1
Conrad Associates
5990 Sepulveda Wd.,Suite 200
P.O.Box 514
Nkn Nuys,CA 91408-0514
(818)901-0853
Apr i 1 10, 1991 (800)4Conrod In sa ffi m Caffom
(800)533-7049 In caffgnla
(818)901-7504 FAX
David F. Romero, Director
Public Works Department Raymondlraya
955 Morro Street P1e*11811
San Luis Obispo, CA 93401 J.Renard 1ef
6mcUmre VIMaaeloUK
Dennis Slmonlan,AIA
Afcht d
Re: Palm Street Parking Structure and Antonio S.Wlsoni
Marsh Street Parking Structure A00*ft S.E.
Dear Mr. Romero:
We received your letter dated March 26, 1991 in regards to epoxy
injection for crack repair. The undersigned paid a visit to the
structures on April 4 , 1991 and walked through the two parking
structures with Tom Gingg to see the cracks referred to in your
letter. In the Palm Street parking structure the cracks in the
concrete walls and slabs appear to be of the same size and location
as observed about a year ago. These cracks are caused by shortening
(creep and shrinkage) of the postensioned floor system and are not
uncommon in this type of structure.
Since it was a very warm day it was practically impossible to find
the slab cracks (which were leaking according to Tom Gingg) in the
Marsh Street structure.
Even though the above captioned cracks do not impair the structural
safety of the structure, the cra�k ��sealed bby en�oxy
injection to preventa f,rt,r� rnrrc�d;nQ o�obm of,, e__reinforcing
steel and lengthening the useful life of the structures.
We hope this information is sufficient for your needs at this time.
If you have any questions please call.
Sincerely,
CONRAD ASSOCIATES
Antonio S. Luisoni S.E.
Associate
APR
A DMSION OF CONRAD BUILDING SMMS.INC.
Fred H. Schott 81 Associates, Inc.
CIVIL&STRUCTURAL ENGINEERING•LAND PLANNING R E C E I V E D
SEP 2 8 1990
Se tember 27 , 1990 ENGINEERING DIVISION
P cm of SAN LUIS OSISM
Mr. Wayne Peterson
San Luis Obispo City Engineer
955 Morro Street
San Luis Obispo, CA 93401
Subject: Slab Cracking in the Northerly half of the Parking
Structure Slab at the roof level
Dear Wayne:
Per your request we have made a site inspection, reviewed the original
concrete mix designs prepared by Kaiser (#56055 & 6084 dated 5/26/89)
and the revised and apparently approved mix design by Pacific Geoscience
(Job No. PT-5420-W01 dated Sept. 7 , 1989) . We have also reviewed the
General Structural Notes and specification requirements for concrete in
the Construction documents as well as made a cursory examination of the
structural plans and details as they might relate to slab cracking.
The original (Kaiser) mix designs would have resulted in substantially
greater shrinkage than the Pacific Geoscience mix design. While the mix
design used is considerably finer than a mix designed to minimize
shrinkage, it was obviously satisfactory in most of the structure.
Most of the visible cracks in the northerly half of the roof slab run
parallel to the beams (perpendicular to the direction of span for the
slabs) . Some of these cracks do not extend through the slab while
others do. There are a few cracks on the underside of the slab in the
most northerly bay which are perpendicular to the beams (parallel to the
slab span) .
Our professional judgement is that the partial depth cracks in the top
of the Slab are nl a-Etic _hri.^.kage C�.1.ck '::i,i1c the full dept-h .^..^..'�..$ :an
y— y.. s. .. ..•
draping shrinkage cracks emanating from the plastic shrinkage cracks. It
is quite probable that this particular pour was made on a relatively
dry, windy and probably warm day. None of acks aDDear to be
s+rt•.. *�*��l—�a >,_g___and should not af_ ec. th<e_structgrjpLlpe�f,ormance__of
th lab : n the near future Unfortunately_thr- full_depth.._cracka.._. wiJ.l
allm rainwater to__penetrate_t-o_.the.-.slab_.r..einfor.c n.g steel resulting ir_
fu ter .rus.zn -
_g_of the__.teinfor-cing._and ..4palling_of _the...adjacent concrete.
Tl�oncrete should__be sealed. to prev_en _._.Lhis__..fut.u>te _deter crati.on.
Evox% grout of� a crjzks u installation of a_surface membrane _ will
accom lish that erbd. we would recommend the latter course since one
would seal the entire surface--not just the larger cracks. This surface
membrane must have sufficient flexibility and elasticity to bridge over
any and all cracks.
SAN LUIS OBISPO OFFICE
(805)544-7276 SANTA MARIA OFFICE (805)925-3433
200 Suburban Rood.Suite A 9 San Luis Obispo.California 93401 222 west Carmen Lone.Suite 104 • Santa Marla.California 93454
'iptember 27 , 1990
Wayne Peterson Page 2
The cracks in the bottom surface of the end bay appear to reflect the
prestressing strands and probably resulted from movement of the strands
during concrete placement in the adjacent bay while the concrete was
only partially hardened. Again these cracks do not appear to be
structural in nature and should not affect the performance of the slab.
The reinforcing steel in the slab is parallel to the cracks and may or
may not be subjected to moisture in the cracks. It would probably be
wise to seal by epoxy grouting or caulking.
A second note of concern relates to the lateral force resisting system
in the structure. The project structural calculations (sheets R1
through R47) do not cover lateral forces and a review of the plans does
not reveal any obvious comprehensive and integrated lateral force
resisting system. We suggest that you obtain copies of the lateral
force system calculations and check the plans to insure that the
calculation results have been incorporated into the plans and details.
If you have any further questions in this matter please do not hesitate
to contact us.
. Sincerely yours,
Fred H. Schott
FHS:nsb
i
APPLIED
O ENGINEERING
P.O. Box 4445 708 Fiero Lane, Unit 12
San Luis Obispo, California 93403 David M. Carter P.E.
805/544-5684 Jeffrey CTParker P.E.
November 9, 1990 C E i V a o
City of San Luis Obispo NO VI
Engineering/Parking 3 1990
955 Morro street �''a Esn�,u,�0er�
San Luis Obispo, California 93401
Attention: Wayne Peterson
Subject: 290087 -- Palm Street Parking Garage
Evaluation of Concrete Cracking
Dear Wayne:
in accordance with your request, we observed existing cracking of
concrete shear walls at the subject project with you on September
4, 1990.
Generally the cracks observed were diagonal cracks extending from
the top outer ends of shear walls to the interior lower edge of
the shear walls. These cracks appear at lines of resistance
where shear walls occur at opposite ends of the building such as
at the north and west wall. For the purpose of this reportsouth an, Palm
Street
is
walls which occur eapproximately rmidlengthth and uof.
thethTha buildingd heast
ave
sustained no discernable damage.
The west wall is continuous across the west end of the building,
but is divided into 3 effective walls by control joints.
virtually all of the cracking in the west wall occurs in the two
end sections. The north wall occurs in two sections at opposite
ends of the building, and the cracks are most severe near the
ends of the building. in addition, the cracking was noted to be
more severe at the lower levels.
There is a pour strip extending across the structure at
approximately midlength. This effectively uncouples the shear i
walls along the north side from the effects of elastic
shortening. The cracks appear to be a little more severe at the
west end shear walls where there is no such pour strip to
mitigate the effects of elastic shortening.
The floor slabs are prestressed and are subject to the volumetric
changes associated with prestressing. The walls are not
prestressed, and undergo no such volumetric changes . The floor
slabs' are cast into the walls.
i
Wayne Peterson
November 9, 1990
page 2
It is our opinion that the cracks in the shear walls are due to a
combination of stresses caused by elastic shortening of the floor
slabs due to prestressing, and creep in the floor slabs due to
the sustained compression from prestressing. Essentially,
top ends of the shear walls together b
rigid in compariare being pulled
floor slabs, and the bottoms of the shear walls are relatively _
son. The diagonal cracks described above are the
result. The west end wall is being stressed by the slab from
both elastic shortening and the continuing action of creep in the
slab. The north end wall is being stressed by the slab primarily
from creep in the slab due to the sustained compression from
prestressing, and not from
Since the length of the slab is subsoritantiallynal more
shortening.
width, the effects of only the Gree more than the
direction have an effect similar to the sum of elasticthe shortening
and creep in the transverse direction.
The total effects of creep can be in the range of double that due
to the initial elastic shortening. Based upon the a
age of the structure, we estimate that between 70% and 85%oOfmthe
effects of. creep have been experienced to date.
We have reviewed the material we received which was Sup
contain calculations showing the magnitude of stress intheeshear
walls. This documentation
operation of the programs used�toained calculateythe xshear swalls, and
"ad no actual calculations for the specific ro 'ect. of the
do not know the level of stress in the shear walls. Th However,
we must assume they are fairly highly stressed, and cannot
accomodate the partial loss of the concrete component of shear
resistance due to the cracking.
We recommend that epoxy
who has
Tis may a accomplished b iniactinn he fi=n—moo Leit_he
previouslyY the injection . sub-contractor
parkin Performed similar work on the Marsh Street
g structure for which we
assume exist. Alternately, it may be accomplished
fiwithonmaterials
available locally. We have investigated an injection system by
Anchor-it, and have
specifications Prepared the attached guideline
to describe groposed materials and procedures for
the Anchor-it system. These materials are available locally
through Cuesta Equipment, but the process requires some training.
Therefore, the procedure must be supervised by a contractor
or
manufacturer's representative experienced in this type of work .
You should be aware that since not all of the creep has occurred
as described above, it is possible that additional cracking will
occur after the current cracks are repaired. We- do
the_t _you wait to E�air the cracks since the ema�n ercof�the
creep w'IT't`ake a number of years to occur, and if the cracks
become contaminated, any injection may be an ineffective repair.
We suggest that you repair the current cracks, and resolve
problems of any further cracking if and when they occur.
�j
Wayne Peterson
November 9, 1990 page 3
It is the intent of the procedures described above to return the
shear walls to as near their new condition as possible. It will
restore the monolithic structure of the walls. It will not
increase their load carrying capability above that originally
available, nor will it necessarily preclude future cracking.
Therefore,' we cannot be responsible for the original design of
the structure. This responsibility remains with the original
design Engineer.
We hope this information is sufficient for your needs at this
time. If you have any questions, please call.
Sincerely yours,
afE3S/ MU
pyq�r,-
v Z.
David M. Cart r No. 1955 .
SE1955/9-30-93 z SER 3O1998 .= ,�
Jlq UCN�P
—� Of CALF i iii►
SECTION 5. LEGAL RELATIONS AND RESPONSIBILITIES TO THE PUBLIC.
.S
Y. Relief from Maintenance and Responsibility. Upon the request of the
Contractor, the City of San Luis Obispo may relieve him of the duty of r
maintaining and protecting certain portions of the work that have been
completed in all respects in accordance with the requirements of the
Contract and to the satisfaction of the Engineer, and thereafter except
with his consent, the Contractor will not be required to do further work
thereon. In addition, such action by the City will relieve the Contractor
of responsibility for injury or damage to said completed portions of the
work resulting from use by public traffic or from the action of the
elements or from any other cause, but not from injury or damage resulting
from the Contractor's own operations or from his negligence.
However, nothing in this Article "W" providing for relief from maintenance
and responsibility will be construed as relieving the Contractor of full
responsibility for making good the defective work or materials found at
any time before the formal written acceptance of the entire contract by
the City of San Luis Obispo.
Z. Personal Liability. Neither the City Council, the City Engineer, nor
any other officer or authorized assistant or agent shall be personally
responsible for any liability arising under the Contract.
A-A. Responsibility for Damage. The City of San Luis Obispo, the City
Council, the City Engineer, or his authorized assistants or agents, shall
not be answerable or accountable in any manner for any loss or damage that
may happen to the work or any part thereof, or for loss or damage to any
material or equipment used in performing the work.
B-B. Responsibility of the City. The City of San Luis Obispo shall not
be held responsible for the care or protection of any material or parts of
the work prior to final acceptance of the work, except as expressly
provided in these specifications.
C-C. Guarantee. The Contractor shall be responsible for faulty materials
or vnr4n�nah+n and shall remedy any defects resulting therefrom appearing
within one year from the completion of the project and shall pay for any
damage to other work resulting therefor. �q,,M jT ;
D-D. Acceptance of Contract. when the Engineer has made the final
inspection and has determined that the contract has been completed in all
respects in accordance with the plans and specifications, he will
recommend that the City of San Luis Obispo formally accept the Contract.
Unless conditions to the acceptance are imposed by the City of San Luis
Obispo, immediately after acceptance by the City, the Contractor shall be
relieved of the duty of maintaining and protecting the work as a whole,
and he will not be required to perform any further work thereon, except as
provided in Article "C-C", Guarantee, in this Section of the
specifications.
• 5-e