HomeMy WebLinkAboutItem 6g - Award Construction Contract for the Grand Avenue Sign & Striping Modiciations, Specifications 2000615-01 Item 6g
Department: Public Works
Cost Center: 9501
For Agenda of: 10/21/2025
Placement: Consent
Estimated Time: N/A
FROM: Aaron Floyd, Interim Public Works Director
Prepared By: Luke Schwartz, Transportation Manager
SUBJECT: AWARD A CONSTRUCTION CONTRACT FOR THE GRAND AVENUE
SIGN & STRIPING MODIFICATIONS, SPECIFICATION NUMBER
2000615-01
RECOMMENDATION
1. Authorize the City Manager to award a construction contract to Toste Construction,
Inc. in the amount of $228,890.00 for the Grand Ave Sign and Striping Modifications
project, Specification Number 2000615-01, using remaining funds in the 2024
Roadway Sealing project account (2000615); and
2. Approve the plans (Attachment A) and specifications (Attachment B) for the Grand
Avenue Sign and Striping Modifications Project, Specification Number 2000615 -01;
and
3. Authorize the City Engineer to approve Contract Change Orders not to exceed a total
construction contract value of $275,000, using remaining funds in the 2024 Roadway
Sealing project account (2000615).
POLICY CONTEXT
On May 17, 2022, Council approved a Purchasing Policy Update to the Financial
Management Manual that required Council approval for Public Projects that cost over
$200,000.
Implementation of the project aligns with the City’s Draft Vision Zero Action Plan, and
Traffic Safety Report, which recommend improvements such as modifications to the
Grand Avenue/Loomis intersection and measures to reduce vehicle speeds along Grand
Avenue. Additionally, the project supports the City’s Major Goals of Climate Action, Open
Space, and Sustainable Transportation by improving safety and access to sustainable
transportation modes.
DISCUSSION
As part of the 2024 Roadway Sealing Project, a pilot complete street project was installed
on Grand Avenue, with the purpose of reducing excessive vehicle speeds, improving
bicycle and pedestrian facilities, and enhancing safety for all road users. The pilot project,
Page 139 of 415
Item 6g
which was completed in March of 2025, included a “road diet”1, new and enhanced
pedestrian crossings, buffered and protected bike lanes, and turn restrictions at the Grand
Avenue/Loomis Street/US 101 Southbound Ramps intersection to address collision
trends. These improvements were installed using lower-cost, temporary materials to allow
for further monitoring before implementing permanent improvements in the future when
Grand Avenue is scheduled for repaving (planned for summer 2027).
While preliminary monitoring and community feedback indicate that some of the intended
benefits of the pilot complete street project have been observed in terms of high-end
vehicle speed reductions and increased comfort for pedestrians and bicyclists, Public
Works staff is recommending some refinements to current design elements now rather
than waiting for the permanent roadway improvements in future years. These
refinements, described herein as the Grand Avenue Sign and Striping Modifications
(Project), include the following:
1. Northbound Grand Avenue Restriping – Restripe northbound Grand Avenue
between McCollum and Slack Street to begin the transition from one -to-two
northbound travel lanes several blocks further upstream of the Cal Poly entrance.
While the current road diet configuration operates acceptably for the vast majority
of the day, increased vehicle queues have been observed in the northbound
direction for the 15-minute peak period of the morning weekday commute into Cal
Poly, specifically during the early weeks of each quarter. The proposed restriping
will add additional vehicle queuing capacity to reduce spillbacks during the morning
commute and special events, minimizing potential for traffic to spill back to the US
101 ramps. See Figure 1 below for modified road diet limits.
2. Additional Flex Posts – Additional flex posts will be installed in areas where illegal
or unsafe vehicle maneuvers have been observed, such as at the Grand & Loomis
intersection, where some drivers are making illegal left turns. Flex posts fronting
the SLO Classical Academy will also be shifted to provide more width for vehicles
to queue on Grand Avenue during afternoon school pick-up times without illegally
blocking the bike lane or adjacent vehicle lane.
3. Measures to Improve Visibility and Safety at Grand Avenue & US 101 Southbound
On-Ramp – Observations of traffic conditions on southbound Grand Avenue
approaching the US 101 Southbound On-Ramp indicate that further measures are
needed to reduce vehicle speeds and potential conflicts between turning vehicles,
pedestrians, and cyclists. The Project includes (a) addition of a radar speed
feedback sign on southbound Grand, (b) addition of a “TURNING VEHICLES
YIELD TO BIKES/PEDS” warning sign with flashing beacon at the on -ramp, and
1 A road diet typically involves the narrowing or removal of vehicle lanes on a multilane roadway where
traffic volumes can be accommodated with fewer traffic lanes. Road diets are identified by FHWA as a
proven safety countermeasure that reduce crashes by 19%-47% on average. The pilot road diet on
Grand Avenue reduced the roadway from five lanes to three lanes from just north of Monterey Street to
just south of Slack Street.
Page 140 of 415
Item 6g
(c) revisions to pavement markings to increase visibility and clarity of the road
configuration for vehicles entering the on-ramp.
Figure 1: Revised Grand Avenue Road Diet Limits
Project Plans are provided as Attachment A, and Project Specifications are provided as
Attachment B. The striping modifications on Grand Avenue were originally included as a
bid alternative in the Roadway Sealing 2024 project, which was completed in March 2025.
As part of the project, Grand Avenue was reduced from two lanes in each direction to one
lane in order to improve multi-modal transportation and safety for all road users. Following
completion, staff received feedback from representatives of San Luis Obispo Classical
Academy, local residents, and Cal Poly expressing concerns with the new striping
configuration, specifically regarding vehicle queuing on northbound Grand Avenue during
the peak morning commute and during large events at Cal Poly. In response, staff
monitored the intersection and observed traffic congestion and vehicle queues extended
back to Loomis Street and nearing the US 101 ramps during the peak 15 minutes of the
morning commute.
Initial engineer’s estimates, based on recent construction bid costs, indicated that total
Project costs were anticipated to remain under $200,000, which is within the threshold
that can be approved at the City Manager level per Section 203 of the City’s Purchasing
Policy. Staff advertised the Project in late spring 2025 with the goal of completing
improvements during the Cal Poly summer break. A bid opening was held on June 24,
2025, at which only one bid was received. The bid amount significantly exceeded the
engineer’s estimate of $130,000, as shown in the table below. Upon revie w, staff
determined that the sole bidder, Sterndahl Enterprises, failed to submit the original copy
of their Bidder’s Bond, rendering the bid non-responsive and leading to its rejection. Staff
subsequently re-advertised the Project, extending the advertisement period to encourage
broader participation and more competitive bids.
Page 141 of 415
Item 6g
Table 1: Bid results for the bid opening held on June 24th,2025
The project was re-advertised, and a second bid opening was held on August 21, 2025.
Two bids were received; however, both exceeded the Engineer’s Estimate.
Table 2: Bid results for the bid opening held on August 21,2025
Staff recommends awarding the construction contract to Toste Construction, Inc., who
was determined to be the lowest responsive and responsible bidder following a review of
the bid forms for compliance with the project requirements.
Previous Council or Advisory Body Action
The Grand Avenue pilot complete street improvements were originally approved by City
Council on May 21, 2025 as part of the 2024 Roadway Sealing project, which was also
presented to the City Active Transportation Committee (ATC) for concurrence . The ATC
did not object to the proposed modifications, but did e xpress interest in exploring further
intersection improvements at the Grand/ Ave/Slack Street intersection in the future, such
as a traffic signal or roundabout, which may reducing queuing and allow for potentially
restoring the full northbound lane reductions at a later date. An update on the proposed
sign and striping modifications was provided by staff to City Council via email on February
26, 2025, and these proposed changes were presented to the Active Transportation
Committee (ATC) at their March 20, 2025 meeting.
Public Engagement
Grand Avenue pilot complete street improvements were originally included in the 2023–
2025 Financial Plan as part of th e Roadway Sealing 2024 project, which was supported
by an extensive public outreach effort. This effort included presentations and regular
coordination with Cal Poly, a public workshop at the City/County Library, multiple
presentations to the ATC, community workshops, and the development of a dedicated
project website. Direct mailers were also sent to residences and schools along Grand
Avenue. Since completion of the pilot project installation, staff has engaged with
representatives of Cal Poly, Teach Elementary and SLO Classical Academy, SLO
Garbage, and collected input from various community members. A few minor
modifications were already implemented based on this input, such as removing/shifting
flex posts at select locations. The most prominent areas of feedback that led to the current
sign and striping design recommendations were (a) concerns about northbound queueing
on Grand Ave during the AM peak commute period, and (b) lingering concerns regarding
high speeds on southbound Grand and turning conflict s at the US 101 Southbound On-
Engineer’s Estimate Sterndahl Enterprises LLC
$130,000 $225,972
Engineer’s Estimate Toste Construction, Inc Sterndahl Enterprises LLC
$130,000 $228,890 $244,972
Page 142 of 415
Item 6g
Ramp. A more robust “after study” data collection and public outreach effort will be
conducted later in 2026 to help guide permanent design recommendations for Grand
Avenue as part of the planned 2027 Paving Project.
CONCURRENCE
This Project has been reviewed and has concurrence from the City Public Works
Department, Finance Department, City Attorney’s Office, and City Administration.
ENVIRONMENTAL REVIEW
The Project qualifies for an Exemption to the California Environmental Quality Act
pursuant to State CEQA Guidelines Sections 15301 (Existing Facilities) because the
Project consists of the repair and maintenance of existing roadways, and minimally
disruptive surface improvements within an existing built urban environment (pavement
markings sign posts, etc.) in which there is negligible or no expansion of use. A Notice of
Exemption will be filed through the Community Development Department .
FISCAL IMPACT
Budgeted: Yes Budget Year: 2025-26
Funding Identified: Yes
Fiscal Analysis:
The total estimated cost for the Project is $275,000, which includes $228,890 for the base
construction contract plus construction contingencies. The project will be funded from the
2024 Roadway Sealing project account (2000615), which has a current balance of
$451,525, comprised of Local Revenue Measure and SB1 Road Repair funds. If
approved, after the reallocation, there will be $176,525 remaining in the Roadway Sealing
2024 account.
Funding Sources Total Budget
Available
Current Funding
Request
Remaining
Balance
Capital Outlay Fund Local
Revenue Measure -
Roadway Sealing 2024 $430,625 $254,100 $176,525
(2000615)
SB1 Road Repair Fund-
Roadway Sealing 2024
(2000615)
$20,900 $20,900 $0
Total $451,525 $275,000 $176,525
Page 143 of 415
Item 6g
Fiscal Impact Summary
Grand Ave Sign and Striping Modifications, Specification No. 2000615-01
Grand Ave Sign and
Striping
Modifications
(2000615-01)
Grand Ave Sign and
Striping
Modifications
(2000615-01) Project Totals
Funding Source Capital Outlay Fund -
LRM SB1 Fund
Fund # 401 211
Bid Total: $207,990 $20,900 $228,890
Contingencies (20%) $45,110 $0 $45,110
Total for Construction $249,588 $20,900 $270,488
Public Relations $0 $0 $0
Materials Testing: $500 $0 $500
Printing: $500 $0 $500
Total Project Cost $254,100 $20,900 $275,000
Capital Outlay (LRM)
- 2000615-01 $254,100 $254,100
SB1 Funds - 2000615-
01 $20,900 $20,900
Total Project Budget
(2000615-01): $254,100 $20,900 $275,000
Any additional unspent funds after project completion will be transferred to the Street
Reconstruction and Resurfacing account for further implementation of the Pavement
Management Plan or to the completed projects account.
ALTERNATIVES
Deny approval to award the Construction Contract. City Council could choose to deny
the award of the construction contract to Toste Construction, Inc. This alternative would
delay the implementation of planned improvements along Grand Avenue, which are
intended to enhance safety and mobility for both drivers and bicyclists.
Page 144 of 415
ITEM 6g -AWARD A CONSTRUCTION
CONTRACT FOR THE GRAND AVENUE
SIGN & STRIPING MODIFICATIONS,
SPECIFICATION NUMBER 2000615-01
Key Questions on the Grand Avenue Sign &
Striping Project
1.Northbound Queuing at Grand Ave/Slack St
2.Pilot vs. Permanent Design
3.Costs Higher Than Anticipated
4.Grand/Loomis/US 101 SB On-Ramp Intersection Design
Grand/Slack Intersection Northbound Queuing
10/21/25 at 7:55 am
Grand/Loomis/US 101 SB On-Ramp Intersection
Westbound View
Current Configuration Proposed Configuration
Grand/Loomis/US 101 SB On-Ramp Intersection
Southbound View
Current Configuration Proposed Configuration