HomeMy WebLinkAboutItem 15 - COUNCIL READING FILE_c_Project Review Presentation NEW (2)CAPITAL PROJECTS
UPDATE
OCTOBER 2020
RECOMMENDATION
Receive and file a status report on key projects within the City’s currently
adopted Capital Improvement Plan
20/21 CIP BUDGET SUPPLEMENT REFRESHER
20/21 CIP BUDGET SUPPLEMENT REFRESHER
CIP Project Prioritization:
•Proceed: Construct in FY20/21
•Proceed: Continue Planning/Design
•Hold: Shovel Ready for Future
Funding/Stimulus
•Defer (Defunded by FY20/21 Budget)
20/21 CIP BUDGET SUPPLEMENT REFRESHER
243 CIP
Projects
$207.8M
Deferred CIP
Projects
45 Projects, e.g.:
-Laguna Lake Dredging
-Fleet Replacements
-Farmer’s Market Bollards
-Sinsheimer Stadium
Irrigation and Drainage
Replacements
-California/Taft RAB
-Anholm Greenway Phase
2 (Ramona to Downtown)
Continuing
FY19/21
CIP Projects
New/
Supplemental
CIP Funding
27 Projects,
e.g.:
-Downtown Parklets
-Downtown Banner Arms
and Signage
-Ped Crosswalk Beacons
and Safety Improvements
-Bike/Ped Quick Builds
-Orcutt/Tank Farm
Roundabout
CIP Work totals approximately $40 Million
with Removal of WRRF and Water
Treatment Plant Work,
20/21 CIP BUDGET SUPPLEMENT REFRESHER
General Funds
Local Revenue Measure
Projects Placed on Hold
Total GF Projects Placed on Hold: $1,068,254
20/21 CIP BUDGET SUPPLEMENT REFRESHER
ID#Fund Number of
Projected Budget Number of
Projects Budget % change
(Budget)
1 Capital Outlay 52 8,707,762$ 42 7,416,143$ -15%
2 LRM 102 17,101,672$ 86 15,256,379$ -11%
3 Parking 17 5,856,602$ 12 5,000,102$ -15%
4 Transit 6 565,121$ 7 1,095,549$ 94%
5 Water 39 32,349,508$ 38 33,001,950$ 2%
6 Sewer 34 133,712,483$ 38 134,688,483$ 1%
7 SB1 2 1,325,000$ 3 795,548$ -40%
8
Transportation Impact
Fee 20 9,801,808$ 17 10,617,690$ 8%
TOTAL 272 209,419,956$ 243 207,871,844$ -1%
Planned Revised
Total Remaining Budget for General Fund Projects (snap -shot as of 6/2 Supplemental Budget) $3,750,518
Total Remaining Budget for LRM Projects (snap-shot as of 6/2 Supplemental Budget) : $10,559,057
Much of these funds are
currently being expended
with the first CIP projects of
the year
ATP & BIKESHARE
RFP
•Scope of Work –Prepare City’s first
comprehensive bike & ped plan (Active
Transportation Plan. Present detailed policy
framework and RFP for Bikeshare System
•Budget –$140K for consultant support for
both efforts
•Current Progress / Milestone:
•October 2020 –Draft ATP for Public Review
•November 2020 –Final ATP to Planning Comm.
•December 2020 –Final ATP & Bikeshare RFP to
City Council
•Early 2021 –Bikeshare RFP Release (if directed
by Council)
•2nd Half 2021 –Potential Bikeshare System
Deployment (if directed by Council)
Major City Goal
Sustainable Transportation
RRST TAFT TO
PEPPER
•Scope of Work –Construct separated
shared use path along California with
bike/ped bridge to connect Railroad Safety
Trail to Downtown
•Budget –$6.14M total ($3.24M Caltrans
ATP Grant, $2.9M TIF). Low Bid
•Low Bid $420K under eng.estimate
•Construction Start –October 2020
•Construction Complete –July 2021
Major City Goal
Sustainable Transportation
ORCUTT TANK FARM
ROUNDABOUT
•Scope of Work –Design and construct a
roundabout at the intersection of Orcutt and Tank
Farm Road
•Budget/Funding –$3.67M (TIF, USHA Grant)
•Current Progress / Milestone
•Confirmed all components constructed as City
CIP
•Design: 100% Design by October
•Critical Path Items:
•PG&E Utility Undergrounding: 1st Quarter 2021
•ROW Dedication by Developer: 1st Quarter
•Jurisdictional Permits: 2nd Quarter
•Estimate Construction Start –Spring 2021
•Estimated Completion –Jan 2022
Sustainable Transportation
BROAD CORRIDOR PHB
•Scope of Work –Construct a Pedestrian
Hybrid Beacon at Broad and Woodbridge
•Budget/Funding –$420k ($140K USHA
Grant)
•Current Progress / Milestone –100%
Design by October
•Update necessary to SLOCOG Cooperative
Agreement as SHA funding will be used.
Advertise for construction by end of 2021
•Estimate Construction Start –Summer 2021,
dependent on lead time for signal
equipment.
Sustainable Transportation
PEDESTRIAN CROSSING
IMPROVEMENTS
•Scope of Work:
•Install enhanced crossings with Rapid Rectangular
Flashing Beacons (RRFBs) at priority pedestrian/bike
crossings:
1.Tank Farm/Poinsettia
2.Johnson/Sydney (SRTS for Sinsheimer Elem)
3.Monterey/Buena Vista
4.Ramona/Foothill Plaza
5.South/King (Nipomo-King Neighborhood Greenway)
6.Islay/Broad (Islay Neighborhood Greenway)
7.Islay/Osos (Islay Neighborhood Greenway)
•Budget/Funding –$200k (includes annual bicycle
facilities improvements and traffic safety funds)
•Current Progress / Milestone –Design 65%
•Estimated Construction Start –
•Monterey/Buena Vista –October 2020
•Remaining Locations –1st Quarter 2021
Sustainable Transportation
ANHOLM
NEIGHBORHOOD
GREENWAY
•Scope of Work:
•Phase 1A –Foothill/Ferrini Crossing (Complete)
•Phase 1B –LDS Church Path and Ramona Cycletrack
•Phase 2 –Ramona to Downtown Cycletrack, Pedestrian
Improvements and 101 Undercrossing Public Art
•Budget/Funding –$700k for Phase 1B only (includes
$200K SLOCOG SRTS Grant)
•Current Progress / Milestone –Design 65% complete
for Phase 1B & 2.State Urban Greening Grant application
in, would fund $1.6M towards Phase 1B & Phase 2 (Grant
Shortlist Nov 2020; Final Grant Award March 2021)
•Estimated Construction Start –Summer 2021 for Phase
1B. If awarded grant,Phase 2 may also begin Summer
2021.
Sustainable Transportation
PRADO ROAD BRIDGE
Major City Goal
Sustainable Transportation
•Scope of Work –
➢Replace aging 2 lane bridge with 6 vehicle lanes
(4 thru lanes + turn lanes) + bike/ped facilities
➢Widen Prado/South Higuera Intersection &
install bicycle protected intersection
•Budget –$13 mil
➢$6 mil from Caltrans Bridge Replacement
Program, $7 mil from TIF
•Current Milestone
➢Confirmed Independent Utility
➢NEPA/CEQA document under review
➢Beginning Final Design & ROW Acquisition
•Timeline
➢Estimated Construction Start: Late 2022/Early
2023; 2-year construction schedule
PRADO ROAD
INTERCHANGE
•Scope of Work –
➢New overcrossing and NB Ramps at
Prado/US 101; 5 lanes and separated
bike/ped facilities
➢Re-alignment of Elks Lane.
Coordination with incoming
development
•Budget –
➢Construction cost shared by San Luis
Ranch, SLOCOG and SLO County
➢City shares construction costs and
funds all design costs
➢$30 million shortfall –pursuing
Federalization and grants to fill gap
Major City Goal
Sustainable Transportation
PRADO ROAD
INTERCHANGE
•Current Milestone –
➢Project Approval / Environmental
Document "PA/ED" (Choose
preferred interchange type)
➢Confirmed Independent
Utility/project scope with Caltrans
➢Review of CEQA/NEPA
➢Preparing plans for each Interchange
alternate
•Estimated Construction Start –2022
•Construction Finish –2026
Major City Goal
Sustainable Transportation
ROADWAY SEALING 2020
•Scope of Work –Slurry seal and re-stripe
19 miles of local roads.
•Budget –$1.9 mil
•Progress:
➢Construction nearly complete (punchlist
items only)
➢Additional curb,gutter and ramp work
added to project
➢Bob Jones trail (Prado to LOVR) and
Emerson Parking Lot also re-sealed
➢Complete paperwork and closeout project
•Estimated completion of construction:
Oct 2020
Fixing the “Leff
Street Lake”
Curb ramp in front
of Parks and Rec to
be replaced
Major City Goal -Multi-Modal
Transportation
BRIDGE DECK SEALING
2020
•Scope of Work –Apply methacrylate crack
sealant over three bridge decks:
•Nipomo at Higuera (Children’s Museum)
•South Broad at Fuller
•Fuller at South Broad
•Budget –$75,000
•Milestone: Project Complete
South Broad Street –Before and After
Measure G Priority
MARSH STREET BRIDGE
REPLACEMENT
•Scope of Work –Replace structurally deficient concrete
bridge and deteriorating sewer siphon underneath the
bridge.
•Budget/Funding –Approved as part of the 2015-
17 Financial Plan,the current project budget is $6,559,048.
•Current Progress / Milestones
•Micro pile and footing installation completed
•New sewer siphon installed
•Abutment walls completed
•Installing bridge deck & soldier pile retaining wall
•No conflicts with public outreach, adjacent businesses, traffic
detour, creek diversion
•Project at 60% completion, $3.6 M funding still available
•Scheduled Construction Finish –January 8, 2021.
Council Goal
NORTH BROAD STREET
NEIGHBORHOOD PARK
•Scope of Work –New park at 533 Broad (existing
community garden). Additional improvements at
the intersection of Broad and Lincoln Street.
•Budget/Funding –$75,000 Design Budget,
Additional $43,000 Allocated for Zone Change
Process, $665,000 Construction Budget
•Current Progress / Milestone –Design at 90%.
Environmental Review in progress. Initial Study
under review with City Planning Department. Next
Steps: 30 Day public review of Initial Study then
Planning Commission Meeting
•Estimate Construction Start –Summer 2021
CHENG PARK
REVITALIZATION
•Scope of Work –Update the existing park. Improve
security (with fencing and visibility) and
functionality (fix pond).
•Budget/Funding –$50,000 Design Budget;
$150,000 Construction Budget (2021-22)
•Current Progress / Milestone –Scoping Meeting
complete. Work on hiring Landscape Architect
Consultant for design.
•Estimate Construction Start –Next fiscal year when
construction budget is available.
ISLAY HILL PARK
PLAYGROUND
RENOVATION
•Scope of Work –Replacement of the existing
playground with new playground equipment.
•Budget –$80,000 Design Budget, $538,500
Construction Budget. This project is funded by
Local Revenue Measure G.
•Current Progress / Milestone –Construction
complete. Contractor and City working on final
paperwork items
•Construction Timeline: May 18th -September 8th
Measure G Priority
SOUTH HILLS RADIO
SITE UPGRADES
•Scope of Work –Replacement of existing radio site
with new 100’ tower, equipment building, and
generator.
•Budget –$75,000 Design Budget; Estimated
$900,000 Construction Budget (Construction,
Inspection Services, and Contingency).
•Current Progress / Milestone –Construction almost
complete. Tower, Building, and Generator in place.
Radio Equipment has been moved to the new
building and working correctly. Working on new
generator start up and punchlist items.
•Estimate Construction Start –Construction started
May 4th. Project to be completed by the beginning
of October.
Measure G Priority
FIRE STATION 2
TOWER/KVEC TOWER
•Scope of Work –Install new tower to provide the vertical
separation required to correct receiver signal problems in
the area.
•Budget/Funding –2019-21 Financial Plan designated
$250,000 in FY 2020/21 of LRM funds and Developer
Contribution of $354,750 at permit issuance
•Current Progress / Milestone –Working with Cal Poly
•Working on finalizing an agreement with Cal Poly
•Current discussion is between Cal Poly Strategic Business
Services and the Deputy City Manager
•30 Year Term 60/40 split City/Cal Poly based on occupancy
•Estimate Construction Start –Pending decision with Cal
Poly.
•Cal Poly estimates 12 months for construction
Measure G Priority
2020-21 IT PROJECT
OVERVIEW PROJECTS
•Public Safety MDC & In-Car Video
•VM Infrastructure Upgrade
•Audio Recording Warranty Extension
•ShoreMicro Radio Warranty Support
•911 Phone System Warranty Extension
•Projects on Hold:Shovel Ready
•Access Control
•Fire Radio Receive Site
•Scope of Work –Seven Projects
consisting of hardware replacement,
warranty extension and hardware
upgrade.
•Budget –$936,250 Total ($615,200
Local Revenue Measure, $289,050
Gen. Fund, $11,875 Water Fund,
Sewer $9,989,$1,716 Whale Rock,
$4,455 Transit, $3,965 Parking)
•Current Progress / Milestone –
•2 Projects in Progress
TRANSIT YARD PARKING
STUDY AND SOLAR
INSTALLATIONS
•Scope of Work –
•Optimize transit yard parking spaces to accommodate Solar
Array and EV Infrastructure Installation (Parking Study)
•ForeFront Power (FFP) solar panel installations
•PG&E EV Fleet Ready Program -Charging Infrastructure
•Budget/Funding –
•$74,467 for Parking Layout Study
•Bus EV Infrastructure –Funded through PG&E EV Fleet Ready
program agreement
•Solar Panel Installations –Funded by Power Purchase
Agreement with Forefront Solar
•Current Progress / Milestone
•Solar and Parking Layout study recently finalized.
•PG&E preparing an agreement based on City's commitment
to purchasing Electric buses and chargers in the next 5 years.
•Construction Phases –3 Components.
•ForeFront Power (FFP) Install Solar Array Structure
(March/April 2021)
•PG&E Improvements
ENERGY EFFICIENT
LIGHTING RETROFITS
•Scope of Work –
•Replace existing interior lighting in Parking
Structure 919 Palm with energy efficient LED
lights and fixtures.
•Budget/Funding –
•No direct cost to the City.Project cost will be
incorporated into the City's existing energy bill.
•Estimated Savings of 103,000 kWh, or $27,865
annually.
•Current Progress / Milestone –
•Construction began August 18.
•Estimated Completion –August 20.
Major City Goal
Climate Action
WRRF UPGRADE
Completed:
•Phase 1 and 2 Utility relocations -Minimal impacts to
plant operations
•Dewatering operations >> Waterboard Approvals
•Biofilter demolition
•Credits: $103,980 Change Orders: $683,979 (0.50%)
Performance Metrics:
•Cash Flow: Positive through January 2021 (JTD $15.8 M)
•Earned Value: 20% of time / 10% of budget
•CWA Participation: 78.3% (goal 30%) (15 of 18 union
contractors)
•Federal/State Audits: 2
•Safety: 0 Recordable Injuries
•Noise complaints: 1
•Odor complaints: 1
•Traffic complaints: 0
WRRF UPGRADE
3 Month Look Ahead:
•COVID Challenges
•Partnering Session 5 held August 12
•MBR Excavation
•Sewer Junction Box
•UV Excavation
•Biofilter Demolition
•Primary Clarifiers
•Fire Loop
Finish Target Date –Spring 2023.
WRRF UPGRADE
WRRF UPGRADE
WATER TREATMENT PLANT
ENERGY EFFICIENCY PROJECT
•Scope of Work –
•Upgrade ozone generators to utilize liquid
oxygen, transfer pump station with VFDs,
plant service water with new booster pump
station, and SCADA control system
•Budget –$14.2M
•Current Progress / Milestone:
➢Design-Build Project: Phase 1 Installation
currently underway, Issue For Construction
drawings mid October
•Estimate Delivery/Start of Work –
•New ozone generators on-site 9/30, project
completion July 2021
CONSTRUCTION DELIVERY SCHEDULE (CIP –PUBLIC PROJECTS ONLY)
PRIVATE CONSTRUCTION UPDATES
•Active Encroachment Permits –373
•Subdivision Work (Tracts)
•Avila Ranch (Underground onsite/Offsite)
•San Luis Ranch (Underground onsite/Traffic signal and frontage improvements offsite)
•Righetti Ranch (Vertical construction on site/Punch list offsite –Orcutt Rd.)
•West creek (Vertical construction on site/Punch list offsite -Orcutt Rd.)