HomeMy WebLinkAbout10-06-2020 Item 15 Reading File (2)CA PITAL PROJECTS
UPDAT E
OCTOBER 2020
RECOMMENDAT ION
Receive and file a status repor t on key projects within the City’s cur rently
adopted Capital Improvement Plan
20/21 CIP BUDGET SUPPLEMENT REFRESHER
20/21 CIP BUDGET SUPPLEMENT REFRESHER
CIP Project Prioritization:
•Proceed: Constr uct in FY20/21
•Proceed: Continue Planning/Design
•Hold: Shovel Ready for Future
Funding/Stimulus
•Defer (Defunded by FY20/21 Budget)
20/21 CIP BUDGET SUPPLEMENT REFRESHER
243 CIP
Projects
$207.8M
Defer red CIP
Projects
45 Projects, e.g.:
-Laguna Lake Dredging
-Fleet Replacements
-Fa rmer’s Market Bollards
-Sinsheimer Stadium
Irrigation and Drainage
Replacements
-California/Taft RAB
-Anholm Greenway Phase
2 (Ramona to Downtown)
Continuing
FY19/21
CIP Projects
New/
Supplemental
CIP Funding
27 Projects,
e.g.:
-Downtown Parklets
-Downtown Banner Arms
and Signage
-Pe d Crosswalk Beacons
and Safety Improve ments
-Bike/Ped Quick Builds
-Orcutt/Tank Farm
Roundabout
CIP Work totals approximately $40 Million
with Removal of WRRF and Wa ter
Treatment Plant Wo rk,
20/21 CIP BUDGET SUPPLEMENT REFRESHER
General Funds
Local Revenue Measure
Projects Placed on Hold
To tal GF Projects Placed on Hold:$1,068,254
20/21 CIP BUDGET SUPPLEMENT REFRESHER
ID #Fund Number of
Projected Budget Number of
Projects Budget % change
(Budget)
1 Capital O utlay 52 8,707,762$ 42 7,416,143$ -15%
2 LRM 102 17,101,672$ 86 15,256,379$ -11%
3 Parking 17 5,856,602$ 12 5,000,102$ -15%
4 Transit 6 565,121$ 7 1,095,549$ 94%
5 Water 39 32,349,508$ 38 33,001,950$ 2%
6 Sewer 34 133,712,483$ 38 134,688,483$ 1%
7 SB1 2 1,325,000$ 3 795,548$ -40%
8
Transportation Impact
Fee 20 9,801,808$ 17 10,617,690$ 8%
TOTAL 272 209,419,956$243 207,871,844$-1%
Planned Revised
To tal Remaining Budget for General Fund Projects (snap-shot as of 6/2 Supplemental Budget) $3,750,518
To tal Remaining Budget for LRM Projects (snap-shot as of 6/2 Supplemental Budget) : $10,559,057
Much of these funds are
curre ntly being expended
with the first CIP projects of
the year
AT P & BIKESHARE
RFP
•Scope of Wo rk –Prepare City’s first
comprehensive bike & ped plan (Active
Transportation Plan.Present detailed policy
framework and RFP for Bikeshare System
•Budget –$140K for consultant support for
both efforts
•Curre nt Progress / Milestone:
•October 2020 –Draft ATP for Public Review
•November 2020 –Final ATP to Planning Comm.
•December 2020 –Final ATP & Bikeshare RFP to
City Council
•Early 2021 –Bikeshare RFP Release (if directed
by Council)
•2nd Half 2021 –Po tential Bikeshare System
Deployment (if directed by Council)
Major City Goal
Sustainable Transportation
RRST TAFT TO
PEPPER
•Scope of Wo rk –Construct separated
shared use path along Califor nia with
bike/ped bridge to connect Railroad Safety
Trail to Downtown
•Budget –$6.14M total ($3.24M Caltrans
ATP Grant,$2.9M TIF).Low Bid
•Low Bid $420K under eng.estimate
•Construction Start –October 2020
•Construction Complete –July 2021
Major City Goal
Sustainable Transportation
ORCUTT TANK FARM
RO UNDABOUT
•Scope of Wo rk –Design and construct a
ro undabout at the intersection of Orcutt and Tank
Fa rm Road
•Budget/Funding –$3.67M (TIF, U SHA Grant)
•Current Progress / Milestone
•Confirmed all components constructed as City
CIP
•Design:100% Design by October
•Critical Path Items:
•PG&E Utility Undergrounding: 1st Quarter 2021
•ROW Dedication by Developer: 1st Quarter
•Jurisdictional Permits: 2nd Quarter
•Estimate Construction Start –Spring 2021
•Estimated Completion –Jan 2022
Sustainable Transportation
BROA D CORRIDOR PHB
•Scope of Wo rk –Construct a Pedestrian
Hybrid Beacon at Broad and Wo odbridge
•Budget/Funding –$420k ($140K USHA
Grant)
•Curre nt Progress / Milestone –100%
Design by October
•Update necessary to SLOCOG Cooperative
Agreement as SHA funding will be used.
Advertise for construction by end of 2021
•Estimate Construction Start –Summer 2021,
dependent on lead time for signal
equipment.
Sustainable Transportation
PEDESTRIAN CROSSING
IMPROV EMENTS
•Scope of Wo rk:
•Install enhanced crossings with Rapid Rectangular
Flashing Beacons (RRFBs) at priority pedestrian/bike
crossings:
1.Tank Farm/Poinsettia
2.Johnson/Sydney (SRTS for Sinsheimer Elem)
3.Monterey/Buena Vista
4.Ramona/Foothill Plaza
5.South/King (Nipomo-King Neighborhood Greenway)
6.Islay/Broad (Islay Neighborhood Greenway)
7.Islay/Osos (Islay Neighborhood Greenway)
•Budget/Funding –$200k (includes annual bicycle
facilities improvements and traffic safety funds)
•Current Progress / Milestone –Design 65%
•Estimated Construction Start –
•Monterey/Buena Vista –October 2020
•Remaining Locations –1st Quarter 2021
Sustainable Transportation
ANHOLM
NEIGHBORHOOD
GREENWAY
•Scope of Wo rk:
•Phase 1A –Fo othill/Ferrini Crossing (Complete)
•Phase 1B –LDS Church Path and Ramona Cycletrack
•Phase 2 –Ramona to Downtown Cycletrack, P edestrian
Improvements and 101 Undercrossing Public Art
•Budget/Funding –$700k for Phase 1B only (includes
$200K SLOCOG SRTS Grant)
•Current Progress / Milestone –Design 65% complete
for Phase 1B & 2.State Urban Greening Grant application
in,wo uld fund $1.6M towards Phase 1B & Phase 2 (Grant
Shortlist Nov 2020;Final Grant Award March 2021)
•Estimated Construction Start –Summer 2021 for Phase
1B.If awarded grant,Phase 2 may also begin Summer
2021.
Sustainable Transportation
PRADO ROA D BRIDGE
Major City Goal
Sustainable Transportation
•Scope of Wo rk –
Ø Replace aging 2 lane bridge with 6 vehicle lanes
(4 thru lanes + turn lanes) + bike/ped facilities
Ø Widen Prado/South Higuera Intersection &
install bicycle protected intersection
•Budget –$13 mil
Ø $6 mil from Caltrans Bridge Replacement
Program,$7 mil from TIF
•Curre nt Milestone
Ø Confirmed Independent Utility
Ø NEPA/CEQA document under review
Ø Beginning Final Design & ROW Acquisition
•Timeline
Ø Estimated Construction Start:Late 2022/Early
2023;2-ye ar construction schedule
PRADO ROA D
INTERCHANGE
•Scope of Wo rk –
Ø New overcrossing and NB Ramps at
Prado/US 101;5 lanes and separated
bike/ped facilities
Ø Re-alignment of Elks Lane.
Coordination with incoming
development
•Budget –
Ø Construction cost shared by San Luis
Ranch,SLOCOG and SLO County
Ø City shares construction costs and
funds all design costs
Ø $30 million shortfall –pursuing
Fe deralization and grants to fill gap
Major City Goal
Sustainable Transportation
PRADO ROA D
INTERCHANGE
•Curre nt Milestone –
Ø Project Approval / Environmental
Document "PA/ED" (Choose
preferred interchange type)
Ø Confirmed Independent
Utility/project scope with Caltrans
Ø Review of CEQA/NEPA
Ø Preparing plans for each Interchange
alternate
•Estimated Construction Start –2022
•Construction Finish –2026
Major City Goal
Sustainable Transportation
ROADWAY SEALING 2020
•Scope of Wo rk –Slurry seal and re-stripe
19 miles of local roads.
•Budget –$1.9 mil
•Progress:
Ø Construction nearly complete (punchlist
items only)
Ø Additional curb,gutter and ramp work
added to project
Ø Bob Jones trail (Prado to LOVR) and
Emerson Parking Lot also re-sealed
Ø Complete paperwork and closeout project
•Estimated completion of construction:
Oct 2020
Fixing the “Leff
Street Lake”
Curb ramp in front
of Parks and Rec to
be replaced
Major City Goal -Multi-Modal
Transportation
BRIDGE DECK SEALING
2020
•Scope of Wo rk –Apply methacrylate crack
sealant over three bridge decks:
•Nipomo at Higuera (Children’s Museum)
•South Broad at Fuller
•Fuller at South Broad
•Budget –$75,000
•Milestone:Project Complete
South Broad Street –Before and After
Measure G Priority
MARSH STREET BRIDGE
REPLACEMENT
•Scope of Wo rk –Replace structurally deficient concrete
bridge and deteriorating sewer siphon underneath the
bridge.
•Budget/Funding –Approve d as part of the 2015-
17 Financial Plan,the current project budget is $6,559,048.
•Current Progress / Milestones
•Micro pile and footing installation completed
•New sewer siphon installed
•Abutment walls completed
•Installing bridge deck & soldier pile retaining wall
•No conflicts with public outreach,adjacent businesses,traffic
detour, c re ek diversion
•Project at 60% completion,$3.6 M funding still available
•Scheduled Construction Finish –January 8,2021.
Council Goal
NORTH BROA D STREET
NEIGHBORHOOD PARK
•Scope of Wo rk –New park at 533 Broad (existing
community garden).Additional improvements at
the intersection of Broad and Lincoln Street.
•Budget/Funding –$75,000 Design Budget,
Additional $43,000 Allocated for Zone Change
Process,$665,000 Construction Budget
•Curre nt Progress / Milestone –Design at 90%.
Environmental Review in progress.Initial Study
under rev iew with City Planning Department.Next
Steps:30 Day public rev iew of Initial Study then
Planning Commission Meeting
•Estimate Construction Start –Summer 2021
CHENG PARK
REVITALIZATION
•Scope of Wo rk –Update the existing park.Improve
security (with f encing and visibility) and
functionality (fix pond).
•Budget/Funding –$50,000 Design Budget;
$150,000 Construction Budget (2021-22)
•Curre nt Progress / Milestone –Scoping Meeting
complete. Wo rk on hiring Landscape Architect
Consultant for design.
•Estimate Construction Start –Next fiscal year when
construction budget is available.
ISLAY HILL PARK
PLAYGROUND
RENOVA TION
•Scope of Wo rk –Replacement of the existing
playground with new playground equipment.
•Budget –$80,000 Design Budget,$538,500
Construction Budget.This project is funded by
Local Revenue Measure G.
•Curre nt Progress / Milestone –Construction
complete. C ontractor and City working on final
paperwork items
•Construction Timeline:May 18th -September 8th
Measure G Priority
SOUTH HILLS RADIO
SITE UPGRADES
•Scope of Wo rk –Replacement of existing radio site
with new 100’tower, e quipment building, a nd
generator.
•Budget –$75,000 Design Budget;Estimated
$900,000 Construction Budget (Construction,
Inspection Services,and Contingency).
•Curre nt Progress / Milestone –Construction almost
complete. Tower, B uilding, a nd Generator in place.
Radio Equipment has been moved to the new
building and working corre ctly. Wo rking on new
generator start up and punchlist items.
•Estimate Construction Start –Construction started
May 4th. P roject to be completed by the beginning
of October.
Measure G Priority
FIRE STAT ION 2
TOWER/KVEC TOW ER
•Scope of Wo rk –Install new tower to prov ide the vertical
separation required to correct receiver signal problems in
the area.
•Budget/Funding –2019-21 Financial Plan designated
$250,000 in FY 2020/21 of LRM funds and Developer
Contribution of $354,750 at permit issuance
•Current Progress / Milestone –Wo rking with Cal Poly
•Wo rking on finalizing an agreement with Cal Poly
•Current discussion is between Cal Poly Strategic Business
Services and the Deputy City Manager
•30 Year Term 60/40 split City/Cal Poly based on occupancy
•Estimate Construction Start –Pe nding decision with Cal
Po ly.
•Cal Poly estimates 12 months for construction
Measure G Priority
2020-21 IT PROJECT
OV ERVIEW PROJECTS
•Public Saf ety MDC & In-Car Video
•VM Infrastructure Upgrade
•Audio Recording Warranty Extension
•ShoreMicro Radio Warranty Support
•911 Phone System Wa rranty Extension
•Projects on Hold:Shovel Ready
•Access Control
•Fire Radio Receive Site
•Scope of Wo rk –Seven Projects
consisting of hardware replacement,
warranty extension and hardware
upgrade.
•Budget –$936,250 To tal ($615,200
Local Revenue Measure,$289,050
Gen.Fund,$11,875 Wa ter Fund,
Sewer $9,989,$1,716 Whale Rock,
$4,455 Transit,$3,965 Parking)
•Curre nt Progress / Milestone –
•2 Projects in Progress
TRANSIT YARD PARKING
STUDY AND SOLAR
INSTALLATIONS
•Scope of Wo rk –
•Optimize transit yard parking spaces to accommodate Solar
Array and EV Infrastructure Installation (Parking Study)
•Fo re Front Power (FFP) solar panel installations
•PG&E EV Fleet Ready Program -Charging Infrastructure
•Budget/Funding –
•$74,467 for Parking Layout Study
•Bus EV Infrastructure –Funded through PG&E EV Fleet Ready
program agreement
•Solar Panel Installations –Funded by Power Purchase
Agreement with Forefront Solar
•Current Progress / Milestone
•Solar and Parking Layout study recently finalized.
•PG&E preparing an agreement based on City's commitment
to purchasing Electric buses and chargers in the next 5 years.
•Construction Phases –3 Components.
•Fo re Front Power (FFP) Install Solar Array Structure
(March/April 2021)
•PG&E Improvements
ENERGY EFFICIENT
LIGHTING RETROFITS
•Scope of Wo rk –
•Replace existing interior lighting in Parking
Structure 919 Palm with energy efficient LED
lights and fixtures.
•Budget/Funding –
•No direct cost to the City.Project cost will be
incorporated into the City's existing energy bill.
•Estimated Savings of 103,000 kWh,or $27,865
annually.
•Curre nt Progress / Milestone –
•Construction began August 18.
•Estimated Completion –August 20.
Major City Goal
Climate Action
WRRF UPGRADE
Completed:
•Phase 1 and 2 Utility relocations -Minimal impacts to
plant operations
•Dewatering operations >> Wa terboard Approvals
•Biofilter demolition
•Credits:$103,980 Change Orders:$683,979 (0.50%)
Performance Metrics:
•Cash Flow:Po sitive through January 2021 (JTD $15.8 M)
•Earned Value:20% of time / 10% of budget
•CWA Participation:78.3% (goal 30%) (15 of 18 union
contractors)
•Fe deral/State Audits:2
•Safety:0 Recordable Injuries
•Noise complaints:1
•Odor complaints:1
•Traffic complaints:0
WRRF UPGRADE
3 Month Look Ahead:
•COVID Challenges
•Par tnering Session 5 held August 12
•MBR Excavation
•Sewer Junction Box
•UV Excavation
•Biofilter Demolition
•Primary Clarifiers
•Fire Loop
Finish Target Date –Spring 2023.
WRRF UPGRADE
WRRF UPGRADE
WATER TREATMENT PLANT
ENERGY EFFICIENCY PROJECT
•Scope of Wo rk –
•Upgrade ozone generators to utilize liquid
ox ygen,transfer pump station with VFDs,
plant service water with new booster pump
station,and SCADA control system
•Budget –$14.2M
•Curre nt Progress / Milestone:
Ø Design-Build Project:Phase 1 Installation
currently underway, I ssue For Construction
drawings mid October
•Estimate Delivery/Start of Wo rk–
•New ozone generators on-site 9/30,project
completion July 2021
CONSTRUCTION DELIVERY SCHEDULE (CIP –PUBLIC PROJECTS ONLY)
PRIVAT E CONSTRUCTION UPDATES
•Active Encroachment Permits –373
•Subdivision Wo rk (Tracts)
•Av ila Ranch (Underground onsite/Offsite)
•San Luis Ranch (Underground onsite/Traffic signal and frontage improvements offsite)
•Righetti Ranch (Vertical construction on site/Punch list offsite –Orcutt Rd.)
•We st creek (Vertical construction on site/Punch list offsite -Orcutt Rd.)