COUNCIL AGENDA REPORT ITEM NUMBER:
FROM: Jim Stockton
Recreation Di or
SUBJECT: Request for Appropriation From Parkland Development Fund
to Complete SLO Recreation Center Rehabilitation Project.
(City Plan No. M-43D)
CAO RECOMMENDATION:
By motion, appropriate $ 92,900 from Parkland Development Fund
balances for increased asbestos abatement costs ($70,800) and recommended
project improvements ($22,100) related to the Recreation Center
Rehabilitation project.
BACKGROUND:
In late 1990, the City Council authorized staff to advertise for bids
to accomplish the rehabilitation of the City Recreation Center. Bids were
received and with Council authority the CAO executed a contract with
Shetler Construction Company to accomplish the rehabilitation work. j
By Council action prior to execution of the construction contract, a
tentative budget was approved calling for a "Comprehensive" rehabilitation
of the Center rather than a phased project. The approved tentative budget
identified funding from three sources; an appropriation from the Parkland
Development Reserve, debt financing to equal the Parkland funds, and
assistance from a State Grant in the amount of $300,000. The budget was
as follows:
Re-hab Construction w/contingencies $ 826,600
Bidding Assistance and Project Administration 27,300
Equipment and Furnishings 25,000
Asbestos Abatement 65,000
Landscaping 30.000
Total $ 973,900
Work on the project began with an asbestos abatement program which
removed all the visable and known sources of this toxic substance. Actual
rehabilitation work on the building began on January 18, 1991. The
project was less than one month into the demolition phase when another
source of suspected asbestos was uncovered. Testing proved that the new
asbestos find was positive and large; the County Air Quality Control
recommended that the job be shut down until it was removed. In an attempt
to get the job back on line and to lessen the possibility of jeopardy to
the City from the General Contractor claims for job delays, the asbestos
abatement crews were again called to the site. They completed the
removal, but the cost thereof made a shamble of the project budget.
Asbestos abatement totaled approximately $135,800, $70,800 over original
budget estimates.
+��n�i�►►►�IIIIIIf�P° ���N city of sar, ,_ais OBispo
COUNCIL AGENDA REPORT
Page 2
Two other high cost items were experienced as the job progressed that were
not anticipated when the original budget was presented to Council. They
include:
1. The City's seismic study of public buildings recommended
structural upgrades at the Center that were accomplished by job change
orders. ($18,400)
2. An upgraded fire alarm/warning system required by the local
fire authority to compliment the fire sprinkling system. ($34,300)
A summary as well as a complete listing of change orders is attached
(see Exhibits B & Q .
CONCURRENCES:
To address this project's budget concerns, an on-site meeting was
called and attended by representatives from Administration, Finance,
Public Works, Recreation, Energy Conservation and Building Maintenance.
This group was to survey the work already completed and determine what
remained to be accomplished to make the Recreation Center a fully
functional public facility, energy efficient operationally and one that
would require only a minimum of daily maintenance.
Representatives from all Departments/Divisions attending this meeting
reached consensus on the items necessary to bring this project to closure.
A listing of this committee's recommendations and their estimated costs
are attached hereto and marked EXHIBIT "A" .
i
FISCAL IMPACT:
In developing the original Recreation Center Project budget, three
major sources of funding were recommended and approved by Council; they
included:
1. State Grant assistance $ 296,900
2. Debt Financing 338,500
3. Funding from Parkland Development Reserves 338.500
Total $ 973,900
Parkland Development Reserves were selected as a funding vehicle in
that the majority of this reserve is generated from park in-lieu fees
which are intended to improve/expand park and recreation facilities for
the Community. It is requested that the $92,900 necessary to complete the
"Comprehensive Rehabilitation" of the Recreation Center be appropriated
from this reserve.
i��h�►b��I�lllllll�ll°;�9��IU city of San t. 3 osIspo
COUNCIL AGENDA REPORT
Page 3
During mid-year (1991-92) budget studies it was estimated that the
Parkland Development Reserve would total $1,194,000 by the close of the
1991-93 Fiscal Cycle. The appropriation of $92,900 to complete the
Recreation Center from this Reserve will have no impact on the 1991-93
Council Work Program to improve existing parks and playgrounds. The
requested appropriation will have only minor negative impact on the
closing Parkland Reserve balance at the close of FY 1992-93.
ALTERNATIVES.-
1.
LTERNATIVES:1. Appropriate $92,900 from the Parkland Development Reserve Fund to
complete the "Comprehensive Rehabilitation" of the Recreation Center.
This alternative would insure a completed job and a fully functional
recreation facility for the Community.
2. Do not approve the requested increase of funding for this
project. This alternative would allow a facility that could be partially
used but would appear to the user, unfinished. It would necessitate the
use of funds originally earmarked for furnishing and landscaping the
project to meet asbestos and structural cost overruns.
ATTACHMENTS:
* A listing of this committee's recommendations and their estimated
costs are attached hereto and marked EXHIBIT "A" .
* A summary of change orders is marked EXHIBIT "B" .
i
* A listing of change orders is marked EXHIBIT "C" .
���K�� ►►�Illllll�p q���ll city of San t: -�-S OBISpo
COUNCIL AGENDA REPORT
Page 4
EXHIBIT "A"
By Department/Division meeting consensus the following listed items
were recommended as necessary to bring closure to the Recreation Center
Rehabilitation project. It was the committees recommendation that these
items be completed by a combination of minor contracts, city force account
work and community service projects to keep the cost of each to a
minimum. The items are so marked.
(MC) Minor Contract
(FA) Force Account work by city employees
(CS) Community Service Projects
1. MC - Installation of low energy lighting in gymnasium $ 5,500 *
2. FA - Installation of low energy lighting in Craftroom #1 800 *
3. FA - Installation of low energy lighting in Craftroom #2 900 *
4. CS - Materials and paint to finish Craftrooms #1 and #2 1,000
5. FA - Improve front (Santa Rosa) entry to disabled standard 1,200
6. FA - Make and install chimney cap 200
7. MC - Refinish gymnasium floor 7,000
8. MC - Key all door locks to match P&R keying system 2,500
9. FA - Purchase and install new backboards and volleyball
standard floor anchors 3.000
Total $ 22,100
i
* After installation, these items will qualify for the PG&E
rebates with the rebates to be deposited in Parkland Development
Reserve Fund.
�I�Nni���uVlllllll�l►° ��UIII city of san Luis OBlspo
COUNCIL AGENDA REPORT
Page 5
EXHIBIT "B"
SUMMARY OF CHANGE ORDERS
Asbestos
Construction Abatement Total
Budget $ 826,600 $ 65,000 $ 891,600
Projected Actual Budget
* Original Construction
contract $ 659,300 $ 65,000 $ 724,300
* Change Orders to Date 167,300 70,800 238,100
* Recommended additional
change orders 22. 100 22.100
Total $ 848,700 $ 135,800 $ 984,500
Additional Funding Needed S 22,100 $ 70.800 $ 92,900
I
c -
��,�H���►►�Illll�ul►���'►��III city of San t, OBISPO
= COUNCIL AGENDA-REPORT
Page 6
RECREATION CENTER REHABILITATION PROJECT EXHIBIT "C"
CHANGE ORDERS BY CATEGORY
CATEGORY I: STRUCTURAL CHANGES MANDATED BY CITY'S SEISMIC EVALUATION
CATEGORY II: UA'FORSEEN ITEMS DISCOVERED AFTER PROJECT START
CATEGORY III: ADDITIONAL WORK RECOMMENDED BY CIP-BRT
CATEGORY IV: CHANGES RESULTING FROM:
A. NOT BEING CALLED FOR ON PLANS
B. BEING IN CONFLICT ON DIFFERENT PAGES OF PLANS
C. INCORRECT DETAIL ON PLANS
D. NO DETAIL INCLUDED ON PLANS
CATEGORY V: CHANGE ORDERS EXPERIENCED AS JOB PROGRESSED (To 1-28-92)
CATEGORY VI: CHANGES THAT YET MAY ARISE
CHANGE ORDER DESCRIPTION CHANGE ORDER AMObNT
CATEGORY I: STRUCTURAL, REOUIRED BY SEISMIC STUDY.
1098 S.I. LOG 3-1 SHEAR $ 6,799.00
1100 S.I. LOG 3-2 CHIMNEY 2,151.00
1101 S.I. LOG 3-3 STRUC @ CRAFT 5,533.00
1111 STAIR LANDING UPSTAIRS 1,530.00
1172 HEADER @ MEETING RM OVRS 600.00
1082 POST & BEAM STRUCTURAL SUPPORTS 1 . 787.00
i
I
TOTAL CATEGORY I CHANGES TO DATE $ 18.400.00
CATEGORY II: UNFORSEEN ITEMS FOUND AFTER PROJECT START.
1056 TERMITE DAMAGE @ FOUNTAIN $ 1,172.00
1059 GAS LINE AFTER BID DATE 110.00
1067 FIRE RATED DOOR #25 1,697.00
1096 WINDOW @ BOY SCOUT WING 1,592.00
1115 FIREPLACE FLOORING 205.00
1127 WALLS BUILT ON CURBS 6,012:00
1131 FIRE EXTING MISSING 630.00
1135 TERMITE DAMAGE @ ACTIVITY ROOM 2,046.00
1136 TERMITE DAMAGE @ HANDICAP RAMP 1, 180.00
1201 DEMO & REFRAME SECOND FLOOR SKYLIGHT 468.00
1205 MAIN LINE WATER FILTER 249.00
1091 (7-22-91) CHANGE CEILING & FLOOR - ACT.RM. CLO. 1,822.00
1235 ( ) WH POP-OFF VL 137.00
TOTAL CATEGORY II CHANGES TO DATE $ 15.361.00
NEW TOTAL 1-27-92 S 17. 320.00
city Of Sar. .-ass OBISPO
COUNCIL AGENDA REPORT
RECREATION CENTER REHABILITATION PROJECT - CHPNGE ORDERS PAGE 2
CHANGE ORDER # DESCRIPTION CHANGE ORDER AMOUNT
CATEGORY III: ADDITIONAL WORK RECOMMENDED BY CIP-BRT
1055 GYM ROOF REPLACEMENT $ 12,713.00
1057 ROOM FINISHES - ROOM -s
126,127,128,129 AND ENTRANCE 21,691.00
1103 ELECTRICAL BALLAST CHANGES 4.480.00
TOTAL CATEGORY III CHANGES S 38 .884.00
CATEGORY IV: NOT INCLUDED IN PLANS ORDETAILS
1047 TELEPHONE TERM. BOARD $ 553.00
1051 REFINISH ENTRY CEILING 1,000.00
1061 DETAIL FLSHG ELEC 673.00
1063 TILE AT ENTRY 1,103.00
1083 S.I. 1-1 GLAZING 799.00
1088 S.I. 1-7 EXIT SIGNS 853.00
1107 SIDING UNDER STAIRWAY 208.00
1109 TECTUM CEILING ATTMNT 4,129.00
1110 MECHANICAL RADIATORS 1,411.00
1124 FLASHING HAND. RANP/FRAM 493.00
1174 FASCIA DETAIL @ GYM WON'T 1,490.00
1175 CHANGE WATER CLOSETS 140.00
1176 CHANGE SHOWER HEADS 1,212.00
1177 7" VENT TO RANGE HOOD 411.00
1179 NEW COMBUSTION AIR INTAKE 974.00
1180 ADD LOUVERS/REAR MECH 1,753.00
1050 REMOVE EXISTING STUCCO @ CRAFT ROOM 2,795.00
1202 REMOVE EXISTING SIDING UPPER FLOOR
AND FRONT OF BUILDING 2,180.00
1204 CHANGE TO ENTRY DOORS SANTA ROSA
ENTRY 503.00
1237 (7-22-91) DEMO AIR INTAKE ON ROOF AND FIX ROOF 612.00
1236 ( ) DEMO ROOF & BUILD PAR. WALL 2,760.00
TOTAL CATEGORY IV CHANGES TO DATE $22. 680.00
NEW TOTAL 1-27-92 $26.052.00
1111111111110111111 aty of San L. --S osIspo
All
COUNCIL AGENDA REPORT
RECREATION CENTER REHABILITATION PROJECT - CHANGE ORDERS PAGE 3
CATEGORY V: - CHANGES EXPERIENCED AS JOB PROGRESSED
1064 (II) ROOF BACKING @ SCREEN WALL $ 533.00
1065 (IV) FUR OUT WALL-MEN BATH 352.00
1068 (II) REP BOWED WALL CRAFTS 1,181.00
1070 (IV) DOOR AND HADW CHANGES 7,691.00
1071 (II) TERMITE DAMAGE @ GYM 62.00
1074 (II) ADD STRAP/SCREEN WALL 40.00
1075 (II) BRACING FOR SPLICED JOIST 271.00
1077 (??) UPGRADE FIRE ALARM SYSTEM 34,350.00
1122 (II) ASBESTOS IN STRUCTURE 28,000.00
1273 (IV) ADD FLASHING @ GYM ENTRY 162.00
1277 (II) ADD SWITCH & PHOTO CELL 150.00
1281 (II) CONDUIT BRACES IN GYM 117.00
TOTAL CATEGORY V CHANGES TO DATE (1-28-92) $72,909.00
CATEGORY VI: CHANGE ORDERS THAT MAY ARISE BEFORE JOB COMPLETION
**** Additional electric work second floor
$ 500.00
**** Grease trap removal 500.00
**** Handrails for physically impared 1,400.00
**** Unresolved change orders 10,000.00
**** Termite Eradication 6,800.00
**** Miscellaneous 2,500.00
TOTAL CATEGORY' VI (MAYBE) .CHANGE ORDERS $219700.00
TOTAL CHANGE ORDERS ALL CATEGORIES: (NEW NUMBERS 1-27-92)
CATEGORY I: $ 18,400.00
CATEGORY II: 17,320.00
CATEGORY III: 38,884.00
CATEGORY IV: 26,052.00
CATEGORY V: 72,909.00
CATEGORY VI: 21 ,700.00
TOTAL CHANGE ORDERS AND ANTICIPATED CHANGE ORDERS
AS OF JANUARY 27, 1992 -------------------------- $ 1959265.00