HomeMy WebLinkAbout91118A Bid ResultsItem No.Item Description
Unit of
Measure
Estimated
Quantity Item Price Total Item Price Total
1 Mobilization and Demobilization LS 1 ---250,000$ ---325,000$
2 Storm Water Pollution Prevention LS 1 ---40,000$ ---99,600$
3 Sheeting, Shoring and Bracing LS 1 ---400,000$ ---234,000$
4 OSHA Compliance LS 1 ---10,000$ ---13,000$
5 Permits and Temp. Constr. Easement Compliance LS 1 ---30,000$ ---40,000$
6 Dewatering LS 1 ---450,000$ ---700,000$
7 Utility Location and Potholing LS 1 ---85,000$ ---114,000$
8 Traffic Control, Detours, and Access LS 1 ---60,000$ ---280,000$
9 Relocate Motel 6 Sewer Lateral LS 1 ---22,000$ ---74,000$
10 Relocate Motel 6 Water Service LS 1 ---7,500$ ---18,000$
11 Gas Service for Standby Generator LS 1 ---12,000$ ---19,000$
12 Recycled Water Service and Meter LS 1 ---12,000$ ---21,000$
13 Construction Surveying LS 1 ---65,000$ ---94,000$
14 Demolition, Removal, and Abandonment LS 1 ---180,000$ ---267,000$
15 48-Inch Sewer Manhole EA 1 30,000$ 30,000$ 24,000$ 24,000$
16 72-Inch Sewer Manhole EA 2 35,000$ 70,000$ 76,000$ 152,000$
17 Approach Manhole EA 1 105,000$ 105,000$ 171,000$ 171,000$
18 12-Inch HDPE DR17 Sewer (STA 1+42 to STA 6+04)LF 458 160$ 73,280$ 140$ 64,120$
19 12-Inch HDPE DR17 Sewer (STA 109+81 to STA 111+00)LF 103 700$ 72,100$ 668$ 68,804$
20 Jack and Bore 30-inch Steel Casing LF 460 1,450$ 667,000$ 2,700$ 1,242,000$
21 Temporary Sewer Connection to Existing Wet Well LS 1 ---50,000$ ---105,000$
22 10-inch HDPE DR17 Sewer Forcemain LF 105 800$ 84,000$ 756$ 79,380$
23 Temporary Sewer Bypass Pumping LS 1 ---85,000$ ---126,000$
24 Lift Station Site Work - Concrete LS 1 ---130,000$ ---120,000$
25 Lift Station Site Work – Walls LS 1 ---160,000$ ---137,000$
26 Lift Station Site Work – Earthwork and Grading LS 1 ---85,000$ ---195,000$
27 Lift Station Site Work – Wet Well, Piping, and Valves LS 1 ---990,000$ ---620,000$
28 Lift Station Site Work – Pumps and Prerotation Basins LS 1 ---250,000$ ---201,000$
29 Lift Station Site Work – Hand Rails, Fencing, Guard Posts, and
Miscellaneous Metal LS 1 ---40,000$ ---92,000$
30 Electrical and Instrumentation LS 1 ---600,000$ ---434,000$
31 Commissioning and Startup LS 1 ---25,000$ ---49,000$
32 Communications Manholes and Conduit LS 1 ---40,000$ ---60,000$
33 Double Barrel Siphon (STA 6+06 to STA 8+50) LS 1 ---160,000$ ---223,000$
34 12-Inch HDPE Gravity Sewer (STA 8+50 to STA 10+32)LF 178 200$ 35,600$ 430$ 76,540$
35 Connection to Existing Manhole EA 2 16,000$ 32,000$ 16,000$ 32,000$
36
Remove and Replace Existing Caltrans Fence, and Relocate
Caltrans Gate LS 1 ---15,000$ ---13,000$
37
Pipe Trench Foundation/ Subgrade Stabilization (rock refill
encased in filter fabric) – As needed, and as directed by the City
Representative LF 250 70$ 17,500$ 97$ 24,250$
38
Perform Authorized Pipe Trench Foundation/Subgrade
Stabilization (compaction of in-situ subgrade material) – As
needed, and as directed by the City Representative LF 250 70$ 17,500$ 60$ 15,000$
5,457,480$ 6,622,694$
Item No.Item Description Unit of
Measure
Estimated
Quantity Item Price Total Item Price Total
1 Mobilization and Demobilization LS 1 25,000$ 25,000$ 30,000$ 30,000$
2 Sheeting, Shoring and Bracing LS 1 40,000$ 40,000$ 124,000$ 124,000$
3 Dewatering LS 1 85,000$ 85,000$ 200,000$ 200,000$
4 Traffic Control, Detours, and Access LS 1 40,000$ 40,000$ 67,000$ 67,000$
5 6-Inch HDPE DR17 Sewer (STA 100+08 to STA 109+81)LF 959 530$ 508,270$ 460$ 441,140$
6 Jack and Bore 16-inch Steel Casing LF 40 1,000$ 40,000$ 4,800$ 192,000$
7 48-Inch Sewer Manhole EA 2 32,000$ 64,000$ 24,000$ 48,000$
802,270$ 1,102,140$
Base + Add.
Alt. A: 6,259,750$ 7,724,834$
TOTAL:
Raminha Construction Specialty Construction
TOTAL:
ADDITIVE ALTERNATIVE A:
Raminha Construction Specialty Construction
Page 1 of 1
City of San Luis Obispo, Bid Results
Calle Joaquin Lift Station Replacement
Specification No. 91118A