HomeMy WebLinkAbout04/07/1992, C-3 - MISSION PLAZA CREEK WALL REPAIR 111111I1IIIg111� �ll � MEETING DATE:
C� 0 S� � _.�S �B�Sp� April 7, 1ITEM
992
COUNCIL AGENDA REPORT NUMBEfl:
FROM:
David F. Romero, Public Works Director
SUBJECT:
Mission Plaza Creek Wall Repair
CAO RECOMMENDATION:
By motion, approve the Mission Plaza Creek Wall Repairs in concept
and direct staff to prepare plans and specifications and obtain
necessary processing approvals.
BACKGROUND:
During a heavy storm in March 1991, San Luis Obispo Creek undercut
several walls in Mission Plaza. During April, staff removed a number
of newly exposed reinforcing bars which presented a hazard to the
public. During May staff received approval from the Game Warden for
repairs to the undermining, with work to be conducted during the summer
when creek flows are low, following conditions of our general
maintenance permit from the Fish and Game Department. The City did not
need to clear at that time with the Corps of Engineers, since this was
an emergency project to correct several undermines.
In August, City crews poured 33 cubic yards of concrete grout to
correct the undermining. There was some surplus grout, and this was
placed and rounded in front of existing built-up rubble concrete walls
on either side of the creek (Areas 1 and 2 on exhibit) , exposing to
public view approximately 2 cubic yards of concrete. After a
Councilperson's complaint, staff hired a contractor to chip off the
newly poured concrete to near the face of the original rubble concrete
wall along the east bank. Staff also tried twice (unsuccessfully) to
stain the exposed concrete along the west bank to give it a more
natural appearance.
At the February 4, 1992 meeting, Councilperson Pinard presented a
series of slides showing the condition of the concrete pours. These
slides were taken before staff attempts to correct the unsightly
appearance. The City Council directed staff to "redo" the repairs.
During mid-February, a heavy storm started additional erosion in this
immediate area of Mission Plaza.
In response to Council direction, Public Works and Planning staff met
at the site in late February to reach agreement regarding the best
approach toward correction to previous work and correction and
protection regarding recent erosion. Staff agreed that work was needed
in four areas (see exhibit) .
Area #1 Cover face of partially corrected rubble concrete wall
with native stone facing to match nearby retaining wall or
face with medium-small boulders to match those to be
placed in Area #2.
C-3- 1
�,,,7�i►►Iu►IIIIIIIII►' ����h city of San t OBISpo
COUNCIL AGENDA REPORT
Creek Repair
Page Two
Area #2 Place large boulders (or fabricate concrete boulders in
place similar to those at the Apple Farm Millhouse) in
front of recently grouted west bank concrete rubble wall.
This will cover up the existing exposed concrete pour and
provide protection from future erosion.
Area #3 Place large boulders (or fabricate concrete boulders)
along east bank (and slightly downstream) in area starting
to erode.
i
Area #4 Construct approximately 50 feet of concrete rubble wall
about 2 feet high along east bank (slightly north) to
protect a fig tree at the water's edge. This wall could
also be constructed of native serpentine stone. Modify
small corrugated metal pipe (which has been in place since
before Mission Plaza was developed) so pipe will not be
visible.
Note: Areas 1, 3 and 4 would also receive additional landscaping
ALTERNATIVES:
A. Do nothing.
The undermining has been corrected and the final (partially
corrected) condition doesn't look too bad. If heavy rains are
over for the season, erosion at other spots won't get worse for
about a year. Meanwhile, some of the eroding areas may heal
UP-
A-1. Conduct hand or brush hammer chipping of partially removed
concrete still remaining on face of existing concrete rubble
wall, so as to expose original concrete rubble slabs (this work
would be done by City crews) .
B. Do all repair work with laid-up rubble concrete walls or
constructed fieldstone walls. This will match existing and
will avoid the huge expense and complication of having to put
equipment into the creek to move and place large boulders.
C. Fabricate concrete imitation boulders in place, instead of
moving in real boulders. Much of the cost in placing real
boulders involves crane placement of a loader in the creek,
modification of the creek bed to allow the loader to travel to
the worksite while carrying boulders, and finally cleaning up
the creek at the end of the job, all done to strict Fish and
Game requirements. This could all be avoided by utilizing a
relatively new process of pouring the boulders in place. This
process was used at the Apple Farm on a recent project.
�����:�►��►IVIIIIIIIIIII�►�uil����1ll city of san ' Is oBispo
= COUNCIL AGENDA REPORT
Creek Repair '
Page Three
I
FISCAL IMPACT:
At this early stage, it is impossible to come up with firm estimates of
the construction cost. Based on discussions with a contractor and
engineering staff, the following can be used as general guidelines for
construction cost.
Full job as recommended by Planning $25, 000
Alternative A No cost at this time
Alternative B $15, 000
Alternative C $20, 000
The Mission Plaza account currently has $200, 000 in it, though it may
be depleted soon to pay for appraisals, legal fees and acquisition
costs.
APPROVALS OF OTHER AGENCIES:
The project is subject to environmental review, the ARC and Park and
Recreation Commission review and approval. It also requires Fish and
Game approval and most importantly, Corps of Engineers approval.
Because of Corps of Engineers procedures, we estimate this approval
will require one year.
i ACTION PLAN:
1. Obtain concept approval and prepare preliminary cost estimates
- April 1992 .
2. Prepare preliminary plans - May-June 1992 . j
3 . Obtain concept approval from various city agencies and Fish and
Game - July-August 1992.
4. Apply for Corps of Engineers permit - July 1992.
5. Obtain Corps of Engineers permit - July 1993.
6. Obtain environmental determination - July 1993.
7 . Prepare final plans and specifications - June-July 1993 .
8. Obtain final approvals of city commissions - July 1993.
9. Council approval of plans and specifications - August 1993 .
10. CAO award contract - September 1993. C
�II�»b�►►1VIIIlIII���� ��N�ll city of San l -3 OBIspo
COUNCIL AGENDA REPORT
Creek Repair
Page Four
I
11. Construction - October 1993 .
12 . Completion of work - November 1, 1993.
The Action Plan schedule assumes engineering staff prioritizes this
design ahead of other already scheduled work, and assumes no glitches
(other than routine delays) in obtaining processing approvals. If we
limit our creek work to the small walls, we might obtain quicker Corps
of Engineers approval but would still not do the work until late summer
1993 when creek flows are low.
i
I
I
Attachment: Exhibit A - map of Mission Plaza
Exhibit B - detail from Corps of Engineers
I
i
i
i
creekrepelr/dfr•36
l
- - Q
mrai
LU
IF.tX.;.�f� /w T` N •� �•
wto
43
ti
—� i . ` '�`� � •,.`. :•;-' 41 !%.. 'v'r � '.tib 1 �.' ,� . '. �.
•_ - w � I .1t ivy� � �\ `:' / ;;. •�• ; `
-
75
_ moLO CL wLU
cr: VD 4m
CL—
. I u- }T Tr C _. ... . _ .,.--... _
U.
Ll1 _
0
Oc = m
Q
Z O
C 0r 7 I C �- L:1 T
1111M S,
4 = U o LLJ
p z
■.� L O
y cwLL
CZ
to LLJ C3
a� c aA
MM
p mag
\ u -
I. J O O uLi U]
4odI CIS U3 00
v -
• Qt•Cj Z .
rA4K =V
CIS
- � _ p =-:_ .-- - '- :: _.=•��'=�_'=�� Q LL's -
C6 r-
Cc
O v7
CD
cc
LLJ
40'ja
jr
iiW U _ _ •'1►� __.-:;.. ,- =+�t/) k-.O
LLI 'a
o LLS U-
v. V YOn
a
• Yr. UCC
AL. - - _ tJ
3iLU
`Ad W-
44P ar
gL
uj
cn
CJS U _.r.,,-•:�- Z Z f. Q
r
ci L3
C 3-�
1IIINQ MEETING DATE:
WIIM11 1 city of Sap CUis oBiSpo• April 7 1992
COUNCIL AGENDA REPO AE^^NUMB
P
FROM:
Action ElFIA
David F. Romero, Public Works DirectorCAoCfl O CDDDIR.
L7'ACAo p ��
SUBJECT:. d TTOP-NEY CXAvDIR.
Mission Plaza Creek Wall Repair ��/CPUC.. 0 POLICECFL
P MG1r1T TEA34 [J
PEC.DLR
®r
CREADFITLE. �UTIr DTR.
CAO, RECOMMENDATION:
By motion, approve the Mission Plaza Creek Wall Repairs in con
and direct staff to prepare plans and specifications and obtain
necessary processing approvals, `usinq Alternative B (laid ug
concrete rubble walls) as the basic anproach.
BACKGROUND:
During s heavy; storm .in, March 1991, San Luis Obispo Creek undercut
several 'walls in Mission' Plaza. During April, staff removed a number
of new l °expose d rye i forci{i9:: axs;. which presented''a,. hazard to the
public. During"May staff recezved approval' from the ' Game Warden for
repairs to the undermining, . with• work to be conducted during the summer
when creek flows are low, following conditions of our general
maintenance permit from the Fish` and Game Department. The City did not
need to clear at that time with the Corps of Engineers, since this was
an emergency project to correct several undermines.
In August, City crews poured 33 cubic yards of concrete grout to
correct the undermining. There was some surplus grout, and this was
placed and rounded in front of existing built-up rubble concrete walls
on either side of the creek (Areas 1 and 2 on exhibit) , exposing to
public view approximately 2 cubic yards of concrete. After a
Councilperson's complaint, staff hired a contractor to chip off the
newly poured concrete to near the face of the original rubble concrete
wall along the east bank. Staff also tried twice . (unsuccessfully) to
stain the exposed concrete along the west bank to give it a more
natural appearance.
At the February 4, : 1992 meeting, Councilperson Pinard presented a
series of slides showing the condition of the concrete pours. These
slides were taken before staff attempts to correct the unsightly
appearance. The City Council directed staff to "redo" the repairs.
During mid-February, a heavy storm started additional erosion in this
immediate area of Mission Plaza.
In response to Council direction, Public Works and Planning staff met
at the site in late February to reach agreement regarding the best
approach toward correction to previous work and correction and
protection• regarding. recent erosion. Staff agreed that work was needed
'in four areas (see exhibit) .
Area #1 Cover face of partially corrected rubble concrete wall
with native stone facing to match 'nearby retaining wall or
face with medium-small boulders to match those .to be
placed in Area ,#2: